TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN METODE PDM (PRECEDENCE DIAGRAM METHOD) STUDI KASUS : PEMBANGUNAN JEMBATAN DESA RANTAU LIMAU MANIS, KECAMATAN TABIR ILIR, KABUPATEN MERANGIN, PROVINSI JAMBI Diajukan Sebagai Salah Satu Syarat Memperoleh Gelar Sarjana Teknik Pada Program Studi Teknik Sipil Fakultas Tenkik Sipil Dan Perencanaan Universitas Bung Hatta Oleh : NAMA : MOHD IRVAN NPM : 1610015211071 PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK SIPIL DAN PERENCANAAN UNIVERSITAS BUNG HATTA PADANG 2021
12

TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

Oct 27, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

TUGAS AKHIR

PERENCANAAN PENJADWALAN WAKTU DENGAN METODE PDM

(PRECEDENCE DIAGRAM METHOD)

STUDI KASUS : PEMBANGUNAN JEMBATAN DESA RANTAU LIMAU

MANIS, KECAMATAN TABIR ILIR, KABUPATEN MERANGIN,

PROVINSI JAMBI

Diajukan Sebagai Salah Satu Syarat Memperoleh Gelar Sarjana Teknik Pada

Program Studi Teknik Sipil Fakultas Tenkik Sipil Dan Perencanaan

Universitas Bung Hatta

Oleh :

NAMA : MOHD IRVAN

NPM : 1610015211071

PROGRAM STUDI TEKNIK SIPIL

FAKULTAS TEKNIK SIPIL DAN PERENCANAAN

UNIVERSITAS BUNG HATTA

PADANG

2021

Page 2: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …
Page 3: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …
Page 4: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …
Page 5: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

UNIVERSITAS BUNG HATTA

PERENCANAAN PENJADWALAN WAKTU DENGAN METODE PDM (PREDENCE

DIAGRAM METHOD) STUDI KASUS : PEMBANGUNAN JEMBATAN DESA

RANTAU LIMAU MANIS, KECAMATAN TABIR ILIR, KABUPATEN MERANGIN,

PROVINSI JAMBI

MohdIrvan1), IndraKhaidir2), RobbyPermata3)

Prodi Teknik Sipil, Fakultas Teknik Sipil dan Perencanaan, Universitas Bung Hatta, Padang Email : [email protected], [email protected], [email protected]

Abstrak

Untuk mendukung pertumbuhan ekonomi Pemerintah Kabupaten Merangin melakukan pembangunan

Jembatan Rantau Limau Manis Kabupaten Merangin yang bertujuan dapat menggantikan jembatan yang

sebelumnya sudah ada, karena jembatan sebelumnya sudah terlihat rusak. Pembangunan Jembatan Rantau

Limau Manis Kabupaten Merangin direalisasikan dengan biaya dari APBD (Anggaran Pendapatan Belanja

Daerah) Tahun 2019 dibawah pengawasan dari Dinas Pekerjaan Umum Propinsi Jambi. Yang mana untuk

Kontraktok yaitu PT. Wijaya Kesuma Mandiri dan untuk Konsultan yaitu PT. Wandra Cipta Engineering

Consultant. Pembangunan jembatan ini memiliki masa pelaksanaan dari tanggal 02 Juni 2020-22 Desember

2020. Proyek inilah yang akan dijadikan studi kasus pada penulisan tugas akhir, karena pada pelaksanaan

proyek tersebut terjadi keterlambatan dan banyak terjadi penjadwalan ulang pada berapa item pekerjaan.

