GE 159 Plastics Avenue Pittsfield, MA 01201 USA
Transmitted via Overnight Courier
March 9,2011
Mr. Dean Tagliaferro Mr. Michael Gorski U.S. Environmental
Protection Agency Regional Director Region I - New England Western
Regional Office 10 Lyman Street, Suite 2 Department of
Environmental Protection Pittsfield, MA 01201 436 Dwight Street
Springfield, MA 01103
Re: GE-PittsfieldlHousatonic River Site Monthly Status Report
Pursuant to Consent Decree for February 2011 (GECD900)
Dear Mr. Tagliaferro and Mr. Gorski:
Enclosed are copies of General Electric's (GE's) monthly
progress report for February 2011 activities conducted by GE at the
GE-Pittsfield/Housatonic River Site. This monthly repOJi is
submitted pursuant to Paragraph 67 of the Consent Decree (CD) for
this Site, which was entered by the U.S. District Court on October
27,2000.
The enclosed monthly repOJi includes not only the activities
conducted by GE under the CD, but also other activities conducted
by GE at the GE-Pittsfield/Housatonic River Site (as defined in the
CD). The report is formatted to apply to the various areas of the
Site as defined in the CD, and to provide for each area, the
information specified in Paragraph 67 of the CD. The activities
conducted specifically pursuant to or in connection with the CD are
marked with an asterisk. GE is submitting a separate monthly repOJi
to the Massachusetts Department of Environmental Protection (MDEP),
with a copy to the United States Environmental Protection Agency
(EPA), describing the activities conducted by GE at propeliies
outside the CD Site pursuant to GE's November 2000 Administrative
Consent Order from MDEP.
The enclosed monthly repOJi includes, where applicable, tables
that list the samples collected during the subject month, summarize
the analytical results received during that month from sampling or
other testing activities, and summarize other groundwater
monitoring and oil recovery information obtained during that month.
Also, enclosed for each of you (and for Weston) is a CD-ROM that
contains these same tables of the analytical data and monitoring
information in electronic form.
Please call me if you have any questions.
Sincerely,
Richard W. Gates Remediation Project Manager
Enclosure
Corporate EllvlronlT'entol Programs
-
Mr. Dean Tagliaferro and Mr. Michael Gorski March 9, 2011
Page 2 of2
cc: Richard Fisher, EPA Robeti Cianciarulo, EPA (cover letter
only) Tim Conway, EPA (cover letter only) Rose Howell, EPA (cover
letter and CD-ROM of report) Holly Inglis, EPA (hard copy and
CD-ROM ofreport) Susan Svirsky, EPA (Items 7, 15, and 20 only) R.
Leitch, USACE (CD-ROM of report)
John Ziegler, MDEP (hard copy and CD-ROM ofrepOJi)
Eva Tor, MDEP (cover letter and CD-ROM ofrepOJi)
Karen Pelto, MDEP
Nancy E. Harper, MA AG
Susan Peterson, CT DEP
Field Supervisor, US FWS, DOl
Kenneth Finkelstein, Ph.D., NOAA (Items 13, 14, and 15 only)
Mayor James Rubetio, City of Pittsfield
William Hines, Director, Pittsfield Economic Development
Authority
Linda Palmieri, Weston
Jack Yablonsky, Berkshire Gas (CD-ROM of report)
Richard Nasman, P.E., Berkshire Gas (cover letter only)
Michael Carroll GE (CD-ROM ofrepOJi)
Andrew Silfer, GE (cover letter only)
Rod McLaren, GE (CD-ROM of report)
James Nuss, ARCADIS
James Bieke, Goodwin Procter
Kevin Russell, Anchor QEA (narrative only)
Teresa Bowers, Gradient
Public Information Repositories (1 hard copy,S copies of
CD-ROM)
GE Internal Repository (1 hard copy)
(WiD separate CD-ROM, except where noted)
G:IGEIGE]ittsfield_GenerallReports and PresentationslMonthly
Reportsl20 11102-11 ILetterdoc
-
February 2011
MONTHLY STATUS REPORT
PURSUANT TO CONSENT DECREE
FOR
GE-PITTSFIELD/HOUSATONIC RIVER SITE
GENERAL ELECTRIC COMPANY
PITTSFIELD, MASSACHUSETTS
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Background.doc
-
Background
The General Electric Company (GE), the United States
Environmental Protection Agency (EPA), the Massachusetts Department
of Environmental Protection (MDEP), and other governmental entities
have entered into a Consent Decree (CD) for the
GE-Pittsfield/Housatonic River Site, which was entered by the U.S.
Court on October 27, 2000. In accordance with Paragraph 67 of the
CD, GE is submitting this monthly report, prepared on GE’s behalf
by ARCADIS (formerly Blasland, Bouck & Lee, Inc.), which
summarizes the status of activities conducted by GE at the
GE-Pittsfield/Housatonic River Site ("Site") (as defined in the
CD).
This report covers activities in the areas listed below (as
defined in the CD and/or the accompanying Statement of Work for
Removal Actions Outside the River [SOW]). Only those areas that
have had work activities for the month subject to reporting are
included. The specific activities conducted pursuant to or in
connection with the CD are noted with an asterisk.
General Activities (GECD900)
GE Plant Area (non-groundwater) 1. 20s, 30s, 40s Complexes
(GECD120) 2. East Street Area 2 – South (GECD150) 3. East Street
Area 2 – North (GECD140) 4. East Street Area 1 – North (GECD130) 5.
Hill 78 and Building 71 Consolidation Areas (GECD210/220) 6. Hill
78 Area – Remainder (GECD160) 7. Unkamet Brook Area (GECD170)
Former Oxbow Areas (non-groundwater) 8. Former Oxbow Areas A
& C (GECD410) 9. Lyman Street Area (GECD430) 10. Newell Street
Area I (GECD440) 11. Newell Street Area II (GECD450) 12. Former
Oxbow Areas J & K (GECD420)
Housatonic River 13. Upper ½-Mile Reach (GECD800) 14. 1½-Mile
Reach (only for activities, if any, conducted by GE) (GECD820) 15.
Rest of the River (GECD850)
Housatonic River Floodplain 16. Current Residential Properties
Adjacent to 1½-Mile Reach (Actual/Potential Lawns)
(GECD710) 17. Non-Residential Properties Adjacent to 1½-Mile
Reach (excluding banks)
(GECD720) 18. Current Residential Properties Downstream of
Confluence (Actual/Potential Lawns)
(GECD730)
Other Areas 19. Allendale School Property (GECD500) 20. Silver
Lake Area (GECD600)
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Background.doc
-
Groundwater Management Areas (GMAs) 21. Plant Site 1 (GECD310)
22. Former Oxbows J & K (GECD320) 23. Plant Site 2 (GECD330)
24. Plant Site 3 (GECD340) 25. Former Oxbows A&C (GECD350)
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Background.doc
-
GENERAL ACTIVITIES GE-PITTSFIELD/HOUSATONIC RIVER SITE
(GECD900)
FEBRUARY 2011
a. Activities Undertaken/Completed
b.
Continued GE-EPA electronic data exchanges for the Housatonic
River Watershed.*
Sampling/Test Results Received
- Sample results were received for routine sampling conducted
pursuant to GE’s NPDES Permit for the GE facility. Sampling records
and results are provided in Attachment A to this report.
- NPDES Discharge Monitoring Reports (DMRs) for the period of
January 1 through January 31, 2011, are provided in Attachment B to
this report.
c. Work Plans/Reports/Documents Submitted
- Submitted to EPA and MDEP the 2011 revisions of the Stormwater
Pollution Prevention Plan (SWPPP) in accordance with GE’s NPDES
Permit.
- Submitted to EPA and MDEP the 2010 Baseline Monitoring Plan
Final Summary Report.
- Submitted to EPA and MDEP a summary of 2010 BMP and SWPPP
activities in accordance with GE’s NPDES Permit.
- Submitted to EPA and MDEP the 64G Groundwater Treatment
Facility PCB Optimization Study Report in accordance with GE’s
NPDES Permit.
- Submitted to MDEP revised draft sections of a license renewal
application for GE’s Building 78 under the Resource Conservation
and Recovery Act (RCRA).
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
- Continue NPDES Permit-related sampling and monitoring
activities.
- Attend public and Citizens Coordinating Council (CCC)
meetings, as appropriate.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
GE’s August 3, 2010 follow-up plan relating to the finding in
October 2009 of residual oil in certain pipes located north of
Building OP-2 is under EPA review.
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 1
PLANT AREA
20s, 30s, 40s COMPLEXES (GECD120)
FEBRUARY 2011
a. Activities Undertaken/Completed
- GE transferred the former 40s Complex to the Pittsfield
Economic Development Authority (PEDA) on February 16, 2011.
- GE worked with PEDA on development of a draft Grant of
Environmental Restriction and Easement (ERE) covering the portion
of Woodlawn Avenue adjacent to the former 20s Complex, combined
with the portion of that road within East Street Area 2-North.*
This ERE is discussed further under Item 3 (East Street Area
2-North) below.
b. Sampling/Test Results Received
None
c. Work Plans/Reports/Documents Submitted
None
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
- Jointly with PEDA, submit a request to EPA and MDEP for an
extension of the 5-year duration for retention of the temporary
stockpile of crushed building demolition materials, as well as
continuation of the structural embankments consisting of such
materials as a temporary feature, in the former 40s Complex.*
- It is anticipated that PEDA will prepare draft amended EREs
for the former 20s Complex and the former 30s Complex.*
- Activities relating to the draft ERE covering the portion of
Woodlawn Avenue adjacent to the former 20s Complex, combined with
the portion of that road within East Street Area 2-North, are
discussed further under Item 3 (East Street Area 2-North).*
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
None
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 2
PLANT AREA
EAST STREET AREA 2-SOUTH
(GECD150)
FEBRUARY 2011
a. Activities Undertaken/Completed
- Collected and transferred approximately 3,426,846 gallons of
water generated during remediation activities to Building 64G
Groundwater Treatment Facility for treatment.*
- Conducted PCB sampling of decontamination solution generated
from well activities, as indicated in Table 2-1.
- Continued water sampling as part of the NPDES Permit-related
Optimization Study, as indicated in Table 2-1.
- Performed February 2011 dry weather flow inspection activities
associated with Drainage Basin 005 under GE’s NPDES Permit.
- Provided comments to EPA regarding the sampling plan developed
by the Massachusetts Department of Transportation (MassDOT) for its
planned widening of East Street.
b. Sampling/Test Results Received
See attached tables.
c. Work Plans/Reports/Documents Submitted
None
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
Perform March 2011 dry weather flow inspection activities
associated with Drainage Basins 005 and 006 under GE’s NPDES
Permit.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
f.
