Causes of Tube Failure1. Overheating.2. Erosion.3. Corrosion.4.
Material Defects.5. Manufacturing Defects.
OverheatingOverheating can be localised, extensive, prolonged or
of a short duration. Metallographic analysis indicates the
approximate temp. to which the tube was subjected before failure
occured. Observation of the grain growth & microstructure of
the failed tube material also indicates if the overheating was of a
prolonged or short duration.Water wall tube failure results in a
burst with a fish mouth opening. Occasionally cracks will also
appear up to length of 2 Mts. on either side of the burst.This may
lead the power station authorities to apprehend that the tube is of
the CRW type. Bursting occurs due to excessive reactive force cause
by change of state from water to steam. In case of SH tube failure
takes the form of a narrow opening with multiple stallite cracks.
The reasons for overheating of water wall or SH tubes are, 1.
Chocking with foreign material.2. Starvation due to,a) Improper
circulation.b) Insufficient flow3. Flame impingement4. Secondary
burning of fuel.5. Other causes.
Choking with foreign materialsForeign materials like mill
scales, weld slag, sand, electrodes bits, rust products, chips,
small tools, nuts etc. Which collect at the bends or weld joints
where the internal cross section is restricted will cause choking
of tubes. These materials enter the tube during various stages of
manufacture, shipping and / or erection. Choking of tube with
foreign materials will impede the flow fully or partially &
cause overheating.Precautions can be taken to mitigate tube choking
at various stages of manufacture, shipping, storage & erection.
By using TIG root welding for all SH coils at shop & site, the
problem of choking can be minimised by eliminating the construction
at the weld joints due to excessive weld penetration to check the
blocking of tube with foreign material an instrument called
contract flow meter (developed by CE research lab UK, &
manufactured by Land Pyrometers LTD, UK) can be used. This meter
can be used during the commissioning of new boiler to ensure that
there is not blockage of & in the case of operating boiler, it
can be used during overheating.
Starvation due to improper circulation:-Insufficient circulation
in the water walls may lead to departure from onset of nucleate
boiling & may lead to overheating. Which in turn will result in
tube failures. Where the failure is traced to improper circulation,
the same can be improved in the region of water wall by providing
additional downcorners / spider tubes to the existing
downcomers.
Starvation due to insufficient flow:-Starvation can occurs in SH
tubes due to an insufficient flow resulting in overheating. This is
generally observed in the binder tubes of the platen SH. These
binder coils have a number of bends & are longer in length than
the other coils in the platen. The flow through these binder coils
is, therefore, inadequate. The prolong overheating in such tubes
results in creep failure. Such failures can be avoided by replacing
the long binder tubes with shorter tubes, which in turn increases
internal flow, & prevents overheating. Overheating can also be
avoided by allowing cooler steam through the wrapper tubes of
platen to better cooling of the tube materials.The materials of the
bottom portion of the outermost coils of platen can also be
replaced by stainless steel to enhance their life since the bottom
most portion faces direct radiation from the furnace.
Flame ImpingementWater wall failures occur mostly near the
burners. This is due to the flame impingement from burners, which
get distorted in service. To avoid such failures new burner nozzles
such as honeycomb types, which resist distortion, are now
used.Additional peep holes can also be provided for better
monitoring of the flame & observation of the burner
tip.Arrangements could be made to supply mellowing air to bring
down air temperature wherever necessary so that the combustion
front can be kept away from the burner nozzles.
Secondary burning of fuel:-In certain cases oil from the oil gun
may flash on to the tubes & then burning takes place which
results in overheating the tubes. Even in coal fired boilers, the
unburnt fuel particles may catch fire at the top of the furnace or
in the second pass causing secondary combustion, explosion, or
overheating of the tubes. This can be avoided by proper control of
the atomisation of oil, coal particle size & the firing
rate.
