PERENCANAAN PENGELOLAAN AIR LIMBAH KOMUNAL BERBASIS MASYARAKAT PERMUKIMAN PADAT DI KELURAHAN WONOKROMO JURUSAN TEKNIK LINGKUNGAN FAKULTAS TEKNIK SIPIL dan PERENCANAAN INSTITUT TEKNOLOGI SEPULUH NOPEMBER (ITS) SURABAYA 2014 Tugas Akhir RE-091324 Mahasiswa: Tania Ratnasari 3310 100006 Dosen Pembimbing: Ir. Eddy S. Soedjono. Dipl. SE. MSc. PhD
23

Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Mar 10, 2019

Download

Documents

doduong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

PERENCANAAN PENGELOLAAN AIR LIMBAH KOMUNAL BERBASIS MASYARAKAT PERMUKIMAN PADAT DI KELURAHAN WONOKROMO

JURUSAN TEKNIK LINGKUNGAN FAKULTAS TEKNIK SIPIL dan PERENCANAAN

INSTITUT TEKNOLOGI SEPULUH NOPEMBER (ITS) SURABAYA 2014

Tugas Akhir RE-091324

Mahasiswa: Tania Ratnasari 3310 100006 Dosen Pembimbing: Ir. Eddy S. Soedjono. Dipl. SE. MSc. PhD

Page 2: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Latar Belakang

2

PERKEMBANGAN DAN PEMBANGUNAN SANITASI DI KOTA SURABAYA TIDAK MERATA

MENURUT MPSS, WONOKROMO MERUPAKAN AREA BERESIKO TINGGI SANITASI

TANKI SEPTIK BELUM MEMENUHI SYARAT MENYEBABKAN PENCEMARAN

Page 3: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

MPSS (MEMORANDUM PROGRAM SEKTOR SANITASI)

3

“UNTUK MENINGKATKAN AKSES LAYANAN AIR LIMBAH BERPENGHASILAN RENDAH DAN PERMUKIMAN PADAT ADALAH

DENGAN CARA PEMBANGUNAN PENGOLAHAN AIR LIMBAH KOMUNAL” MPPS,2012

Peta Area Beresiko Sanitasi

Page 4: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Rumusan Masalah

4

Kondisi sanitasi di Kelurahan Wonokromo belum memadai

Kelurahan Wonokromo merupakan daerah padat penduduk dengan lahan yang terbatas

Tingkat ekonomi tergolong kalangan menengah kebawah

Page 5: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Tujuan

5

Merencanakan saluran dan pengolahan air limbah komunal berbasis masyarakat

Menentukan prakiraan biaya sistem operasional dan pemeliharaan pengolahan air limbah

Page 6: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Gambaran Umum Lokasi Perencanaan

6

• RW 1 Kelurahan Wonokromo • Luas area pelayanan 0,96 Ha • Jumlah KK 90 KK = 360 orang • Setiap rumah yang dilayani

memiliki septik tank tetapi beberapa tidak sesuai standart

• 70 rumah terlayani berada di tepi sungai Jagir

Page 7: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Kondisi Eksisting

7

Page 8: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

1 m 1 m 3 m

8

• Lebar Jalan Pulo Wonokromo = 5 meter

• Luas lahan tersedia untuk IPAL= 6 x 5,5 m = 33 m2

Page 9: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Kuisioner

9

• Survey dilaksanakan pada tanggal 25-27 April 2014 • Rincian pembagian kuisioner menggunakan rumus:

Dimana: n : jumlah sampel responden N : jumlah anggota populasi (KK) Z : nilai tabel normal standar (1,96) d : sampling error (tingkat kesalahan yang diperbolehkan) 10% P : proporsi yang disetujui, (0,5 – 0,99) (1-p) : proporsi yang tidak disetujui

No Jumlah 1 162 24

40

Penerima KuisionerWarga dekat lokasi IPAL Komunal

Warga terlayani di sepanjang sungai JagirJumlah

= 40

Page 10: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Hasil Analisa Kuisioner

10

A. Kepemilikan Jamban dan Tanki Septik

B. Kemauan masyarakat dalam pembangunan IPAL Komunal.

No Kepemilikan Jamban dan Tangki Septik Jumlah1 Punya 402 Tidak 0

40Jumlah

No Presepsi Pembangunan IPAL Komunal Jumlah1 Setuju 392 Tidak Setuju 1

40Jumlah

Page 11: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Hasil Analisa Kuisioner

11

D. Keterlibatan Masyarakat dalam OM No Keterlibatan dalam OM Jumlah1 1 - 3x/minggu 32 1-3x/bulan 363 Tidak Ikut 1

40Jumlah

C. Kesediaan membayar iuran No Kesediaan Membayar Iuran OM Jumlah1 Rp 0-Rp 5.000 32 Rp 5.001-Rp 20.000 263 Rp 20.001-Rp 35.000 94 Rp 35.001-dst 2

40Jumlah

Page 12: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Sistem Penyaluran Air Limbah

12

Bak Kontrol Manhole

Sambungan Rumah Pipa Servis

Tanki Septik

Pipa Sekunder

Ilustrasi

Page 13: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Sistem Penyaluran Air Limbah

• Debit air limbah

13

Tahun 2014 2015 2016 2017 2018 2019Persentase Air Limbah % 80% 80% 80% 80% 80% 80%Q Air Bersih rata-rata L//hari 0,62 0,64 0,66 0,69 0,71 0,73Q Air Bersih rata-rata L/detik 53424 55296 57312 59328 61200 63216