Remediation activities were suspended in December 2010, and
shipments of excavated material stored in Building 65 were
suspended in January 2011. These activities will resume in spring
2011.*
Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
TABLE 2-1 DATA RECEIVED AND/OR SAMPLES COLLECTED DURING FEBRUARY
2011
EAST STREET AREA 2 - SOUTH GENERAL ELECTRIC COMPANY - PITTSFIELD
MASSACHUSETTS
Sample Date Received by Project Name Field Sample ID Date Matrix
Laboratory Analyses GE or ARCADIS
Decontamination Solution Generated from Well Activities E2699-1
2/10/11 Water SGS PCB 2/24/11 Optimization Study OPT-A-011811
1/18/11 Water Columbia TSS, TSS (f) 2/7/11 Optimization Study
OPT-A-012611 1/26/11 Water Columbia TSS, TSS (f) 2/11/11
Optimization Study OPT-A-012611 1/26/11 Water SGS PCB 2/7/11
Optimization Study OPT-B-012611 1/26/11 Water SGS PCB 2/7/11
Optimization Study OPT-C-012611 1/26/11 Water SGS PCB 2/7/11
Optimization Study OPT-CO-012611 1/26/11 Water SGS PCB 2/7/11
Optimization Study OPT-D-011811 1/18/11 Water Columbia TSS, TSS (f)
2/7/11 Optimization Study OPT-D-012611 1/26/11 Water Columbia TSS,
TSS (f) 2/11/11 Optimization Study OPT-D-012611 1/26/11 Water SGS
PCB 2/7/11 Optimization Study OPT-DUP-38 (OPT-A-012611) 1/26/11
Water Columbia TSS 2/11/11 Optimization Study OPT-DUP-39
(OPT-A-012611) 1/26/11 Water Columbia TSS (f) 2/11/11 Optimization
Study OPT-DUP-40 (OPT-CO-012611) 1/26/11 Water SGS PCB 2/7/11
Optimization Study OPT-IT-012611 1/26/11 Water SGS PCB 2/7/11
Notes: 1. The parent sample location associated with the field
duplicate is presented in parenthesis. 2. (f) - Indicates filtered
analysis requested.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Tracking Logs\ Tracking.xlsm - TABLE 2-1 1 of 1
3/9/2011
-
TABLE 2-2 PCB DATA RECEIVED DURING FEBRUARY 2011
DECONTAMINATION SOLUTION GENERATED FROM WELL ACTIVITIES EAST
STREET AREA 2-SOUTH
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID Date
Collected Aroclor-1016, 1221, -1232, -1242, -1248 Aroclor-1254
Aroclor-1260 Total PCBs
E2699-1 2/10/2011 ND(0.000067) 0.00025 ND(0.000067) 0.00025
Notes: 1. Sample was collected by Veolia ES Technical Solutions,
L.L.C. and submitted to SGS
Environmental Services, Inc. for analysis of PCBs. 2. ND -
Analyte was not detected. The number in parenthesis is the
associated detection
limit.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 2-2 Page 1
of 1 3/9/2011
-
TABLE 2-3 DATA RECEIVED DURING FEBRUARY 2011
OPTIMIZATION STUDY EAST STREET AREA 2-SOUTH
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID: Parameter Date Collected:
OPT-A-011811 01/18/11
OPT-A-012611 01/26/11
OPT-B-012611 01/26/11
OPT-C-012611 01/26/11
PCBs-Unfiltered Aroclor-1248 DR 0.00036 ND(0.0000095)
ND(0.0000095) Aroclor-1254 DR ND(0.0000095) 0.00022 ND(0.0000095)
Aroclor-1260 DR ND(0.0000095) ND(0.0000095) ND(0.0000095) Total
PCBs DR 0.00036 0.00022 ND(0.000015) Inorganics-Unfiltered Total
Suspended Solids 2.70 4.40 [4.40] NA NA Inorganics-Filtered Total
Suspended Solids 2.10 3.60 [3.90] NA NA
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 2-3 Page 1
of 2 3/9/2011
-
1. Samples were collected by ARCADIS and submitted to Columbia
Analytical Services, Inc. and SGS Environmental Services, Inc. for
analysis of PCBs and total suspended solids (TSS).
2. NA Not Analyzed.3. ND Analyte was not detected. The number in
parenthesis is the associated detection limit.4. DR Data received
and reported in Table 2-4 of the January 2011 CD Monthly Report. 5.
Only those constituents detected in one or more samples are
summarized.6. Field duplicate sample results are presented in
brackets.
TABLE 2-3 DATA RECEIVED DURING FEBRUARY 2011
OPTIMIZATION STUDY EAST STREET AREA 2-SOUTH
GENERAL ELECTRIC COMPANY -P ITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID: Parameter Date Collected:
OPT-CO-012611 01/26/11
OPT-D-011811 01/18/11
OPT-D-012611 01/26/11
OPT-IT-012611 01/26/11
PCBs-Unfiltered Aroclor-1248 0.00040 [0.00057] DR ND(0.0000094)
0.0032 Aroclor-1254 ND(0.0000095) [0.00082] DR ND(0.0000094) 0.012
Aroclor-1260 ND(0.0000095) [0.000084] DR ND(0.0000094) 0.0027 Total
PCBs 0.00040 [0.00147] DR ND(0.000015) 0.0179 Inorganics-Unfiltered
Total Suspended Solids NA ND(1.00) ND(1.00) NA Inorganics-Filtered
Total Suspended Solids NA ND(1.00) ND(1.00) NA
Notes: 1. Samples were collected by ARCADIS and submitted to
Columbia Analytical Services, Inc. and SGS Environmental Services,
Inc. for
analysis of PCBs and total suspended solids (TSS). 2. NA -- Not
Analyzed. 3. ND -- Analyte was not detected. The number in
parenthesis is the associated detection limit. 4. DR -- Data
received and reported in Table 2-4 of the January 2011 CD Monthly
Report. 5. Only those constituents detected in one or more samples
are summarized. 6. Field duplicate sample results are presented in
brackets.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx -2 -3 Page 2
of 2 3/9/2011
-
ITEM 3
PLANT AREA
EAST STREET AREA 2-NORTH
(GECD140)
FEBRUARY 2011
a. Activities Undertaken/Completed
- Completed development of a draft ERE for East Street Area
2-North (excluding Woodlawn Avenue).*
- Worked with PEDA on development of a draft ERE for the portion
of Woodlawn Avenue within this RAA, combined with the portion of
that road adjacent to the former 20s Complex.*
- Continued survey work for the above-referenced EREs.*
- Continued discussions with PEDA relating to the
above-referenced EREs and other activities associated with future
transfer of the former 19s Complex and Woodlawn Avenue to PEDA.
- Sent request to MassDOT for a subordination agreement for the
ERE for East Street Area 2North.*
- Continued work on a draft Final Completion Report (FCR) for
East Street Area 2-North.*
- Prepared a topographic survey plan for the former 19s Complex
and the portion of Woodlawn Avenue within this RAA.*
- Performed February 2011 dry weather flow inspection activities
associated with Drainage Basin 005 under GE’s NPDES Permit.
b. Sampling/Test Results Received
None
c. Work Plans/Reports/Documents Submitted Impacts
- Provided draft proposal (in coordination with PEDA) for the
remaining concrete slabs of certain buildings in East Street Area
2-North to EPA for review (February 16, 2011; retransmitted with
minor corrections on February 17, 2011).*
- Provided draft ERE for East Street Area 2-North (along with a
figure illustrating GE’s and PEDA’s understanding of the
anticipated restricted areas) to EPA and MDEP for review (February
16, 2011; revised figure transmitted on February 17, 2011).*
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 3
(cont’d)
PLANT AREA
EAST STREET AREA 2-NORTH
(GECD140)
FEBRUARY 2011
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
- Following EPA’s review of the draft proposal for the remaining
concrete slabs of certain buildings in East Street Area 2-North,
finalize that proposal and submit it to EPA.*
- Provide draft ERE (including survey plan) covering the portion
of Woodlawn Avenue within this RAA, combined with the portion of
that road adjacent to the former 20s Complex, to EPA and MDEP for
review.* (Note: PEDA is having continued discussions with EPA and
MDEP regarding the particular types of restricted areas in the
portion of Woodlawn Avenue adjacent to the former 20s Complex.)
- Complete the survey work for the draft ERE for the remainder
of East Street Area 2-North.*
- Following EPA’s review of the draft ERE for East Street Area
2-North (and associated figure) and completion of the survey work
for that ERE, provide a further revised draft ERE and survey plans
to EPA and MDEP for review.*
- Send requests for subordination agreements for the
above-referenced EREs to holders of encumbrances on the properties
subject to those EREs.*
- Continue discussions with PEDA relating to activities
associated with future transfer of the former 19s Complex and
Woodlawn Avenue to PEDA.
- Provide draft FCR for East Street Area 2-North to EPA for
review.*
- Perform March 2011 dry weather flow inspection activities
associated with Drainage Basin 005 under GE’s NPDES Permit.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
Issues relating to EREs are under discussion among GE, PEDA,
EPA, and MDEP.*
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 5
PLANT AREA
HILL 78 & BUILDING 71 CONSOLIDATION AREAS
(GECD210/220)
FEBRUARY 2011
* All activities described below for this item were conducted
pursuant to the Consent Decree.
a. Activities Undertaken/Completed
- Transferred 5,800 gallons of leachate from Building 71
On-Plant Consolidation Area (OPCA) to Building 64G Groundwater
Treatment Facility for treatment (see Table 5-1).
- Received notice from EPA and MDEP that the last draft of the
ERE for the OPCAs (submitted on January 26, 2011) is acceptable to
them.
- Received subordination agreements for this ERE from Pittsfield
Generating Company (PGC) and the City of Pittsfield.
- Completed a draft of the Final Completion Report (FCR) for the
OPCAs.
b. Sampling/Test Results Received
See attached table.
c. Work Plans/Reports/Documents Submitted
Provided draft FCR for the OPCAs to EPA for review (February 24,
2011)
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
Following receipt of the remaining subordination agreements for
the ERE on Hill 78 Area-Remainder (see Item 6 below), finalize the
ERE for the OPCAs and associated survey plans and title insurance
commitment, and execute the ERE.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
GE’s Revised Post-Removal Site Control Plan for the OPCAs,
submitted in January 2011, is under EPA review. That plan includes
an OPCA Post-Closure Groundwater Monitoring Proposal. If that
proposal is approved by EPA in time, GE will conduct the spring
2011 groundwater sampling event at the OPCA monitoring wells as
part of the separate OPCA Post-Closure Groundwater Monitoring
Program (rather than the regular GMA 4 Interim Groundwater Quality
Monitoring Program), as discussed in Item 24.d below.
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
TABLE 5-1 BUILDING 71 CONSOLIDATION AREA LEACHATE TRANSFER
SUMMARY
PLANT AREA - HILL 78 & BUILDING 71 CONSOLIDATION AREAS
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Total Volume of Leachate Transferred
Month / Year (Gallons) February 2010 6,000
March 2010 0
April 2010 7,100
May 2010 4,000
June 2010 0
July 2010 6,000
August 2010 6,000
September 2010 6,000
October 2010 6,000
November 2010 6,000
December 2010 0
January 2011 5,580
February 2011 5,800
Note:1. Leachate is transferred from the Building 71
On-Plant
Consolidation Area to Building 64G for treatment.
Page 1 of 1 G:\GE\GE_Pittsfield_General\Reports and
Presentations\Monthly Reports\2011\02-11\Monitoring Data\
OPCA.xlsActive
3/9/2011
-
ITEM 6
PLANT AREA
HILL 78 AREA - REMAINDER
(GECD160)
FEBRUARY 2011
a. Activities Undertaken/Completed
- Received notice from EPA and MDEP that the last draft of the
ERE for Hill 78 Area-Remainder (submitted on January 26, 2011) is
acceptable to them.*
- Received subordination agreements for this ERE from PGC and
the City of Pittsfield.*
- Continued efforts to obtain subordination agreements from
Berkshire Gas Company, the U.S. Department of the Navy, and
MassDOT.*
- Received comments from EPA on draft FCR for Hill 78
Area-Remainder.*
b. Sampling/Test Results Received
None
c. Work Plans/Reports/Documents Submitted
None
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
- Revise draft FCR and provide it to EPA for review.*
- Continue efforts to obtain subordination agreements from
Berkshire Gas Company, the U.S. Department of the Navy, and
MassDOT.*
- Following receipt of the remaining subordination agreements,
finalize ERE, associated survey plans, and title insurance
commitment, and execute ERE.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
GE is continuing efforts to obtain subordination agreements from
Berkshire Gas, the U.S. Department of the Navy, and MassDOT, and
has requested assistance from EPA and MDEP regarding the latter
two.