Excessive airExcess air plays an important role in the heat
absorption pattern of various zones of the boiler. Too much of
excess air leads to cooler furnace & higher heat absorption
rates in convective paths. The too little amount of excess air
leads to higher furnance temperature resulting in higher radiation,
heat absorption & slagging problems.
In oil fired boilers too much of excess air is favourable to the
formation of SO3 due to the increased availability of O2 thereby
promoting a higher rate of low temp. corrosion. To avoid such
failure O2 content in flue gases should be measured periodically
during operation & adjustments made to achieve design values as
closely as possible. Further, to avoid overheating the flue gas
temperature in different zones should be closely monitored &
kept within the design limits.
Internal DepositsInferior quality of feed water leads to
internal deposits of salts & silica in the water wall tube.
This internal deposit will cause overheating of water wall tubes
leading to failure. To avoid this, the feed water of boiler water
quality should be maintained within the allowable limits as per the
international standards.
The carryover of salts by steam can cause deposits in the tubes
with consequent overheating & failure. To avoid this, the
salts, content in the drum water should be maintained as per the
standard operation with high water levels in drum could lead to
carryover of water drops & dissolved solids leading to internal
tube deposits in SH tubes. These deposits hinder heat transfer
& lead to increase in metal temperature & consequent tube
failure. Hence it is necessary to restrict the drum WATER LEVEL TO
THE prescribed limits under all operating conditions. Other
causesMal-operation can sometimes leads to overheating &
results in tube failure. When high-pressure heaters are out of
service, the convection SH O/L temperature can shoot up leading to
overheating of tubes. This can be avoided by suitable control of
the excess air & the boiler load. During hot restart if the
flow of auxiliary steam from the drum tap off point is high it will
result in a reduced flow through the SH which in turn will lead to
overheating. EROSIONErosion is a second major cause of tube
failure. The tube wall thickness gets reduced due to erosion &
when the thickness is not sufficient to withstand the operating
pressure and temperature of the tube, the tube will fail.
Erosion of SH & economiser tube may be due to following
reasonsi) Flue gas erosion.ii) Erosion due to steam or water.
Flue gas ErosionThe rate of erosion is proportional to the cube
of velocity. The ash content of the Indian coals is of more
abrasive in nature containing high silica & alumina. Due to the
above, if the velocity of the flue gas at narrow gaps between coils
& walls & SH coils and ash hoppers below them is high, then
erosion may occurs in these zones. Therefore the boiler have to be
designed with 15m/s velocities as for as possible.A typical ash
analysis data is given below :Silica -- 55.5 to 56.5%Alumina --
27.3 to 27.9%Unburnt carbon -- 4.4 to 6.2%FeO -- 5.3 to 6.7%Lime --
1.37 to 2.16%Sulphates-- 0.5 to 0.68%
The flue gas erosion in the horizontal SH & economiser can
be prevented by providing baffles. The flue gas erosion in the
bands of the convection SH in the horizontal pass can be prevented
by increasing the height of refractory lining of the ash hoppers in
front of the coils.
Erosion due to steam or waterWhenever there is a tube failure
the water or steam from the faulty tube escapes in the form of a
high velocity jet & when it impinges on the adjacent tube they
get eroded. If the boiler is not shutdown immediately after
detection of the failure & allowed operating for a protected
period the damage due to steam or water erosion will be
considerable.
Additionally, sometimes leakage from the soot blowers or wall
blowers causes erosion of water wall, SH or economiser tubes. In
some boiler, vertical bar type soot blowers have caused tube
failures in the horizontal SH & RH & to overcome this the
sort blowers should be moved from the ceiling to the sidewalls.
Corrosion This can be mainly grouped into two types 1) External
corrosion due to depositing of chemicals.2) Internal corrosion
taking place inside the tube due to impurities in steam and
water.
