Jan 03, 2016
TRB Session 513 - January 23, 2007
Transportation Research Board
Session 513 - Lessons Learned from Large
Airport Development
“Orlando Airport Experience”
Transportation Research Board
Session 513 - Lessons Learned from Large
Airport Development
“Orlando Airport Experience”
TRB Session 513 - January 23, 2007
Airport Statistics and BackgroundAirport Statistics and Background
Capital Improvement PlanCapital Improvement Plan
Lessons LearnedLessons Learned
Planning & DesignPlanning & Design
Land UseLand Use
OtherOther
Airport Statistics and BackgroundAirport Statistics and Background
Capital Improvement PlanCapital Improvement Plan
Lessons LearnedLessons Learned
Planning & DesignPlanning & Design
Land UseLand Use
OtherOther
AgendaAgenda
TRB Session 513 - January 23, 2007
Airport Statistics and BackgroundAirport Statistics and Background
TRB Session 513 - January 23, 2007
13,300 Acres (5,400 hectares) 13,300 Acres (5,400 hectares)
34.7 Million Annual Passengers34.7 Million Annual Passengers
95,000 Average Daily Passengers95,000 Average Daily Passengers
44thth Busiest O&D Domestic Airport Busiest O&D Domestic Airport
Busiest Passenger Airport in the State of FloridaBusiest Passenger Airport in the State of Florida
354,000 Annual Airport Operations 354,000 Annual Airport Operations
13,300 Acres (5,400 hectares) 13,300 Acres (5,400 hectares)
34.7 Million Annual Passengers34.7 Million Annual Passengers
95,000 Average Daily Passengers95,000 Average Daily Passengers
44thth Busiest O&D Domestic Airport Busiest O&D Domestic Airport
Busiest Passenger Airport in the State of FloridaBusiest Passenger Airport in the State of Florida
354,000 Annual Airport Operations 354,000 Annual Airport Operations
By The NumbersOrlando International Airport
(Thru November 30, 2006)
By The NumbersOrlando International Airport
(Thru November 30, 2006)
TRB Session 513 - January 23, 2007
Airport Today
4 Runways Landside Terminal 4 Airsides
Airport Today
4 Runways Landside Terminal 4 Airsides
TRB Session 513 - January 23, 2007
Airside 1Airside 1
Airside 3Airside 3 Airside 4Airside 4
Airside 2Airside 2
TRB Session 513 - January 23, 2007
Actual passenger traffic compared to forecast
Actual passenger traffic compared to forecast
2000-2014
Source: Actual-GOAA records, Forecast-Leigh Fisher Associates, John F. Brown Company.Contact: GOAA Marketing
9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 9123 6 920002001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
24.0
26.0
28.0
30.0
32.0
34.0
36.0
38.0
40.0
Mill
ion
An
nu
al Pass
en
gers
(M
AP)
Actual Traffic
Actual +3.5%
2002 Master Plan
2002 Bond Issue (High)
2002 Bond Issue
2002 Bond +3.0%
2002 Bond Issue (Low)
Actual +3.5% 34.634.8 36.1 37.3 38.6 40.0
2002 Master Plan 30.0 26.0 29.3 30.7 32.0 33.3 34.5 35.7 37.0 38.3 39.6 41.0 42.2 43.5
2002 Bond Issue (High)30.3
29.9 26.5 30.0 31.3 32.7 34.2 35.6 37.0 38.5 40.0
2002 Bond Issue30.3