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 7
PLANT AREA
UNKAMET BROOK AREA
(GECD170)
FEBRUARY 2011
a. Activities Undertaken/Completed
- Provided information to the trustees of the trust that owns
Parcel L12-1-5 regarding an ERE for that property, and received
notice from them that the trust (or a successor owner) will execute
an ERE on that property.*
- Provided draft ERE and associated survey plan for Parcel
L12-1-5 to EPA and MDEP for review.*
- Received notice that the holder of the only recorded
encumbrance on Parcel L12-1-5 that could affect the ERE will
terminate that interest.*
- Received confirmation from the owners of Parcels L12-1-4 and
L12-1-101 that they will execute EREs on those properties.*
- Conducted soil sampling for PCBs and using the Toxicity
Characteristic Leaching Procedure (TCLP) in connection with General
Dynamics excavation activities, as indicated in Table 7-1.
- Performed February 2011 dry weather flow inspection activities
associated with Drainage Basin 005 under GE’s NPDES Permit.
b. Sampling/Test Results Received
See attached tables.
c. Work Plans/Reports/Documents Submitted
Submitted fifth interim draft design submittal for Unkamet Brook
Area-Remainder (Culvert Cleaning Approach and Railroad Spur Beaver
Deterrent/Debris Diversion Approach) to EPA via electronic mail
(February 7, 2011).*
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
- Prepare Revised Final Removal Design/Removal Action (RD/RA)
Work Plan for Unkamet Brook Area-West (due to EPA by April 15,
2011).*
- Conduct discussions with EPA regarding GE’s interim draft
design submittals for Unkamet Brook Area-Remainder.*
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 7
(cont’d)
PLANT AREA
UNKAMET BROOK AREA
(GECD170)
FEBRUARY 2011
d. Upcoming Scheduled and Anticipated Activities (next six
weeks) (cont’d)
- Continue to develop Final RD/RA Work Plan for Unkamet Brook
Area-Remainder.*
- Provide draft EREs and associated survey plans for Parcels
L12-1-4 and L12-1-101 to EPA and MDEP for review.*
- Send requests for subordination agreements to the holders of
encumbrances on Parcels L12-1-4 and L12-1-101.*
- Prepare draft ERE and survey plan for GE-owned Parcel
K11-7-2.*
- Prepare requests for subordination agreements to the holders
of encumbrances on Parcel K11-72.*
- It is anticipated that the City of Pittsfield will prepare an
ERE for Parcel K11-7-9.*
- Perform March 2011 dry weather flow inspection activities
associated with Drainage Basin 009 under GE’s NPDES Permit.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
Based on agreement between GE and EPA, the submittal date for
the Final RD/RA Work Plan for Unkamet Brook Area-Remainder has been
postponed, and GE has submitted various interim draft design
submittals for that area to EPA for review and discussion.*
f. Proposed/Approved Work Plan Modifications
Received EPA’s conditional approval letter for the Final RD/RA
Work Plan for Unkamet Brook Area-West (February 14, 2011).
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
TABLE 7-1 DATA RECEIVED AND/OR SAMPLES COLLECTED DURING FEBRUARY
2011
UNKAMET BROOK AREA GENERAL ELECTRIC COMPANY - PITTSFIELD
MASSACHUSETTS
Date Received by Project Name Field Sample ID Sample Date Matrix
Laboratory Analyses GE or ARCADIS
General Dynamics Excavation Sampling A4798-1 2/3/11 Soil SGS
PCB, TCLP - excludes Pest, Herb 2/18/11
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Tracking Logs\ Tracking.xlsm - TABLE 7-1 1 of 1
3/9/2011
-
TABLE 7-2 PCB DATA RECEIVED DURING FEBRUARY 2011
GENERAL DYNAMICS EXCAVATION SAMPLING UNKAMET BROOK AREA
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in dry weight parts per million, ppm)
Sample ID Date
Collected Aroclor-1016 Aroclor-1221 Aroclor-1232 Aroclor-1242
Aroclor-1248 Aroclor-1254 Aroclor-1260 Total PCBs A4798-1 2/3/2011
ND(0.035) ND(0.035) ND(0.035) ND(0.035) ND(0.035) ND(0.035)
ND(0.035) ND(0.035)
Notes: 1. Sample was collected by Veolia ES Technical Solutions,
L.L.C. and submitted to SGS Environmental Services, Inc. for
analysis of
PCBs and TCLP constituents. 2. Please refer to Table 7-3 for a
summary of TCLP constituents. 3. ND - Analyte was not detected. The
number in parenthesis is the associated detection limit.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 7-2 Page 1
of 1 3/9/2011
-
TABLE 7-3 TCLP DATA RECEIVED DURING FEBRUARY 2011
GENERAL DYNAMICS EXCAVATION SAMPLING UNKAMET BROOK AREA
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID: Parameter ate Collected:
TCLP Regulatory
Limits A4798-1 2/3/2011
Volatile Organics 1,1-Dichloroethene 0.7 ND(0.010)
1,2-Dichloroethane 0.5 ND(0.010) 2-Butanone 200 ND(0.25) Benzene
0.5 ND(0.010) Carbon Tetrachloride 0.5 ND(0.010) Chlorobenzene 100
ND(0.010) Chloroform 6 ND(0.010) Tetrachloroethene 0.7 ND(0.010)
Trichloroethene 0.5 ND(0.010) Vinyl Chloride 0.2 ND(0.010)
Semivolatile Organics 1,4-Dichlorobenzene 7.5 ND(0.050)
2,4,5-Trichlorophenol 400 ND(0.050) 2,4,6-Trichlorophenol 2
ND(0.050) 2,4-Dinitrotoluene 0.13 ND(0.050) Cresol 200 ND(0.050)
Hexachlorobenzene 0.13 ND(0.050) Hexachlorobutadiene 0.5 ND(0.050)
Hexachloroethane 3 ND(0.050) Nitrobenzene 2 ND(0.050)
Pentachlorophenol 100 ND(0.25) Pyridine 5 ND(0.050) Inorganics
Arsenic 5 ND(0.200) Barium 100 0.178 B Cadmium 1 0.00930 B Chromium
5 ND(0.100) L dLead 55 ND(0 100) ND(0.100) Mercury 0.2 0.0000490 B
Selenium 1 ND(0.200) Silver 5 ND(0.100)
Notes: 1. Sample was collected by Veolia ES Technical Solutions,
L.L.C. and submitted to SGS
Environmental Services, Inc. for analysis of PCBs and TCLP
constituents. 2. Please refer toTable 7-2 for a summary of PCBs. 3.
ND - Analyte was not detected. The number in parenthesis is the
associated detection limit.
Data Qualifiers:
Inorganics B - Indicates an estimated value between the
instrument detection limit (IDL) and practical quantitation limit
(PQL).
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 7-3 Page 1
of 1 3/9/2011
-
ITEM 12
FORMER OXBOW AREAS J & K
(GECD420)
FEBRUARY 2011
* All activities described below for this item were conducted
pursuant to the Consent Decree.
a. Activities Undertaken/Completed
None
b. Sampling/Test Results Received
None
c. Work Plans/Reports/Documents Submitted
None
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
None
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
GE has received permission from the owner of Parcel K10-11-5 for
access to that property to perform inspections to date. GE will
continue efforts, as appropriate, to obtain a long-term access
agreement for that property.
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 13
HOUSATONIC RIVER AREA
UPPER ½ MILE REACH
(GECD800)
FEBRUARY 2011
* All activities described below for this item were conducted
pursuant to the Consent Decree.
a. Activities Undertaken/Completed
None
b. Sampling/Test Results Received
None
c. Work Plans/Reports/Documents Submitted
None
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
None
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
GE submitted a report evaluating the total organic carbon (TOC)
content and effectiveness of the isolation layer on the river
sediments on March 14, 2007. The Final Completion Report for the
Upper ½-Mile Reach Removal Action will be submitted following EPA
review and approval of that report.
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 14
HOUSATONIC RIVER AREA
1½ MILE REACH
(GECD820)
FEBRUARY 2011
a. Activities Undertaken/Completed
On GE’s behalf, ARCADIS performed one round of water column
monitoring at nine locations along the Housatonic River between
Coltsville and Great Barrington, MA, on February 3 and 4, 2011. Two
of these locations are situated in the 1½ Mile Reach: Lyman Street
Bridge (Location 4) and Pomeroy Avenue Bridge (Location 6A). A
composite grab sample was collected at each location and submitted
to Northeast Analytical for analysis of PCBs (total), TSS, POC, and
chlorophyll-a, as identified in Table 14-1. The sample collected at
Pomeroy Avenue Bridge was also analyzed for volatile suspended
solids (VSS). (The other seven locations are discussed under Items
15 and 20 below.)
b. Sampling/Test Results Received
See attached tables.
c. Work Plans/Reports/Documents Submitted
None
d. Upcoming Scheduled and Anticipated Activities (next six
weeks) Documents
- Continue Housatonic River water column monitoring.
- Review EPA’s revisions to its draft FCR for the 1½ Mile Reach
Removal Action, including the Post-Removal Site Control Plan to be
implemented by GE.*
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
No issues.
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
TABLE 14-1 DATA RECEIVED AND/OR SAMPLES COLLECTED DURING
FEBRUARY 2011
HOUSATONIC RIVER - 1 1/2 MILE REACH GENERAL ELECTRIC COMPANY -
PITTSFIELD MASSACHUSETTS
Date Received by Project Name Field Sample ID Sample Date Matrix
Laboratory Analyses GE or ARCADIS
Monthly Water Column Location-4 2/4/11 Water NEA PCB, TSS, POC,
Chlorophyll-A 2/18/11 Monthly Water Column Location-6A 2/3/11 Water
NEA PCB, TSS, VSS, POC, Chlorophyll-A 2/18/11
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Tracking Logs\ Tracking.xlsm - TABLE 14-1 1 of 1
3/9/2011
-
TABLE 14-2 SAMPLE DATA RECEIVED DURING FEBRUARY 2011
MONTHLY WATER COLUMN SAMPLING HOUSATONIC RIVER - 1 1/2 MILE
REACH
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID Location Date
Collected Aroclor-1016, -1232, -1242, -1254, -1260 Aroclor 1221
Aroclor 1248 Total PCBs POC TSS Chlorophyll (a) VSS
LOCATION-4 Lyman Street Bridge 02/04/11 ND(0.0000220)
ND(0.0000220) ND(0.0000220) ND(0.0000220) 0.49 1.58 0.00093 NA
LOCATION-6A Pomeroy Ave. Bridge 02/03/11 ND(0.0000059) 0.0000190 PB
0.00000720 PE 0.0000262 0.37 2.10 0.0012 1.50
Notes: 1. Samples were collected by ARCADIS, and submitted to
Northeast Analytical, Inc. for analysis of PCBs (unfiltered), total
suspended solids (TSS), particulate organic carbon (POC),
chlorophyll (a) and volatile suspended solids (VSS). 2. Sampling
methods involved the collection of composite grab samples at each
location, representative of three stations (25, 50, and 75 percent
of the total river width at each location)
at 50 percent of the total river depth at each station. 3. NA -
Not Analyzed. 4. ND - Analyte was not detected. The number in
parenthesis is the associated detection limit.