.Penulis mencoba menerapkan metode ini pada pembangunan proyek tersebut agar durasi dan item

pekerjaan bisa dilaksanakan dengan waktu yang efektif. Oleh karena itu penulis melakukan perencanaan

penjadwalan waktu dengan menggunakan metode PDM. Metode PDM ini mendefenisikan proyek sebagai

suatu rangkaian kegiatan yang hanya terjadi sekali, dimana pelaksanaannya sejak awal sampai akhir

dibatasi oleh kurun waktu tertentu. Hasil penelitian diperoleh bahwa dengan metode PDM penyelesaian

proyek memiliki waktu penyelesaian proyek Pembangunan Jembatan Desa Rantau Limau Manis,

Kecamatan Tabir Ilir, Kabupaten Merangin, Provinsi Jambi diperoleh 168 hari. Perhitungan PT. Wijaya

Kesuma Mandiri menjadwalkan proyek Pembangunan Jembatan Desa Rantau Limau Manis, Kecamatan

Tabir Ilir, Kabupaten Merangin, Provinsi Jambi selesai dalam waktu 22 Desember 2020 , sedangkan

dengan perhitungan menggunakan metode PDM diperoleh waktu akhir penyelesaian proyek 07 Desember

2020.

Kata Kunci: Jembatan, perencanaan, penjadwalan waktu, metode PDM.

Pembimbing I

Indra Khaidir, ST, M.Sc

Pembimbing II

Robby Permata ST, MT, Ph.D

Page 6: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

KATA PENGANTAR

Puji syukur atas khadirat Allah subhanahu wa ta‟ala penulis ucapkan, yang telah

memberikan rahmat dan hidayah-Nya. Seiring dengan itu, penulis juga tidak lupa

mengirimkan shalawat dan salam kepada junjungan alam, yakni Rasulullah

Shalallahu ‘alaihi wassalam melalui perantaranya kita dapat merasakan dan

menikmati kehidupan yang penuh dengan perkembangan ilmu pengetahuan seperti

yang kita rasakan saat ini, Sehingga penulis dapat menyelsaiakan Tugas Akhir ini

dengan Judul “PERENCANAAN PENJADWALAN WAKTU DENGAN

METODE PDM (PRECEDENCE DIAGRAM METHOD) STUDI KASUS :

PEMBANGUNAN JEMBATAN DESA RANTAU LIMAU MANIS,

KECAMATAN TABIR ILIR, KABUPATEN MERANGIN, PROVINSI

JAMBI’’

Setelah mengalami serangkaian perbaiakan, baik kekurangan, kelengkapan data

maupun kesalahan-kesalahan dalam penulisan. Tugas Akhir ini merupakan salah

satu syarat mendapatkan gelas strata 1 (S-1) pada program Studi Teknik Sipil dan

Perencanaan Fakultas Teknik Sipil dan Perencanaan di Universitas Bung Hatta.

Dalam penyelesaian tugas akhir ini penulis banyak mendapatkan bimbingan dan

bantuan serta dorongan dan motivasi dari berbagai pihak, sehingga penulis dapat

menyelesaikan tugas akhir ini. Untuk itu dalam kesempatan ini dengan kerendahan

hati penulis ingin mengucapkan terima kasih yang sebanyak-banyaknya kepada :

1. Bapak Prof. Dr. Ir. Nasfryzal Carlo, M.Sc. selaku Dekan Fakultas Teknik Sipil

dan Perencanaan Unversitas Bung Hatta.

2. Ibu Dr. Rini Mulyani, S.T., M.Sc (Eng) selaku Ketua Prodi Teknik Sipil,

Fakultas Teknik Sipil dan Perencanaan Unversitas Bung Hatta

Bapak Indra khaidir, ST, M.Sc selaku Pembimbing I dan Bapak Robby

Permata, ST,.MT,.Ph.D selaku pembimbing II yang telah memberikan

bimbingan, arahan, masukan dan pengalaman beliau dalam penulisan Laporan

Tugas Akhir ini kepada penulis

3. Kedua orang tua dan keluarga penulis yang terhebat, sumber semangat penulis,

Berkat doa, motivasi dan dukungan yang tak terkira telah menjadikan penulis

semangat sehingga dapat menyelesaikan Laporan Tugas Akhir ini.