29.9 25.6 28.6 29.7 30.8 31.7 32.7 33.7 34.8 35.8
2002 Bond +3.0% 35.8 36.9 38.0 39.1 40.3
2002 Bond Issue (Low)30.3
29.9 24.4 26.8 27.5 28.1 28.8 29.4 30.0 30.6 31.2
1,538,000 aboveMaster Plan Forecast
TRB Session 513 - January 23, 2007
Capital Improvement PlanCapital Improvement Plan
TRB Session 513 - January 23, 2007
Terminal Projects (2006-2020)Terminal Projects (2006-2020)
$4.1 Billion over 15 years$4.1 Billion over 15 years
Airsides 1 & 3 RehabilitationAirsides 1 & 3 Rehabilitation
Airside 4 Airside 4
Modifications/Rehabilitation Modifications/Rehabilitation
North Terminal CapacityNorth Terminal Capacity
South Terminal ComplexSouth Terminal Complex
SecuritySecurity
IT Improvements IT Improvements
Hyatt Hotel Hyatt Hotel
Asset Preservation/R&R Asset Preservation/R&R
$4.1 Billion over 15 years$4.1 Billion over 15 years
Airsides 1 & 3 RehabilitationAirsides 1 & 3 Rehabilitation
Airside 4 Airside 4
Modifications/Rehabilitation Modifications/Rehabilitation
North Terminal CapacityNorth Terminal Capacity
South Terminal ComplexSouth Terminal Complex
SecuritySecurity
IT Improvements IT Improvements
Hyatt Hotel Hyatt Hotel
Asset Preservation/R&R Asset Preservation/R&R
TRB Session 513 - January 23, 2007
ProposedSouth Terminal
ProposedSouth Terminal
TRB Session 513 - January 23, 2007
ProposedSouth Terminal
Phase 1
ProposedSouth Terminal
Phase 1
TRB Session 513 - January 23, 2007
Airfield Projects (2006-2020)Airfield Projects (2006-2020)
$1.0 Billion over 15 years$1.0 Billion over 15 years
Airfield Capacity/ TaxiwayAirfield Capacity/ Taxiway
ProjectsProjects
Wildlife Attractant Mitigation Wildlife Attractant Mitigation
ProjectsProjects
Secure Service Road ExtensionSecure Service Road Extension
Asset Preservation/R&RAsset Preservation/R&R
ProjectsProjects
$1.0 Billion over 15 years$1.0 Billion over 15 years
Airfield Capacity/ TaxiwayAirfield Capacity/ Taxiway
ProjectsProjects
Wildlife Attractant Mitigation Wildlife Attractant Mitigation
ProjectsProjects
Secure Service Road ExtensionSecure Service Road Extension
Asset Preservation/R&RAsset Preservation/R&R
ProjectsProjects
TRB Session 513 - January 23, 2007
Roadway & Parking Projects (2006-2020)Roadway & Parking Projects (2006-2020)
$419 Million over 15 years$419 Million over 15 years
Widen South Access RoadWiden South Access Road
Loop Road SignageLoop Road Signage
Mitigate Cut Through TrafficMitigate Cut Through Traffic
Enplane/Deplane DriveEnplane/Deplane Drive
Widen Tradeport DriveWiden Tradeport Drive
Extend Heintzelman Blvd.Extend Heintzelman Blvd.
Expand Parking Expand Parking
Asset Preservation/R&R Asset Preservation/R&R
ProjectsProjects
$419 Million over 15 years$419 Million over 15 years
Widen South Access RoadWiden South Access Road
Loop Road SignageLoop Road Signage
Mitigate Cut Through TrafficMitigate Cut Through Traffic
Enplane/Deplane DriveEnplane/Deplane Drive
Widen Tradeport DriveWiden Tradeport Drive
Extend Heintzelman Blvd.Extend Heintzelman Blvd.
