Transportation Estimators Association Annual Conference Synthesis on Construction Unit Cost Development Stuart D. Anderson, PhD, PE Texas Transportation Institute (TTI) September 2009
Mar 28, 2015
Transportation Estimators AssociationAnnual Conference
Synthesis on
Construction Unit Cost Development
Stuart D. Anderson, PhD, PE
Texas Transportation Institute (TTI)September 2009
Overview Problem Description Objectives Synthesis Approach Follow-Up Analysis and Results Recommendations
Ou
tlin
e
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Synthesis on
Construction Unit Cost Development
Project cost estimating – Important component of the project development process Planning Scoping Design PS&E
Common estimating approaches Historical Bid Based Estimation Cost Based Estimation
Project estimates adjusted based on project type and size (i.e., complexity), market conditions, location and time
OverviewProblem
DescriptionObjectives Follow-upApproach
AnalysisResults
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Recommendations
Lack of systematic methodology to analyze and develop unit costs for construction projects
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
OverviewProblem
DescriptionObjectives Follow-upApproach
AnalysisResults
Recommendations
Explore the current state of practice followed by other state agencies for developing construction
Provide summary of the estimation practices followed by different state agencies
Compare estimation practice of TxDOT with other state agencies
Overview Objectives
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Problem Description
Follow-upApproachAnalysisResults
Recommendations
Approach
Texas Department of Transportation (TxDOT) Survey One Question
Online Survey Approach Structure Flowchart Results
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
“Do you have a formal process that uses a systematic tool for developing unit prices that categorizes for issues such as complexity, total quantities, difficulty, and type of project? Please point us to your system on the web or transmit electronically or by mail”
Sent to all state construction engineers Replies received from 37 state agencies No state stated that they had any formal process for construction
unit price development 14 state agencies stated they use a systematic tool for developing
unit prices to support project estimation
TxDOT Survey
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ApproachObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
Divided into two sections: Section I – Construction Unit Cost Section II – Maintenance Unit Cost
Survey request sent to Subcommittee on Construction and Subcommittee on Design membership list (one survey per state per subcommittee)
A total of 104 online survey request sent to state agencies Received a total of 38 responses from 36 state agencies
Online Survey - Approach
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ApproachObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
Section I – Construction Unit Cost General
• Identifying estimating techniques that are coupled with unit cost development procedures
Acquiring Unit Cost Information• System used in extraction of unit costs from past contract details
Storing Unit Cost Information• Methods used in storing unit cost details in the database
Accessing Unit Cost Information• Mechanism to access unit cost information
Applying Unit Cost Information• Use of unit cost information in estimation process
Online Survey - Structure
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ApproachObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
Online Survey - Results
General Section
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ApproachObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
Online Survey - Results
General Section
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ApproachObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
Online Survey - Results
General Section
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Well documented process or procedure for developing unit construction cost estimating?
ApproachObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
Online Survey - Results
Acquiring Unit Cost Information
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ApproachObjectivesOverview Problem Description
Follow-upAnalysisResults
Recommendations
Types of historical bid data acquired from bid details
Online Survey - Results
Storing Unit Cost Information
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ApproachObjectivesOverview Problem Description
Follow-upAnalysisResults
Recommendations
Storing Historical unit cost information
Online Survey - Results
Applying Unit Cost Information – Formal Process/Procedure
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Project Size, Location & Complexity
Current Market Condition
Impact of Inflation
ApproachObjectivesOverview Problem Description Follow-up
AnalysisResults
Recommendations
Follow-upApproach
Selection criteria for follow-up interviews
Estimating approach Historical Bid Based Estimating Cost Based Estimating
Trns*port Users Proposal Estimating System (PES), Cost Estimating System
(CES), Estimator Non – Trns*port Users Innovative approach to estimating Sophisticated databases for historical unit costs Guidance on developing project estimates
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
ObjectivesOverview Problem Description
AnalysisResults
Recommendations
Follow-Up Interviews - Approach
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Telephone Interviews California Department of Transportation Florida Department of Transportation New York State Department of Transportation Utah Department of Transportation Virginia Department of Transportation Washington State Department of Transportation Texas Department of Transportation
Dallas District Fort Worth District
Personal Interviews Minnesota Department of Transportation Texas Department of Transportation – Bryan District
Planning Planning
Cost Estimate
Excel
ScopingProject Cost Estimating
System (PCES)
DesignTrns*port Proposal
and Estimates
System (PES)
PS&EEstimator, Info Tech Pvt. Ltd
Virginia Department of Transportation (VDOT)
Cost Based Estimation(Rational Estimation)
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
VDOT updates equipment, labor and material rates periodically
Over five years of historical data are maintained in its BAMS/DSS database
Comprehensive two year historical bid price listing providing three low bidders available on their internet
Virginia Department of Transportation (VDOT)
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Factors VDOT considers when adjusting unit prices Project site conditions Time limit Sequence of construction Seasonal Limitations Regional conditions Current market conditions Quantities/price relationships Inflation and risks associated with project
Virginia Department of Transportation (VDOT)
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Unit prices adjusted based on the recent bids received as well Labor rates increased by 50% - 52% to reflect labor burden Production rates calculated using
Site Manager Bid Item Duration Data System (BIDDS) Experience VDOT considers 24 months data for establishing unit prices
Regression analysis carried out if sufficient historical data are available, else weighted average is used
Virginia Department of Transportation (VDOT)
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Planning Excel
