Top Banner
TSO-DSO Samarbete i Sverige Etablering av Svensk arbetsgrupp kopplat till CIGRE´ C2-C6 JWG 36 Svk Driftråd, möte 2016-03-08 Ulf Moberg, Per Wikström & Christer Norlander Svk
12

TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Sep 22, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

TSO-DSO Samarbete i Sverige

Etablering av Svensk arbetsgrupp kopplat till

CIGRE´ C2-C6 JWG 36

Svk Driftråd, möte 2016-03-08 Ulf Moberg, Per Wikström & Christer Norlander Svk

Page 2: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Bakgrund

> Det framtida elsystemet

> Förändrade roller och ansvar

> Projekt Driftsäkerhet

> En fråga som får allt större fokus

> Att sortera ut de här rollerna kommer att vara viktigt för systemets driftsäkerhet

och anpassning och även för marknadsdesignen

Page 3: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Bakgrund

> Cigré WG - ”System Operation Emphasizing DSO/TSO

Interaction and Coordination”

> ENTSO-E projekt - ”TSO-DSO cooperation"

> InnoGrid 2020+ – ”The Distribution and Transmission Research

and Innovation Conference”

> På programmet finns frågor som rör de nya förutsättningar för DSO:er och nya

gränssnittet mellan DSO:er och TSO:er

Page 4: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Bakgrund

EDSO President Christian Buchel:

> “EDSO wants to be the interface between Europe’s DSOs and

the European institutions, promoting the development and

large-scale testing of smart grid models and technologies in

real-life situations, new market designs and regulation.”

Page 5: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Vilket arbete pågår inom Svk

> Ellagsöversyn – ett modernt systemansvar.

> Vi har även börjat titta på gränsytan Systemansvarig –

Nätägare – Nätägare.

> Inom ramarna för driftsäkerhetsprojektet tittar vi på

systemtjänsterna.

> Leveranssäkerhet – hela kedjan

Page 6: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Lyon (France), 15-18 June 2015

Personalforum Energie

Köln, 06.11.2014

Dr. Katharina Herrmann

source: dena-Verteilnetzstudie, 2012

Past: Central generation capacity Today: Decentralised generation capacities

1 MN

Generators

1 MN

controllable

loads

Energy distribution has changed dramatically

TSO

DSO

110-kV-MV/LV

TSO

DSO DSO

110-kV-MV/LV

TSO

380-kV/220-KV

TSO

380-kV/220-KV

Page 7: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Lyon (France), 15-18 June 2015

Energiewende + Cooperation = Success

System responsibility lies with the TSO

Rules of coordinated operation evolving for 50

years

New players (RES) have to be attracted to deliver

ancillary services

DSOs connect most of RES to the grid and enable

exploitation of such potentials

Cascading principles ensure that all players in the

energy system are included

Such principles have to be developed in a joint effort

DSO Working Group (ARGE VNB Ost) was set up in

due time

The ARGE, in collaboration with 50Hertz, is

developing solutions and performing pilot projects

Page 8: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Lyon (France), 15-18 June 2015

Personalforum Energie

Köln, 06.11.2014

Dr. Katharina Herrmann

Key elements of the agreement

Further development of ancillary services

to integrate RES-based power generation

Better coordination of grid and system

operations

Direct exchange of operating data

Performance of pilot projects

Joint efforts for legal and regulatory

changes

10-point program – Milestones of cooperation between

DSOs and TSO 50Hertz

http://www.50hertz.com/Portals/3/Content/Dokumente/Medien/Positionspapiere/20140915_10-Punkte-Programm_Systemdienstleistungen-Kurzfassung.pdf

http://www.50hertz.com/Portals/3/Content/Dokumente/Medien/Positionspapiere/10_Punkte_Programm_Systemsicherheit-Langfassung.pdf

Page 9: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Lyon (France), 15-18 June 2015

Black start and

islanding potential

Commissioning with/without

energisation

Coordination across

grid levels (concepts)

Ancillary services as well as market- and grid-related measures

Frequency control

Voltage control

Restoring supply

Operational management

Primary control reserve

Secondary control reserve

Minute reserve supply

Switchable and interruptible loads

Automatic

frequency relays

Feed-in management

Redispatch / congestion management

Operational planning /

disconnection planning

Reserve power plants

Data interchange (energy information network)

Interaction between measures needs to be considered! What will be the „green“ share in future?

Reactive power control

Control of generating units

Operation of compensation resources

Short-circuit power

Transformer stepping and

switchover

Page 10: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Syfte och Mål

> Att skapa samförstånd och samverkansformer mellan TSO – DSO:er

> Att etablera en gemensam Svensk arbetsgrupp

> Nuläge

> Trender

> Identifierade problemställningar

> Rapportering i Svk Driftråd

> Referensgrupp mot CIGRE´ arbetsgrupp C2 – C6 JWG 36

(uppstartad)

Page 11: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

Att här och nu

> Besluta om deltagare, Convenor, tidplan

> ( Ej för stort eller för formellt styrt, viktigt med framdrift och

effektivt arbete med icke förutfattade ideér)

> Att med föreslagna deltagare ta fram mandat och uppdrag

> Rapportering och hur arbetet skall slutgiltigt redovisas

> Vilka andra ”parter”, myndigheter, organisationer kan önskas ha

intresse

Page 12: TSO-DSO Samarbete i Sverige - Svenska kraftnät · DSO Working Group (ARGE VNB Ost) was set up in due time The ARGE, in collaboration with 50Hertz, is developing solutions and performing

TSO

380 kV

220 kV

110 kV

20/10 kV

380 V

Dispersed

Generation

Industry

Households

Utilities

TS

O-G

rid

DS

O-G

rid

Bulk-Industry

DSO

Conventional

Generation

Grid responsibility TSO versus DSO

according to voltage levels in Germany

CIGRE Session 2014 - Opening Panel | Klaus Kleinekorte | 25th August 2014 | © Amprion 12