Top Banner
TRANSMISSION LINE & SUBSTATION PROJECTS COMPANY: ENTERGY SERVICES, INC. CUSTOMER: ARKANSAS ELECTRIC COOPERATIVE CORP (AECC) FACILITIES STUDY EJO NO. F4PPAR0525 Facility Study: T017 TRANSMISSION SERVICE FACILITIES STUDY OASIS# 77494473 System Impact Study: S001 Revision: 0 Rev Issue Date Description of Revision Prepared By Approved By A 3/1/13 Shell to team for input KC/IK AH B 3/21/13 Submitted for Construction input KC/IK AH C 4/1/13 Assembled for JET vote KC/IK AH 0 4/9/13 JET comments incorporated KC/IK AH
53

TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

Jun 29, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

TRANSMISSION LINE & SUBSTATION PROJECTS

COMPANY: ENTERGY SERVICES, INC.

CUSTOMER: ARKANSAS ELECTRIC COOPERATIVE CORP (AECC)

FACILITIES STUDY

EJO NO. F4PPAR0525

Facility Study: T017

TRANSMISSION SERVICE FACILITIES STUDY

OASIS# 77494473

System Impact Study: S001

Revision: 0

Rev Issue Date

Description of Revision Prepared

By Approved

By

A 3/1/13 Shell to team for input KC/IK AH

B 3/21/13 Submitted for Construction input KC/IK AH

C 4/1/13 Assembled for JET vote KC/IK AH

0 4/9/13 JET comments incorporated KC/IK AH

Page 2: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

2

TABLE OF CONTENTS

1.0 PROJECT SUMMARY ........................................................................... 4

1.1 Background and Project Need ................................................................................. 4

1.2 Scope Summary ....................................................................................................... 4

1.2.1 2013-2017 Approved Entergy Construction Plan Projects......................... 4

1.2.2 Upgrade the Haskell-Woodlawn Switching Station 115 kV Transmission Line 4

1.2.3 Upgrade the Hot Springs-Butterfield 115kV Transmission Line ................. 5

1.2.4 Upgrade the Butterfield-Haskell 115 kV Transmission Line ....................... 5

1.2.5 Upgrade the Carpenter Dam-Malvern South 115 kV Transmission Line ... 5

1.2.6 Upgrade the Arklahoma-Tigre Bay Sw. Station 115 kV Transmission Line 5

1.2.7 Upgrade the Tigre Bay Sw. Station-Panther Valley Switching Station 115 kV Transmission Line ............................................................................................ 6

1.2.8 Upgrade the Panther Valley Sw. Station-Fountain Lake 115 kV transmission line ................................................................................................... 6

1.2.9 Hot Springs EHV Substation: Replace two 115 kV autotransformer breakers ................................................................................................................ 6

1.2.10 Financial Rights for Supplemental Upgrades ........................................... 6

1.3 Cost Summary.......................................................................................................... 6

1.4 Schedule Summary .................................................................................................. 7

1.5 Automatic Generation Control .................................................................................. 7

2.0 SAFETY REQUIREMENTS .................................................................... 7

3.0 GENERAL ASSUMPTIONS ................................................................... 7

4.0 SCOPE OF WORK ................................................................................. 9

4.1 Upgrade the Haskell - Woodlawn Sw. Station 115 kV Transmission Line (936.1) ... 9

4.1.1 Haskell to Woodlawn Tap Point Rebuild.................................................. 10

4.1.2 Woodlawn Tap Point to Woodlawn switching station Reconductor ........ 11

Safety consideration and risks during construction: ..................................................... 14

Long lead Delivery Items: ............................................................................................. 14

4.2 Upgrade the Hot Springs-Butterfield 115 kV Transmission Line (936.1) ................ 15

Hot Springs-Butterfield Reconductor/ Rebuild ..................................................... 15

4.3 Upgrade the Butterfield-Haskell 115 kV Transmission Line (936.1) ....................... 18

Butterfield to Haskell Reconductor/ Rebuild ........................................................ 18

4.4 Upgrade the Carpenter Dam-Malvern South 115 kV Transmission Line (969) ...... 21

Carpenter Dam-Malvern South Rebuild .............................................................. 21

4.5 Upgrade the Arklahoma-Tigre Bay Switching Station 115 kV Transmission Line .. 24

Page 3: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

3

4.6 Upgrade the Tigre Bay Sw. Station-Panther Valley Switching Station 115 kV Transmission Line ............................................................................................... 25

4.7 Upgrade the Panther Valley Switching Station-Fountain Lake 115 kV Transmission Line ..................................................................................................................... 26

4.8 Hot Springs EHV Substation: Replace Two 115 kV Autotransformer Breakers ..... 27

Construction Sequencing and Special Issues .............................................................. 28

4.8 Butterfield Switching station ................................................................................... 31

4.10 Carpenter Dam Substation ................................................................................. 35

5.0 COST .................................................................................................... 37

6.0 UPGRADE CLASSIFICATION ............................................................. 37

7.0 SCHEDULE .......................................................................................... 38

8.0 RISK ASSESSMENT ............................................................................ 40

9.0 CONFIRMED RESERVATIONS ........................................................... 41

10.0 PRE-888 TRANSACTIONS ................................................................ 46

11.0 STUDY QUEUE .................................................................................. 48

12.0 ATTACHMENTS ................................................................................. 49

12.1 Table of Acronyms ............................................................................................... 49

12.2 Substation one lines ............................................................................................. 49

Page 4: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

4

1.0 PROJECT SUMMARY

1.1 Background and Project Need

The purpose of this Facilities Study is to determine the availability of transfer capability across Entergy’s transmission system from Entergy (EES) to Entergy (EES) to evaluate the Arkansas Electric Cooperative Corp (AECC) request for 660 MW of yearly network transmission service. The time period for this transfer is from 9/1/2017 until 9/1/2037. The direction of the transaction is EES to EES. The study was performed on the latest available 2017-2024 winter and 2018-2024 summer peak seasonal models using PSS/E and MUST software by Power Technologies Incorporated (PTI).

The facilities study identifies any transmission constraints resulting from the requested power transfer. The facilities study also includes cost estimates to correct any transmission constraints.

1.2 Scope Summary

The Facilities Study has identified some transmission constraints.

1.2.1 2013-2017 Approved Entergy Construction Plan Projects

The following project is approved in the 2013-2017 Entergy Construction Plan. This project is required to be in-service prior to the start of transmission service.

• Benton N.-Benton S.: Construct new 115 kV line – Expected ISD Summer 2013.

• Sheridan South 500 kV upgrade: Mabelvale 500 kV substation (replace 3 breakers, 13 switches, and 2 line traps) – Expected ISD Summer 2014.

1.2.2 Upgrade the Haskell-Woodlawn Switching Station 115 kV Transmission Line

The Haskell-Woodlawn Sw. Station 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV or Sheridan-Mabelvale 500 kV transmission line. It is required that the Haskell-Woodlawn Sw. Station 115 kV transmission line and all associated line equipment be upgraded from a capacity of 159 MVA to at least 240 MVA. The proposed upgrade rating is 261 MVA.

The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this same customer (OASIS #76583976). However, the proposed capacity of this upgrade in the previous study (OASIS #76583976) was 217 MVA. As noted above, this study requires a proposed capacity of 261 MVA. Therefore, this required upgrade would satisfy both transmission service requests (OASIS #77494473 and OASIS #76583976) if this request (OASIS #77494473) is confirmed.

Page 5: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

5

The amount of capacity created by this upgrade is 102MW, and the customer’s use of the capacity created is 75MW.

1.2.3 Upgrade the Hot Springs-Butterfield 115kV Transmission Line

The Hot Springs-Butterfield 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Hot Springs-Butterfield 115 kV transmission line and all associated line equipment be upgraded from a capacity of 239 MVA to at least 273 MVA. The proposed upgrade rating is 320 MVA.

The amount of capacity created by this upgrade is 81MW, and the customer’s use of the capacity created is 38W.

1.2.4 Upgrade the Butterfield-Haskell 115 kV Transmission Line

The Butterfield-Haskell 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Butterfield-Haskell 115 kV transmission line and all associated line equipment be upgraded from a capacity of 239 MVA to at least 266 MVA. The proposed upgrade rating is 320 MVA.

The amount of capacity created by this upgrade is 81MW, and the customer’s use of the capacity created is 31MW.

1.2.5 Upgrade the Carpenter Dam-Malvern South 115 kV Transmission Line

The Carpenter Dam-Malvern South 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Carpenter Dam-Malvern South 115 kV transmission line and all associated line equipment be upgraded from a capacity of 111 MVA to at least 121 MVA. The proposed upgrade rating is 176 MVA.

The amount of capacity created by this upgrade is 65MW, and the customer’s use of the capacity created is 11MW

1.2.6 Upgrade the Arklahoma-Tigre Bay Sw. Station 115 kV Transmission

Line

The Arklahoma-Tigre Bay Sw. Station 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Arklahoma-Tigre Bay Sw. Station 115 kV transmission line and all associated line equipment be upgraded from a capacity of 201 MVA to at least 211 MVA.

Review of the facilities studies workbook noted in section 4.5 indicates a revision is necessary to the workbook, and this upgrade is not needed.

