Top Banner
1 INTRODUCTION 1.1 ECIS project The NOS-ECIS alignment presented in Figure 1 is approximately 18.5 km long (11.5 miles), and extends from the NORS connection located in the Baldwin Hills area of Culver City, westerly along Exposition Boulevard towards downtown Los Angeles. The eas- tern end of the alignment terminates just east of the Los Angeles River, near the intersection of Mission Road and Jesse Street. The alignment is primarily located within the densely developed urban area of central and south central Los Angeles. The tunnel is divided into four construction units with start and end points corresponding to locations of working and retrieval shafts used for tunneling. A general presentation of the design is presented else- where by Hanks et al. (1999). Aspects of construction for portions of the project are presented by Crow et al. (2003), and Budd & Goubanov (2003). This paper addresses aspects of tunnel construction on Unit 1. 1.2 Unit 1 The tunnel was driven 2.5 km (8200-ft) from the Siphon Structure near the intersection of Jefferson Boulevard and LaCienega Boulevard to the North Outfall Replace- ment Sewer (NORS) connection structure (Figure 2). The tunnel drive was downhill at a constant gradient of 0.12% from east to west over this reach. The EPB- TBM used for mining the tunnel was manufactured in Toronto, Canada by Lovat Inc. and commissioned as Angie. The TBM was 4.72 m (15.5-ft) in diameter and weighed approximately 283 tonnes (624,000 lbs). North American Tunneling 2004, Ozdemir (ed) © 2004 Taylor & Francis Group, London, ISBN 90 5809 669 6 441 Tunneling through an operational oilfield and active faults on the ECIS Project, Los Angeles, CA, USA Eric Keller City of Los Angeles, Bureau of Engineering, Los Angeles, CA, USA Matthew Crow Parsons Brinkerhoff/Brown & Root Services J.V., Los Angeles, CA, USA ABSTRACT: A 2.5 km (1.8 mile) long tunnel has been driven by a 4.7 m (15.5 ft) diameter EPB-TBM through sands and gravels of the Lakewood formation and very stiff massive clays and silts with minor occur- rences of sand of the San Pedro formation. The Unit 1, western section, of the East Central Interceptor Sewer (ECIS) project tunnels beneath major utility lines with shallow cover, crosses the seismically active Newport- Inglewood Fault Zone beneath Baldwin Hills, and navigates through the Inglewood Oil Fields. The paper describes the hazard assessment and construction considerations of tunneling through faults and outlines risk avoidance planning to avoid abandoned oil wells. The paper then describes the performance of the TBM in the different ground conditions encountered, the forward probing method used to monitor for gas and the search for existing oil wells using a magnetometer both in a probe hole from the tunnel and also from the surface. Procedures are included describing the re-abandonment of an existing oil well discovered elsewhere on the project, and how successful implementation enabled the project to proceed safely. Figure 1. Plan of ECIS sewer tunnel alignment. Copyright © 2004 Taylor & Francis Group plc, London, UK
8

Tunneling through an operational oilfield and active ...

Jan 14, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Tunneling through an operational oilfield and active ...

1 INTRODUCTION

1.1 ECIS project

The NOS-ECIS alignment presented in Figure 1 isapproximately 18.5 km long (11.5 miles), and extendsfrom the NORS connection located in the BaldwinHills area of Culver City, westerly along ExpositionBoulevard towards downtown Los Angeles. The eas-tern end of the alignment terminates just east of the

Los Angeles River, near the intersection of MissionRoad and Jesse Street. The alignment is primarilylocated within the densely developed urban area ofcentral and south central Los Angeles.

The tunnel is divided into four construction unitswith start and end points corresponding to locationsof working and retrieval shafts used for tunneling. A general presentation of the design is presented else-where by Hanks et al. (1999). Aspects of constructionfor portions of the project are presented by Crow et al.(2003), and Budd & Goubanov (2003). This paperaddresses aspects of tunnel construction on Unit 1.

1.2 Unit 1

The tunnel was driven 2.5 km (8200-ft) from the SiphonStructure near the intersection of Jefferson Boulevardand LaCienega Boulevard to the North Outfall Replace-ment Sewer (NORS) connection structure (Figure 2).

The tunnel drive was downhill at a constant gradientof 0.12% from east to west over this reach. The EPB-TBM used for mining the tunnel was manufactured inToronto, Canada by Lovat Inc. and commissioned as“Angie”. The TBM was 4.72 m (15.5-ft) in diameterand weighed approximately 283 tonnes (624,000 lbs).