Spreadsheet, TRACER
ScopingExcel
Spreadsheet, TRACER Design
Trns*port Estimator
PS&ETrns*port Estimator
Historical Bid Based Estimation
New York State Department of Transportation(NYSDOT)
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
- Preliminary Cost Estimation Spreadsheet
- Bridge Feature Cost Estimate Summary Spreadsheet
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Tracer - Preliminary estimates, flexible to adapt to special requirements of NYSDOT
Bridge costs are estimated using the ‘Bridge Shoulder Break Area methodology’ developed by NYSDOT
Estimates are validated against current project or recently completed projects of similar scope
Letting and Award System (LAS) extracts all bid information to be stored in BAMS/DSS
7 to 12 months of historical data used for establishing unit prices
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
New York State Department of Transportation(NYSDOT)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Historical unit costs are made available as: Weighted Average Item Price Report (WAIPR)
Provides weighted averages of three low bidders for each line item based on the region and year of letting
Regional and Statewide Average Award Price Report (RSWAAPR) Generated using Crystal Reports Software Provides average award price for each line item at the regional and
statewide level NYSDOT performs a check on unit prices for major items of work
using cost based estimationSynthesis on Construction Unit Costs Development
Texas Transportation Institute (TTI)
New York State Department of Transportation(NYSDOT)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Planning Concept
Cost Estimate
Form – Excel Spreadsheet Scoping
PDBS
DesignPDBS
PS&EPDBS
Historical Bid Based Estimation
Utah Department of Transportation (UDOT)
PDBS – Project Development Business System
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Utah Department of Transportation (UDOT)
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
UDOT maintains guidelines for determining unit prices while estimating
Guidelines outline the methods available for developing estimates at various phases of project
UDOT stores all bid information in its PDBS database
PDBS allows users to search bid data based on date range, quantity range, funding source, awarded bid and units
UDOT uses weighted average for a duration of 3 months and 12 months to determine unit prices
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Utah Department of Transportation (UDOT)
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Red Flag Analysis : aids the engineer in developing an Engineer’s Estimate that account for factors affecting project’s cost
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Planning MP3, PLCE
ScopingEBASE, Excel
Spreadsheet
DesignEBASE, Excel
Spreadsheet
PS&EEBASE
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Cost Based Estimation
Washington State Department of Transportation (WSDOT)
Historical Bid Based Estimation
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
WSDOT uses a combination of cost base estimating and historical bid based estimating for preparing final Engineers Estimate
Work items comprising largest dollar value of project estimated using cost based estimating (80-20 Rule)
WSDOT maintains cost estimating guidelines which outlines the:
Estimating Techniques to be used at different project phases
Factors influencing the unit prices
WSDOT stores all the bid information from the submitted bids into its EBASE database
WSDOT considers three to six months of historical data for establishing unit price
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Washington State Department of Transportation (WSDOT)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
WSDOT - Unit Bid Analysis System
Washington State Department of Transportation (WSDOT)
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Washington State Department of Transportation (WSDOT)
WSDOT – Bid Tabs Pro
Follow-upApproachObjectivesOverview Problem Description
AnalysisResults
Recommendations
Follow-upAnalysisResults
Research Findings
Historical bid based estimating is still preferred form of estimating for almost all the agencies
Cost Based Estimating is used only for preparing Engineers Estimate by very few agencies (VDOT, MnDOT)
Most state agencies rely on Excel Spreadsheet to prepare Planning and Scoping Level Estimates
Agencies like FDOT, Caltrans, VDOT have devised their own system to compute preliminary estimates based on Cost-Per-Mile values of typical sections
Sophisticated systems like Trns*port CES, Estimator and PDBS are used for developing the final Engineers Estimate
ApproachObjectivesOverview Problem Description
Recommendations
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Research Findings
Few agencies like FDOT and Caltrans have their historical bid data based on Market Area
Preferred form of storing historical bid data:
1. Standard Construction Line Item
2. Project Types
3. Work Categories
Preferred statistical technique to apply on historical data:
1. Weighted Average
2. Simple Average
3. Scatter Plot with best fit
Agencies like UDOT and TxDOT use moving averages (One month & Twelve months) for determining unit prices
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Follow-upAnalysisResults
ApproachObjectivesOverview Problem Description
Recommendations
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Conclusions
State agencies have different approaches for developing unit costs
Some state agencies have systematic approaches to prepare project estimates, but have no written documentation on the entire process
including documentation for developing unit costs
State agencies do not have a systematic process with respect to adjustment of unit costs
Adjustments to unit costs are mainly based on experience and engineering judgment in state highway agencies
Follow-upAnalysisResults
ApproachObjectivesOverview Problem Description
Recommendations
Synthesis on Construction Unit Costs Development Texas Transportation Institute (TTI)
Recommendations - General
Consider Cost-Based Estimating for items of work related to Hot Mix Asphalt, Steel, and Concrete
Consider the use of Cost-Based Estimating for project estimation in the Design and PS&E phases or a combination of both cost-based
estimating and historical bid-based estimating, with cost-based estimating used to estimate major items of work
Consider using information systems with powerful searching and reporting capabilities to access historical bid data
Consider developing an approach similar to the Red Flag Analysis of UDOT to adjust estimates based on unique project and site
characteristics
Follow-upAnalysisResults
ApproachObjectivesOverview Problem Description
Recommendations
Submitted Bids
Acquiring Unit Cost
- Information Systems- Type of Historical Bid Data
Storing Unit Cost
- Information Systems- Calendar Duration
- Listing of Historical Data- Categories of Historical Data
Historical database
Accessing Unit Cost
- Information Systems
Applying Unit Cost
- Calendar Duration- Statistical Technique
- Number of Bids- Factors influencing Unit Prices
General
- Estimating Techniques & Tools- Innovative Approach
Prepare Base Estimates
Determine Risk/Contingency
Unit Cost Development Framework
Follow-upAnalysisResults
ApproachObjectivesOverview Problem Description
Recommendations
Thank You! http://tti.tamu.edu/documents/0-6023-1.pdf