Page 6: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

6

1.2.7 Upgrade the Tigre Bay Sw. Station-Panther Valley Switching Station 115 kV Transmission Line

The Tigre Bay Sw. Station-Panther Valley Sw. Station 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Tigre Bay Sw. Station-Panther Valley Sw. Station 115 kV transmission line and all associated line equipment be upgraded from a capacity of 201 MVA to at least 210 MVA.

Review of the facilities studies workbook noted in section 4.6 indicates a revision is necessary to the workbook, and this upgrade is not needed.

1.2.8 Upgrade the Panther Valley Sw. Station-Fountain Lake 115 kV

transmission line

The Panther Valley Sw. Station-Fountain Lake 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Panther Valley Sw. Station-Fountain Lake 115 kV transmission line and all associated line equipment be upgraded from a capacity of 201 MVA to at least 210 MVA.

Review of the facilities studies workbook noted in section 4.7 indicates a revision is necessary to the workbook, and this upgrade is not needed.

1.2.9 Hot Springs EHV Substation: Replace two 115 kV autotransformer

breakers

The Hot Springs-Arklahoma 115 kV transmission line overloads for the loss of the Hot Springs 500/115 kV autotransformer. Replacement of breakers B1501 and B1502 to increase their fault interrupting capability would allow the 115 kV bus tie to be closed, and thus, alleviate this constraint. This project is proposed in the 2013-2017 Entergy Construction Plan with an expected ISD of Summer 2013.

1.2.10 Financial Rights for Supplemental Upgrades

No FFR payments are required.

1.3 Cost Summary

The estimated total project cost is $27,293,613. This includes AFUDC and does not include Tax Gross Up which may apply if and where applicable. The estimate includes AFUDC and it will be waived should customer elect to make prepayment. The project cost is in 2013 dollars without any escalation. The ICT has assigned $561,557 as Base Plan upgrades and $26,732,056 as Supplemental Upgrade based on Attachment T of Entergy’s Open Access Transmission Tariff (OATT).

Page 7: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

7

1.4 Schedule Summary

The start of transfer is from 9/1/2017. Construction to alleviate all constraints would be completed by 10/27/2017 provided approval to proceed with the project is granted by 1 October 2013. Since the gap is only two months, after the development of project execution plan, it is likely that 1 Sept 2017 date can be achieved by scheduling tasks in more details.

1.5 Automatic Generation Control

Not applicable.

2.0 SAFETY REQUIREMENTS

Safety is a priority with Entergy. Safety will be designed into substations and lines. The designs will be done with the utmost safety of personnel in mind for construction, operation, and maintenance of the equipment. All employees working directly or indirectly for Entergy shall adhere to all rules and regulations outlined within the Entergy Safety manual. Entergy requires safety to be the highest priority for all projects. All Entergy and Contract employees must follow all applicable safe work procedures.

3.0 GENERAL ASSUMPTIONS

• Sufficient time will be allowed in approving the project enabling Entergy to prepare a

Project Execution Plan (PEP) and be able to complete the project, as per outlined in the schedule described provided below.

• Assumptions have been made in developing estimates without performing site visits, surveys, and soil borings. During PEP, these tasks will be completed and could have an impact on estimates and schedule.

• All costs above represent good faith estimates in escalated dollars based on 2013 rates, and could change considerably after development of a detailed PEP.

• Relay settings and RTU configurations details need to be specified during PEP stage, such as equipment and schemes for pilot protections.

• System changes will be modeled in ASPEN. Relay Impact Analysis will be performed by a settings engineer during PEP stage to identify requirements for relay/CT replacement, and settings revisions at the local and remote stations in the area. For example, affected elements include Z2, Z3, and ground over current settings, and so on. Some obsolete relays may need to be replaced.

• Communicate the project and protection coordination with nuclear, generation plants, load customers and other interconnected utilities, as appropriate.

• Comply with PRC-001, PRC-023 and relevant procedures, standards and guidelines, as appropriate. o PRC-001 protection coordination between transmission and generation could

affect the following stations � Blakely Dam � Carpenter Dam

Page 8: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

8

� Lake Catherine Plant � Remmel Dam

o Any affected stations should be notified per PRC-001. o The increase in MVA limit of the line conductor could affect PRC-023 requirements

between the following stations: � Woodlawn-Hot Springs 115kV � Carpenter Dam-Woodward 115kV � Cheetah-Arklahoma 115kV

• New RTU configurations or revisions will be necessary for stations where new equipment is installed or equipment replacement takes place. For example, there may be a need to map the additional points from a new or different relay.

• N-1 outage process and MISO modeling will be performed during PEP development.

Page 9: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

9

4.0 SCOPE OF WORK

4.1 Upgrade the Haskell - Woodlawn Sw. Station 115 kV Transmission Line (936.1)

General • The route for the Facility Study will consist of two sections:

o The first four miles of this line is 666 ACSR conductor on wooden H-Frames, built in the 1970’s. These four miles will have to be rebuilt in the existing Right Of Way.

o The last mile of this line (from the Woodlawn Tap, north to Woodlawn Switching station) was rebuilt in 2012 with 666 ACSR. These structures are adequate and can be reused. The existing conductor can be replaced with new ACSS conductor to achieve the desired rating.

Page 10: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

10

Transmission Line Data

Line Capacity MVA

Existing Line Rating 154

Required Line Rating (Minimum) – 1205A

240

Proposed Line Rating (based on Equipment to be installed)

261

Affected line length in miles 5.04

4.1.1 Haskell to Woodlawn Tap Point Rebuild • Provide a single circuit 115kV line from the Woodlawn Tap Point to Woodlawn switching

station, approximately 4.1 miles.

• The line will consist of single pole delta configuration structures.

• New topographical surveying will be required to support the design of this line.

• Soil borings will also be required.

• The route is in existing Right of Way.

• No new ROW will have to be procured.

Structures and Foundations • All structures will be estimated as steel poles.

• 35 Single Pole Delta Braced Post Steel Structures

• One (1) Three Pole Dead End guyed Steel Structure

• Soil Borings do not exist. It is assumed that all poles will be direct embedded. The deadend poles are assumed to be backfilled with concrete, the remainder to be backfilled with crushed rock. It is assumed that rock will be encountered on 40 percent of the structures, requiring rock drilling.

Conductor and Insulators • The conductor installed will be about 60,000 pounds (4.1 miles) of 666 ACSS. This is

rated for 1312 Amps, or 261 MVA at 115 kV.

• This segment will utilize 15 dead end insulators, and 105 braced post insulators. All insulators will be compression type polymer insulators with corona rings.

Shield Wire • The segment will use 24,550 feet of OPGW fiber.

• It is assumed that Avian protection will be required. Spacing will be approximately fifteen (15’) feet between diverters.

Removals • Remove 37 – wooden 2 pole H structures.

Page 11: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

11

• Remove 111 - insulators.

• Remove 60,000 pounds of 666 ACSR wire.

• Remove 24,550 feet of OPGW fiber.

4.1.2 Woodlawn Tap Point to Woodlawn switching station Reconductor

• The west circuit of the existing structures of this circuit will be reconductored with 666 ACSS conductor. This will allow the segment to be rated at 261 MVA.

• The existing structures and foundations are adequate to provide both support and clearance for the new conductor.

Conductor and Insulators • The conductor installed will be about 15,000 pounds (0.99 miles) of 666 ACSS. This is

rated for 1312 Amps, or 261 MVA at 115 kV.

• The polymer insulators will be reused, but 18 new compression deadends and 18 new suspension shoes will be required.

Shield Wire • No additional shield wire is required. OPGW fiber is already installed.

• Avian protection will remain on the existing shield wire. Removals • Remove 15,000 lbs of 666 ACSR wire.

Environmental Permitting Based on provided information related to routing, proposed construction efforts and desk-top analyses, the following efforts for environmental permitting, related activities and associated costing are provided. • Assume that the T-line currently exist as double-poled H-structures that will be

removed and replaced with single-pole structures resulting in a reduction in the overall number of poles with a wider span between poles than does currently exist.

• Assume the existing line is approximately 5.25 miles in length (4.25 miles of single circuit and 1.0 mile of double circuit single pole.

• Assume the Entergy T-line exists within its own 100 ft. right-of-way (ROW) and will be rebuilt within the same with no new ROW being required.

• Assume that no Federal connectivity exists within the scope of the project and as such, no compliance with the National Environmental Policy Act (NEPA) will be required.

• Agency consultation would include US Fish & Wildlife Service (USFWS), Arkansas Department of Environmental Quality (ADEQ), Arkansas Historic Preservation Program (State Historic Preservation Office-SHPO), National Resource Conservation Service (NRCS), USACE and the Arkansas Game and Fish Commission (AGFC). Archeological/historical sites have been identified in near proximity to the Saline River in another recent project (Benton North to Benton South). Threatened and endangered mussel species have also been documented to occur in nearby reaches of the Saline River. As such, special attention to these resources will likely be required by the governing agencies. While construction is expected to occur within

Page 12: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

12

the existing ROW, these concerns will need to be addressed and agency approval will be required.