Data Qualifiers:
PB - Aroclor 1221 is being used to report an altered PCB pattern
exhibited by the sample. Actual Aroclor 1221 is not present in the
sample, but is reported to more
accurately quantify PCBs present in a sample that has undergone
environmental alteration. PE - Aroclor 1248 is being used to report
an altered PCB pattern exhibited by the sample. Actual Aroclor 1248
is not present in the sample, but is reported to more
accurately quantify PCBs present in a sample that has undergone
environmental alteration.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 14-2 Page
1 of 1 3/9/2011
-
ITEM 15
HOUSATONIC RIVER AREA
REST OF THE RIVER
(GECD850)
FEBRUARY 2011
a. Activities Undertaken/Completed
On GE’s behalf, ARCADIS performed one round of water column
monitoring at nine locations along the Housatonic River between
Coltsville and Great Barrington, MA, on February 3 and 4, 2011. Two
locations are situated in the 1½ Mile Reach of the Housatonic River
and were discussed in Item 14. One location is at the outlet of
Silver Lake and is discussed in Item 20 below. Of the remaining six
locations, two are located upstream of the 1½ Mile Reach: Hubbard
Avenue Bridge (Location 1) and Newell Street Bridge (Location 2).
The four remaining locations are situated in the Rest of the River:
Holmes Road Bridge (Location 7); New Lenox Road Bridge (Location
9); Schweitzer Bridge (Location 12); and Division Street Bridge
(Location 13). An additional location (Woods Pond Headwaters
[Location 10]), that is normally part of the monthly monitoring,
was not sampled during this monitoring event as the location was
inaccessible due to snow and ice. Composite grab samples were
collected at each location sampled and submitted to Northeast
Analytical for analysis of PCBs (total), TSS, POC, and
chlorophyll-a, as identified in Table 15-1.
b. Sampling/Test Results
c.
See attached tables.
Work Plans/Reports/Documents Submitted
d.
None
Upcoming Scheduled and Anticipated Activities (next six
weeks)
Continue Housatonic River monthly water column monitoring.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
GE’s Revised Corrective Measures Study Report, submitted in
October 2010, is under EPA review.*
f. Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
TABLE 15-1 DATA RECEIVED AND/OR SAMPLES COLLECTED DURING
FEBRUARY 2011
HOUSATONIC RIVER - REST OF RIVER GENERAL ELECTRIC COMPANY -
PITTSFIELD MASSACHUSETTS
Date Received by Project Name Field Sample ID Sample Date Matrix
Laboratory Analyses GE or ARCADIS
Monthly Water Column Sampling HR-D1 (Location-12) 2/3/11 Water
NEA PCB, TSS, POC, Chlorophyll-A 2/18/11 Monthly Water Column
Sampling Location-1 2/4/11 Water NEA PCB, TSS, POC, Chlorophyll-A
2/18/11 Monthly Water Column Sampling Location-12 2/3/11 Water NEA
PCB, TSS, POC, Chlorophyll-A 2/18/11 Monthly Water Column Sampling
Location-13 2/3/11 Water NEA PCB, TSS, POC, Chlorophyll-A 2/18/11
Monthly Water Column Sampling Location-2 2/4/11 Water NEA PCB, TSS,
POC, Chlorophyll-A 2/18/11 Monthly Water Column Sampling Location-7
2/3/11 Water NEA PCB, TSS, POC, Chlorophyll-A 2/18/11 Monthly Water
Column Sampling Location-9 2/3/11 Water NEA PCB, TSS, POC,
Chlorophyll-A 2/18/11
Note: 1. The parent sample location associated with the field
duplicate is presented in parenthesis.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Tracking Logs\ Tracking.xlsm - TABLE 15-1 1 of 1
3/9/2011
-
1. Samples were collected by ARCADIS, and submitted to Northeast
Analytical, Inc. for analysis of unfiltered PCBs, total suspended
solids (TSS), particulate organic carbon (POC), and chlorophyll
(a).
2. Sampling methods involved the collection of composite grab
samples at each location, representative of three stations (25, 50,
and 75 percent of the total river width at each location) at 50
percent of the total river depth at each station.
3. ND Analyte was not detected. The number in parenthesis is the
associated detection limit.4. Field duplicate sample results are
presented in brackets.
Data Qualifiers:
AG - Aroclor 1260 is being reported as the best Aroclor match.
The sample exhibits an altered PCB pattern.PD Aroclor 1242 is being
used to report an altered PCB pattern exhibited by the sample.
Actual Aroclor 1242 is not present in the sample, but is reported
to more accurately quantify PCBs present in a sample that has
undergone environmental alteration.
TABLE 15-2 SAMPLE DATA RECEIVED DURING FEBRUARY 2011
MONTHLY WATER COLUMN SAMPLING HOUSATONIC RIVER -RE ST OF
RIVER
GENERAL ELECTRIC COMPANY -P ITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID Location Date
Collected Aroclor-1016, -1221, -1232,-1248, -1254 Aroclor 1242
Aroclor 1260 Total PCBs POC TSS Chlorophyll (a)
LOCATION-1 Hubbard Avenue Bridge 02/04/11 ND(0.0000220)
ND(0.0000220) ND(0.0000220) ND(0.0000220) 0.84 2.80 0.00130
LOCATION-2 Newell Street Bridge 02/04/11 ND(0.0000220)
ND(0.0000220) ND(0.0000220) ND(0.0000220) 0.66 2.08 0.000970
LOCATION-7 Holmes Road Bridge 02/03/11 ND(0.0000220) ND(0.0000220)
0.0000530 AG 0.0000530 0.31 1.50 0.00120 LOCATION-9 New Lenox Road
Bridge 02/03/11 ND(0.0000220) 0.0000290 PD ND(0.0000220) 0.0000290
0.28 1.50 0.000770 LOCATION-12 Schweitzer Bridge 02/03/11
ND(0.0000220) 0.0000380 PD 0.0000240 AG 0.0000620 0.26 1.79
0.00140
02/03/11 [ND(0.0000220)] [0.0000360 PD] [0.0000270 AG]
[0.0000630] [0.63] [1.30] [0.00170] LOCATION-13 Division Street
Bridge 02/03/11 ND(0.0000220) ND(0.0000220) ND(0.0000220)
ND(0.0000220) 0.45 ND(1.00) 0.00930
Notes: 1. Samples were collected by ARCADIS, and submitted to
Northeast Analytical, Inc. for analysis of unfiltered PCBs, total
suspended solids (TSS), particulate organic carbon
(POC), and chlorophyll (a). 2. Sampling methods involved the
collection of composite grab samples at each location,
representative of three stations (25, 50, and 75 percent of the
total river width at each
location) at 50 percent of the total river depth at each
station. 3. ND -- Analyte was not detected. The number in
parenthesis is the associated detection limit. 4. Field duplicate
sample results are presented in brackets.
Data Qualifiers:
AG - Aroclor 1260 is being reported as the best Aroclor match.
The sample exhibits an altered PCB pattern. PD -- Aroclor 1242 is
being used to report an altered PCB pattern exhibited by the
sample. Actual Aroclor 1242 is not present in the sample, but is
reported to more
accurately quantify PCBs present in a sample that has undergone
environmental alteration.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx -1 5-2 Page
1 of 1 3/9/2011
-
ITEM 20
OTHER AREAS
SILVER LAKE AREA
(GECD600)
FEBRUARY 2011
a. Activities Undertaken/Completed
- On GE’s behalf, ARCADIS performed one round of water column
monitoring at the Silver Lake Outfall on February 4, 2011, as noted
in Table 20-1, and also obtained a gauge reading (see Item
21.a).
- PEDA obtained concurrence by the Pittsfield Conservation
Commission on PEDA’s allocation of certain flood storage
compensation to GE for use in GE’s remediation/restoration
activities at the Silver Lake Area.*
- PEDA provided GE with a copy of a Notice of Intent signed by
PEDA and Western Massachusetts Electric Company (WMECo) regarding
the transfer to PEDA of the WMECoowned bank property on the
northern side of the Lake.
b.
- GE continued efforts to obtain access permission for
performance of forthcoming remediation activities.*
Sampling/Test Results Received
See attached tables.
c. Work Plans/Reports/Documents Submitted
d.
None
Upcoming Scheduled and Anticipated Activities (next six
weeks)
- Continue efforts to obtain access permission for performance
of forthcoming remediation activities.*
- Continue communications with EPA and other parties regarding a
CD Modification to address the plantings to be installed on the
northern bank of Silver Lake.*
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
f.
Certain issues relating to GE’s Revised Final RD/RA Work Plan
(submitted in November 2010) and the performance of
remediation/restoration activities at this RAA are under discussion
with EPA.*
Proposed/Approved Work Plan Modifications
None
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
TABLE 20-1 DATA RECEIVED AND/OR SAMPLES COLLECTED DURING
FEBRUARY 2011
SILVER LAKE AREA GENERAL ELECTRIC COMPANY - PITTSFIELD
MASSACHUSETTS
Date Received by Project Name Field Sample ID Sample Date Matrix
Laboratory Analyses GE or ARCADIS
Monthly Water Column Location-4A 2/4/11 Water NEA PCB, TSS
2/18/11
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Tracking Logs\ Tracking.xlsm - TABLE 20-1 1 of 1
3/9/2011
-
1. Sample was collected by ARCADIS, and submitted to Northeast
Analytical, Inc. for analysis of unfiltered PCBs and total
suspended solids (TSS).2. Sampling methods involved the collection
of single grab 50 percent of the total river width, and 50 percent
of the total river depth.3. ND Analyte was not detected. The number
in parenthesis is the associated detection limit.
Data Qualifiers:
PB - Aroclor 1221 is being used to report an altered PCB pattern
exhibited by the sample. Actual Aroclor 1221is not present in the
sample, but is reported to more accurately quantify PCBs present in
a sample that has undergone environmental alteration. PD Aroclor
1242 is being used to report an altered PCB pattern exhibited by
the sample. Actual Aroclor 1242 is not present in the sample, but
is reported to more accurately quantify PCBs present in a sample
that has undergone environmental alteration.
TABLE 20-2 SAMPLE DATA RECEIVED DURING FEBRUARY 2011
MONTHLY WATER COLUMN SAMPLING SILVER LAKE AREA
GENERAL ELECTRIC COMPANY -P ITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID Location Date
Collected Aroclor-1016,
-1232, -1248, -1254 Aroclor 1221 Aroclor 1242 Aroclor 1260 Total
PCBs TSS LOCATION-4A Silver Lake Outlet 2/4/2011 ND(0.0000220)
0.0000700 PB 0.0000240 PD ND(0.0000220) 0.0000940 1.60
Notes:
1. Sample was collected by ARCADIS, and submitted to Northeast
Analytical, Inc. for analysis of unfiltered PCBs and total
suspended solids (TSS). 2. Sampling methods involved the collection
of single grab 50 percent of the total river width, and 50 percent
of the total river depth. 3. ND -- Analyte was not detected. The
number in parenthesis is the associated detection limit.
Data Qualifiers:
PB - Aroclor 1221 is being used to report an altered PCB pattern
exhibited by the sample. Actual Aroclor 1221is not present in the
sample, but is reported to more
accurately quantify PCBs present in a sample that has undergone
environmental alteration. PD -- Aroclor 1242 is being used to
report an altered PCB pattern exhibited by the sample. Actual
Aroclor 1242 is not present in the sample, but is reported to
more accurately quantify PCBs present in a sample that has
undergone environmental alteration.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx -2 0-2 Page
1 of 1 3/9/2011
-
ITEM 21
GROUNDWATER MANAGEMENT AREAS
PLANT SITE 1 (GMA 1)
(GECD310)
FEBRUARY 2011
* All activities described below for this item were conducted
pursuant to the Consent Decree.
a. Activities Undertaken/Completed
General:
- Conducted routine groundwater elevation monitoring and
non-aqueous-phase-liquid (NAPL) monitoring/recovery activities.
- Conducted sampling of well water generated from well 17N, as
indicated in Table 21-1.
- Conducted yearly waste analysis of dense NAPL (DNAPL) derived
from wells LSSC-07, LSSC-08I and LS-30, as indicated in Table
21-1.