Expand Parking Expand Parking
Asset Preservation/R&R Asset Preservation/R&R
ProjectsProjects
TRB Session 513 - January 23, 2007
SummarySummary
$ 5.7 Billion over 15 years$ 5.7 Billion over 15 years
$ 4.1 Billion - Terminal$ 4.1 Billion - Terminal
$ 1.0 Billion - Airfield s$ 1.0 Billion - Airfield s
$ 419 Million - Roadway & $ 419 Million - Roadway &
ParkingParking
$ 159 Million - Other$ 159 Million - Other
Includes $645 Million in Includes $645 Million in
Asset Preservation/R&R Asset Preservation/R&R
ProjectsProjects
$ 5.7 Billion over 15 years$ 5.7 Billion over 15 years
$ 4.1 Billion - Terminal$ 4.1 Billion - Terminal
$ 1.0 Billion - Airfield s$ 1.0 Billion - Airfield s
$ 419 Million - Roadway & $ 419 Million - Roadway &
ParkingParking
$ 159 Million - Other$ 159 Million - Other
Includes $645 Million in Includes $645 Million in
Asset Preservation/R&R Asset Preservation/R&R
ProjectsProjects
TRB Session 513 - January 23, 2007
Lessons LearnedLessons Learned
TRB Session 513 - January 23, 2007
Planning and DesignPlanning and Design
Land Use Land Use
OtherOther
Planning and DesignPlanning and Design
Land Use Land Use
OtherOther
Lessons LearnedLessons Learned
TRB Session 513 - January 23, 2007
1.1. FLEXIBILITY! FLEXIBILITY!
2.2. Landside/Airside vs Unit Terminal ConceptsLandside/Airside vs Unit Terminal Concepts
3.3. Evolution of the Airside BuildingEvolution of the Airside Building
4.4. Capacity AnalysisCapacity Analysis
5.5. Emerging TrendsEmerging Trends
1.1. FLEXIBILITY! FLEXIBILITY!
2.2. Landside/Airside vs Unit Terminal ConceptsLandside/Airside vs Unit Terminal Concepts
3.3. Evolution of the Airside BuildingEvolution of the Airside Building
4.4. Capacity AnalysisCapacity Analysis
5.5. Emerging TrendsEmerging Trends
Lessons Learned
Planning and Design
Lessons Learned
Planning and Design
TRB Session 513 - January 23, 2007
1. FLEXIBILITY! 1. FLEXIBILITY!
LandLand
Overbuild when economically possibleOverbuild when economically possible
Three Level TerminalThree Level Terminal
Ability to add additional curbAbility to add additional curb
Size of airsides have evolvedSize of airsides have evolved
Security Security
Simple buildings targeted to be experienced from Simple buildings targeted to be experienced from interior. Exterior enhanced with landscaping.interior. Exterior enhanced with landscaping.
1. FLEXIBILITY! 1. FLEXIBILITY!
LandLand
Overbuild when economically possibleOverbuild when economically possible
Three Level TerminalThree Level Terminal
Ability to add additional curbAbility to add additional curb
Size of airsides have evolvedSize of airsides have evolved
Security Security
Simple buildings targeted to be experienced from Simple buildings targeted to be experienced from interior. Exterior enhanced with landscaping.interior. Exterior enhanced with landscaping.
Lessons LearnedPlanning and DesignLessons Learned
Planning and Design
TRB Session 513 - January 23, 2007
One more reason to remain flexible!One more reason to remain flexible!
TRB Session 513 - January 23, 2007
Hurricane Charley – August 13, 2004Hurricane Charley – August 13, 2004
7:30 PM
TRB Session 513 - January 23, 2007
TRB Session 513 - January 23, 2007
2. Landside/Airside vs Unit Terminal Concepts2. Landside/Airside vs Unit Terminal Concepts
Landside/airside with APM’s used at MCO to place Landside/airside with APM’s used at MCO to place airsides in stable soil locations, minimize walking airsides in stable soil locations, minimize walking distance and to serve domestic O&D trafficdistance and to serve domestic O&D traffic
Double Bag Handling & Security ScreeningDouble Bag Handling & Security Screening
South Terminal will offer hybrid concept with unit South Terminal will offer hybrid concept with unit terminal and landside/airside elementsterminal and landside/airside elements
Terminal A vs Terminal BTerminal A vs Terminal B
2. Landside/Airside vs Unit Terminal Concepts2. Landside/Airside vs Unit Terminal Concepts