• Based on desk-top analysis of area-specific topographic, aerial and USFWS wetland status maps for Arkansas, the landscape of the proposed T-line rebuild has been identified to include area agriculture, pasture and timber practices. Close proximity and/or crossing of the existing T-line to mapped jurisdictional wetlands and/or streams includes the Saline River and an associated finger, Dodson Creek, four un-named tributaries to Dodson Creek, a large tributary to Dotted Lake, three un-named tributaries to Trace Creek, three fingers of Trace Creek and a large pond near the Wright Chapel area offer the potential of construction impacts. Performance of on-the-ground surveys to fully determine the extent, potential impacts and Best Management Practices (BMPs) concerned with jurisdictional wetlands and/or other waters of the US (WOUS) will be required. The United States Army Corps of Engineers (USACE) has a nationwide permit (NW-12) available for utility line activities that includes utility line substations and foundations for overhead utility line towers, poles and anchors. The nature of the efforts to secure a nationwide permit may include field survey and delineation, delineation report, consultation with Clean Water Act (CWA) commenting agencies, development of a Wetland Impact Mitigation Plan (including the negotiation of credits with an approved mitigation bank) if required and the preparation and submittal of the permit application to the USACE. Since this is an existing line upgrade that will not include new ROW and/or related permanent impacts (dredging or filling) mitigation cost is not anticipated or included within this cost estimate.

• Construction Planning Support could include Constructability Review to assess site conditions requiring special consideration during the development of best management practices (BMPs) or regulatory permitting from the County government or the Arkansas Highway Transportation Department. It could include the review of stream crossings and consideration for all-weather access based on hydrological calculations of watershed size, topography, land use, etc. Ecologically/geographically sensitive areas will be identified and clearly marked. .

• Arkansas Department of Environmental Quality (ADEQ) requires compliance with applicable regulations for coverage under the Construction Storm Water General NPDES Permit. It includes the development and implementation of the Notice of Intent (NOI) and the Storm Water Pollution Prevention Plan (SWPPP) to provide a site-specific description of the best management practices to prevent contamination of the site storm flows from potential pollutants associated with construction activities. The plan also outlines implementation, inspection and maintenance requirements.

• Routine inspection and monitoring required by NPDES Construction Storm Water General Permit for the SWPPP. This will include review of BMPs and permit monitoring requirements, travel to construction site once per 7 days and preparing inspection reports. It will identify incidents of non-compliance and associated conditions, recommendations for corrective actions, their status and effectiveness including assessment of proper installation and maintenance.

• Installation of Best Management Practices (BMPs) in accordance with SWPPP. Migratory Bird Treaty Act protection covers most bird species found in the project area. Construction to (Avian Powerline Interaction Committee (APLIC) standards as described in Entergy’s Avian Protection Plan. Review of the area indicates concerns for wintering waterfowl and other water birds utilizing the habitats associated with the 14 water body crossings. At a minimum, 25 % of length of the ROW could be

Page 13: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

13

impacted total to approximately 1.3 miles. Bird collision protection is recommended for these areas at a placement of 1/15ft. of line length. Installation will occur during construction when the lines are clipped in.

• Concern exist that MITC (methyl isothiocyanate) tubes could be present as a pole treatment for the poles that will be removed. If so identified, that portion of the pole containing the MITC tube will be cut and properly disposed of prior to pole removal by the public. This is typically captured as a construction cost for demo and rebuild. No costing is provided for this effort.

• Contracting support for additional site visits above those noted as SWPPP inspections to develop more detailed erosion/sediment controls to be included in contract specifications prepared by Entergy. This will include any additional or modified BMPs in revisions of the SWPPP site maps and will support Entergy during the contracting process and after Entergy has selected the BMP installation contractor.

• Actions performed necessary to terminate the NPDES permit upon completion of construction and stabilization associated with the project. This will include photo documentation, delivery of all project documentation, and preparation of Notice of Termination (NOT) with signatures for submittal to the regulatory authority.

*This projection excludes costing for wetland mitigation as noted above. If the route remains within the existing ROW, no new ROW is required, only temporary impacts exist as identified and no clearing is involved (only some tree-trimming.

*The above estimate has been included in the overall project costs. Construction Methodology:

• Based on discussions with SOC, it is assumed that an outage will most likely not be granted for more than 6 weeks at a time. This means that some of the t-line re-builds will need to be constructed in three different outages. This will add substantial cost and time to the project.

• Construction has been asked to be prepared at all times return the line to service in a short amount of time (10 hours), the line will have to be rebuilt one structure at a time and cost and construction time will increase.

• In order to reconductor the double circuit section, both the Woodlawn-Haskell and Woodlawn to Bauxite lines must be in an outage. It is assumed that both lines can be in an outage at the same time. If an outage on both lines simultaneously is not granted, cost will increase as hot work may be required. Regardless, timing of construction will be critical and will be dictated by the periods of time in which Transmission Planning can operate the grid with both lines out of service.

• Regulations and internal policies will require that Abnormal Protection System Requests (APS) be submitted and approved before outages are approved for any transmission line work that could affect relay protection.

• Construction will likely begin at Haskell and the single section of line will be rebuilt. After this section is rebuilt, the double circuit section will be rebuilt.

• Parts of this line lie in low areas that can tend to flood in seasons of high water. Should the construction fall within flooded periods, cost will increase as different and/or additional equipment will be required, as well as increased Storm Water Pollution Prevention Plan costs.

Page 14: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

14

• Due to the fact that the area is known to flood occasionally, track equipment will be specified by Construction for this project.

• The SWPPP measures will be installed prior to mobilizing a transmission line crew. • After line construction is complete, SWPPP measures must be removed and the

Right-Of-Way restored to original conditions or stabilized to meet ADEQ requirements

Outage Planning

After project approval, outages will be submitted to TOC. The chances of obtaining the line outage approval during extreme cold or hot conditions are minimal. However, it is anticipated that the transmission line construction will be performed during spring or fall. This will enhance the ability to obtain the necessary outages. There could be some difficulty in obtaining simultaneous outages for the double-circuit portion of line that is approximately 1-mile in length. This section will need careful planning and construction timing to fall within a window that will allow an outage simultaneously on the Woodlawn-Haskell and Woodlawn-Bauxite 115kV transmission lines. Based on discussion with the SOC, it will be difficult to even get 6 week outages for the Woodlawn to Hot Springs branch or Fountain Lake to Panther Valley section.

Safety consideration and risks during construction:

All Entergy safety rules will be observed and practiced during construction. EPZ techniques will be required during the entire transmission line construction. Risks associated with the transmission line cut-in include outage submittal and approval, weather conditions, and progress of the substation construction.

Long lead Delivery Items:

• Poles -22 weeks • Conductors – 25 weeks • Insulators – 20 weeks

Relay Settings:

See relay settings comments in 4.3.

Page 15: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

15

4.2 Upgrade the Hot Springs-Butterfield 115 kV Transmission Line (936.1)

General The Hot Springs-Butterfield 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Hot Springs-Butterfield 115 kV transmission line and all associated line equipment be upgraded from a capacity of 239 MVA to at least 273 MVA.

• The affected line is approximately 3.69 miles. • Line and line equipment at both terminals would need to be rated at a minimum of

1371 amps (273 MVA @ 115 kV).

Line Capacity MVA

Existing Line Rating 239

Required Line Rating (Minimum) – 1371A

273

Proposed Line Rating (based on Equipment to be installed)

320

Affected line length in miles 3.7

Hot Springs-Butterfield Reconductor/ Rebuild • The existing line will be reconductored with 954 ACSS Conductor.

• The existing line is supported on the North side of single pole vertical configuration double circuit structures. These structures also support line 968.1 which bypasses Butterfield sub and proceeds towards Malvern North Switching Station. The existing structures are of adequate class to support the new conductor, but approximately six structures will require replacement in order to maintain standard design clearances at the full rating of the new conductor.

• New ground surveying will be required to verify the accuracy of the existing LIDAR (Light Detection and Ranging) surveys with regard to new obstructions.

• Soil borings will not be required. The new structures will be at the same location as the replaced structures.

• The route is in existing Right of Way.

• No new ROW will have to be procured.

Structures and Foundations • All structures will be estimated as steel poles.

• Approximately six single pole double circuit vertical Braced Post Steel Structures will need to be replaced in order to maintain standard ground clearances.

Page 16: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

16

• The existing borings show good soils which will allow directly embedded foundations, backfilled with crushed rock. There is some shale on the Hot Springs end of the line, which may complicate excavation.

Conductor and Insulators • The conductor installed will be about 75,000 pounds (3.7 miles) of 954 ACSS. This is

rated for 1607 Amps, or 320 MVA at 115 kV.

• The polymer insulators will be reused, but 24 new compression deadends and 90 new suspension shoes will be required.

Shield Wire • No additional shield wire is required. OPGW fiber is already installed.

• It is assumed that Avian protection will be required on this segment. Spacing will be approximately fifteen (15’) feet between diverters.

Removals • Remove 6 – directly embedded steel poles. • Remove 70,000 pounds of 1272 ACSR conductor.

Long Delivery Items

Quantity Material Description *Lead Time

(weeks) 60,000 # 954 ACSS Conductor 25

Relay Settings

See relay settings comments in 4.3.

Construction methodology

• Based on discussions with SOC, it is assumed that an outage will most likely not be granted for more than 6 weeks at a time. This means that some of the t-line re-builds will need to be constructed in three different outages. This will add substantial cost and time to the project.

• Construction has been asked to be prepared at all times return the line to service in a short amount of time (10 hours), the line will have to be rebuilt one structure at a time and cost and construction time will increase.

• In order to reconductor the double circuit section, both the Hot Springs to Butterfield and Hot Springs to Malvern North lines must be in an outage. It is assumed that both lines can be in an outage at the same time. If an outage on both lines simultaneously is not granted, cost will increase as hot work may be required. Regardless, timing of construction will be critical and will be dictated by the periods of time in which Transmission Planning can operate the grid with both lines out of service.