East Street Area 1-North and South:
- Continued automated groundwater and NAPL pumping at North Side
and South Side Caissons. No light NAPL (LNAPL) was removed from the
North Side Caisson in February. No LNAPL was removed from the South
Side Caisson in February.
- Continued routine well monitoring and manual NAPL removal
activities. Approximately 1.102 liters (0.291 gallon) of LNAPL were
removed from this area during February.
East Street Area 2-South:
- Continued automated groundwater and LNAPL removal activities.
A total of approximately 3,507,825 gallons of groundwater was
recovered from pumping systems 64R, 64S, 64V, 64X, RW-1(S),
RW-1(X), and RW-2(X). In addition, approximately 489 gallons of
LNAPL were removed from pumping systems 64R, 64V, GMA1-17W,
RW-1(S), RW-2(X), RW-4, 64X, and 64S Caisson.
- Continued automated DNAPL removal activities. Approximately 25
gallons of DNAPL were removed from pumping system RW-3(X) during
February.
- Continued routine well monitoring and manual NAPL removal
activities. Approximately 23.830 liters (6.288 gallons) of LNAPL
were removed from wells in this area during February. Approximately
3.701 liters (0.977 gallon) of DNAPL were removed from wells in
this area during February.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 21
(cont’d)
GROUNDWATER MANAGEMENT AREAS
PLANT SITE 1 (GMA 1)
(GECD310)
FEBRUARY 2011
a. Activities Undertaken/Completed (cont’d)
East Street Area 2-South (cont’d):
- Treated/discharged approximately 3,426,846 gallons of water
through Building 64G Groundwater Treatment Facility.
East Street Area 2-North:
- Continued well monitoring and NAPL removal activities. No
LNAPL was removed from wells in this area in February.
20s, 30s, and 40s Complexes:
- Continued well monitoring and NAPL removal activities. No
LNAPL was recovered from this area during February.
Lyman Street Area:
- Continued automated groundwater and NAPL removal activities.
Approximately 127,311 gallons of groundwater were recovered from
pumping systems RW-1R, RW-2, and RW-3. No LNAPL was removed from
the automated recovery systems during February.
- Continued routine well monitoring and NAPL removal activities.
Approximately 0.308 liter (0.081 gallon) of LNAPL was removed from
wells in this area during February. Approximately 0.923 liter
(0.244 gallon) of DNAPL was removed from wells in this area during
February.
Newell Street Area II:
- Continued automated DNAPL removal activities. No DNAPL was
removed by System 2 in February.
- Continued routine well monitoring and NAPL removal activities.
No LNAPL was removed from this area during February. Approximately
1.073 liters (0.283 gallon) DNAPL were recovered from wells in this
area during February.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 21
(cont’d)
GROUNDWATER MANAGEMENT AREAS
PLANT SITE 1 (GMA 1)
(GECD310)
FEBRUARY 2011
a. Activities Undertaken/Completed (cont’d)
Newell Street Area I:
- No activities.
Silver Lake Area:
- Continued routine monitoring of lake level.
b. Sampling/Test Results Received
See attached tables.
c. Work Plans/Reports/Documents Submitted
None
d. Upcoming Scheduled and Anticipated Activities (next six
weeks)
- Continue routine groundwater and NAPL monitoring/recovery
activities.
- Prepare and submit Fall 2010 NAPL Monitoring Report. That
report will also include a NAPL Volatilization Assessment Proposal
identifying all occupied (or potentially occupied) buildings in GMA
1 where the presence of LNAPL in the groundwater is less than 15
feet from the ground surface and within 30 feet laterally from the
buildings (due to EPA by March 14, 2011; see Item 21.f below).
- Conduct spring 2011 bailing round.
- Initiate preparations for spring 2011 sampling event and
groundwater elevation/NAPL monitoring round.
e. General Progress/Unresolved Issues/Potential Schedule
Impacts
The decommissioning of well ESA1N-52, located in East Street,
has been postponed pending discussions with the City of Pittsfield
to confirm the proper procedures needed to remove this well.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
ITEM 21
(cont’d)
GROUNDWATER MANAGEMENT AREAS
PLANT SITE 1 (GMA 1)
(GECD310)
FEBRUARY 2011
f. Proposed/Approved Work Plan Modifications
GE and EPA have agreed that GE will combine the Fall 2010 NAPL
Monitoring Report (originally due to EPA by February 28, 2011) and
the NAPL Volatilization Assessment Proposal (originally due to EPA
by March 15, 2011) into a single document, to be submitted to EPA
by March 14, 2011.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\2-11 CD Monthly Text Final.doc
-
TABLE 21-1 DATA RECEIVED AND/OR SAMPLES COLLECTED DURING
FEBRUARY 2011
GROUNDWATER MANAGEMENT AREA 1 GENERAL ELECTRIC COMPANY -
PITTSFIELD MASSACHUSETTS
Sample Date Received by Project Name Field Sample ID Date Matrix
Laboratory Analyses GE or ARCADIS
Soil and Debris from Maintenance of 32, 30, P-3 and 51-8 Wells
Soil-Debris-1 1/26/11 Soil SGS PCB, TCLP - Excludes Pest, Herb
2/11/11 Well Development Water Sampling from CC-R Well GMA1-CC-R
1/24/11 Groundwater SGS PCB, VOC, SVOC, Total RCRA 8 Metals
2/7/11
Well Development Water Sampling from ESA2-6R and 95-4RR Wells
GMA1-6R/95-4RR 1/24/11 Groundwater SGS PCB, VOC, SVOC, Total RCRA 8
Metals 2/7/11 Well Development Water Sampling from GMA1-29 and
Gma1-30 Wells GMA1-29/30 1/24/11 Groundwater SGS PCB, VOC, SVOC,
Total RCRA 8 Metals 2/7/11
Well Water Generated from Well 17N B2710/E2688 2/3/11 Water SGS
PCB, VOC, SVOC, Total Metals 2/18/11 Yearly Waste Analysis of DNAPL
Wells LSSC-07, LSSC-08I and LS-30 PTA497935-1 2/15/11 Oil SGS PCB,
VOC, SVOC, Total Metals
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Tracking Logs\ Tracking.xlsm - TABLE 21-1 1 of 1
3/9/2011
-
TABLE 21-2 DATA RECEIVED DURING FEBRUARY 2011
WELL DEVELOPMENT WATER SAMPLING FROM 95-4RR, GMA1-6R, GMA1-29,
GMA1-30 AND CC-R WELLS GROUNDWATER MANAGEMENT AREA 1
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID: Parameter Date Collected:
GMA1-6R/95-4RR 01/24/11
GMA1-29/30 01/24/11
GMA1-CC-R 01/24/11
Volatile Organics Acetone 220 ND(0.010) ND(0.10) Benzene
ND(0.10) 0.015 0.019 J Chlorobenzene 0.50 0.065 0.34
Tetrachloroethene ND(0.10) 0.00062 J ND(0.020)
Trichlorofluoromethane ND(0.10) 0.00072 J ND(0.020) PCBs-Unfiltered
Aroclor-1248 ND(0.33) 0.00023 0.0011 J Aroclor-1254 0.97 0.00031
0.0026 Aroclor-1260 4.9 0.000076 0.013 Total PCBs 5.87 0.000616
0.0167 Semivolatile Organics 1,2-Dichlorobenzene 0.0017 J 0.00086 J
ND(0.0051) 1,3-Dichlorobenzene 0.0035 J 0.0031 J ND(0.0051)
1,4-Dichlorobenzene 0.0066 0.024 0.0018 J 2-Chlorophenol 0.015
0.0022 J 0.0046 J Acenaphthene ND(0.0051) 0.0021 J ND(0.0051)
Acetophenone 0.0019 J ND(0.0051) ND(0.0051) Anthracene 0.0025 J
ND(0.0051) ND(0.0051) Benzo(a)anthracene 0.0014 J ND(0.0051)
ND(0.0051) Benzo(a)pyrene 0.0011 J ND(0.0051) ND(0.0051)
Fluoranthene 0.0037 J ND(0.0051) ND(0.0051) Naphthalene 0.0013 J
0.0016 J 0.0023 J Phenanthrene 0.0091 ND(0.0051) ND(0.0051) Pyrene
0.0051 ND(0.0051) ND(0.0051) Inorganics-Unfiltered Barium 0.0997 B
0.176 ND(0.100) Cadmium 0.000320 B 0.000310 B 0.000280 B Chromium
0.00396 B ND(0.0100) ND(0.0100) MMercury 0 000282 B 0.000282 B ND(0
00028 )ND(0.000285) 0 00044 0.000445 Selenium 0.00340 B ND(0.0200)
ND(0.0200) Silver 0.000410 B 0.000410 B 0.000470 B
Notes: 1. Samples were collected by Veolia ES Technical
Solutions, L.L.C. and submitted to SGS Environmental Services,
Inc.
for analysis of volatiles, PCBs, semivolatiles and metals. 2. ND
- Analyte was not detected. The number in parentheses is the
associated detection limit. 3. Only those constituents detected in
one or more samples are summarized.
Data Qualifiers:
Organics (volatiles, PCBs, semivolatiles) J - Indicates an
estimated value less than the practical quantitation limit
(PQL).
Inorganics B - Indicates an estimated value between the
instrument detection limit (IDL) and PQL.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 21-2 Page
1 of 1 3/9/2011
-
TABLE 21-3 PCB DATA RECEIVED DURING FEBRUARY 2011
SOIL AND DEBRIS FROM MAINTENANCE OF 32, 30, P-3 AND 51-8 WELLS
GROUNDWATER MANAGEMENT AREA 1
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in dry weight parts per million, ppm)
Sample ID Date
Collected Aroclor-1016, 1221, -1232, -1242, -1248 Aroclor-1254
Aroclor-1260 Total PCBs
Soil-Debris-1 1/26/2011 ND(1.4) 2.8 11 13.8
Notes:
1. Sample was collected by Veolia ES Technical Solutions, L.L.C.
and submitted to SGS Environmental Services, Inc. for analysis of
PCBs and TCLP constituents.
2. Please refer to Table 21-4 for a summary of TCLP
constituents. 3. ND - Analyte was not detected. The number in
parenthesis is the associated detection limit.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 21-3 Page
1 of 1 3/9/2011
-
TABLE 21-4 TCLP DATA RECEIVED DURING FEBRUARY 2011
SOIL AND DEBRIS FROM MAINTENANCE OF 32, 30, P-3 AND 51-8 WELLS
GROUNDWATER MANAGEMENT AREA 1
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID: Parameter Date Collected:
TCLP Regulatory
Limits Soil-Debris-1
1/26/2011 Volatile Organics 1,1-Dichloroethene 0.7 ND(0.010)
1,2-Dichloroethane 0.5 ND(0.010) 2-Butanone 200 ND(0.25) Benzene
0.5 ND(0.010) Carbon Tetrachloride 0.5 ND(0.010) Chlorobenzene 100
ND(0.010) Chloroform 6 ND(0.010) Tetrachloroethene 0.7 ND(0.010)
Trichloroethene 0.5 ND(0.010) Vinyl Chloride 0.2 ND(0.010)
Semivolatile Organics 1,4-Dichlorobenzene 7.5 ND(0.050)
2,4,5-Trichlorophenol 400 ND(0.050) 2,4,6-Trichlorophenol 2
ND(0.050) 2,4-Dinitrotoluene 0.13 ND(0.050) Cresol 200 ND(0.050)
Hexachlorobenzene 0.13 ND(0.050) Hexachlorobutadiene 0.5 ND(0.050)
Hexachloroethane 3 ND(0.050) Nitrobenzene 2 ND(0.050)
Pentachlorophenol 100 ND(0.25) Pyridine 5 ND(0.050) Inorganics
Arsenic 5 ND(0.200) Barium 100 0.246 B Cadmium 1 ND(0.100) Chromium
5 ND(0.100) L dLead 55 0 0689 B 0.0689 B Mercury 0.2 ND(0.000570)
Selenium 1 ND(0.200) Silver 5 0.0328 B
Notes: 1. Sample was collected by Veolia ES Technical Solutions,
L.L.C. and submitted to SGS
Environmental Services, Inc. for analysis of PCBs and TCLP
constituents. 2. Please refer to Table 21-3 for a summary of PCBs.