Landside/airside with APM’s used at MCO to place Landside/airside with APM’s used at MCO to place airsides in stable soil locations, minimize walking airsides in stable soil locations, minimize walking distance and to serve domestic O&D trafficdistance and to serve domestic O&D traffic
Double Bag Handling & Security ScreeningDouble Bag Handling & Security Screening
South Terminal will offer hybrid concept with unit South Terminal will offer hybrid concept with unit terminal and landside/airside elementsterminal and landside/airside elements
Terminal A vs Terminal BTerminal A vs Terminal B
Lessons LearnedPlanning and DesignLessons Learned
Planning and Design
TRB Session 513 - January 23, 2007
TRB Session 513 - January 23, 2007
Double Bag Handling
Airside 4 FIS
Opened in 1990 1,500 Pax per/hr Modified once since 1990
Double Bag Handling
Airside 4 FIS
Opened in 1990 1,500 Pax per/hr Modified once since 1990
TRB Session 513 - January 23, 2007
ProposedSouth
Terminal
ProposedSouth
Terminal
120 Gates (ultimate)
48 Contact Gates
72 Gates by APM
TRB Session 513 - January 23, 2007
September 1981
Terminal A vs Terminal B (MCO – 1981) Terminal A vs Terminal B (MCO – 1981)
B A
TRB Session 513 - January 23, 2007
B
A
TRB Session 513 - January 23, 2007
3. Evolution of the Airside Building3. Evolution of the Airside Building
Size of AirsideSize of Airside
Configuration of Airside Configuration of Airside
3. Evolution of the Airside Building3. Evolution of the Airside Building
Size of AirsideSize of Airside
Configuration of Airside Configuration of Airside
Lessons LearnedPlanning and DesignLessons Learned
Planning and Design
TRB Session 513 - January 23, 2007
Airsides 1 & 3 – Opened 1981Airsides 1 & 3 – Opened 1981
TRB Session 513 - January 23, 2007
Airside 4 – Opened 1990Airside 4 – Opened 1990
TRB Session 513 - January 23, 2007
Airside 2 – Opened 2000Airside 2 – Opened 2000
September 2000
TRB Session 513 - January 23, 2007
4. Capacity Analysis4. Capacity Analysis
Moving target Moving target (example – security checkponits)(example – security checkponits)
Find the weak links in the chainFind the weak links in the chain
Routinely monitor peak hour statisticsRoutinely monitor peak hour statistics
Balanced Facility RequirementsBalanced Facility Requirements
4. Capacity Analysis4. Capacity Analysis
Moving target Moving target (example – security checkponits)(example – security checkponits)
Find the weak links in the chainFind the weak links in the chain
Routinely monitor peak hour statisticsRoutinely monitor peak hour statistics
Balanced Facility RequirementsBalanced Facility Requirements
Lessons LearnedPlanning and DesignLessons Learned
Planning and Design
TRB Session 513 - January 23, 2007
Terminal Vertical Circulation
Terminal Vertical Circulation
Terminal Roadsand Ramps
Terminal Roadsand Ramps
Landside TerminalCurbs
Landside TerminalCurbs
Entering andExiting Weaves
Entering andExiting Weaves
Ticketing LobbyTicketing Lobby
Garage PublicParking
Garage PublicParking
Baggage ClaimBaggage Claim
Baggage Make-upBaggage Make-up
FIS CapacityFIS Capacity
Security CheckPointSecurity CheckPoint
Capacity AnalysisCapacity Analysis
TRB Session 513 - January 23, 2007
Enplaning and Deplaning Passenger Peak Hour Trends
Enplaning and Deplaning Passenger Peak Hour Trends
OIA - Peak Hour Trend Line
0
0.03
0.06
0.09
0.12
0.15
0.18
Month
Pe
ak
Ho
ur
Pe
rce
nta
ge
Deplanement Pk.Hr. % Enplanement Pk.Hr. %
March 2003 Enplanement Pk. Hr. @ 11% March 2003 Deplanement Pk. Hr. @ 10%
TRB Session 513 - January 23, 2007
Airside Activity TrendsSeek to Balance Activity on all Airsides
Airside Activity TrendsSeek to Balance Activity on all Airsides
OIA - Scheduled Enplanements by Airside by Month
0
5000
10000
15000
20000
25000
Month
Av
era
ge
d D
aily
Sc
he
du
led
S
ea
ts
Airside 1Airside 2Airside 3Airside 4
TRB Session 513 - January 23, 2007
Airport Activity TrendsScheduled Enplaning Seats January 2007
Airport Activity TrendsScheduled Enplaning Seats January 2007
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Day of Week
Tue
Thr
Sat0
1,000
2,000
3,000
4,000
5,000
6,000
Daily Scheduled Seat
Count
Hour Of Day
OIA Scheduled Seats - Overall January 2007 - Enplanements
TRB Session 513 - January 23, 2007