• Regulations and internal policies will require that Abnormal Protection System Requests (APS) be submitted and approved before outages are approved for any transmission line work that could affect relay protection.

Page 17: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

17

• Parts of this line lie in low areas that can tend to flood in seasons of high water. Should the construction fall within flooded periods, cost will increase as different and/or additional equipment will be required, as well as increased Storm Water Pollution Prevention Plan costs.

• Due to the fact that the area is known to flood occasionally, track equipment will be specified by Construction for this project.

• The SWPPP measures will be installed prior to mobilizing a transmission line crew. • After line construction is complete, SWPPP measures must be removed and the

Right-Of-Way restored to original conditions or stabilized to meet ADEQ requirements

Page 18: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

18

4.3 Upgrade the Butterfield-Haskell 115 kV Transmission Line (936.1)

General The Butterfield-Haskell 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Butterfield-Haskell 115 kV transmission line and all associated line equipment be upgraded from a capacity of 239 MVA to at least 266 MVA.

• The affected line is approximately 11.09 miles. • Line and line equipment at both terminals would need to be rated at a minimum of

1335 amps (266 MVA @ 115 kV).

Line Capacity MVA

Existing Line Rating 239

Required Line Rating (Minimum) – 1335A

266

Proposed Line Rating (based on Equipment to be installed)

320

Affected line length in miles 11.09

Butterfield to Haskell Reconductor/ Rebuild • The existing line will be reconductored with 954 ACSS Conductor.

• For approximately the first ten spans, the line is supported on the North side of single pole vertical configuration double circuit structures. These structures also support line 968.1 which then branches off towards Malvern North Switching Station. The remainder of the line is constructed of concrete single-pole delta structures. The existing structures are of adequate class to support the new conductor, but approximately twenty structures will require replacement in order to maintain standard design clearances at the full rating of the new conductor.

• New ground surveying will be required to verify the accuracy of the existing LIDAR surveys with regard to new obstructions.

• Soil borings will not be required. The new structures will be at the same location as the replaced structures.

• The route is in existing Right of Way.

• No new ROW will have to be procured.

Structures and Foundations • All structures will be estimated as concrete poles.

• Approximately one (1) Single Pole double circuit vertical Braced Post Steel Structure and 19 Single pole single circuit delta braced post structures will need to be replaced in order to maintain standard ground clearances.

Page 19: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

19

• The existing borings show good soils which will allow directly embedded foundations, backfilled with crushed rock.

Conductor and Insulators • The conductor installed will be about 220,000 pounds (11.1 miles) of 954 ACSS. This is

rated for 1607 Amps, or 320 MVA at 115 kV.

• The polymer insulators will be reused, but 33 new compression deadends and 360 new suspension shoes will be required.

Shield Wire • No additional shield wire is required. OPGW fiber is already installed.

• It is assumed that Avian protection will not be added to this segment, since it does not pass near water or through expansive open areas.

Removals • Remove 20 – directly embedded concrete poles. • Remove 70,000 pounds of 1272 ACSR conductor.

Long Delivery Items

Quantity Material Description *Lead Time

(weeks) 60,000 # 954 ACSS Conductor 25

Relay Settings

• Revise ASPEN model. • If reconductoring results in a change of line impedance greater than 5%, revise zone

impedance reaches at Hot Springs and Woodlawn Substations. • Review and revise overcurrent relay settings at Hot Springs and Woodlawn as

necessary. • Apply PRC-023 requirements. • Review and revise zone 2 and 3 for the following transmission lines if necessary:

o Mabelvale—Woodlawn 115kV o River Ridge—Woodlawn 115kV o Arklahoma—Hot Springs 115kV Line #1 o Arklahoma—Hot Springs 115kV Line #3 o Woodward—Hot Springs 115kV

• Provide on/off site technical support during construction. • Complete “AS-BUILT” process for all relay settings issued.

Construction methodology

• Based on discussions with SOC, it is assumed that an outage will most likely not be granted for more than 6 weeks at a time. This means that some of the t-line re-builds will need to be constructed in three different outages. This will add substantial cost and time to the project.

Page 20: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

20

• Construction has been asked to be prepared at all times return the line to service in a short amount of time (10 hours), the line will have to be rebuilt one structure at a time and cost and construction time will increase.

• In order to reconductor the double circuit section, both the Butterfield to Haskell and Hot Springs to Malvern North lines must be in an outage. It is assumed that both lines can be in an outage at the same time. If an outage on both lines simultaneously is not granted, cost will increase as hot work may be required. Regardless, timing of construction will be critical and will be dictated by the periods of time in which Transmission Planning can operate the grid with both lines out of service.

• Regulations and internal policies will require that Abnormal Protection System Requests (APS) be submitted and approved before outages are approved for any transmission line work that could affect relay protection.

• Parts of this line lie in low areas that can tend to flood in seasons of high water. Should the construction fall within flooded periods, cost will increase as different and/or additional equipment will be required, as well as increased Storm Water Pollution Prevention Plan costs.

• Due to the fact that the area is known to flood occasionally, track equipment will be specified by Construction for this project.

• The SWPPP measures will be installed prior to mobilizing a transmission line crew. • After line construction is complete, SWPPP measures must be removed and the

Right-Of-Way restored to original conditions or stabilized to meet ADEQ requirements

Page 21: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

21

4.4 Upgrade the Carpenter Dam-Malvern South 115 kV Transmission Line (969)

General

The Carpenter Dam-Malvern South 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Carpenter Dam-Malvern South 115 kV transmission line and all associated line equipment be upgraded from a capacity of 111 MVA to at least 121 MVA.

• The new line will be approximately 13.40 miles. • Line and line equipment at both terminals would need to be rated at a minimum of

608 amps (121 MVA @ 115 kV).

Line Capacity MVA

Existing Line Rating 111

Required Line Rating (Minimum) – 608A

121

Proposed Line Rating (based on Equipment to be installed)

176

Affected line length in miles 13.4

Carpenter Dam-Malvern South Rebuild

• Provide a single circuit 115kV line from the Carpenter Dam to the Malvern South

substation, approximately 13.4 miles.

• The line will consist of single pole delta configuration structures.

• New topographical surveying will be required to support the design of this line.

• Soil borings will also be required.

• The route is in existing Right of Way.

• No new ROW will have to be procured.

Structures and Foundations • All structures will be estimated as steel poles.

• 115 Single Pole Delta Braced Post Steel Structures

• Five Three Pole Dead End guyed Steel Structure

• Soil borings do not exist. It is assumed that all poles will be direct embedded. The deadend poles are assumed to be backfilled with concrete, the remainder to be backfilled with crushed rock. It is assumed that rock will be encountered on 40 percent of the structures, requiring rock drilling.

Conductor and Insulators

Page 22: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

22

• The conductor installed will be about 190,000 pounds (13.4 miles) of 666 ACSR. This is rated for 882 Amps, or 176 MVA at 115 kV.

• This segment will utilize 42 dead end insulators, and 330 braced post insulators. All insulators will be compression type polymer insulators with corona rings.

Shield Wire • The segment will use 92,000 feet of OPGW fiber.

• It is assumed that Avian protection will be required on one fourth of the line. Spacing will be approximately fifteen (15’) feet between diverters.

Removals • Remove 116 – wooden pole H structures.

• Remove 370 - insulators.

• Remove 100,000 pounds of 397ACSR wire.

• Remove 180,000 feet of steel shield wire.

Relay Settings

• PRC-001: Carpenter Dam • PRC-001: Blakely Dam • Revise ASPEN model. • If reconductoring results in a change of line impedance greater than 5%, revise zone

impedance reaches at Carpenter Dam and Woodward Substations. • Review and revise overcurrent relay settings at Carpenter Dam and Woodward as

necessary. • Apply PRC-023 requirements. • Review and revise zone 2 and 3 for the following transmission lines if necessary:

o Hot Springs—Carpenter Dam 115kV o Arklahoma—Carpenter Dam 115kV o Blakely Dam—Carpenter Dam 115kV o Stuttgart Ricuskey--Woodward 115kV o Pine Bluff Dierks--Woodward 115kV o White Bluff—Woodward 115kV Line #1 o White Bluff—Woodward 115kV Line #2 o Hot Springs—Woodward 115kV o Degray SPA—Woodward 115kV o Fordyce—Woodward 115kV o Monticello East—Woodward 115kV o Pine Bluff South—Woodward 115kV

• Provide on/off site technical support during construction. • Complete “AS-BUILT” process for all relay settings issued.

Construction Methodology

• Based on discussions with SOC, it is assumed that an outage will most likely not be granted for more than 6 weeks at a time. This means that some of the t-line re-builds will need to be constructed in three different outages. This will add substantial cost and time to the project.

Page 23: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

23

• Construction has been asked to be prepared at all times return the line to service in a short amount of time (10 hours), the line will have to be rebuilt one structure at a time and cost and construction time will increase.

• Regulations and internal policies will require that Abnormal Protection System Requests (APS) be submitted and approved before outages are approved for any transmission line work that could affect relay protection.

• Parts of this line lie in low areas that can tend to flood in seasons of high water. Should the construction fall within flooded periods, cost will increase as different and/or additional equipment will be required, as well as increased Storm Water Pollution Prevention Plan costs.

• Due to the fact that the area is known to flood occasionally, track equipment will be specified by Construction for this project.