3. ND - Analyte was not detected. The number in parenthesis is the
associated detection limit.
Data Qualifiers:
Inorganics B - Indicates an estimated value between the
instrument detection limit (IDL) and
practical quantitation limit (PQL).
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 21-4 Page
1 of 1 3/9/2011
-
1. Sample was collected by Veolia ES Technical Solutions, L.L.C.
and submitted to SGS Environmental Services, Inc. for analysis of
volatiles, PCBs, semivolatiles and metals.
2. Only detected constituents are summarized.3. Indicates that
all constituents for the parameter group were not detected.
Data Qualifiers:
Organics (volatiles, PCBs, semivolatiles)J Indicates an
estimated value less than the practical quantitation limit
(PQL).
Inorganics
TABLE 21-5 DATA RECEIVED DURING FEBRUARY 2011
WELL WATER GENERATED FROM WELL 17N
GROUNDWATER MANAGEMENT AREA 1
GENERAL ELECTRIC COMPANY - PITTSFIELD, MASSACHUSETTS (Results
are presented in parts per million, ppm)
Sample ID: Parameter Date Collected:
B2710/E2688 02/03/11
Volatile Organics None Detected --PCBs-Unfiltered Aroclor-1248
0.0040 J Aroclor-1254 0.023 Aroclor-1260 0.11 Total PCBs 0.137
Semivolatile Organics 1,2,4,5-Tetrachlorobenzene 0.0010 J
1,2,4-Trichlorobenzene 0.023 1,2-Dichlorobenzene 0.012
1,3-Dichlorobenzene 0.050 2,4-Dichlorophenol 0.0030 J
Inorganics-Unfiltered Barium 0.128 Cadmium 0.00217 B
Notes: 1. Sample was collected by Veolia ES Technical Solutions,
L.L.C. and submitted to
SGS Environmental Services, Inc. for analysis of volatiles,
PCBs, semivolatiles and metals.
2. Only detected constituents are summarized. 3. ---- Indicates
that all constituents for the parameter group were not
detected.
Data Qualifiers:
Organics (volatiles, PCBs, semivolatiles) J -- Indicates an
estimated value less than the practical quantitation limit
(PQL).
Inorganics B - Indicates an estimated value between the
instrument detection limit (IDL) and PQL.
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Analytical Data Tables\ Tables.xlsx - 21-5 Page
1 of 1 3/9/2011
-
TABLE 21-6 MEASUREMENT AND REMOVAL OF RECOVERABLE LNAPL
EAST STREET AREA 1 - NORTH & SOUTH GROUNDWATER MANAGEMENT
AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Well Name
Date Depth
to Water (ft BMP)
Depth to LNAPL (ft BMP)
LNAPL Thickness
(feet)
LNAPL Removed
(liters)
February 2011 Removal (liters)
GMA 1 - East Street Area 1 - South 76 2/18/2011 8.79 7.69 1.10
0.678 0.678
GMA 1 - East Street Area 1 - North 25 2/16/2011 7.18 7.10 0.08
0.049 0.049 105 2/16/2011 7.38 7.35 0.03 0.018 0.018 106 2/17/2011
10.32 9.74 0.58 0.357 0.357
Total Manual LNAPL Removal for February 2011: 1.102 liters 0.291
gallons
Note: 1. ft BMP - feet Below Measuring Point.
Page 1 of 1
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Monitoring Data\ GMA 1-ESA1.xlsLNAPL
3/9/2011
-
Collected Recovered Percent
TABLE 21-7 AUTOMATED LNAPL & GROUNDWATER RECOVERY SYSTEMS
MONTHLY SUMMARY
EAST STREET AREA 1 - NORTH & SOUTH GROUNDWATER MANAGEMENT
AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Caisson Month
Vol. LNAPL Collected (gallon)
Vol. Water Recovered
(gallon) Percent
Downtime Northside February 2010 0.0 7,550
March 2010 0.0 33,300 14.58
April 2010 0.0 36,950 10.71
May 2010 0.0 13,600
June 2010 0.0 14,950 0.83
July 2010 0.0 9,600
August 2010 0.0 10,450
September 2010 0.0 6,650
October 2010 0.0 3,650
November 2010 0.0 5,150
December 2010 0.0 9,750
January 2011January 2011 0.00.0 19,050,
February 2011 0.0 16,200
Southside February 2010 0.0 60,940
March 2010 3.0 77,270 9.03
April 2010 0.0 68,430 10.71
May 2010 0.0 53,620 11.11
June 2010 0.0 84,250 0.83
J l 2010July 2010 0 00.0 60 650 60,650
August 2010 0.0 57,480
September 2010 0.0 68,070
October 2010 0.0 40,452
November 2010 2.5 84,230
December 2010 0.0 103,880
January 2011January 2011 0.00.0 72,170,
February 2011 0.0 63,652
Note: 1. Northside Caisson flow meter replaced and intialized in
January 2010.
Page 1 of 1
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Monitoring Data\ GMA 1-ESA1.xlsAutoRecovery
3/9/2011
-
TABLE 21-8 ROUTINE WELL MONITORING
EAST STREET AREA 1 - NORTH & SOUTH GROUNDWATER MANAGEMENT
AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Well Name
Measuring Point Elev.
(feet) Date
Depth to Water (ft BMP)
Depth to LNAPL
(ft BMP)
LNAPL Thickness
(feet)
Depth to DNAPL (ft BMP)
Total Depth
(ft BMP)
DNAPL Thickness
(feet)
Corrected Water Elev.
(feet) GMA 1 - East Street Area 1 - North
25 1,000.70 2/16/2011 7.18 7.10 0.08 --- 16.55 0.00 993.59 105
1,002.85 2/16/2011 7.38 7.35 0.03 --- 17.38 0.00 995.50 106
1,004.06 2/17/2011 10.32 9.74 0.58 --- 17.69 0.00 994.28
North Caisson 997.84 2/3/2011 17.30 17.29 0.01 --- 19.80 0.00
980.55 North Caisson 997.84 2/10/2011 17.30 17.29 0.01 --- 19.80
0.00 980.55 North Caisson 997.84 2/16/2011 17.39 17.38 0.01 ---
19.80 0.00 980.46 North Caisson 997.84 2/24/2011 17.51 17.50 0.01
--- 19.80 0.00 980.34
GMA 1 - East Street Area 1 - South 31R 1,000.23 2/17/2011 9.69
--- 0.00 --- 15.10 0.00 990.54 33 999.50 2/22/2011 5.71 --- 0.00
--- 21.69 0.00 993.79 34 999.90 2/18/2011 4.42 --- 0.00 --- 21.81
0.00 995.48 72 1,000.62 2/18/2011 5.86 --- 0.00 --- 22.44 0.00
994.76
72R 1,000.75 2/23/2011 6.92 --- 0.00 --- 13.04 0.00 993.83 75
1,000.65 2/18/2011 7.76 --- 0.00 --- 22.81 0.00 992.89 76 1,000.45
2/18/2011 8.79 7.69 1.10 --- 22.89 0.00 992.68
South Caisson 1,001.11 2/3/2011 13.97 13.95 0.02 --- 15.00 0.00
987.16 South Caisson 1,001.11 2/10/2011 14.00 13.98 0.02 --- 15.00
0.00 987.13 South Caisson 1,001.11 2/16/2011 14.02 14.00 0.02 ---
15.00 0.00 987.11 South Caisson 1,001.11 2/24/2011 13.98 13.97 0.01
--- 15.00 0.00 987.14
Notes: 1. ft BMP - feet Below Measuring Point. 2. --- indicates
NAPL was not present in a measurable quantity.
Page 1 of 1
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Monitoring Data\ GMA 1-ESA1.xlsMonitoring
3/9/2011
-
TABLE 21-9 AUTOMATED LNAPL/DNAPL & GROUNDWATER RECOVERY
SYSTEMS
EAST STREET AREA 2 - SOUTH GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD MASSACHUSETTS
February 2011
Recovery System
Location Month
Oil Collected
(gallon)
Water Recovered
(gallon) Percent
Downtime 17W February 2010 8
March 2010 29 0.69 April 2010 0 May 2010 0 June 2010 0 July 2010
1
August 2010 1 September 2010 2
October 2010 1 November 2010 1 December 2010 1 January 2011 1
February 2011 1
64R February 2010 10 207,185 March 2010 63 315,088 0.69 April
2010 13 409,804 May 2010 38 315,515 June 2010 50 108,507 0.83 July
2010 13 2,449
August 2010 0 234 September 2010 0 78
October 2010 0 74 November 2010 0 756 December 2010 0 58,709
January 2011 0 13,863 February 2011 0 165
64S System February 2010 175 562,253 March 2010 125 1,173,097
0.69 April 2010 388 1,174,787 May 2010 217 751,918 June 2010 275
595,798 1.67 July 2010 13 192,941
August 2010 0 125,196 September 2010 25 135,731
October 2010 0 241,520 November 2010 0 53,364 December 2010 50
370,789 January 2011 0 379,311 February 2011 13 207,582
64V February 2010 494 814,400 March 2010 864 1,198,000 0.69
April 2010 605 1,013,400 May 2010 320 842,300 June 2010 349 977,200
0.83 July 2010 473 729,500
August 2010 308 635,100 September 2010 452 710,000
October 2010 488 671,500 November 2010 660 698,300 December 2010
693 946,200 January 2011 398 754,100 February 2011 191 673,700
Page 1 of 3 G:\GE\GE_Pittsfield_General\Reports and
Presentations\Monthly Reports\2011\02-11\Monitoring Data\ GMA
1-ESA2.xlsActiveSum
3/9/2011
-
TABLE 21-9 AUTOMATED LNAPL/DNAPL & GROUNDWATER RECOVERY
SYSTEMS
EAST STREET AREA 2 - SOUTH GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD MASSACHUSETTS
February 2011
Recovery System
Location Month
Oil Collected
(gallon)
Water Recovered
(gallon) Percent
Downtime
64X February 2010 12 388,800 March 2010 50 518,400 3.47 April
2010 5 403,200 May 2010 14 388,800 June 2010 12 504,000 0.83 July
2010 123 417,600
August 2010 244 403,200 September 2010 80 489,600
October 2010 136 417,600 November 2010 12 403,200 December 2010
11 504,000 January 2011 77 417,600 February 2011 223 403,200
RW-2(X) February 2010 0 529,773 March 2010 0 638,070 0.69 April
2010 0 940,150 May 2010 0 790,610 June 2010 0 1,009,556 0.83 July
2010 0 836,449
August 2010 18 597,042 September 2010 0 650,874
October 2010 0 619,283 November 2010 0 597,254 December 2010 0
728,508 January 2011 0 613,128 February 2011 0 585,514
RW-1(S) 1 February 2010 32 454,396 March 2010 46 747,418 0.69
April 2010 35 747,264 May 2010 40 542,031 June 2010 45 596,864 0.83
July 2010 43 424,571
August 2010 66 354,852 September 2010 116 359,626
October 2010 96 368,039 November 2010 78 395,276 December 2010
72 565,709 January 2011 41 393,662 February 2011 39 325,872
RW-1(X) February 2010 0 266,084 March 2010 5 477,074 0.69 April
2010 5 325,230 May 2010 0 245,637 June 2010 0 307,238 0.83 July
2010 0 267,373
August 2010 0 238,247 September 2010 0 265,356
October 2010 0 241,721 November 2010 4 235,547 December 2010 5
298,760 January 2011 0 202,061 13.79 February 2011 0 236,214
Page 2 of 3 G:\GE\GE_Pittsfield_General\Reports and
Presentations\Monthly Reports\2011\02-11\Monitoring Data\ GMA
1-ESA2.xlsActiveSum
3/9/2011
-
TABLE 21-9 AUTOMATED LNAPL/DNAPL & GROUNDWATER RECOVERY
SYSTEMS
EAST STREET AREA 2 - SOUTH GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD MASSACHUSETTS
February 2011
Recovery System
Location Month
Oil Collected
(gallon)
Water Recovered
(gallon) Percent
Downtime
RW-4 February 2010 0 941,780 March 2010 6.2 1,239,425 0.69 April
2010 2.1 1,031,121 May 2010 0 955,661 June 2010 0 1,209,207 0.83
July 2010 18.7 951,492
August 2010 43.8 940,327 September 2010 48.4 571,022
October 2010 49.9 1,140,980 November 2010 31.2 1,097,835
December 2010 24.9 1,371,656 January 2011 20.9 1,134,138 February
2011 23 1,075,578
RW-3(X) February 2010 21 March 2010 39 0.69 April 2010 27 May
2010 40 June 2010 34 July 2010 36
August 2010 32 September 2010 55
October 2010 8 November 2010 16 December 2010 17 January 2011 30
February 2011 25
Summary of Total Automated Removal Water: 3,507,825 Gallons
LNAPL: 489 Gallons DNAPL: 25 Gallons
Notes:
1. The flow meter at recovery well RW-1(S) was reset in July
2009.