North American Tunneling 2004, Ozdemir (ed) © 2004 Taylor & Francis Group, London, ISBN 90 5809 669 6

441

Tunneling through an operational oilfield and active faults on the ECIS Project, Los Angeles, CA, USA

Eric KellerCity of Los Angeles, Bureau of Engineering, Los Angeles, CA, USA

Matthew CrowParsons Brinkerhoff/Brown & Root Services J.V., Los Angeles, CA, USA

ABSTRACT: A 2.5 km (1.8 mile) long tunnel has been driven by a 4.7 m (15.5 ft) diameter EPB-TBMthrough sands and gravels of the Lakewood formation and very stiff massive clays and silts with minor occur-rences of sand of the San Pedro formation. The Unit 1, western section, of the East Central Interceptor Sewer(ECIS) project tunnels beneath major utility lines with shallow cover, crosses the seismically active Newport-Inglewood Fault Zone beneath Baldwin Hills, and navigates through the Inglewood Oil Fields. The paperdescribes the hazard assessment and construction considerations of tunneling through faults and outlines riskavoidance planning to avoid abandoned oil wells. The paper then describes the performance of the TBM in thedifferent ground conditions encountered, the forward probing method used to monitor for gas and the search forexisting oil wells using a magnetometer both in a probe hole from the tunnel and also from the surface.Procedures are included describing the re-abandonment of an existing oil well discovered elsewhere on the project,and how successful implementation enabled the project to proceed safely.

Figure 1. Plan of ECIS sewer tunnel alignment.

Copyright © 2004 Taylor & Francis Group plc, London, UK

Page 2: Tunneling through an operational oilfield and active ...

Along the alignment, one maintenance hole was con-structed 1680 m (5512 ft) from the NORS connectionshaft, which served as a ventilation shaft. Cal-OSHArequired the installation of an emergency rescue cham-ber after a maximum distance of 1524 m (5000-ft)without a ventilation shaft. All excavated soil wasremoved from the Siphon Outlet Shaft (Figure 4) atthe intersection of LaCienega and Jefferson Boulevards.

2 UNDERGROUND CONDITIONS

2.1 Topography

The longitudinal section of the tunnel alignment is pre-sented on Figure 5. The tunnel alignment on Unit 1 isbeneath the steep hilly terrain of the Baldwin Hills fromthe intersection of La Cienega Boulevard and RodeoRoad to the NORS connection over a distance of about1.8 km (5905-ft). The alignment of the eastern sectionof Unit 1 is beneath ground of low relief. The tunnelinvert is approximately 16 m (52.5-ft) below ground atthe eastern end (siphon outlet) and approximately 23 m(75.5-ft) below ground at the NORS connection. At thedeepest location beneath Baldwin Hills, the tunnelinvert is 112 m (367.5-ft) below ground surface.

2.2 Geological setting

The project is located in the northern margin of theL.A. basin (Yerkes et al., 1965), described as a 75 by20 km lowland coastal plain that slopes south and

442

Figure 2. Exposed previous shaft shoring around the existingNORS connection structure.

Figure 3. Lovat EPB-TBM, “Angie”.

Figure 4. Launch of Unit 1 TBM at Siphon Outlet Shaftfrom staging above Unit 2 TBM servicing arrangements.

Figure 5. Longitudinal section of ECIS project.

Copyright © 2004 Taylor & Francis Group plc, London, UK

Page 3: Tunneling through an operational oilfield and active ...

west. Figure 5 shows the profile and the geologicalconditions through which the tunnels were driven.Additional information on the geotechnical aspects ofthe project are presented elsewhere in the proceedingsby Seeley (2004).

2.3 Predicted geological conditions

The initial 230 m reach of tunnel was expected to bedriven entirely within the silty sands and silts of theLakewood Formation with occasional cobbles andboulders. A 100 m reach around Station 22�10 ofmixed face conditions resulting from the transitioninto the San Pedro Formation from the overlyingLakewood Formation was anticipated. The tunnel wasthen to be driven entirely through the San PedroFormation. The Baldwin Hills Fault was expected at Station 16�90 and another Fault expected at Station18�10. Changes in lithology were to be expectedacross these faults accompanied by groundwater undera hydraulic head of up to 10 m above the tunnel invert.