• The SWPPP measures will be installed prior to mobilizing a transmission line crew. • After line construction is complete, SWPPP measures must be removed and the

Right-Of-Way restored to original conditions or stabilized to meet ADEQ requirements

Page 24: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

24

4.5 Upgrade the Arklahoma-Tigre Bay Switching Station 115 kV Transmission Line

General

The Arklahoma-Tigre Bay Sw. Station 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Arklahoma-Tigre Bay Sw. Station 115 kV transmission line and all associated line equipment be upgraded from a capacity of 201 MVA to at least 211 MVA. No T-Line work is required. Per drawing A2505P01 through A2505P02, this line was rebuilt in 1998 to current standards and strung with 954 ACSR Cardinal rated for 217 MVA The rating for this T-Line segment should be revised on the ratings worksheet to reflect a rating of 1088 Amps which is 217 MVA at 115 kV.

• The new line will be approximately 1.37 miles. • Line and line equipment at both terminals would need to be rated at a minimum of

1059 amps (211 MVA @ 115 kV).

Line Capacity MVA

Existing Line Rating 217

Required Line Rating (Minimum) – 1059A

211

Proposed Line Rating (based on Equipment to be installed)

NA

Affected line length in miles 1.37

Page 25: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

25

4.6 Upgrade the Tigre Bay Sw. Station-Panther Valley Switching Station 115 kV Transmission Line

General

The Tigre Bay Sw. Station-Panther Valley Sw. Station 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Tigre Bay Sw. Station-Panther Valley Sw. Station 115 kV transmission line and all associated line equipment be upgraded from a capacity of 201 MVA to at least 210 MVA. No T-Line work is required. Per drawing A2505P01 through A2505P02, this line was rebuilt in 1998 to current standards and strung with 954 ACSR Cardinal rated for 217 MVA The rating for this T-Line segment should be revised on the ratings worksheet to reflect a rating of 1088 Amps which is 217 MVA at 115 kV.

• The new line will be approximately 6.64 miles. • Line and line equipment at both terminals would need to be rated at a minimum of

1054 amps (210 MVA @ 115 kV).

Line Capacity MVA

Existing Line Rating 217

Required Line Rating (Minimum) – 1054 A

210

Proposed Line Rating (based on Equipment to be installed)

NA

Affected line length in miles 6.64

Page 26: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

26

4.7 Upgrade the Panther Valley Switching Station-Fountain Lake 115 kV Transmission Line

General The Panther Valley Sw. Station-Fountain Lake 115 kV transmission line overloads for the loss of the Sheridan-Magnet Cove 500 kV transmission line. It is required that the Panther Valley Sw. Station-Fountain Lake 115 kV transmission line and all associated line equipment be upgraded from a capacity of 201 MVA to at least 210 MVA.

No T-Line work is required. Per drawing A2505P01 through A2505P02, this line was rebuilt in 1998 to current standards and strung with 954 ACSR Cardinal rated for 217 MVA The rating for this T-Line segment should be revised on the ratings worksheet to reflect a rating of 1088 Amps which is 217 MVA at 115 kV.

• The new line will be approximately 3.35 miles • Line and line equipment at both terminals would need to be rated at a minimum of

1054 amps (210 MVA @ 115 kV).

Line Capacity MVA

Existing Line Rating 217

Required Line Rating (Minimum) – 1054A

210

Proposed Line Rating (based on Equipment to be installed)

NA

Affected line length in miles 3.35

.

Page 27: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

27

4.8 Hot Springs EHV Substation: Replace Two 115 kV Autotransformer Breakers

General

The Hot Springs-Arklahoma 115 kV transmission line overloads for the loss of the Hot Springs 500/115 kV autotransformer. Replacement of breakers B1501 and B1502 to increase their fault interrupting capability would allow the 115 kV bus tie to be closed, and thus, alleviate this constraint. Hot Spring EHV SS breakers B1501 and B1502 should be upgraded to 63kA breakers. This project is proposed in the 2013-2017 Entergy Construction Plan with an expected ISD of Summer 2013. Site All site preparation resulting in ground disturbance must implement best management practices (BMPs) to prevent sediment from going off-site. No construction activities will be allowed outside the existing substation fence due to a Native American cultural feature located adjacent to the substation. Any construction activities outside the existing fence line will require a Phase I Environmental Site Impact (ESI) study and a State Historic Preservation Office (SHPO) permit prior to any construction activities.

Foundations • Install approximately 120 ft of 3” PVC conduits. Four, 3” PVC conduits will be

installed from each breaker to the nearest manhole location.

• Disturbed areas with be filled with 6” of crushed rock.

Electrical • Disconnect and remove existing circuit breakers B1501 and B1502.

• Cut existing anchor bolts flush with top of breaker foundations.

• Install new 63kA breakers and fasten them to the existing foundations using hilti bolts.

• Reconnect existing above ground “pigtails” to new breakers.

• Remove existing above ground conduits and install new above ground conduits to the breakers.

• New jumpers will be triple 954 ACSR jumpers to get to a 3000A rating. The 3000A jumpers are needed so that the conductors themselves are not the limiting element in the corresponding bays.

Relay • Current project (expected ISD: May 2013) will complete relay design on this project.

No further relay work will be needed.

Relay Settings • Revise settings if required based on selection of new CT ratios.

Communications and SCADA • Reconfigure for any additional alarms.

Page 28: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

28

CONSTRUCTION MANAGEMENT PLAN

Construction Sequencing and Special Issues

The overall proposed construction sequence, and associated issues/assumptions, can be summarized as follows:

• All construction will take place on Company’s property.

• Work will be taking place near energized transmission lines during all phases of construction. All contractors, both electrical and non-electrical, should be aware of published guidelines for maintaining clearance (different for electrical vs. non-electrical workers).

• All construction activities will be managed by Company personnel.

• Foundation construction inside the fence will be contracted out. This work will either be bid out or assigned to an approved vendor.

• It is currently assumed that a majority of Substation Electrical and Relay construction will be contracted out since Asset Management may have inadequate in-house resources available to support this project. AM will be given first right-of-refusal for this work. At a minimum, AM will still need to be involved in final checkout and commissioning of all Relay equipment.

• Substation Electrical construction may be covered by a Contract Inspector, or Operations Coordinators. Relay construction coordination will be covered by in-house personnel.

• Construction schedule will follow the project schedule.

Construction Plan

Site:

• Receive and review site package.

• Prepare bid package and bid project for site work.

• Evaluate and award bid.

• Contractor to perform site work.

Foundations/Conduits/Grounding:

• Receive and review foundation package.

• Prepare bid package and bid project for foundation work.

• To avoid outages for foundation work the foundations need to be spread footer if possible, but if they are not of this type then outages may be needed to get drilling machinery in the station.

• Evaluate and award bid.

• Contractor to perform foundation work.

Electrical:

• Receive and review electrical package.

• Prepare bid package and bid project for electrical work.

• If the shield wire is removed lightning masts need to be put up in their place.

Page 29: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

29

• Evaluate and award bid.

• Contractor to perform electrical work.

• Review and walk-down for in-service connections.

Relay:

• Review relay installation plan.

• Receive and review relay plan.

• The relay designer needs to verify if the PT inputs to the relays or the DC sources to relays in existing control house are daisy chained. If this is the case then this can be remedied during the operating bus outage that will be taken during the electrical construction, but a supplementary design package may be required.

• Prepare bid package and bid project for wiring work.

• Evaluate and award bid. Schedule resources for relay installation and testing.

• Review power connections tie-in.

• Review phasing/testing for in-service tie in.

Other:

• Material coordination, disposition, and return.

• Hazards Identification.

• Review and address safety/working clearances.

• Review and submit as-built drawings.

• Close out project

Outage Plan • Outage requests will be submitted in TAORS for all transmission line/bus/equipment

outages. Refer to preliminary project schedule (Attachment A) for proposed outage dates based on the assumed project start date.

• The detail outage plan will be developed at a later date. Bus outages and possibly line outages will be required to relocate the existing capacitor bank as well as installing the new capacitor bank. We will work with TOPS to limit the outages required and the time the station will be w/o a capacitor bank.

• Once the base line schedule is developed including procurement dates for all material, a detailed outage schedule will be developed. As soon as this schedule is received, Construction will enter all required AORS request.

Line or Bus Device

#s Reason

Est. Duration

Substation Buses

Operating Bus Replace 115kV Breakers TBD Transfer Bus Replace 115kV Breakers TBD

Page 30: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

30

ROW, PERMITTING, and ENVIRONMENTAL COMPLIANCE PLANS Permitting & Environmental

• Less than one (1) acre of ground disturbance is anticipated during construction activities for this project during; therefore, a Stormwater Pollution Prevention Permit (SWPPP) will not be required. However, the implementation of best management practices (BMPs) will be required to prevent any sediment from reaching an unnamed tributary located 100-foot to the southwest. Sediment fences must be placed down gradient of the construction areas inside the existing substation fence along the site perimeter.

• No construction activities will be allowed outside the existing substation fence since a historic site is located adjacent to the substation, i.e., a Native American site. Additional permits would be required before any such activities could occur outside the existing substation property.

• All new electrical equipment installed during this project will strictly follow avian protection standards as set forth in Entergy’s Substation Wildlife Manual.

Special Safety Considerations during Construction and Site Visits

• There are no known safety and environmental hazards that are known or expected to be present.