Page 3 of 3 G:\GE\GE_Pittsfield_General\Reports and
Presentations\Monthly Reports\2011\02-11\Monitoring Data\ GMA
1-ESA2.xlsActiveSum
3/9/2011
-
TABLE 21-10 WELL MONITORING AND RECOVERY OF LNAPL
EAST STREET AREA 2 - NORTH & SOUTH / 20s, 30s, & 40s
COMPLEXES GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Well Name
Date Depth
to Water (ft BMP)
Depth to LNAPL (ft BMP)
LNAPL Thickness
(feet)
LNAPL Removed
(liters)
February 2011 Removal (liters)
East Street Area 2 - South 13 2/11/2011 19.61 18.83 0.78 0.481
0.481 14 2/11/2011 19.56 18.88 0.68 0.419 0.419
25R 1/31/2011 21.72 21.71 0.01 0.006
0.0182/14/2011 22.18 22.17 0.01 0.006 2/21/2011 22.27 22.26 0.01
0.006
29
1/31/2011 18.67 18.66 0.01 0.006
0.0242/7/2011 18.71 18.70 0.01 0.006 2/14/2011 18.91 18.90 0.01
0.006 2/21/2011 18.86 18.85 0.01 0.006
48 2/11/2011 18.30 16.31 1.99 1.227 1.227 55 2/11/2011 14.96
13.62 1.34 0.826 0.826
95-04RR 2/11/2011 15.76 15.66 0.10 0.247 0.247
ES2-15R
1/31/2011 15.62 13.16 2.46 1.517
6.6052/7/2011 15.81 13.10 2.71 1.671 2/14/2011 16.08 13.32 2.76
1.702 2/21/2011 15.98 13.20 2.78 1.715
GMA1-14
1/31/2011 19.79 19.78 0.01 0.006
0.0242/7/2011 19.99 19.98 0.01 0.006 2/14/2011 20.33 20.32 0.01
0.006 2/21/2011 20.41 20.40 0.01 0.006
GMA1-15
1/31/2011 17.53 16.18 1.35 0.832
2.9042/7/2011 17.40 16.21 1.19 0.734 2/14/2011 17.70 16.37 1.33
0.820 2/21/2011 17.02 16.18 0.84 0.518
GMA1-16 2/10/2011 13.52 13.44 0.08 0.049 0.049
GMA1-19
1/31/2011 12.53 12.14 0.39 0.240
0.5592/7/2011 12.28 12.13 0.15 0.092 2/14/2011 12.56 12.41 0.15
0.092 2/21/2011 12.42 12.20 0.22 0.135
ESA2S-PZ-1
1/31/2011 14.95 12.90 2.05 1.264
4.7232/7/2011 14.65 12.89 1.76 1.085 2/14/2011 15.11 13.11 2.00
1.233 2/21/2011 14.76 12.91 1.85 1.141
ESA2S-PZ-2
1/31/2011 12.73 12.36 0.37 0.228
0.4422/7/2011 12.58 12.36 0.22 0.135 2/14/2011 12.68 12.66 0.02
0.012 2/21/2011 12.54 12.43 0.11 0.067
ESA2S-PZ-6
1/31/2011 14.88 14.25 0.63 0.388
0.8922/7/2011 14.61 14.20 0.41 0.252 2/14/2011 14.74 14.47 0.27
0.166 2/21/2011 14.41 14.27 0.14 0.086
ESA2S-PZ-7
1/31/2011 15.80 13.98 1.82 1.122
4.3902/7/2011 16.02 13.90 2.12 1.307 2/14/2011 16.11 14.17 1.94
1.196 2/21/2011 15.21 13.97 1.24 0.765
Total LNAPL Removal East Street Area 2 - South for February
2011: 23.830 liters 6.288 gallons
Total LNAPL Removal for February 2011: 23.830 liters 6.288
gallons
Note: 1. ft BMP - feet Below Measuring Point.
Page 1 of 1
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Monitoring Data\ GMA 1-ESA2.xlsLNAPL
3/9/2011
-
TABLE 21-11 WELL MONITORING AND RECOVERY OF DNAPL
EAST STREET AREA 2 - NORTH & SOUTH / 20s, 30s, & 40s
COMPLEXES GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Well Name
Date Depth
to Water (ft BMP)
Depth to DNAPL (ft BMP)
DNAPL Thickness
(feet)
DNAPL Removed
(liters)
February 2011 Removal (liters)
East Street Area 2 - South E2SC-03I* 2/22/2011 9.80 39.24 6.00
3.701 3.701
Total DNAPL Removal East Street Area 2 - South for February
2011: 3.701 liters 0.977 gallons
Total DNAPL Removal for February 2011: 3.701 liters 0.977
gallons
Note: 1. ft BMP - feet Below Measuring Point
Page 1 of 1
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Monitoring Data\ GMA 1-ESA2.xlsDNAPL
3/9/2011
-
TABLE 21-12 64G TREATMENT PLANT DISCHARGE DATA
GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Date Housatonic River
Discharge (gallons)
Recharge Pond Discharge (gallons)
Total Discharge (gallons)
February 2010 3,765,500 104,457 3,869,957
March 2010 5,497,600 40,836 5,538,436
April 2010 6,086,710 178,635 6,271,755
May 2010 5,012,180 211,489 5,223,669
June 2010 3,792,660 263,780 4,236,440
July 2010 3,613,250 299,406 3,912,656
August 2010 2,960,320 301,621 3,261,941
September 2010 2,431,150 305,952 2,737,102
October 2010 3,666,440 167,594 3,834,034
November 2010 3,589,280 193,924 3,783,204
December 2010 4,148,310 137,854 4,286,164
January 2011 3,891,960 157,751 4,049,711
February 2011 3,285,680 141,166 3,426,846
After treatment, the majority of the water processed at GE's
Building 64G groundwater treatment facility is discharged to the
Housatonic River through NPDES permitted Outfall 005. However, as
part of GE's overall efforts to contain NAPL within the site and to
optimize NAPL recovery operations, a portion of the treated water
discharged from the 64G facility is routed to GE's on-site recharge
pond located in East Street Area 2-South.
Page 1 of 1
G:\GE\GE_Pittsfield_General\Reports and Presentations\Monthly
Reports\2011\02-11\Monitoring Data\ GMA 1-ESA2.xls64G-Discharge
3/9/2011
-
TABLE 21-13 ROUTINE WELL MONITORING
EAST STREET AREA 2 - NORTH & SOUTH / 20s, 30s, & 40s
COMPLEXES GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Well Name
Measuring Point Elev.
(feet) Date
Depth to Water (ft BMP)
Depth to LNAPL (ft BMP)
LNAPL Thickness
(feet)
Depth to DNAPL (ft BMP)
Total Depth
(ft BMP)
DNAPL Thickness
(feet)
Corrected Water Elev.
(feet) 30's Complex
GMA1-29 989.72 2/15/2011 13.33 --- 0.00 --- 19.74 0.00 976.39
RF-02 983.36 2/15/2011 7.55 --- 0.00 --- 19.22 0.00 975.81
RF-03S 984.53 2/15/2011 8.85 --- 0.00 --- 14.94 0.00 975.68
RF-16R 986.48 2/15/2011 10.63 --- 0.00 --- 16.22 0.00 975.85
East Street Area 2 - South 13 990.88 2/11/2011 19.61 18.83 0.78
--- 23.22 0.00 972.00 14 991.61 2/11/2011 19.56 18.88 0.68 ---
25.28 0.00 972.68
18R NA 1/31/2011 13.58 --- 0.00 --- 18.74 0.00 NA 18R NA
2/7/2011 13.52 --- 0.00 --- 18.75 0.00 NA 18R NA 2/14/2011 13.74
--- 0.00 --- 18.74 0.00 NA 18R NA 2/21/2011 13.51 --- 0.00 ---
18.74 0.00 NA 19R 985.30 1/31/2011 13.59 --- 0.00 --- 20.33 0.00
971.71 19R 985.30 2/7/2011 13.53 --- 0.00 --- 20.33 0.00 971.77 19R
985.30 2/14/2011 13.79 --- 0.00 --- 20.34 0.00 971.51 19R 985.30
2/21/2011 13.54 --- 0.00 --- 20.35 0.00 971.76 25R 997.47 1/31/2011
21.72 21.71 0.01 --- 30.50 0.00 975.76 25R 997.47 2/7/2011 21.91
--- 0.00 --- 30.49 0.00 975.56 25R 997.47 2/14/2011 22.18 22.17
0.01 --- 30.50 0.00 975.30 25R 997.47 2/21/2011 22.27 22.26 0.01
--- 30.49 0.00 975.21
26RR 1,000.58 2/11/2011 23.69 23.54 0.15 --- 28.30 0.00 977.03
29 991.59 1/31/2011 18.67 18.66 0.01 --- 21.48 0.00 972.93 29
991.59 2/7/2011 18.71 18.70 0.01 --- 21.48 0.00 972.89 29 991.59
2/14/2011 18.91 18.90 0.01 --- 21.49 0.00 972.69 29 991.59
2/21/2011 18.86 18.85 0.01 --- 21.50 0.00 972.74 30 989.34
2/11/2011 13.44 13.32 0.12 --- 22.37 0.00 976.01 37 980.37
2/28/2011 Well covered by 12-14 feet of snow and ice. NA NA NA
40R 991.60 2/11/2011 Dry at 12.49 feet BMP NA NA NA 48 992.39
2/11/2011 18.30 16.31 1.99 --- 22.48 0.00 975.94
49R 988.71 2/10/2011 16.19 --- 0.00 --- 24.88 0.00 972.52 49RR
989.80 2/10/2011 17.26 --- 0.00 --- 22.93 0.00 972.54
55 985.97 2/11/2011 14.96 13.62 1.34 --- 26.54 0.00 972.26 64R
993.37 2/3/2011 16.38 16.37 0.01 --- 20.50 0.00 977.00 64R 993.37
2/10/2011 16.32 16.30 0.02 --- 20.50 0.00 977.07 64R 993.37
2/16/2011 16.60 16.59 0.01 --- 20.50 0.00 976.78 64R 993.37
2/24/2011 16.51 16.50 0.01 --- 20.50 0.00 976.87 64S 984.48
2/3/2011 19.22 --- 0.00 --- 28.70 0.00 965.26 64S 984.48 2/10/2011
19.56 --- 0.00 --- 28.70 0.00 964.92 64S 984.48 2/16/2011 19.43 ---
0.00 --- 28.70 0.00 965.05 64S 984.48 2/24/2011 19.46 --- 0.00 ---
28.70 0.00 965.02
64S-Caisson NA 2/3/2011 10.61 10.55 0.06 --- 14.55 0.00 NA
64S-Caisson NA 2/10/2011 10.54 10.52 0.02 --- 14.55 0.00 NA
64S-Caisson NA 2/16/2011 10.56 10.55 0.01 --- 14.55 0.00 NA
64S-Caisson NA 2/24/2011 10.54 10.52 0.02 --- 14.55 0.00 NA
64V 987.29 2/3/2011 20.99 20.82 0.17 P 29.60 < 0.01 966.46
64V 987.29 2/10/2011 21.90 21.67 0.23 P 29.60 < 0.01 965.60 64V
987.29 2/16/2011 20.93 20.64 0.29 P 29.60 < 0.01 966.63 64V
987.29 2/24/2011 21.10 20.54 0.56 P 29.60 < 0.01 966.71
64X(N) 984.83 2/3/2011 12.18 12.16 0.02 --- 15.85 0.00 972.67
64X(N) 984.83 2/10/2011 12.20 12.18 0.02 --- 15.85 0.00 972.65
64X(N) 984.83 2/16/2011 12.24 12.22 0.02 --- 15.85 0.00 972.61
64X(N) 984.83 2/24/2011 12.44 12.42 0.02 --- 15.85 0.00 972.41
64X(S) 981.56 2/3/2011 15.66 15.63 0.03 --- 23.82 0.00 965.93
64X(S) 981.56 2/10/2011 16.84 16.81 0.03 --- 23.82 0.00 964.75
64X(S) 981.56 2/16/2011 15.86 15.79 0.07 --- 23.82 0.00 965.77
64X(S) 981.56 2/24/2011 16.62 16.57 0.05 --- 23.82 0.00 964.99
64X(W) 984.87 2/3/2011 18.95 18.94 0.01 --- 24.35 0.00 965.93
Page 1 of 3 G:\GE\GE_Pittsfield_General\Reports and
Presentations\Monthly Reports\2011\02-11\Monitoring Data\ GMA
1-ESA2.xlsMonitoring
3/9/2011
-
TABLE 21-13 ROUTINE WELL MONITORING
EAST STREET AREA 2 - NORTH & SOUTH / 20s, 30s, & 40s
COMPLEXES GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Well Name
Measuring Point Elev.