1) External corrosion due to depositing of chemicals carried by
ash.On review of ash analysis detailed under flue errosion, it can
be seen that ash consists of sulfate up to 0.5 to 0.681. This type
of corrosion results mainly from the deposits of ash on tube
surface. The deposits may be classified either as slagging or
fouling.
SlaggingThis is the deposition of molten or partially fused
particles of fuel constituents (non-combustible) on furnace tube
surface. Though it is usually is associated on furnace tube
surface, slagging can also occurs in screen tube and in the super
heater when molten ash carried over into these solutions and is
exposed to excessively high gas temperature.
FoulingFouling on other hand is the condensation of combustible
constituents such as sodium sulphate on fly ash particles and on
boiler tube in area of the unit where temperature are such that the
constituents are remain in the liquid state. The combustibles, fly
ash, and flue gas react chemically to form the deposit.
Phosphate depositThis is also similar to the sodium deposits
fouling, which are initiated by the attack of acidic phosphorous
compounds on the tube metal & the fly ash particles. Indian
coals do not contain phosphorous as one of the major constituents
and as such this type of corrosion is rarely expected.
Low Temperate Corrosion This is caused by sulphuric acid, &
can occur in the economisers of some units if the feed water temp.
is lower than about 150C. However the feed water temperature is
most of the utility boilers & the sulphur content of the coal
burnt are such that dew point problems already rarely encountered.
Condensation problem further down stream where lower temperature
exists may corrode air heater, precipitator, hoppers, fans, ducts
& stacks. As the sulpher content is more in the fuel oil &
also as the flue gas temperature will be low during starting
usually the air preheaters will be experiencing the cold corrosion
problems. To overcome this problem, steam coiled Air preheater
should be kept in service till flue gas temperature rises above
300C.
RemedyAll the deposits, which cause corrosion of the above
types, are easily soluble in water & will be loose also. This
deposit can be cleaned by normal operation of soot blowers. When
this method is not totally effective, water washing during outage
is recommended. It is very important to schedule water washing so
that the tube surfaces can be dried out immediately after cleaning,
as otherwise corrosion will occur. A good approach is to water just
before returning a boiler to service. If this is not possible, fire
at a low rate until tubes are dry.Design ImprovementsIn coal fired
boilers most major corrosion problems are caused by coal ash with
in a specific temp. range certain coal produce liquid ash compounds
that are very corrosive to all conventional boiler materials. This
temp. range normally extend from about 1000F to 1200F essentially
restricts attack to the SH & RH .Engineers weigh carefully the
four major factors that influence the severity of coal ash
corrosion viz. Ash properties, ash deposition rate, tube external
temperature, & tube chromium content, before finalizing the
design of SH & RH surfaces. If the high temp. Corrosion occurs
inspite of design efforts, the option for correcting the problems
are limited; for example the following remedial measures may be
resorted to. 1) Replace damaged tubes with one of higher Chromium
Content.2) Switch to a fuel with more favourable ash
characteristics. 3) Install stainless steel tube shields. These
shields will effectively keep the liquid ash from the tube surface
& operate at temperature above that at which liquid phase can
exist. Extensive shielding however, inhibits heat transfer
performance.
Internal corrosion due to impurities in water &
steamInternal corrosion is mainly due to improper feed water
treatment. The most prevalent forms of waterside attack in the
drumtype utility boiler are, i) Hydrogen damage.ii) Bulks under
deposit corrosion. iii) Corrosion fatigue.iv) Stress corrosion. v)
Steam blanketting. vi) Oxidation. vii) Pitting. viii) Galvanic
attack.ix) Caustic embrittlement.
i) Hydrogen Damage This induces brittle fracture & will
occur beneath a relatively dense deposit when boiler water pH is
too low. The accepted thereby of this type of attacks is that the
hydrogen atoms are produced between the deposit and the tube
surface. They in turn react with cementite a hard brittle iron
compound at the grain boundaries of the tube material to form
molecular methane gas, which removes carbon from metal weakening it
by creating fissures in its grain structure.The pressure of the gas
that is formed literally blows the material apart. This damage is
most common where condenser leakage occurs in units cooled by sea
water. Some metal loss may be caused by corrosion mechanism, but
the tube which failure would occur.ii) Bulk Under deposit Corrosion
This is caused by the concentration of traces amounts so soluble
corrosive compounds usually strong alkalies, such as sodium
hydroxide between the tube walls & a relatively porous deposit.
