Top Banner
Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors Authority Presented by Susan Martinovich
11

Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

Dec 17, 2015

Download

Documents

Randall West
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

Tropicana Avenue To Blue Diamond Road

I-15 South Design-Build

Project

Paving the Way to a More Mobile Las Vegas

Presented to

Las Vegas Convention and Visitors Authority

Presented by

Susan Martinovich

Page 2: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

Improvements to I-15 from Tropicana Ave. to South of Blue Diamond Rd., including:

Widening I-15

Addition of Collector Distributor roads

Improved ramps at interchanges Tropicana Avenue Russell Road I-215 Blue Diamond Road Silverado Ranch Blvd

What is the I-15 South Design-Build

Project?

Page 3: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

Improvements to I-15 from Tropicana Ave. to south of Blue Diamond Rd., including:

New bridges over I-15 at Warm Springs Road

and Sunset Road

Landscaping and Aesthetics

Intelligent Transportation System Ramp Meters Variable Message Signs Cameras

What is the I-15 South Design-Build

Project?

Page 4: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

I-15 South Design-Build Project

Blue Diamond Rd.

Silverado Ranch Blvd.

Russell Rd.

215

Tropicana Ave.

Page 5: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

• Design-Build Lump Sum Contact

$246,500,000

• Prelim. Engr. (includes procurement)

$16,000,000• Construction Engineering

$17,000,000

• Incentives, Escalations, and Utilities

$6,000,000

Project Costs

Page 6: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

• Notice to Proceed – September 2009

• Design substantially completed – Fall

2010

• Construction began – December 2009

• All I-15 Lanes completed and open -

March 2012

• Project Completion – Spring 2012

Schedule

Page 7: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

• Design - 95% complete

• Construction - 48 % complete

Project Status

Page 8: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

Budget/Cash

Flow

Page 9: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

• Currently 300+/- working on design and construction

• Peak employment estimated at 400+/-

Employment

Page 10: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

• Southbound I-15 auxiliary lane and 2-lane off ramp to Silverado Ranch Road - Open

• Northbound I-15 Auxiliary lane from Silverado Ranch - Open

• Sunset Bridge - Under Construction• I-15/I-215 interchange - Under Construction• C-D Roads and bridges - Under Construction• Russell Road (widening) - Under Construction

Construction to Date

Page 11: Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors.

Upcoming

Milestones• Sunset Bridge • Open January 13

• Warm Springs Bridge• To be demolished Feb 2011• To re-open as 6-lane bridge

Spring 2012

• I-15/ I-215 Construction• To be complete Feb 2012

• Russell Road Widening• To be complete Aug 2011