• There is no hot work planned. • Outages will be closely coordinated with the TOC, SOC and DOC. • A part-time on-site safety inspector may be used during this project

Page 31: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

31

4.8 Butterfield Switching station

General

• Need to replace line disconnect switches B3317 and B8617and through bus – from 1200A to a minimum of 1,371A.

Site • No site work required. Foundations • No site work required.

Electrical • Remove two (2) existing 115kV, 1200A Line Switches. • Remove existing 115kV operation bus. • Install two (2) 115kV, 2000A Vertical Break Line Switches motor operated, with

quick break attachment and ground switch. • Install bundle 954 KCMIL ACSR operation bus. • Install jumpers, fittings and other miscellaneous materials to support the complete

installation and safe operation. • Install above ground conduits.

Relay Design

• Purchase and install one (1) MOS-2 (motor operated switch) Panel at Butterfield for switch B3317 (to Haskell) and switch B8617 (to Hot Springs EHV).

• Run new cables from motor ops to panel.

Long Delivery Items

Quantity Material Description *Lead Time

(weeks)

2 Install two (2) 115kV, 2000A Vertical Break Line Switches motor operated, with quick break attachment and ground switch.

20

1 MOS-2 Panel 12-14

Construction methodology The overall proposed construction sequence, and associated issues/assumptions, can be summarized as follows:

• All construction will take place on Company’s property. • Work will be taking place near energized transmission lines during all phases of

construction. All contractors, both electrical and non-electrical, should be aware of published guidelines for maintaining clearance (different for electrical vs. non-electrical workers).

• A mobile transformer or switch will be required to complete construction.

Page 32: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

32

• All construction activities will be managed by Company personnel. • Foundation construction inside the fence will be contracted out. This work will

either be bid out or assigned to an approved vendor. • It is currently assumed that a majority of Substation Electrical and Relay

construction will be contracted out since Asset Management (AM) may have inadequate in-house resources available to support this project. AM will be given first right-of-refusal for this work. At a minimum, AM will still need to be involved in final checkout and commissioning of all Relay equipment.

• Substation Electrical construction may be covered by a Contract Inspector, or Operations Coordinators. Relay construction coordination will be covered by in-house personnel.

• Construction schedule will follow the project schedule.

Construction Plan

Electrical:

• Receive and review electrical package. • Prepare bid package and bid project for electrical work. • If the shield wire is removed lightning masts need to be put up in their place. • Evaluate and award bid. • Contractor to perform electrical work. • Review and walk-down for in-service connections.

Relay:

• Review relay installation plan. • Receive and review relay plan. • The relay designer needs to verify if the PT inputs to the relays or the DC sources

to relays in existing control house are daisy chained. If this is the case then this can be remedied during the operating bus outage that will be taken during the electrical construction, but a supplementary design package may be required.

• Prepare bid package and bid project for wiring work. • Evaluate and award bid. Schedule resources for relay installation and testing. • Review power connections tie-in. • Review phasing/testing for in-service tie in.

Other:

• Material coordination, disposition, and return. • Hazards Identification. • Review and address safety/working clearances. • Review and submit as-built drawings. • Close out project

Outage Planning

• An outage will be required on the high voltage bus. • A mobile transformer or switch will be required to complete construction.

Page 33: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

33

4.9 Haskell Switching Station

General

• Need to replace line disconnect switches B1312 and B1633 and through bus – from 1200A to a minimum of 1,336A.

Site • No site work required. Foundations • No site work required.

Electrical • Remove two (2) existing 115kV, 1200A Line Switches. • Remove existing 115kV operation bus. • Install two (2) 115kV, 2000A Vertical Break Line Switches motor operated, with

reduce voltage vacuum interrupter and ground switch. • Install bundle 954 KCMIL ACSR operation bus. • Install jumpers, fittings and other miscellaneous materials to support the complete

installation and safe operation. • Install above ground conduits.

Relay Design

• Purchase and install one (1) MOS-2 Panel at Haskell for switch B1633 (to Butterfield) and switch B1312 (to Woodlawn SS).

• Run new cables from motor ops to panel.

Long Delivery Items

Quantity Material Description *Lead Time

(weeks)

2 Install two (2) 115kV, 2000A Vertical Break Line Switches motor operated, with reduce voltage vacuum interrupter and ground switch.

20

1 MOS-2 Panel 12-14

Construction methodology

The overall proposed construction sequence, and associated issues/assumptions, can be summarized as follows:

• All construction will take place on Company’s property. • Work will be taking place near energized transmission lines during all phases of

construction. All contractors, both electrical and non-electrical, should be aware of

Page 34: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

34

published guidelines for maintaining clearance (different for electrical vs. non-electrical workers).

• A mobile transformer or switch will be required to complete construction. • All construction activities will be managed by Company personnel. • Foundation construction inside the fence will be contracted out. This work will

either be bid out or assigned to an approved vendor. • It is currently assumed that a majority of Substation Electrical and Relay

construction will be contracted out since Asset Management may have inadequate in-house resources available to support this project. AM will be given first right-of-refusal for this work. At a minimum, AM will still need to be involved in final checkout and commissioning of all Relay equipment.

• Substation Electrical construction may be covered by a Contract Inspector, or Operations Coordinators. Relay construction coordination will be covered by in-house personnel.

• Construction schedule will follow the project schedule.

Construction Plan

Electrical:

• Receive and review electrical package. • Prepare bid package and bid project for electrical work. • If the shield wire is removed lightning masts need to be put up in their place. • Evaluate and award bid. • Contractor to perform electrical work. • Review and walk-down for in-service connections.

Relay:

• Review relay installation plan. • Receive and review relay plan. • The relay designer needs to verify if the PT inputs to the relays or the DC sources to

relays in existing control house are daisy chained. If this is the case then this can be remedied during the operating bus outage that will be taken during the electrical construction, but a supplementary design package may be required.

• Prepare bid package and bid project for wiring work. • Evaluate and award bid. Schedule resources for relay installation and testing. • Review power connections tie-in. • Review phasing/testing for in-service tie in.

Other:

• Material coordination, disposition, and return. • Hazards Identification. • Review and address safety/working clearances. • Review and submit as-built drawings. • Close out project

Outage Planning • An outage will be required on the high voltage bus. • A mobile transformer or switch will be required to complete construction.

Page 35: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

35

4.10 Carpenter Dam Substation

General

Need to replace alternate bus DS B8676 from 600A to a minimum of 1200A. Site • No site work required. Foundations • No site work required.

Electrical • Remove one (1) existing 115kV, 1200A Disconnect Switch. • Remove existing 115kV operation bus. • Install one (1) 115kV, 2000A Vertical Break Disconnect Switch. • Install jumpers, fittings and other miscellaneous materials to support the complete

installation and safe operation.

Relay Design

• No Relay Design Work needed.

Long Delivery Items

Quantity Material Description *Lead Time

(weeks)

1 115kV, 2000A Vertical Break Disconnect Switch 20

Construction methodology The overall proposed construction sequence, and associated issues/assumptions, can be summarized as follows:

• All construction will take place on Company’s property. • Work will be taking place near energized transmission lines during all phases of

construction. All contractors, both electrical and non-electrical, should be aware of published guidelines for maintaining clearance (different for electrical vs. non-electrical workers).

• A mobile transformer or switch will be required to complete construction. • All construction activities will be managed by Company personnel. • Foundation construction inside the fence will be contracted out. This work will

either be bid out or assigned to an approved vendor.

Page 36: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

36

• It is currently assumed that a majority of Substation Electrical and Relay construction will be contracted out since Asset Management may have inadequate in-house resources available to support this project. AM will be given first right-of-refusal for this work. At a minimum, AM will still need to be involved in final checkout and commissioning of all Relay equipment.

• Substation Electrical construction may be covered by a Contract Inspector, or Operations Coordinators. Relay construction coordination will be covered by in-house personnel.

• Construction schedule will follow the project schedule. • Construction Plan

Electrical:

• Receive and review electrical package. • Prepare bid package and bid project for electrical work. • If the shield wire is removed lightning masts need to be put up in their place. • Evaluate and award bid. • Contractor to perform electrical work. • Review and walk-down for in-service connections.

Relay:

• Review relay installation plan. • Receive and review relay plan. • The relay designer needs to verify if the PT inputs to the relays or the DC sources to

relays in existing control house are daisy chained. If this is the case then this can be remedied during the operating bus outage that will be taken during the electrical construction, but a supplementary design package may be required.

• Prepare bid package and bid project for wiring work. • Evaluate and award bid. Schedule resources for relay installation and testing. • Review power connections tie-in. • Review phasing/testing for in-service tie in.

Other:

• Material coordination, disposition, and return. • Hazards Identification. • Review and address safety/working clearances. • Review and submit as-built drawings. • Close out project

Outage Planning • An outage will be required on the transfer bus.

Page 37: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

37

5.0 COST

The ICT has reviewed and determined whether each required upgrade will be considered a Base Plan Upgrade or a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT. The costs shown in the table include all applicable overheads and AFUDC, but do not include tax gross up. Entergy incurs a tax liability proportional to the amount of customer contributions.

2012 2013 2014 2015 2016 2017 Total

Direct $ 75 $ 491,862 $ 1,674,600 $ 10,183,091 $ 6,927,276 $ 5,036,761 $24,313,665

Indirect $ 26 $ 69,594 $ 204,922 $ 1,133,762 $ 781,383 $ 790,261 $ 2,979,948

Total $ 101 $ 561,456 $ 1,879,521 $ 11,316,854 $ 7,708,659 $ 5,827,022 $27,293,613

6.0 UPGRADE CLASSIFICATION

The ICT has reviewed and determined whether each required upgrade will be considered a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT.