Airside Activity Trends Scheduled Deplaning Seats January 2007
Airside Activity Trends Scheduled Deplaning Seats January 2007
0 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Day of Week
Tue
Thr
Sat
0
1,000
2,000
3,000
4,000
5,000
6,000
Daily Scheduled Seat
Count
Hour Of Day
OIA Scheduled Seats - Overall January 2007 - Deplanements
TRB Session 513 - January 23, 2007
5. Emerging Trends5. Emerging Trends
Disney Magical Express and remote Check-inDisney Magical Express and remote Check-in
Registered TravelerRegistered Traveler
Rental Car FacilitiesRental Car Facilities
5. Emerging Trends5. Emerging Trends
Disney Magical Express and remote Check-inDisney Magical Express and remote Check-in
Registered TravelerRegistered Traveler
Rental Car FacilitiesRental Car Facilities
Lessons LearnedPlanning and DesignLessons Learned
Planning and Design
TRB Session 513 - January 23, 2007
1.1. Overlay Zoning Districts in cooperation with local Overlay Zoning Districts in cooperation with local governmentsgovernments
Forecast airport build-out noise contoursForecast airport build-out noise contours
Single event noise levelsSingle event noise levels
Composite mapComposite map
Develop control zones Develop control zones
2.2. Wildlife AttractantsWildlife Attractants
1.1. Overlay Zoning Districts in cooperation with local Overlay Zoning Districts in cooperation with local governmentsgovernments
Forecast airport build-out noise contoursForecast airport build-out noise contours
Single event noise levelsSingle event noise levels
Composite mapComposite map
Develop control zones Develop control zones
2.2. Wildlife AttractantsWildlife Attractants
Lessons LearnedLand Use
Lessons LearnedLand Use
TRB Session 513 - January 23, 2007
55 DNL 55 DNL 60 DNL60 DNL65 DNL65 DNL70 DNL70 DNL75 DNL75 DNL
RunwaysRunways
2020 DNL 2020 DNL NOISE NOISE
CONTOURSCONTOURS
2020 DNL 2020 DNL NOISE NOISE
CONTOURSCONTOURS
Bo
gg
y C
ree
k R
oa
d
Gre
ene
Way
TRB Session 513 - January 23, 2007
75 dBA75 dBA
80 dBA80 dBA
RunwaysRunways
Lmax NOISE Lmax NOISE CONTOURS - CONTOURS -
TYPICAL TYPICAL AIRCRAFTAIRCRAFT
Lmax NOISE Lmax NOISE CONTOURS - CONTOURS -
TYPICAL TYPICAL AIRCRAFTAIRCRAFT
Bo
gg
y C
ree
k R
oa
d
Gre
ene
Way
TRB Session 513 - January 23, 2007
OPERATIONS OPERATIONS AND LAND AND LAND
USE CONTROL USE CONTROL ZONE LIMITSZONE LIMITS
OPERATIONS OPERATIONS AND LAND AND LAND
USE CONTROL USE CONTROL ZONE LIMITSZONE LIMITS
Bo
gg
y C
ree
k R
oa
d
Gre
ene
Way
Zone B Zone B Zone C Zone C Zone D Zone D Zone E Zone E OIA/OEA PropertyOIA/OEA PropertyDevelopments With Agreements With GOAA
Developments With Agreements With GOAA
TRB Session 513 - January 23, 2007
Orange County Rural/Agricultural Zoning
Orange County Rural/Agricultural Zoning
City of Orlando Conservation ZoningCity of Orlando Conservation Zoning
Osceola County Agricultural ZoningOsceola County Agricultural Zoning
AREAS WITH HIGH AREAS WITH HIGH POTENTIAL FOR POTENTIAL FOR
REZONINGREZONING
AREAS WITH HIGH AREAS WITH HIGH POTENTIAL FOR POTENTIAL FOR
REZONINGREZONING
City of Orlando Hold ZoningCity of Orlando Hold Zoning
Bo
gg
y C
ree
k R
oa
d
Gre
ene
Way
TRB Session 513 - January 23, 2007
January 2001January 2001
Prepare ALP supplement to Prepare ALP supplement to
address changes for address changes for
drainage and wildlife drainage and wildlife
attractant projectsattractant projects
January 2001January 2001
Prepare ALP supplement to Prepare ALP supplement to
address changes for address changes for
drainage and wildlife drainage and wildlife
attractant projectsattractant projects
Wildlife Attractants Wildlife Attractants
TRB Session 513 - January 23, 2007
1.1. Management Tools – Staff CommitteesManagement Tools – Staff Committees
ConstructionConstruction
Construction Finance OversightConstruction Finance Oversight
Design ReviewDesign Review
1.1. Management Tools – Staff CommitteesManagement Tools – Staff Committees
ConstructionConstruction
Construction Finance OversightConstruction Finance Oversight
Design ReviewDesign Review
Lessons LearnedOther
Lessons LearnedOther
TRB Session 513 - January 23, 2007
Thank You!Thank You!