(60-90 % porosity compared to theoretically dense magnetite). The
term caustic gouging is sometimes used to describe this form of
corrosion, which is characterised by rapid attack & subsequent
tube failure.iii) Corrosion Fatigue Material that undergoes cyclic
strain may suffer fatigue failure. The strain can be mechanical in
nature such as vibration or thermal such as soot blower condense
quenching, corrosion or oxidation can accelerate failure in other
words, failure may occur after fewer cycles at a lower level or
strain in a corrosive environment.iv) Stress Corrosion
CrackingPortion of austenitic stainless steel SH elements
containing residual stress such as stress supports & ring welds
are susceptible to cracking in high temp. water containing chloride
or hydroxide compounds & oxygen. Though such condition are
relatively uncommon, they do occurs after because of operator
error. Stress corrosion attack on the secondary SH tube was caused
by inadvertent use of a boil out cleaning solution containing
caustic. The boiler was fired only a few hours, but the damage was
significant, and tube replacement was required.v) Steam
Blanketting: -Steam blanketting phenomenon occurs in tubes, which
are slightly inclined, for example flow started slag screen tubes
since the steam flow in some what restricted resulting in
obstruction for heat transfer. In such environment if the feed
water possesses caustic soda, it may give rise to general wasting
of the crown of the tube or the formation of grooves at the water
line.vi) Oxidation Oxidation of low alloy ferritic steels operating
at temp. above about 450C is a natural phenomenon in the boiler
water side environment. All materials used in high temp. SH &
RH tubing are subjected to oxidation, although at different rates.
Problems arise when oxide scale on the tubes internal surface
become so thick that differential expansion between the oxide and
the parent metal results in spalling of the oxide from the metal
surface a process called exfoliation. The loose flakes are hard
& brittle & generally range from the size of a match HEAD
to that of a quarter. Loose scale can clog tubes at bends causing
their failure by overheating.PittingThis is mainly due to the
difference in effective electrode potential between adjacent areas
of the metal surface. This can result due to the following
reasons.1. Differential heat treatment resulting in localised
difference in stress concentration.2. Surface irregularities such
as scratches & cuts developing during manufacturing.3.
Different concentration in dissolved compounds. The effect of
individual factor depends upon their relative magnitude & most
of them are independent.Galvanic Attack The corrosion of the less
noble member of a pair of metal which are joined together is called
Galvanic corrosion or Dissimilar metal corrosion. The effects of
galvanic corrosion are often serious especially in sea water power
station as feed water conditions are conductive, since at
temperature that occurs in the high pressure boiler tubing, are
very high Galvanic attack will be more severe in these
areas.Caustic embrittlementThis is due to the caustic ALKALINITY
formed in the drum & the scale of this caustic soda reacts with
the metal & may result in cracking at welding joints where the
welding is weakMaterial DefectsSome of the tube failures in the
boiler may be due to the usage of the defective raw materials.
Though different quality control measurement are adopted in various
stages of the manufacturing, defective materials may find there way
in rare cases and cause failure. High quality of the materials can
be ensured by selecting tubes, which have undergone ultrasonic
tests, & by resorting to strict quality control inspection
procedure. Successful waterside corrosion control requires careful
selection of the material used throughout the steam cycle including
the feed water heaters & condensers.Manufacturing defects Tube
failure may occur due to the defect in the manufacturing process,
such as weld defect, & improper heat treatment. Mix up of
material sometimes lead to failure because of the wrong usage of
materials.Creep and fatigue are very important factors while
designing the thermal power plant equipment. Metals undergoing high
temperature will also be subject both creep and fatigue.
