Tulare Lake Storage and Floodwater Protection Project Jason Gianquinto Semitropic Water Storage District
Tulare Lake Storage and Floodwater Protection Project
Jason GianquintoSemitropic Water Storage District
Water Storage Investment Program Project Overview
Major Project Features1:
• New Tulare Lake Facilities (Kettleman Reservoir) and Aqueduct Tie-in• Kings River Flood Flow Capture and Conveyance Improvements• Phase 2 SWRU Facilities Construction• Ecosystem Benefit Operations at Keswick Dam, through exchange
agreements
Total Project Cost = $603 millionTotal WSIP Funding Request = $452 million
1 From Chapter 2 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Facilities Locations
2 From Figure 1-1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)3 From Figure 2-1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)4 From Figure 2-2 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
2
3
4
Tulare Lake FacilitiesProposed Facility Features5:
• Kettleman Reservoir• Kettleman Canal• Aqueduct Intertie• PG&E Electrical Facilities• Maintenance Yard• Two Pumping Plants
5 From Section 2.1.1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
SWRU Phase 2 FacilitiesProposed Facility Features6:
• North/South Conveyance System• Distribution System X• Distribution System Y
6 From Section 2.2.1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Project OperationsThe Project generates water supply for local and public benefits:
• Local Water Supply o Capture and regulation of surplus Kings River flows in to
groundwater banking and conjunctive use facilities7
• Public Benefit Water Supplyo Capture and regulation of surplus Delta flows into Semitropic
Groundwater Bank8
o Banked water exchanged for SWP deliveries9
o Exchange water available North of Delta ecosystem purposes10
7 From Section 2.5.1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)8 From Section 2.5.2.1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)9 From Section 2.5.2.2 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)10 From Section 2.4 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Public BenefitsThe Project provides Public Benefits11, as defined by WSIP, including:
• Ecosystem Improvement to Delta fisheries and historic Tulare Lake bed• Flood Management• Recreation Improvement to the historic Tulare Lake Bed• Emergency Response• Project benefits must be quantified and monetized for future (2030 and
2070) conditions.
11 From Chapter 3 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Ecosystem Improvement12
Project integration with SWP/CVP facilities to transport and store surplus Delta flows will improve threatened and endangered salmonid survival by:• Improving temperature on the Sacramento River below Shasta/Keswick
complex,• Increasing egg-to-fry survival, and• Increasing adult salmon that return to spawn.
Ecosystem adaptive management options highlight Project flexibility.Total Monetized Public Benefit for 2030 = $636 million Total Monetized Public Benefit for 2070 = $514 millionTotal Non-Monetized Benefit = 10,240 acres of seasonal, intermittent
open-water habitat12 From Section 3.1.1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Flood Control Improvement13
Kings River flood flow capture will reduce flood risk to prime agricultural lands and disadvantaged communities within the Kings River and Tulare Lake region.
• Kings River flood flows are directed to the San Joaquin system and lost under current operations.
• Total Monetized Public Benefit = $3 million (Flood Damage Reduction)
13 From Section 3.1.2 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Emergency Response14
The Project improves system capability to respond to emergencies or natural disasters in the Delta.
• Ability to make SWRU withdrawals of banked water would provide a water supply to South of Delta SWP users.• 40,000 acre-feet of water for 2030 conditions• 20,000 acre-feet of water for 2070 conditions
• Total Monetized Public Benefit for 2030 = $96 million• Total Monetized Public Benefit for 2070 = $72 million
14 From Section 3.1.4 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Recreation Benefits15
The Project would support waterfowl and migratory bird populations along the Pacific Flyway, and enhance recreational birdwatching opportunities for area residents and outdoor-oriented tourists.
• Total Monetized Public Benefit= $.25 million
15 From Section 3.1.3 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Monetized Public Benefits SummaryEcosystem Flood Control Emergency Response Recreation
Total Benefit
Additional adult returns over Life
of Project)
Total Ecological Benefit
($M)
Total Maximum Flood Damage
Reduction($M) Magnitude (AF)
Value (Based on $2000/AF)
($M)Magnitude
(visitor days)Total Benefit
($M) ($M)
2030 Benefit
6,355 $636 $3.0 40,000 96 8,000 $0.25 $735
2070 Benefit
5,140 $514 $3.0 20,000 72 8,000 $0.25 $589
• Claimed public benefits support a cost-benefit ratio of 1.6 and 1.3, for 2030 and 2070 conditions.16
16 From Section 1.6.1 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
WSIP Non-Public Benefits17
The Project also provides Non-Public Benefits, such as:
• Improved Water Supply and Operational Flexibility for the SWP• Improved Groundwater Banking and Conjunctive Use• Improved Local and Regional Water Supply Reliability• Improved Water Quality in the SWP and Local Groundwater Basin
17 From Section 3.1.3 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Cost Benefit SummaryDescription Cost
Capital Cost
Tulare Lake Facilities $502,442,000
Stored Water Recovery Unit – includes lands $100,445,000
Total Estimated Capital Cost $602,887,000
WSIP Funding Investment (Public Benefits) ($452,159,000)
Remaining Capital Cost after WSIP Investment $150,728,000
Annual Costs
Debt Service (term: 30yrs, rate: 5%) $9,806,000
Operation/Maintenance, estimated $3,530,000
Average Annual Variable expense (Power to CA Aqdct) $7,020,000
Sub-total $20,356,000
COST-BENEFIT
Average Annual Yield (acre-feet) 120,000
Unit Cost of Water ($/acre-foot) at point water supply reaches California Aqueduct. Does not include conveyance from Project to Semitropic or groundwater banking costs needed to manage supply $170
Project Timeline & Milestones18
18 From Section 6.2 of Tulare Lake Storage and Floodwater Protection Feasibility Report (GEI Consultants, Aug 2017)
Project Construction Duration EstimateWSIP Project Schedule 2017 2018 2019 2020 2021 2022 2023 2024
1.0 Tulare Lake Facilities
1.1 Permitting1.2 Design 30%1.3 Design 60%/90%/Final1.4 Bid, Award, NTP, Construction
2.0 Stored Water Recovery Unit
2.1 Permitting2.2 Final Design2.3 Construction
3.0
DWR/SemitropicAmended Banking Agreement
3.1 Amended Agreement