Page 7: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

4. Kekasih tercinta Feby Cinthya Cantika, S.ST yang telah banyak memberikan

semangat, motivasi, dan doanya bagi penulis untuk bisa menyelesaikan laporan

Tugas Akhir Ini.

5. Kawan-kawan Teknik Sipil Angkatan 2016 yang telah banyak memberikan

banyak memberikan semangat, motivasi, dan doanya bagi penulis untuk bisa

menyelesaikan laporan Tugas Akhir ini. Tetap semangat untuk 16.

Semoga bantuan yang telah diberikan menjadi amal ibadah dan diberikan balasan

setimpal dari Allah subhanahu wa ta‟ala. Aamiin. Penulis juga menyadari masih

banyak kelemahan baik dari segi isi maupun tata bahasa, untuk itu penulis berharap

kritik dan saran yang bersifat membangun dari pembaca demi kesempurnaan Tugas

Akhir ini. Akhir kata penulis mohon maaf bila ada kata-kata yang salah dalam

tulisan ini.

Wassalamu’alaikum Warrahmatullahi Wabarakatuh.

Padang, 24 Juni 2021

Mohd Irvan

Page 8: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

ii

DAFTAR ISI

TUGAS AKHIR ....................................................................................................... i

DAFTAR ISI ........................................................................................................... ii

DAFTAR GAMBAR ............................................................................................. iv

DAFTAR TABEL ................................................................................................... v

LAMPIRAN ........................................................................................................... vi

BAB I ...................................................................................................................... 1

PENDAHULUAN ................................................................................................... 1

1.1 Latar Belakang Masalah ................................................................................ 1

1.2 Rumusan Masalah ......................................................................................... 4

1.3 Tujuan Penulisan .......................................................................................... 4

1.4 Batasan Masalah............................................................................................ 4

1.5 Manfaat Penulisan ......................................................................................... 5

1.6 Sistematika Penulisan ................................................................................... 5

BAB II ..................................................................................................................... 6

TINJUAUAN PUSTAKA ....................................................................................... 6

2.1 Proyek ........................................................................................................... 6

2.2 Jenis-jenis Proyek ......................................................................................... 7

2.3 Ciri-ciri Proyek.............................................................................................. 8

2.4 Tahapan Siklus Proyek .................................................................................. 9

2.5 Jembatan ....................................................................................................... 9

2.5.1 Metode Pelaksanaan Pekerjaan ............................................................ 10

LINGKUP PEKERJAAN ................................................................................. 10

Divisi 1. Umum ................................................................................................. 10

Divisi 2. Drainase .............................................................................................. 10

Divisi 3. Pekerjaan Tanah dan Geosintetik ....................................................... 10

Divisi 5. Perkerasan Berbutir ............................................................................ 10

Divisi 7. Struktur ............................................................................................... 11

- Divisi 9. Pekerjaan Harian & Pekerjaan Lain-lain ..................................... 11

2.6 Manajemen Proyek...................................................................................... 12

2.6.1 Tujuan Manajemen Proyek .................................................................. 13

2.6.2 Tahapan Manajemen Proyek ................................................................ 13

2.7 Pengendalian Proyek Konstruksi ................................................................ 17

2.8 Kurva S ....................................................................................................... 19

2.9 Microsoft Project ........................................................................................ 19

Page 9: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

iii

2.10 Macam-macam metode analisis diagram jaringan kerja ........................... 19

2.11 Metode PDM (Precedence Diagram Method)........................................... 23

2.11.1Pengertian PDM .................................................................................. 23

2.11.2 Durasi Kegiatan .................................................................................. 27

2.11.3 Jalur Kritis .......................................................................................... 27

2.11.4 Jadwal Aktivitas ................................................................................. 28

2.12 Penelitian Terdahulu ................................................................................. 30

BAB III ................................................................................................................. 33

METODE PERENCANAAN ............................................................................... 33

3.1 ...................................................................................................................... 33

Metode Perencanaan ......................................................................................... 33