The Inglewood Fault was anticipated to be atStation 15�10, where it would encounter the eastsideof the graben that has down-dropped the San PedroFormation and the overlying Lakewood Formation.This particular fault zone was expected to be roughly3 m wide and to contain sheared clay silts and sandsthat are moist to wet. Change in lithology was expectedfrom one side of the fault to the other. Within thefault, groundwater was likely to be found under ahydraulic head up to 20 m above tunnel invert. Thetunnel was then expected to be within the LakewoodFormation west of the Inglewood Fault.

The next fault to be encountered was at Station14�60, along the west side of the graben mentionedabove. The faults at Stations 00�95, 11�60 and14�50 were anticipated to contain sheared clayey siltsand sands, described as moist to wet. Again, changesin lithology were to be expected at these faults fromone side of the fault to the other. Within this section,groundwater could be anticipated under a hydraulichead of up to 30 m.

All of the faults were anticipated to be potentialtraps for methane, hydrogen sulfide and other gasesassociated with oil fields.

The final 100 m reach of the tunnel was anticipatedto be a mixed face of the San Pedro Formation overlainby the Lakewood Formation. As the contact betweenthe San Pedro and Lakewood Formations dips to thewest, the final 40 m was expected to be completelywithin the Lakewood Formation, which was previouslyencountered during construction of the NORS tunnel.

2.4 Underground conditions as-encountered

In general, the ground conditions encountered weresimilar to those predicted but with the following differences.

Mining across the area identified as the BaldwinHills Fault (Station 18�10), there did not appear tobe any significant change in material. Methane gasregistered at 15% and 18% LEL roughly 30-50 m pastthe proposed fault location. The gas occurrences wereread by the handheld instrument at the discharge pointof the TBM screw conveyor, typically only associatedwith the first TBM advance of the day, and quicklydissipated. The identified fault near Station 16�90manifested with an increase of groundwater, causingthe annular grout to become excessively wet and blowthrough the tail seal brushes.

Excavated soil between Stations 16�18 to 14�10was described primarily as soft clay with fine sands.Near Station 15�70, a pocket of methane gas regis-tered a 55% LEL and quickly dissipated, accompa-nied by an increase in volume of cleaner groundwater.After mining through the Inglewood Fault (Station15�10), material did change to a sandy, silt claywithin the zone of Stations 14�70 to 14�95. Theincrease in groundwater was enough to require pump-ing. The TBM was out of the groundwater conditionby Station 14�60.

Near the Station 11�60 fault, material was stilldescribed primarily as a clay with fine sand, with piecesof sea shells were noted as present in the excavatedsoil until Station 11�15. The soil between Stations9�44 through 8�31 was described as especially hardclay by the Inspector.

From Stations 6�30 through 4�73, in some of thedeepest sections from the surface topography, the veryhard clay was described as “squeezing ground”. Duringprobe hole drilling, the steel augers became almostimpossible to remove requiring probe holes to againbe drilled the following day.

After the Station 00�95 fault, the excavated soilbecame soft, silty clay with an increase in sand andlater also gravel.

One unique feature was the discovery of a pre-existing void at Station 12�90 during the normalprobe hole drilling ahead for gas testing. The voidencountered extended approximately 6 m (20-ft) hor-izontally from the TBM face. The probe hole wasadvancing through the same tight dry clay that hadbeen the case for a number of previous probes. Nowater or gas was encountered when the void was found.PVC pipe casing was inserted into the probe hole andused for pumping approximately 4.6 m3 (6 cu yd) ofgrout to fill the void. The same grout normally usedfor the segment annulus was used to fill this void.

2.5 Contaminated soil

A 150 m reach of the Unit 1 alignment (Station 19�00to 20�50) was beneath soil containing weatheredgasoline and sewage. The contamination area was atthe intersection of LaCienega Boulevard and Rodeo

443

Copyright © 2004 Taylor & Francis Group plc, London, UK

Page 4: Tunneling through an operational oilfield and active ...

Road where the tunnel passes beneath the existingNorth Outfall Sewer (NOS) and both existing and for-mer gasoline service stations. The contract provided a unit price bid item for the excavation, handling anddisposal of this material if necessary, including spe-cific requirements for safe handling of the material.

The tunnel horizon did not encounter any contami-nated soil within the possible identified zone of 150 m.However, the unit bid item was utilized for the excava-tion, handling, and removal of oil contaminated soilswithin the ECIS-NORS connection shaft worksite area.