Creep When metal stressed at sufficiently high temperature it
will continue to deform with time although at a relatively low
rate. This process is known as creep and is of major importance in
selecting metals for service in power plant. This is because at
temperature much above 350C (660F) steels are subjected to this
phenomenon. The figure illustrated that the creep process can be
viewed in three stages. The primary stage in which the initially
high rate of strain remain constant over a period of time, the
second stage in which strain rate remain constant over a period of
time, and the tertiary stage in which strain rate increases
continuously and which culminates in rupture. This behaviour may be
explained in terms of a balance between the effect of straining
which are to be strengthen the material and increase its resistance
to further deformation and effect of heating which are to be soften
the material and decrease resistance to deformation. Thus strain
hardening predominates initially until the strain rate falls to
level at which the opposing influence are in balance accompanied by
continuous deformation until the tertiary stage is reached, where
loss of strength leads to fracture.Fatigue Metals undergoing high
temperature service may also be subjected to fatigue. This process
is one in which failure may arise exposer to many cycle of
alternating stress, with or without super imposition of mean
stress. This type of failure is comparatively rare in power plant.
The predominant failure is creep not fatigue.In power plant, it is
possible to encounter situation that are classified as thermal
fatigue. In these frequency of straining is given by the number of
stops and starts endured the full life of plant (say 5000 to
10,000). The level of strain is enhanced by the creation of thermal
gradient during operation, and/or by geometric strain
concentration. This problem is believed to involve both creep and
fatigue process.Factors affecting fatigue lifeThe rate of cycle
loading has only small effect on fatigue strength. Fatigue strength
increase with increasing rate of cycling probably because of the
increased strain rate.i) The form of the stress cycle such as
square, triangular or sinusoidal wave has no effect on the fatigue
life.ii) The environment in which component undergoes stress
reversal has marked effects on fatigue life. The fatigue life in
vacuum is about 10 times more than that in moist air. This clearly
indicates that the environment has a corrosive effect and reduce
the fatigue life. Fatigue occurring under the specific corrosive
environmental is caused corrosion fatigue.iii) Size of component
has no effect on fatigue life if component is identical one another
in all respects such as defect microstructure, inclusion, etc.
except size. However in certain cases it has been observed that
larger size less is a fatigue life. The decrease fatigue strength
is more for high strength material. This is due to more chance of
imperfection or stress rises in large size components.iv) Stress
gradient has strong effect on fatigue life. Higher stress gradient,
lesser is fatigue life.v) An increase in temperature above room
temperature decrease the fatigue life to increase in the crack
growth rate. Decrease in temperature below room temperature
increase the fatigue life.
Procedure For Failure Investigation & Collection Of Failed
SamplesThe causes for failures are evaluated by removing carefully
the failed material (eg. Tube) along with deposits if present. It
is preferable to pack them with polythene wrappers & box, such
that no corrosion & mechanical damage occur during transits. If
the deposits are loose, water side & fire side deposit are
collected in separate polythene bags with rigid tags. The flame cut
region should be at least 200mm away from the region of failure
since heat produced during flame cutting will change the
microstructure, if the cut region is closed to fail region. For
comparison, it is preferable to have good portion (about 300mm) of
the tube (along with the deposit if it is present) which is
considerably away from the failed region. The samples of material,
which failed due to brittle fracture, should be taken out (if it is
possible) & using rust preventive coatings should protect
fractured facets. In some cases in site micro examination is
carried out when specimen could not be cut or removed. This
technique is also used for fracture analysis. In certain cases it
becomes essential for the metallurgist or chemist to visit the site
& have first hand information regarding the location and
overall nature of failed tubes or any other components. These have
to watch the performance under the existing condition at site. This
will help in the interpretation of complex failures.