3.2 Sumber Data ................................................................................................ 33

3.3 Pengumpulan Data ................................................................................. 33

3.4 Analisa Pengolahan Data ............................................................................ 33

3.5 Perencanaan Metode PDM .......................................................................... 34

3.6 Langkah – langkah Penulisan Tugas Akhir ................................................ 35

BAB IV HASIL DAN PEMBAHASAN ............................................................. 36

4.1 Umum .......................................................................................................... 36

4.1.1 Analisis Data ........................................................................................ 36

4.1.2 Data Proyek .......................................................................................... 37

4.1.3 Jadwal Proyek ...................................................................................... 38

4.2 Pengolahan Data ..................................................................................... 39

4.2.1 Penyusunan Urutan Pekerjaan............................................................ 39

4.2.3 Menyusun Jaringan Kerja .................................................................... 41

4.3 Perhitungan ES, EF, LS dan LF .................................................................. 43

4.3.1 Perhitungan Earlies Start (ES) dan Earliest Finist (EF) ....................... 43

4.3.2 Perhitungan Latest Stars (LS) dan Latest Finist (LF) .......................... 48

4.4 Menghitung Float Time atau Slack ........................................................ 56

4.4.1 Perhitungan Total Float (TF)/ Slack .................................................... 56

4.4.2 Menentukan Lintasan Kritis ................................................................. 61

4.5 Hasil dan Pembahasan................................................................................. 62

BAB V ................................................................................................................... 67

PENUTUP ............................................................................................................. 67

5.1 Kesimpulan ................................................................................................. 67

5.2 Saran ............................................................................................................ 68

DAFTAR PUSTAKA ........................................................................................... 69

Page 10: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

iv

DAFTAR GAMBAR

Gambar 2. 1 Jembatan Tampak Samping dan Jembatan Tampak Atas ................ 11

Gambar 2. 2 Alternatif 1, lambang kegiatan ......................................................... 24

Gambar 2. 3 Alternatif 2, lambang kegiatan ......................................................... 24

Gambar 2. 4 Hubungan Finish to Start(FS) .......................................................... 25

Gambar 2. 5 Hubungan Start to Start (SS) ........................................................... 26

Gambar 2. 6 Hubungan Finish to Finish (FF) ...................................................... 26

Gambar 2. 7 Hubungan Start to Finish (SF) ......................................................... 27

Gambar 2. 8 Jadwal Aktifitas ................................................................................ 28

Gambar 3. 1 Langkah – Langkah Penulisan Tugas Akhir .................................... 35

Gambar 4. 1 Jaringan Kerja .................................................................................. 42

Gambar 4. 2 Jaringan Kerja dengan metode PDM ............................................... 55

Page 11: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

v

DAFTAR TABEL

Tabel 2. 1 Posisi Penelitian ................................................................................... 32

Tabel 4. 1 Data Teknis Proyek .............................................................................. 37

Tabel 4. 2 Durasi item perkejaan .......................................................................... 38

Tabel 4. 3 Urutan Aktivitas Pekerjaan .................................................................. 40

Tabel 4. 4 Perhitungan ES dan EF ........................................................................ 44

Tabel 4. 6 Perhitungan LS dan LF: ....................................................................... 49

Tabel 4. 7 Rekapitulasi Total Float....................................................................... 59

Tabel 4. 8 Pekerjaan yang bersifat kritis ............................................................... 61

Page 12: TUGAS AKHIR PERENCANAAN PENJADWALAN WAKTU DENGAN …

vi

LAMPIRAN

Lampiran 1. 1Diagram Jaringan PDM .................................................................. 70

Lampiran 1. 2 Diagram Jaringan PDM ................................................................. 71

Lampiran 1. 3 Jadwal Rencana Pelaksanaan Pekerjaan ........................................ 72

Lampiran 1. 4 Metode Pelaksanaan Pekerjaan Jembatan Rantau Limau Manis... 73

Lampiran 1.5 Gambar Rencana…………………………………………………119