-
Control Survey - Traversing*CONTROL SURVEYControl the principle
of tying measurements together in such a way as to produce a survey
which is accurate in proportion and scale.The form of control to be
provided depend on the type of survey and the accuracy
demanded.Control consists of traverse survey, triangulation or
trilateration, GPSControl survey provides a framework of survey
points whose relative positions are known.
Control Survey - Traversing
-
Control Survey - Traversing*Traverse surveyMost economical
methodProvide a higher standard of accuracy of control in terms of
time and moneyWidely usedFlexible method of providing control for
site surveys
Control Survey - Traversing
-
Control Survey - Traversing*Traverse surveyDefinitionsTraverseA
series of consecutive lines whose lengths and directions have been
determined from field measurements. Lines are known as legs and end
points pf the lines as stations.TraversingThe act of establishing
traverse stations and making the necessary measurements
Control Survey - Traversing
-
Control Survey - Traversing*Types of Traverse and
classificationClosed Traverse1. Loop. The lines starts and finish
on the same point.2. Link. The lines close on a point of known
position.Open TraverseThese commence at a known point and finish at
an unknown point.Generally be avoided.Traverse may be classified by
the accuracy attained typically precise, semi precise or low
accuracy.
Precise - An accuracy of greater than 1:10000 is expected.Semi
precise - An accuracy of up to 1:10000 or better.Low accuracy an
accuracy less than 1 : 5000
Control Survey - Traversing
-
Control Survey - Traversing*Closed TraverseClosed traverses
provide checks on the measured angles and distancesBecause of this
ability to check the measurements and the results mathematically
adjusted, closed traverses are more desirable.
Control Survey - Traversing
-
Control Survey - Traversing*Appropriate uses of
traversingTraverse survey will be a suitable method if:Control is
to be provided for a site surveyTape and offset linear survey
techniques are inadequate to meet the taskThe accuracy demanded is
grater than can be achieved by tape and offsets surveyThe
introduction of traversing into tape and offset will reduce the
cost and the duration of the job
Control Survey - Traversing
-
Control Survey - Traversing*Traversing FieldworkChoose suitable
equipment and the accuracy requiredCarry out a reconnaissance.
Choose stations positions carefullyBuild, protect and witness
stations. Prepare the witnessing stationsMeasure each traverse legs
at least twice once in each directions.Measure each traverse angle.
Take at least 2 rounds at every station
Control Survey - Traversing
-
Control Survey - Traversing
Control Survey - Traversing
-
Control Survey - Traversing*Traverse ComputationsPrepare a
traverse abstract. Sketch showing all measurements LHAs and
distances, starting data and direction of workingEnsure angles are
closeCalculate WCBsCalculate the coordinate differencesCalculate
the traverse accuracyIf acceptable distribute misclosureCalculate
the final coordinates
Control Survey - Traversing
-
Control Survey - Traversing*1. Traverse AbstractAll lengths
corrected and reduced to horizontalAll angles are mean observed
LHAsGiven Data: WCB AF = 70 00 00Coordinates of A = 500.00 mE,
1000.00 mN
Control Survey - Traversing
-
Control Survey - Traversing*2. Ensure that the angles closeIn
polygon traverse, angular misclosure are found by comparing the
observed angles with one of the following theoretical valueSum of
internal angles = (2n - 4) x 90Sum of external angles = (2n + 4) x
90
Control Survey - Traversing
-
Control Survey - Traversing*Allowable Angular MisclosureThe
allowable misclosure is given by
where K is a multiplication factor of 1 to 3S is the smallest
reading interval on the theodolite in secondsn is the number of
angles measured
Control Survey - Traversing
-
Control Survey - Traversing*Adjustment When the actual
misclosure is known and is compared to its allowable value, two
cases arises:1. If misclosure is acceptable (less than its
allowable) it is divided equally between observed angles2. If its
greater than allowable then angles should be re-measured if no
gross error can be calculated in the angle booking.
Control Survey - Traversing
-
Control Survey - Traversing*3. Calculate WCBsThe forward WCBs of
all traverse legs are required.
Forward Brg. YZ = Back Brg. YX + LHA at Y and in general
:Forward Brg. = Back Bearing + LHAThe forward Brg. of a line
differs from its back by 180
Control Survey - Traversing
-
Control Survey - Traversing*4. Calculate Coordinate DifferencesE
= D. Sin N = D. Cos represent the WCB of the line.
Control Survey - Traversing
-
Control Survey - Traversing*5. Calculate the traverse
accuracyFor a Polygon traverse (theoretically) E = 0 and N=
0Misclosure in Easting =eE = EMisclosure in Northing =eN = N
Linear misclosure = e = (eE2 + eN2)Fractional Linear Misclosure
= FLM = 1 in (D/e)
Control Survey - Traversing
-
Control Survey - Traversing*6. Distributing Linear misclosureIf
the misclosure is acceptable then distributeBowditch Method -
proportional to leg distancesTransit Method proportional to E and
Northing ValuesEqual Adjustment
Control Survey - Traversing
-
Control Survey - Traversing*7. Calculate the final
coordinatesThe adjustments are applied to the original partial
eastings and partial northings values to give the Adjusted partial
eastings and partial northings values.Starting from the initial
known coordinates the Adjusted partial eastings and partila
northings are applied in turn from station to station to give the
final coordinates.As a check final coordinates of the known finish
station are calculated and they must agree exactly with the known
values.
Control Survey - Traversing
-
Control Survey - Traversing*Traverse plottingDraw an accurate
coordinate grid at the required scalePlot the traverse stations.
Scale equal distances along the grid linesJoin the stations to form
traverse linesMeasure these as a check
Control Survey - Traversing
-
Traverse specificationGeneral - general engineering work include
site surveying and setting out1 in 5000 to 1 in 50000(angular
measurement) Electronic theodolite or total station (distance
measurement) Total station or steel
Control Survey - Traversing*
Control Survey - Traversing
**