1. Corrosion Due to corrosion the normal structure of the
material which consists of ferrite & pearlite will change from
ferrite to ferritic & spheroidisition of carbides occur along
the grain boundaries.2. Erosion Due to erosion the normal structure
will change from pearlite to pearritic & spheroidisition of
carbides occur along the grain boundaries.3. CreepsDue to creep the
grain growth occurs along the boundaries which weakness the
material strength & due to which the voids are formed along the
boundaries & in case of prolonged period these voids combine
& fracture takes place.Remedial MeasuresThe corrosion in
general is resulting due to the oxygen present in feed water &
the pH value of feed water. Oxygen may be carried over into boiler
through make up water leaks, etc. Even the minute quantity of O2 is
capable of causing sever corrosion in the boiler working at high
pressure. Since the O2 content carried over the steam will go on
increasing as the pressure of the boiler increases.The table below
shows how the O2 content carried over to steam increases as the
pressure increases.Boiler pressure kg/cm2O2 in feed water: O2 in
steam
12.65000:1
425000:3.2
705000:5.3
1405000:10
Corrosion related problems could generally be avoided if,1.
Recommended water treatment controls are followed.2. Corrosion
products formed in the feed water system are kept within specific
limit.3. Feed water O2 concentration properly controlled.4. Proper
precautions are taken during chemical cleaning operation to prevent
metal attack.5. Drum internal & drum level controls are
maintained in good condition.6. Silica concentration in the boiler
is controlled within limits7. Corrosion products formed in the feed
water system should be minimised by proper phosphate dozing &
hydrazine dosing.8. Feed water O2 concentration should be
controlled by proper deaeration employing effective deaerator.In
modern boiler hydrazine dosing is adopted to effectively remove the
oxygen.N2H4 + O2 N2 + 2H2OThe possible measure to minimise fire
side corrosion/erosion 1) Modifying the physical or chemical
characteristics of deposits with the addition of chemicals. They
may be introduced either by adding with fuel or injecting into the
furnace or sprayed to external surfaces of the tubes. Addition such
as silica based compound, lime, magnesia etc. have been reported to
be useful by way of either raising ash softening temperature or
fixing SO2 from high sulphur coal.2) Use of coating to improve
corrosion or erosion resistance.3) Periodic removal of deposits by
blowing of compressed air or steam.4) Design modification such as
avoidance of sharp bends in the path of flue gas to avoid local
high velocity, decreasing the flue gas velocity to an optimum level
improving combustion condition etc.5) Reducing the ash content of
the coal by using washed or blended coal.6) Use of thicker tubes or
faceted tubes in the corrosion zone.7) Replacement of tubing with
more corrosion resistant tubing.8) Resistance to erosion should
require a hard brittle tube material, which would be unsuitable for
pressure part use. For this reason the pressure part are required
to be designed to allow for a rate of material removal by erosion
within their design life.
Conclusion It is observed from the various failures at various
power stations. Research Institute suggests them to follow the
following practices during operation to avoid frequent failure of
boiler tubes & thus prevents the frequency of outages.1. Proper
operation of boiler whithin the permissible limits of various
parameters.2. Shrouding, shielding the areas, which are prone to
erosion & proper inspection of tube elements during overhaul,
may help to reduce the outages.3. Particular care for operation of
oil guns, proper distribution of secondary air and total airflow
& proper soot blower operation may help to reduce outages.4.
Soot blowers operation, proper care to be taken from retraction or
leaky poppet valve to avoid erosion of nearby tubes may help to
reduce tube failure considerably. Wall soot blowers should be
properly aligned for hot operation of the blower considering the
expansion of furnace & structure.5. Sudden variation of loads
& abnormal operation beyond permissible limits should be
avoided.6. Proper purging of boiler should be carried out during
start up & after every shutdowns.7. Feed water quality should
be maintained within permissible limit.8. Start up fuel
automisation should be checked for its proper operation.