Task Total Cost Base Plan Supplemental FFR Payment Section(s)

Upgrade Haskell to Woodlawn line

$ 4,978,989

$ 4,978,989

4.1

Upgrade Hot Springs to Butterfield Line

$ 2,512,532

$ 2,512,532

4.2

Upgrade Butterfield to Haskell Line

$ 5,709,229

$ 5,709,229

4.3

Carpenter Dam to Malvern South Line

$ 12,733,004

$ 12,733,004

4.4

Arklahoma to Tigre Bay Line

$0 $0 4.5

Tigre Bay to Panther Valley Line

$0 $0 4.6

Panther Valley to Fountain Lake Line

$0 $0 4.7

Hot Springs EHV Substation

$ 561,557

$ 561,557

4.8

Butterfield Switching Station

$ 329,174

$ 329,174

4.9

Haskell Switching Station

$ 342,921

$ 342,921

4.10

Carpenter Dam Substation

$ 123,207

$ 123,207

4.11

Total: $ 27,293,613 $ 561,557 $ 26,732,056

Page 38: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

38

7.0 SCHEDULE

A detailed schedule will be prepared subsequent to customer approval to proceed with the project. Based on the task duration schedules listed below, the overall project in-service date is projected to be November 2017. This assumes customer approval to proceed with the development of PEP by October 2013.

* During line outages, work at Hot Springs, Haskell, Butterfield and

Carpenter Dam will be completed.

Summary: Completed by

Commence design for Hot Springs EHV Substation 12/10/2012

Commence Hot Springs EHV Substation construction 4/1/2013

Submit facility Study 5/19/2013

Hot Springs EHV SS construction completed 5/31/2013

Customer + FP/WOs Approval 10/30/2013

Complete PEP 4/30/2014

Customer approval + Revised FP approval 5/30/2014 Commence design/Notification to agencies working on existing ROW/SWPPP 6/30/2014

Order Substation and line material 8/30/2014

Issue design packages for SS and lines & go for bids 12/30/2014 Award construction contracts / Receive all SS and line material + SWPPP & clearance from owners/agencies to commence construction 2/28/2015

Commence Substations & Line Construction (starting Haskell-Woodlawn Line) and other lines and Substations to follow 3/2/2015

Complete Haskell to Woodlawn line and Substation 10/30/2015

Complete Hot Springs to Butterfield line and Substation 12/11/2015

Complete Haskell to Butterfield line and Substation 10/14/2016

Complete Malvern S to Carpenter Dam line and Substation 10/27/2017

Arklahoma-Tigre Bay Sw. Station Line No work is required

Tigre Bay Sw. Station-Panther Valley Sw. Station Line No work is required

Panther Valley Sw. Station-Fountain Lake Line No work is required

Notes to Duration Schedules:

• Pre-existing scheduled line outages may prevent the commencement of work. Scheduled outages cannot be confirmed until a firm construction schedule is submitted.

• All construction work requiring outages will be performed during off-peak load season. Line outages will be discussed with the SOC and TOC and the assumption is made that line outages will be executed as planned. However, last minute denial of outages by the SOC/TOC along with resulting schedule delay is possible.

• Design and Construction resources are available when required. • Different resource is used for each design, so all designs start at same time.

Page 39: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

39

• Transmission Line and Substation projects will begin subsequent to completion of Definition phase preparing PEP and having customer approval to proceed with the design/procurement and construction

• This schedule does not account for adverse weather conditions. • Schedule durations are high level estimates at this time. A detailed schedule will be

prepared upon project approval. • Scheduling assumption and completion dates for the project:

o All wood structures will be disposed of by either awarding to landowners or

disposed of as regular creosote waste-no specially treated wood. o ROW is accessible by conventional means, no special equipment or extensive

matting. ROW is maintained to the extent clearing is not necessary and no reseeding will be warranted.

o Baseline or preferential contractors will be used eliminating the time required to competitively bid.

Page 40: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

40

8.0 RISK ASSESSMENT

Risk Comment Impact

Material costs steel & Equipment Rising steel, copper, fuel and other market conditions could greatly affect estimated cost.

****

Storm-water plan implementation

Best guess on SWPPP creation, implementation and monitoring can vary greatly dependant on outcome of environmental study.

**

Weather & Equipment Lead Times

Unexpected delays on material lead times, unusually inclement weather will impact schedule but might impact AFUDC costs as well.

**

Wetland mitigation Undetermined until environmental analysis is complete.

***

Outages may not be available

Preliminary schedule only considers general outage constraints. Specific project schedule may be delayed by days, weeks or months dependant on system conditions. Delays of months = increased project costs.

**

Scope based on design assumptions which may change

Varied impact on cost and schedule. ***

*-low impact to cost, ** - moderate impact to cost, ***- high impact to cost, **** - very high

Page 41: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

41

9.0 CONFIRMED RESERVATIONS

OASIS PSE MW Begin End 569011 Entergy Services, Inc. (EMO) 242 3/1/2000 1/1/2014

759196 Entergy Services, Inc. (EMO) 143 1/1/2001 1/1/2021

759294 East Texas Electric Cooperative 31 1/1/2001 1/1/2018

1096986 Tennessee Valley Authority 73 9/1/2003 9/1/2013

1099991 (renewal) City Water & Light, Jonesboro 83 1/1/2010 1/1/2016

1099997 (renewal) City Water & Light, Jonesboro 168 1/1/2010 1/1/2016

1105665 Entergy Services, Inc. (EMO) 236 2/1/2003 2/1/2016

1105666 Entergy Services, Inc. (EMO) 91 2/1/2003 2/1/2027

1105668 Entergy Services, Inc. (EMO) 77 2/1/2003 2/1/2027

1126821 Entergy Services, Inc. (EMO) 101 5/1/2004 5/1/2029

1151106 Entergy Services, Inc. (EMO) 20 6/1/2010 6/1/2029

1168061 Entergy Services, Inc. (EMO) 80 8/1/2004 2/1/2028

1168408 Entergy Services, Inc. (EMO) 247 8/1/2004 2/1/2028

1289686 (delist) Entergy Services, Inc. (EMO) 1 6/1/2007 6/1/2030

1294132 Entergy Services, Inc. (EMO) 526 1/1/2006 1/1/2035

1309874 (renewal) East Texas Electric Cooperative 75 1/1/2009 1/1/2017

1309875 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017

1309876 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017

1356328 Muni Energy Agcy of Miss 40 6/1/2010 6/1/2040

1373643 City of Conway 25 3/1/2010 3/1/2040

1375299 Louisiana Generating LLC 11 3/1/2006 3/1/2013

1375559 CLECO Power LLC (Gen) 675 12/1/2006 12/1/2016

1380484 Osceola Light & Power 9 9/1/2009 9/1/2039

1381398 Constellation Energy Commodities Grp. 34 1/1/2006 1/1/2036

1381400 Constellation Energy Commodities Grp. 34 1/1/2006 1/1/2036

1381404 Constellation Energy Commodities Grp. 17 1/1/2006 1/1/2036

1381406 Constellation Energy Commodities Grp. 17 1/1/2006 1/1/2036

1383852 Arkansas Electric Cooperative Corp. 550 1/1/2007 1/1/2017

1385158 NRG Power Marketing 13 10/1/20070 10/1/2027

1387272 CLECO Power LLC (Gen) 11 4/1/2006 4/1/2016

1401985 Constellation Energy Commodities Grp. 42 8/1/2006 8/1/2036

1410022 Constellation Energy Commodities Grp. 60 3/1/2010 3/1/2040

1422708 (delist) Entergy Services, Inc. (EMO) 1 1/1/2007 1/1/2027

1425495 East Texas Electric Cooperative 50 3/1/2010 3/1/2045

1442453 NRG Power Marketing 320 6/1/2007 6/1/2026

1449495 Entergy Services, Inc. (EMO) 322 6/1/2009 6/1/2059

1460876 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460878 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460879 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460881 Aquila Networks-MPS 75 3/1/2009 3/1/2029