3 OIL WELLS

3.1 Determination of position of oil wells

The alignment passes through the Inglewood oilfield.This oil field produces from sandy reservoirs hun-dreds of meters deep, but oil and gas commonly seeptowards the surface. Not only was there a possibilityof intercepting these deposits, but there was also thepossibility of encountering old wells. Prior to theaward of the contract, the City produced a plan thatidentified the boundaries of the oil field, based uponthe economic limits of ongoing oil production leases.Numerous oil and gas seeps were also reported to theCity (Geotechnical Services and Street Services) overthe years, manifesting the migration of oil and gas outside of the oil field along faults, fractures, bedding planes and within permeable sediments. Thecontract plans incorporated the location of both exist-ing and abandoned oil wells on record with the StateDepartment of Oil & Gas and Geothermal Services(DOGGR). An extract from the plans included asFigure 6 shows the tunnel alignment passing throughthe operational Inglewood oilfield; the black circlesindicating oil wells.

Facilities associated with past and present oil pro-duction, including sumps, drilling ponds, areas ofpast spills, storage tanks, exploratory and productionwells may also be responsible for release of hydro-carbons into the subsurface soils. Moreover the pres-ence of crude oil in the subsurface due to past leakageor spillage is a potential source of contamination with

potential to produce methane gas as a by-product. Fromprevious studies, it was known that prior to 1942 wells were abandoned with drilling mud rather than adeep 150 m cement plug, possibly allowing gas tomigrate to the sewer invert and be encountered duringconstruction of the tunnel.

The alignment was set to avoid these wells, how-ever it was expected that unrecorded or “wildcat” oilwells might lie on the tunnel alignment. Precautionswere therefore taken to investigate for their presence.These unknown wells were not likely to have beenabandoned to modern standards, so significant risk totunneling, but also the risk of cost being incurred intreating the wells to current standards should that berequired.

3.2 Risk management

As the possibility of encountering an unrecorded oilwell during tunneling had been identified as a signif-icant project risk by the City and the Contractor, ajoint task force worked with the State Department ofGas and Geothermal Reserves (DOGGR). Based upona review of the DOGGR maps, it was anticipated thattunnel mining would be no closer than 6 m to anymapped oil well, and that there were likely to be some18 oil wells within 45 m of the tunneling activities.However, to reduce risk of unmarked oil wells, histor-ical documents were also researched and magnetom-eter studies were performed to search for possible oilwells, observed as magnetic anomalies from both thealignment surface and from within the TBM.

3.2.1 Historical researchA combined effort by the City Geotechnical Engi-neering and Construction Management Staff, the con-tractor, and a specialist oil field consultant was madeto research information from the following sources:

• Survey and Operational records of all past and pres-ent wells on the oil field lease of Plains Exploration& Production, (PXP).

• Historic aerial photographs from University ofSouthern California archives.

• Los Angeles County area maps.• Historic and current oil field maps (DOGGR)• Topographic maps for features of possible past oil

well working sites.• ECIS alignment was surveyed, marked along the

ground surface, and walked for visual surface indi-cators including graded areas and foundations.

3.2.2 Surface magnetometer surveyThe City commissioned MACTEC Engineering &Consulting, Inc. to perform a geophysical investigationto search for oil wells within a 12 m by 760 m corridorcorresponding to the ECIS alignment through the

444

Figure 6. Tunnel alignment passing through the operationalInglewood Oilfield.

Copyright © 2004 Taylor & Francis Group plc, London, UK

Page 5: Tunneling through an operational oilfield and active ...

subject oil field in Culver City. Specifically, the mag-netometer would search for undocumented steel wellcasings. The magnetometer measures the magneticfield intensity using the hand held equipment as shownin Figure 7.

This equipment consisted of a Geometrics ModelG-858 magnetometer and GPS system (Trimble Pro-XRS) for horizontal positioning. A second base sta-tion magnetometer was installed at a fixed location tomonitor the natural time-varying magnetic drift cycleand record any bursts of magnetic noise that mightaffect the survey data. Prior to the survey a test surveywas performed of a known abandoned well location(TVIC-15) in order to establish a characteristic mag-netic signature for abandoned wells within the surveyarea. Total magnetic field of the test magnetic anom-aly was approximately 53,000 nanoTeslas (nT).

