TRANSPORTATION & CAPITAL IMPROVEMENTS (TCI) 2012 – 2017 Bond Projects –1 MAIN/SOLEDAD: COMMERCE TO PECAN STREET MAIN/SAN PEDRO/NAVARRO ROUNDABOUT UPDATE September 27, 2016 Presenter: Peter Rodriguez Capital Project Officer Location: Central Library 600 Soledad
24
Embed
TRANSPORTATION & CAPITAL IMPROVEMENTS (TCI)files.constantcontact.com/5c921684301/afbbbe99-9f69-4b57-95be-277… · TRANSPORTATION & CAPITAL IMPROVEMENTS (TCI) 2012 – 2017 Bond Projects
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Design Consultant – CDM Smith – Matt Hunter P.E. – Project Manager
3
Main/Soledad: Commerce to Pecan St.
Main Street Soledad Street
–4
Project Construction Cost: $9.5 million allocated in the 2012 – 2017 Bond
Project Location Map
WESTON CENTRE
ROBERT E. LEE
HOTEL
–5 5
EMBASSY SUITES
FROST BANK
RIVERVIEW
TOWERS
HOTEL
Existing Conditions Main Ave. & Soledad
–6 66
Main Ave. & Soledad Streets:
• One-way streets
• Outdated drive approaches
• Cracks on street pavement
• Broken and cracked sidewalks
• Outdated sidewalk ADA wheel ramps
• Lack of pedestrian and bicycle connectivity
• Outdated storm drainage system
• Curbside Parallel Parking
•Main Ave.• Total roadway reconstruction (Commerce St. to Pecan St.)
• Conversion from one-way to two-way traffic operations.
• 10’ foot wide traffic lanes in each direction
• Variable width sidewalks and paver bands
• 5’ foot wide bike lanes in each direction
Planned Improvements
–7
• 5’ foot wide bike lanes in each direction
• Bulb-outs for street side parallel parking
• Install new storm drain inlets to reduce localized flooding
• Curb and gutter, sidewalks and incidental driveway construction
• Landscaping plan
• Street and pedestrian lighting and amenities (bike-racks, benches)
• ADA compliant wheelchair ramps
• Main: Pecan to Navarro (fog seal /restriping)
7
• Soledad Street• Total roadway reconstruction (Commerce St. to Pecan St.)
• Conversion from one-way to two-way traffic operations
• 10’ foot wide traffic lanes in each direction
• Continues left turn lane
• Variable width sidewalks and paver bands
Planned Improvements
–8
• Variable width sidewalks and paver bands
• Bulb-outs for street side parallel parking
• Install new storm drain inlets to reduce localized flooding
• Curb and gutter, sidewalks and incidental driveway construction
• Landscaping plan
• Pedestrian lighting and amenities (bike racks, benches)
• ADA compliant wheelchair ramps
• Soledad: Pecan to San Pedro (fog seal/restriping)
8
Planned Improvements
–9 9
Planned Improvements
–10 10
Planned Improvements
–11 11
Planned Improvements
–12 12
Traffic Control Plan/Sequence of Work
Sequence of Work (*all durations are weather permitting)
Phase 1– Soledad: Commerce to Pecan Street – duration approx. 3 months (mid Oct 2016- mid Jan 2017)Construct CPS gas and SAWS sewer mains and laterals
Phase 2 – Soledad: Commerce to Pecan Street (West Side) – duration approx. 5-1/2 months (mid Nov 2016-end of Mar 2017)*
–13 13
5-1/2 months (mid Nov 2016-end of Mar 2017)*Construct storm sewer inlets, roadway, curb and gutter, sidewalks and drive approachesConstruct Travis Street
Phase 3 – Soledad: Commerce to Pecan Street (East Side) – duration approx. 2-1/2 months (end of Mar – mid-June 2017)*Construct SAWS water main and laterals storm sewer inletsConstruct roadway, curb and gutter, sidewalks and drive approaches
Traffic Control Plan/Sequence of Work
Sequence of Work (*all durations are weather permitting)
Phase 4 – Main Ave.: Commerce to Houston St. – duration approx. 1 month ( Jan – Feb 2017)*o Construct CPS gas and SAWS water mains and sewer laterals.
Phase 5 – Step 1 Main Ave.: Commerce to Pecan (West Side) – duration approx. 4-1/2 months (mid May-Oct 2017)*o SAWS water work construction
–14 14
o SAWS water work constructiono Construct storm sewer inlets, roadway, curb and gutter, sidewalks and
drive approacheso Construct Travis Street and Salinas Street intersections
Phase 6 – Step 1 Main Ave.: Commerce to Pecan (East Side) – duration approx. 2-1/2 months (end of Aug-mid Nov 2017)*o Storm drain inlet worko Construct storm drain inlets, roadway, curb and gutter, sidewalks and
drive approaches
Traffic Control Plan/Sequence of Work
Sequence of Work (*all durations are weather permitting)
Phase 7 – Soledad: Commerce to Pecan Street – duration approx. 6-1/2 months (May - mid Nov 2017)*o Install Traffic signals on Soledad from Commerce to Martino Install traffic signals on Main Ave for Commerce to Martin
Install small signs
–15 15
o Install small signso Install final riding surface of asphalto Install final stripingo Final Clean up
Main Ave. & Soledad
• Contractor shall provide access at all times to include pedestrian
access, drop off and deliveries
• TCI has notified all affected services (EMS, USPS, etc.), Council
Office
TCI Project Commitments
–16
Office
• Any property owners or stakeholders with special needs will be
identified
• Contractor to notify property owners 48 hour in advance of
driveway construction
• Message boards will be installed to notify public of upcoming
construction
• TCI has coordinated with other TCI divisions and B-Cycle
16
Historic Tiled Entryways
Robert E. Lee Hotel
Alpha Hotel
–17 17
Project Schedule
Main Ave. & Soledad ScheduleMain Ave. & Soledad Schedule
Construction start October 17th 2016
Estimated construction
completion*
November 2017
* Weather permitting
–18 18
For information in regards to the project during the Construction Phase: Please contact: Pete Rodriguez – TCI Capital Projects Officer at 210-207-8154