(feet) Date
Depth to Water (ft BMP)
Depth to LNAPL (ft BMP)
LNAPL Thickness
(feet)
Depth to DNAPL (ft BMP)
Total Depth
(ft BMP)
DNAPL Thickness
(feet)
Corrected Water Elev.
(feet) 64X(W) 984.87 2/10/2011 18.87 18.86 0.01 --- 24.35 0.00
966.01 64X(W) 984.87 2/16/2011 19.00 18.96 0.04 --- 24.35 0.00
965.91 64X(W) 984.87 2/24/2011 18.89 18.87 0.02 --- 24.35 0.00
966.00 95-01R 986.21 2/11/2011 14.23 --- 0.00 --- 19.60 0.00
971.98
95-04RR 987.75 2/11/2011 15.76 15.66 0.10 --- 19.59 0.00 972.08
3-6C-EB-22 986.94 2/11/2011 14.28 --- 0.00 --- 19.38 0.00 972.66
E2SC-03I* 982.12 2/22/2011 9.80 --- 0.00 39.24 45.24 6.00 972.32
E2SC-06 986.00 2/22/2011 12.37 --- 0.00 --- 20.04 0.00 973.63
E2SC-23 992.07 2/10/2011 17.49 --- 0.00 --- 21.15 0.00 974.58
E2SC-24 987.90 2/10/2011 16.06 --- 0.00 --- 21.64 0.00 971.84
ES2-15R 986.20 1/31/2011 15.62 13.16 2.46 --- 19.48 0.00 972.87
ES2-15R 986.20 2/7/2011 15.81 13.10 2.71 --- 19.48 0.00 972.91
ES2-15R 986.20 2/14/2011 16.08 13.32 2.76 --- 19.49 0.00 972.69
ES2-15R 986.20 2/21/2011 15.98 13.20 2.78 --- 19.50 0.00 972.81
GMA1-14 997.43 1/31/2011 19.79 19.78 0.01 --- 22.49 0.00 977.65
GMA1-14 997.43 2/7/2011 19.99 19.98 0.01 --- 22.50 0.00 977.45
GMA1-14 997.43 2/14/2011 20.33 20.32 0.01 --- 22.50 0.00 977.11
GMA1-14 997.43 2/21/2011 20.41 20.40 0.01 --- 22.50 0.00 977.03
GMA1-15 988.59 1/31/2011 17.53 16.18 1.35 --- 17.78 0.00 972.32
GMA1-15 988.59 2/7/2011 17.40 16.21 1.19 --- 17.78 0.00 972.30
GMA1-15 988.59 2/14/2011 17.70 16.37 1.33 --- 17.79 0.00 972.13
GMA1-15 988.59 2/21/2011 17.02 16.18 0.84 --- 17.80 0.00 972.35
GMA1-16 986.82 2/10/2011 13.52 13.44 0.08 --- 19.98 0.00 973.37
GMA1-17E 993.03 2/10/2011 16.61 16.56 0.05 --- 17.29 0.00 976.47
GMA1-17W 992.63 2/3/2011 21.95 21.93 0.02 --- NM 0.00 970.70
GMA1-17W 992.63 2/10/2011 NM NM NM NM NM NM NM GMA1-17W 992.63
2/16/2011 NM NM NM NM NM NM NM GMA1-17W 992.63 2/24/2011 NM NM NM
NM NM NM NM GMA1-19 984.28 1/31/2011 12.53 12.14 0.39 --- 17.14
0.00 972.11 GMA1-19 984.28 2/7/2011 12.28 12.13 0.15 --- 17.15 0.00
972.14 GMA1-19 984.28 2/14/2011 12.56 12.41 0.15 --- 17.15 0.00
971.86 GMA1-19 984.28 2/21/2011 12.42 12.20 0.22 --- 17.15 0.00
972.06
GMA1-20R 984.31 1/31/2011 12.58 --- 0.00 --- 20.05 0.00 971.73
GMA1-20R 984.31 2/7/2011 12.49 --- 0.00 --- 20.04 0.00 971.82
GMA1-20R 984.31 2/14/2011 12.77 --- 0.00 --- 20.05 0.00 971.54
GMA1-20R 984.31 2/21/2011 12.54 --- 0.00 --- 20.04 0.00 971.77
GMA1-21 985.68 1/31/2011 13.68 --- 0.00 --- 19.54 0.00 972.00
GMA1-21 985.68 2/7/2011 13.54 --- 0.00 --- 19.55 0.00 972.14
GMA1-21 985.68 2/14/2011 13.79 --- 0.00 --- 19.55 0.00 971.89
GMA1-21 985.68 2/21/2011 13.52 --- 0.00 --- 19.54 0.00 972.16
GMA1-22 988.45 1/31/2011 16.04 --- 0.00 --- 19.15 0.00 972.41
GMA1-22 988.45 2/7/2011 15.94 --- 0.00 --- 19.15 0.00 972.51
GMA1-22 988.45 2/14/2011 16.18 --- 0.00 --- 19.15 0.00 972.27
GMA1-22 988.45 2/21/2011 15.92 --- 0.00 --- 19.15 0.00 972.53
GMA1-23R 985.67 1/31/2011 13.53 --- 0.00 --- 19.61 0.00 972.14
GMA1-23R 985.67 2/7/2011 13.53 --- 0.00 --- 19.61 0.00 972.14
GMA1-23R 985.67 2/14/2011 13.80 --- 0.00 --- 19.60 0.00 971.87
GMA1-23R 985.67 2/21/2011 13.55 --- 0.00 --- 19.60 0.00 972.12
GMA1-24R 985.40 1/31/2011 13.58 --- 0.00 --- 20.16 0.00 971.82
GMA1-24R 985.40 2/7/2011 13.52 --- 0.00 --- 20.16 0.00 971.88
GMA1-24R 985.40 2/14/2011 13.77 --- 0.00 --- 20.15 0.00 971.63
GMA1-24R 985.40 2/21/2011 13.53 --- 0.00 --- 20.14 0.00 971.87
GMA1-30 985.45 2/10/2011 14.04 --- 0.00 --- 20.15 0.00 971.41
HR-G2-MW-1 982.60 2/10/2011 11.42 --- 0.00 --- 18.25 0.00 971.18
HR-G2-MW-2 981.39 2/10/2011 8.83 --- 0.00 --- 17.67 0.00 972.56
HR-G2-MW-3 987.14 2/10/2011 15.27 --- 0.00 --- 21.45 0.00 971.87
HR-G2-RW-1 976.88 2/10/2011 6.69 --- 0.00 --- 18.71 0.00 971.88
ESA2S-PZ-1 985.04 1/31/2011 14.95 12.90 2.05 --- 23.77 0.00 972.00
ESA2S-PZ-1 985.04 2/7/2011 14.65 12.89 1.76 --- 23.78 0.00 972.03
ESA2S-PZ-1 985.04 2/14/2011 15.11 13.11 2.00 --- 23.78 0.00 971.79
ESA2S-PZ-1 985.04 2/21/2011 14.76 12.91 1.85 --- 23.78 0.00 972.00
ESA2S-PZ-2 984.30 1/31/2011 12.73 12.36 0.37 --- 22.22 0.00
971.91
Page 2 of 3 G:\GE\GE_Pittsfield_General\Reports and
Presentations\Monthly Reports\2011\02-11\Monitoring Data\ GMA
1-ESA2.xlsMonitoring
3/9/2011
-
TABLE 21-13 ROUTINE WELL MONITORING
EAST STREET AREA 2 - NORTH & SOUTH / 20s, 30s, & 40s
COMPLEXES GROUNDWATER MANAGEMENT AREA 1
CONSENT DECREE MONTHLY STATUS REPORT GENERAL ELECTRIC COMPANY -
PITTSFIELD, MASSACHUSETTS
February 2011
Well Name
Measuring Point Elev.
(feet) Date
Depth to Water (ft BMP)
Depth to LNAPL (ft BMP)
LNAPL Thickness
(feet)
Depth to DNAPL (ft BMP)
Total Depth
(ft BMP)
DNAPL Thickness
(feet)
Corrected Water Elev.
(feet) ESA2S-PZ-2 984.30 2/7/2011 12.58 12.36 0.22 --- 22.23
0.00 971.92 ESA2S-PZ-2 984.30 2/14/2011 12.68 12.66 0.02 --- 22.23
0.00 971.64 ESA2S-PZ-2 984.30 2/21/2011 12.54 12.43 0.11 --- 22.24
0.00 971.86 ESA2S-PZ-3 986.62 1/31/2011 14.73 --- 0.00 --- 24.40
0.00 971.89 ESA2S-PZ-3 986.62 2/7/2011 14.73 --- 0.00 --- 24.40
0.00 971.89 ESA2S-PZ-3 986.62