In addition, a utility locating survey was performedto identify potential sources of magnetic interference(i.e. buried metallic utilities) so the associatedresponses would not be mistaken for indications ofabandoned wells. The utility locating survey used aRadiodetection Corp. RD-400 radio-magnetic utilitylocating system and a Fisher Model TW-6M-Scope.

3.2.3 Results of surface magnetometerThis information was processed and presented graph-ically in relation to the tunnel alignment as shown bythe example in Figure 8. Fortunately, the survey indi-cated no wells in the tunnel alignment. The most sig-nificant magnetic anomalies appeared over a surfacepad with some abandoned structures, which was con-sidered as a possible previous oil well site.

However, the signature of the anomaly was onlyindicative only of relatively small, shallowly buried

metal objects (Figure 8) dispersed over an 8 m area,and did not match the signature of the known oil welltest survey.

3.3 Forward probing for gas, and tunnelmagnetometer survey

Contract Specifications required the contractor toprobe ahead of the TBM once gas might be encoun-tered beginning at the Baldwin Hills Fault (Station18�10). The Unit 1 tunnel was classified as “Gassy”by the Cal-OSHA Mining & Tunneling Unit. Probingto perform gas testing was performed in accordancewith the Cal-OSHA Tunnel Safety Orders, requiring aminimum of at least 6.1 m (20-ft) of tested ground toremain beyond the face of the TBM.

Upon reaching Station 7�50, specificationsrequired magnetometer surveys for the remainder ofthe drive to Station 0�00 in order to locate any possi-ble abandoned oil well casings. After probe drillingroughly 58 m (190-ft) with 19 sections of 100 mm (4-in)drilling auger, the drill sections were removed andreplaced with a 46 m (150-ft), 75 mm (3-in) PVC cas-ing. The magnetometer instrument, a FVM-400 VectorFluxgate Magnetometer by MEDA, was inserted inthe casing and forwarded to the end of the casing witha fiberglass rod. The instrument was then backed outof the PVC casing at 0.3 m intervals and a data read-ing taken. Following data collection with the magne-tometer, the same basic procedure was repeated butwith the insertion of an inclinometer, specifically aLittle Dipper by Applied Geomechanics. Data wasstored in a Handspring Visor PDA and utilizing PalmOS-compatible software. The inclinometer providedinformation to determine deviation of the probe holefrom the TBM to the end of the casing.

Data collection from the magnetometer was down-loaded to produce a graph of the magnetic field againstthe Station, for the x, y, and z components. A nearconstant slope of the graph downward after leavingthe TBM influence area represented a “normal” condi-tion. Actual plots depicting a spike in the slope on any

445

Figure 7. Surface hand held magnetometer with GPS forhorizontal positioning.

Possible pipeline250kg 1m bgl

Tunnel Centerline

Small buried metalobject 25 kg 0.5m bgl

4.

7m

Figure 8. Magnetic total field contour map above tunnelalignment oil-well abandonment.

Copyright © 2004 Taylor & Francis Group plc, London, UK

Page 6: Tunneling through an operational oilfield and active ...

of the three components indicated a magnetic anom-aly in a particular Station range.

The left side of Figure 9 for the magnetometer probereadings forward of Station 0�532.5 indicate appar-ent x & z anomalies, whereas the probe readings for-ward of Station 0�696 depicted on the right indicate“normal” xyz.

The total magnetic field at the station of an anom-aly was determined separately by the contractor’sgeophysicist, Spectrum Geophysics, after removingthe Earth’s magnetic field and the field from the TBMfrom the data. The largest Total Resultant MagneticField was 27,646.0 nT. When anomalies were signifi-cantly present, the speed of the TBM was reduced andthe mining operation proceeded ahead carefully.

In some instances, an actual surface exploration wasmade along with review of DOGGR records to againcheck if there was any overlooked possibility of an oilwell. Communication with the on site oil-productioncompany, PXP, was also very helpful in the process ofreviewing records. Mining of the Unit 1 tunnel wassuccessfully completed on August 8, 2003. Due to siteaccess problems, there was a significant delay in mobi-lization for NORS shaft excavation. To enable comple-tion of the tunnel drive, the TBM was not driven intothe shaft, rather the shaft was later constructed aroundthe TBM. The completed shaft is shown in Figure 10.

3.4 Treatment of existing abandoned oil well

Although no oil wells were encountered during Unit 1tunneling, an abandoned well was discovered at theother end of the project alignment as excavationbegan for slurry trench guide-walls at the Mission &Jesse work site (Figure 11). The abandoned oil well

had been cut-off below the surface and as luck wouldhave it, was located within the rectangular shaft siteperimeter.