Q Ave Limbah L/detik 42739 44237 45850 47462 48960 50573Q Ave Limbah m3/detik 42,74 44,24 45,85 47,46 48,96 50,57

Page 14: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

14

Page 15: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Pembebanan SPAL

15

No Jalur Pipa

Jumlah Beban

Penduduk

Q Air Bersih per

Jalur (L/dtk)

% Air Limbah

Q Average Limbah

per Jalur (m3/dtk)

Luas Area Pelayanan

(Ha)F Peak Q Peak

(L/dtk) F Inf Q inf (L/dtk)

Q Peak Total

(L/dtk)

Q Min (L/dtk)

1 T1-T2 4 0,0267 80% 0,000021 0,0028 3,1 0,0001 14 0,000003 0,00007 0,0024712 T2-BK 8 0,0667 80% 0,000053 0,0028 3,1 0,0002 14 0,000009 0,00017 0,0074193 T4-T3 4 0,1067 80% 0,000085 0,0028 3,1 0,0003 14 0,000014 0,00028 0,013044 T3-BK 8 0,1467 80% 0,000117 0,0028 3,1 0,0004 14 0,000019 0,00038 0,0191095 BK-S1 16 0,1867 80% 0,000149 0,0028 3,1 0,0005 14 0,000024 0,00049 0,025523

• Pipa SR (Tipikal)

Page 16: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Penanaman Pipa

16

• Pipa SR (Tipikal)

Awal Akhir Awal Akhir1 T1-T2 6 8 8 7,8 7,4 0,4 0,072 T2-BK 2 8 8 7,4 7 0,4 0,203 T4-T3 6 8 8 7,8 7,4 0,4 0,074 T3-BK 2 8 8 7,4 7 0,4 0,205 BK-S1 7 8 8 7 6 1 0,14

No Jalur Pipa Panjang

Pipa (m)

Elevasi Medan Penanaman Pipa ∆ h Penanaman Pipa (m)

Slope Penanaman

Page 17: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Penanaman Pipa

17

Sumber: Direktorat jendral cipta karya kementrian pekerjaan umum

Page 18: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Dimensi Pipa

18

• Pipa SR (Tipikal) Q peak Q full D D

terpasang

D terpasan

gQ min Q min / Q

full A full V full V min V peak

(m³/s) m³/s m m mm m³/s m³/s m² m/s m/s m/s1 T1-T2 0,00000007 0,8 0,98 1,15 0,0000001 0,015 0,001 0,1 100 0,0024706 34792,765 0,15 0,3 0,008 1,5 0,5 1,72 T2-BK 0,00000017 0,8 0,98 1,15 0,0000002 0,015 0,001 0,1 100 0,0074189 41790,440 0,15 0,3 0,008 2,5 0,9 2,63 T4-T3 0,00000028 0,8 0,98 1,15 0,0000003 0,015 0,002 0,1 100 0,0130401 45909,328 0,15 0,3 0,008 1,5 0,5 1,74 T3-BK 0,00000038 0,8 0,98 1,15 0,0000004 0,015 0,002 0,1 100 0,0191093 48928,452 0,15 0,3 0,008 2,5 0,9 2,65 BK-S1 0,00000049 0,8 0,98 1,15 0,0000005 0,015 0,002 0,1 100 0,0255228 51346,228 0,15 0,3 0,008 2,2 0,7 2,5

No Jalur Pipa n D min/D

V min / V full

d/D Q peak / Q full

V peak/ V full

Page 19: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Instalasi Pengolahan Air Limbah

19

• Penggunaan ABR (Anaerobic Baffle Reactor) - Daerah Perancanaan dataran rendah - Jalan akses untuk pengurasan lumpur tersedia - Material untuk membangun unit ABR mudah didapat - Tidak perlu pengadukan secara mekanik

• Pemeliharaan ABR (Anaerobic Baffle Reactor) - Cek Scum atau busa pada setiap kompartmen - Lumpur dikuras 2-3 tahun sekali.

• Kekurangan ABR (Anaerobic Baffle Reactor) - Gas dan hasil effluen tidak stabil karena sesuai dengan inffluen

Page 20: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

Unit ABR

20

Page 21: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

KESIMPULAN

• KESIMPULAN 1. SPAL dengan sistem gravitasi dengan menggunakan slope penanaman. Diameter yang digunakan: a. SR = 100 mm b. Saluran Sekunder = 100 mm, 150 mm, 200 mm c. Saluran Primer = 250 mm 2. Volume ABR 4 m x 3 m x 2,5 m = 28,8 m2 3. RAB SPAL dan ABR = Rp 235.232.000 4. Prakiraan biaya untuk OM berkisar antara Rp 5.000 - Rp 20.000

21

Page 22: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

SARAN

• SARAN 1. Diperlukan tindak lanjut dari pemerintah untuk merealisasikan

perencanaan ini agar manfaatnya dapat dirasakan oleh warga

2. Diperlukan musyawarah dan membentuk kepanitiaan lebih lanjut agar dapat ditentukan prakiraan biaya secara pasti dan kerja bakti untuk OM

22

Page 23: Tugas Akhir RE-091324 - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-41102-3310100006-Presentation.pdf · Pembebanan SPAL 15 No Jalur Pipa Jumlah Beban Pendudu k Q Air Bersih

TERIMA KASIH

23