Fortunately the oil well was not located in conflictwith the actual slurry wall footprint. A more thoroughreview of DOGGR records was performed for oilfields along the western portion of the project align-ment, but the single isolated well on the easternmostportion of the alignment went undetected.

Removal of the oil well was critical as shaft designrequired excavation to 26 m (85-ft) below the groundsurface. The shaft location could not be moved due tothe confined nature of the site. Staff worked quicklywith a DOGGR field engineer to identify the well,which was recorded abandoned in the 1940’s.

However, to modify the well casing in any waywould require the well to be treated according to presentday standards for abandonment. By way of a changeorder, the contractor provided an oil field welder toremove the well cap and allow DOGGR to determine

446

10000

20000

0

30000

40000

20000

10000

1030 20401030 2040

Fac

e S

tati

on

532

.5

Fac

e S

tati

on

696

.0

Magnetic Field X Component (nanoteslas)

Magnetic Field Y Component (nanoteslas)

Magnetic Field Z Component (nanoteslas)

Distance from TBM face (m) Distance from TBM face (m)

-10000

-40000

-30000

-20000

-10000

Figure 9. Magnetic field graphs – xyz component forTBM face stations 0�532.5 and 0�696.0.

Figure 10. Face of TBM after excavation of NORS shaft.

Figure 11. Abandoned oil well at Mission & Jesse Site.

Copyright © 2004 Taylor & Francis Group plc, London, UK

Page 7: Tunneling through an operational oilfield and active ...

whether the previous plug was secure and that therewas no gas leakage. The City enlisted a DOGGRapproved consultant, Sampson Oil, to perform the oil well research, coordinate the permit applicationwith DOGGR, and oversee the oil well abandonmentprocess. The contractor hired subcontractor Oil FieldServices, Long Beach, a capable contractor who wasable to mobilize, drill out the existing well 215 m(700-ft), install a new cement plug, and demobilizewithin five days. The equipment used is shown onFigure 12.

The cement plug of a mix proportion of 100 kg ofcement to 45 liters of water was poured in two stagesof total volume 20 m3 (725-ft3). Considerable uncer-tainty surrounded the treatment of this old well, as itmight have been filled with discarded oil pipe, piperetrieving tools, wood, or any other kind of debrisavailable at the time to fill the hole in. Fortunately, thehole was fairly clean except for a difficult wooden plug,and drilling took fewer than three days as opposed topotentially 2–3 weeks. After the slurry trench rein-forced concrete guide walls were completed followedby shaft excavation, the existing well casing was cutoff in segments as the excavation progressed. In thissituation, the well was finally cut-off roughly 1.5 m(5-ft) below the working level of the shaft and sealedwith a welded steel plate cap. DOGGR and a represen-tative from LAFD inspected the plugged well casingprior to welding of the final steel plate cover.

The effort required to abandon this unmarked oilwell properly provided the necessary motivation earlyin the project to further research the alignment of theUnit 1 tunnel for any other unmarked oil wells whichmight exist. Potential impact both to project scheduleand budget was a real concern. If encountered, theprocess for abandonment of oil wells along Unit 1would have required further efforts to obtain surfacerights, locate and excavate for the well head, and provide access for the necessary equipment. Fortu-nately, the oil well at the east-end of the project wasthe only one encountered.

4 TBM PERFORMANCE

4.1 EPB TBM

The contractor, a joint venture of Kenny ConstructionCo./J.F. Shea Co. Inc./Traylor Brothers, Inc./Frontier-Kemper Constructors Inc. (KSTF-K) chose to use aTBM machine manufactured by Lovat. A cross sec-tion of the EPB machine is presented in Figure 13;however a comprehensive description of the machineis contained in Crow & Holzhauser (2003) and Budd &Goubanov (2003).

4.2 TBM production

Although the TBM performance for the remainder ofthe ECIS project was presented in Crow and Holzhauser2003, a brief summary is provided herein.

Tunneling of the 2.5 km long tunnel on this Unitstarted on October 13, 2002 from the Siphon OutletShaft to the East and was completed on August 8, 2003.An overall average progress rate of 247 m/month hasbeen achieved.

447

Figure 12. Treating abandoned oil well at Mission & Jesse site.

Plenum

Screw conveyor

Thrust cylinder

Target of laserguidance system

Articulation cylinder

Annulus backfillgrouting

Belt conveyorSegment erector

Lower part of muck ring

0 2 4 6 8 10 12 14Length [m]

Tool gapEPB pressuresensor

Note: Level of EPB pressuresensors1m above and belowHere rotated into display

Bulkhead

Figure 13. Cross-section of Lovat 4.72 m diameter EPB-TBM.

Dec-01Dec-01Jan-02Mar-02Apr-02May-02Jun-02Jul-02

Aug-02Aug-02Oct-02Oct-02Nov-02Dec-02Jan-03Mar-03Apr-03May-03Jun-03Jul-03

Aug-03Aug-03Oct-03

+

10+

00

20+

00

30+

00

40+

00

50+

00

60+

00

70+

00

80+

00

90+

00

100+

00

110+

00

120+

00

130+

00

140+

00

150+

00

160+

00

170+

00

180+

00

UNIT 1Av. = 247 m/month

UNIT 2Av. = 353 m/month

UNIT 3WAv. = 492 m/month

UNIT 3EAv. = 268 m/month

UNIT 4Av. = 265 m/month

2 x 10 hr shifts

1x 10 hr shift

Figure 14. ECIS tunnel production.

Copyright © 2004 Taylor & Francis Group plc, London, UK

Page 8: Tunneling through an operational oilfield and active ...

4.3 Settlement

The surface settlement measured along Unit 1 in bothgranular and cohesive materials was less than 10 mm.Subsurface measurements using multi-point boreholeextensometers were undertaken. In general, the loweranchor located at 1.5 m above the crown of the tunnelmeasured less than 32 mm settlement.

5 CONCLUSIONS

• Tunnels can be successfully driven through activeoilfields, but the importance of adequate site inves-tigation, risk assessment, good planning and imple-mentation of these plans undertaken should not beoverlooked.

• Tunneling through faults in soft ground with aclosed face TBM can be achieved with good siteinvestigation, planning and co-ordination on thepart of the owner, designer and contractor.

• Surface and forward probe magnetometers are usefultools in reducing the risks of tunneling through activeoilfields, but they must be used with care and theirrecords interpreted by experienced geophysicists

• The removal of the environmental nuisance ofinadequately abandoned oil wells can be safely andreadily achieved with the assistance of experiencedoilfield engineers and contractors.

ACKNOWLEDGEMENTS

The authors wish to acknowledge the many indi-viduals comprising the project team for the City of Los Angeles, which was led by Baron Miya of theBureau of Engineering. Thanks also to the team led

by Ted Budd of Kenny Construction who performedthe real work of constructing the project, the largestPublic Works project awarded by the City of LosAngeles to date. Special thanks to Chief ResidentEngineer John Critchfield, who skillfully led theConstruction Management Team. Resident EngineerTom Saczynski, who provided tunneling expertise overboth Unit 1 & 2. Jorg Holzhauser who provided valu-able TBM performance expertise. Lastly, thanks to theBureau of Contract Administration efforts to ensure aquality product, especially inspectors Mel Stanley,Jeff Kemper, Carlos Tirres, and Paul Hernandez.

REFERENCES

Budd, T., and V. Goubanov. 2003. Case History – East CentralInterceptor Sewer, Los Angeles, CA. Proceedings of theRapid Engineering and Tunneling Conference.

Crow. M., B. Miya and T. Budd. Construction of the eastCentral Interceptor Sewer in Los Angeles using EPB-TBMs above the groundwater table. Proceedings ofUnderground Construction, London, 2003.

Crow, M., and J. Holzhauser. 2003. Performance of fourEPB-TBMs above and below the groundwater table onthe ECIS Project, Los Angeles, CA, USA, 2003. RapidExcavation and Tunneling Conference. pp. 905–926.

Hanks, K., Fong, W. Edgerton, and B. Miya.1999. City ofLos Angles Large Diameter Interceptor Sewer Tunnels.Proceedings of the Rapid Engineering and TunnelingConference.

Seeley, T. East Central Interceptor Sewer-EPB mining aboveand below the water table, 2004 North American TunnelingConference.

Yerkes, R.F., T.H. McCulloch, J.E. Schoelhamer, and J.G. Vedder. 1965. Geology of the Los Angeles Basin,California – An Introduction, U.S. Geological SurveyProfessional Paper 420-A.

448

Copyright © 2004 Taylor & Francis Group plc, London, UK