1460898 Louisiana Energy & Power Authority 3 1/1/2009 1/1/2030

1460899 Louisiana Energy & Power Authority 5 1/1/2009 1/1/2030

1461442 Louisiana Energy & Power Authority 12 1/1/2009 1/1/2030

1464028 East Texas Electric Cooperative 168 1/1/2010 1/1/2040

Page 42: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

42

OASIS PSE MW Begin End 1470484 City of West Memphis 20 1/1/2011 1/1/2041

1470811 East Texas Electric Cooperative 186 1/1/2010 1/1/2040

1477069 Entergy Services, Inc. (EMO) 10 11/1/2007 11/1/2037

1480164 Entergy Services, Inc. (EMO) 725 1/1/2005 9/1/2033

1495910 Southwestern Electric 78 5/1/2010 5/1/2013

1498122 Constellation Energy Commodities Grp. 30 4/1/2012 4/1/2042

1498129 City of Conway 50 4/1/2012 4/1/2042

1500582 (delist) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038

1500584 (delist) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038

1514102 East Texas Electric Cooperative 29 1/1/2008 1/1/2017

1514104 East Texas Electric Cooperative 35 1/1/2008 1/1/2017

1514105 (delist) East Texas Electric Cooperative 1 1/1/2008 1/1/2017

1517005 (renewal) NRG Power Marketing 103 1/1/2011 1/1/2026

1525820 (renewal) NRG Power Marketing 3 7/1/2009 7/1/2014

1530287 Empire District Electric 50 3/1/2010 3/1/2030

1530288 Empire District Electric 50 3/1/2010 3/1/2030

1546108 (delist) Entergy Services, Inc. (EMO) 1 1/1/2011 1/1/2051

1552148 (delist) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2014

1555717 (delist) East Texas Electric Cooperative 1 1/1/2010 1/1/2015

1555718 Entergy Services, Inc. (EMO) 158 1/1/2010 1/1/2015

1557220 (delist) Entergy Services, Inc. (EMO) 1 7/1/2009 7/1/2018

1557221 Entergy Services, Inc. (EMO) 520 7/1/2009 7/1/2018

1557602 (delist) East Texas Electric Cooperative 1 1/1/2009 1/1/2017

1564001 (renewal) Louisiana Energy & Power Authority 6 4/1/2009 4/1/2014

1564356 (renewal) NRG Power Marketing 5 9/1/2009 9/1/2025

1585225 (renewal) City of Prescott 22 4/1/2009 4/1/2039

1598022 (renewal) NRG Power Marketing 103 7/1/2010 7/1/2015

1598291 Entergy Services, Inc. (EMO) 206 6/1/2012 6/1/2042

1598885 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014

1598886 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014

1601111 Constellation 5 1/1/2010 1/1/2015

1615102 (renewal) MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1615103 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1615105 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1615108 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014

1629240 MidAmerican Energy, Inc. 7 3/1/2009 3/1/2014

1630065 NRG Power Marketing 40 1/1/2010 1/1/2015

1632265 Merrill Lynch Commodities 1 4/1/2009 4/1/2014

1633701 NRG Power Marketing 20 1/1/2010 1/1/2019

1633702 NRG Power Marketing 20 1/1/2010 1/1/2016

1633703 NRG Power Marketing 20 1/1/2010 1/1/2016

1639337 Entergy Services, Inc. (EMO) 587 3/1/2009 1/1/2019

1639338 Entergy Services, Inc. (EMO) 103 3/1/2009 1/1/2019

1639339 Entergy Services, Inc. (EMO) 32 3/1/2009 1/1/2019

1639340 Entergy Services, Inc. (EMO) 122 3/1/2009 1/1/2019

1639341 Entergy Services, Inc. (EMO) 134 3/1/2009 1/1/2019

1640629 CLECO Power Marketing 58 5/1/2001 1/1/2021

1640630 CLECO Power Marketing 32 5/1/2001 1/1/2021

1643983 (renewal) NRG Power Marketing 300 1/1/2010 1/1/2015

Page 43: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

43

OASIS PSE MW Begin End 1643984 (renewal) NRG Power Marketing 100 9/1/2010 9/1/2015

1644155 CLECO Power Marketing 9 4/1/2009 5/1/2016

1644215 NRG Power Marketing 83 1/1/2010 1/1/2025

1644908 CLECO Power Marketing 41 5/1/2009 5/1/2018

1648049 (delist) Entergy Services, Inc. (EMO) 1 6/1/2010 6/1/2013

1648050 Entergy Services, Inc. (EMO) 100 6/1/2010 6/1/2013

1655366 Missouri Joint Municipal 6 10/1/2009 10/1/2014

1658087 Entergy Services (SPO) 1 6/1/2012 6/1/2042

1658088 SMEPA 21 6/1/2012 6/1/2042

1659388 NRG Power Marketing 25 1/1/2011 1/1/2016

1665288 Merrill Lynch Commodities 15 1/1/2011 1/1/2017

1665492 (renewal) Merrill Lynch Commodities 16 11/1/2009 11/1/2014

1665493 (renewal) Merrill Lynch Commodities 4 11/1/2009 11/1/2014

1665899 Ameren Energy, Inc. 75 9/1/2009 9/1/2014

1668165 Entergy Services (SPO) 600 1/1/2013 1/1/2043

1669126 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016

1669127 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016

1676674 NRG Power Marketing 100 1/1/2011 1/1/2020

1676675 NRG Power Marketing 100 1/1/2011 1/1/2020

1677749 Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015

1679179 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016

1679181 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016

1685869 (renewal) Muni Energy Agcy of Miss 19 1/1/2010 1/1/2018

1689499 Missouri Joint Municipal 3 9/1/2009 9/1/2014

1690613 NRG Power Marketing 25 1/1/2011 1/1/2016

1694305 Entergy Services (SPO) 15 5/1/2010 5/1/2020

1694306 Entergy Services (SPO) 30 5/1/2010 5/1/2020

73454527 Hope Water & Light 10 10/1/2009 10/1/2032

73457918 South Miss Electric Power Assoc. 180 10/1/2009 10/1/2014

73573797 (renewal) American Electric Power 45 1/1/2011 1/1/2029

73586299 (renewal) American Electric Power 6 1/1/2011 1/1/2029

73595626 NRG Power Marketing 13 1/1/2012 1/1/2017

73724303 Arkansas Electric Cooperative Corp. 104 1/1/2010 1/1/2015

73741113 (renewal) Entergy Services, Inc. (EMO) 150 5/1/2010 5/1/2020

73741122 (renewal) Entergy Services, Inc. (EMO) 135 5/1/2010 5/1/2020

73820650 MOWR 5 3/1/2010 3/1/2040

73884547 MOWR 35 8/1/2010 8/1/2040

73884558 MOWR 40 8/1/2010 8/1/2040

73942862 (renewal) Muni Energy Agcy of Miss 13 6/1/2010 6/1/2015

73970673 Cargill Power Markets, LLC 40 1/1/2012 1/1/2016

73987480 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040

73987507 South Miss Electric Power Assoc. 180 6/1/2010 6/1/2015

73990804 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040

74001787 NRG Power Marketing 100 1/1/2011 1/1/2016

74001895 NRG Power Marketing 100 1/1/2011 1/1/2016

74001897 NRG Power Marketing 22 1/1/2011 1/1/2016

74001904 NRG Power Marketing 28 1/1/2011 1/1/2016

74001930 NRG Power Marketing 42 8/1/2006 8/1/2036

74001931 NRG Power Marketing 60 3/1/2010 3/1/2040

Page 44: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

44

OASIS PSE MW Begin End 74001934 NRG Power Marketing 60 4/1/2012 4/1/2042

74233619 WRGS 15 4/1/2012 4/1/2017

74233670 (delist) Entergy Services, Inc. (EMO) 1 8/1/2012 1/1/2038

74236787 NRG Power Marketing 75 6/1/2012 6/1/2017

74236794 NRG Power Marketing 100 6/1/2012 6/1/2017

74236798 NRG Power Marketing 100 6/1/2012 6/1/2017

74305315 NRG Power Marketing 10 1/1/2014 1/1/2017

74305339 NRG Power Marketing 10 1/1/2013 1/1/2023

74356639 NRG Power Marketing 103 1/1/2011 1/1/2016

74356652 NRG Power Marketing 206 6/1/2012 6/1/2017

74356666 NRG Power Marketing 50 1/1/2013 1/1/2014

74408208 Louisiana Energy & Power Authority 13 9/1/2010 9/1/2015

74408225 Louisiana Energy & Power Authority 45 9/1/2010 9/1/2015

74514903 Entergy Services, Inc. (EMO) 20 6/1/2013 6/1/2029

74514911 Entergy Services, Inc. (EMO) 101 6/1/2013 6/1/2029

74691007 NRG Power Marketing 60 1/1/2013 1/1/2018

74728415 Brazos Electric Cooperative 100 1/1/2012 1/1/2017

74777205 (renewal) NRG Power Marketing 300 1/1/2013 1/1/2033

74777208 (renewal) NRG Power Marketing 300 1/1/2015 1/1/2035

74789476 (delist) Entergy Services, Inc. (EMO) 1 1/1/2012 1/1/2016

74829975 (renewal) CLECO Power LLC (Gen) 35 1/1/2011 1/1/2016

74835023 AECI / APM 103 1/1/2012 1/1/2017

74881866 (renewal) NRG Power Marketing 8 3/1/2011 3/1/2021

74899933 Entergy Services (SPO) 322 2/1/2011 2/1/2041

74899954 (delist) Entergy Services, Inc. (EMO) 1 2/1/2012 2/1/2014

74899956 Entergy Services, Inc. (EMO) 100 2/1/2012 2/1/2014

74899968 (delist) Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015

74899969 (delist) Entergy Services, Inc. (EMO) 1 1/1/2012 1/1/2015

74899972 (delist) Entergy Services (SPO) 1 1/1/2015 1/1/2045

74899974 (delist) Entergy Services (SPO) 1 1/1/2015 1/1/2045

74899976 (delist) Entergy Services (SPO) 1 1/1/2015 1/1/2045

74899980 Entergy Services (SPO) 584 1/1/2015 1/1/2045

74899988 (delist) Entergy Services (SPO) 1 6/1/2012 6/1/2042

74899989 Entergy Services (SPO) 485 6/1/2012 6/1/2042

74901827 (delist) Entergy Services, Inc. (EMO) 1 2/1/2011 2/1/2041

74958042 NRG Power Marketing 34 1/1/2006 1/1/2036

74958045 NRG Power Marketing 34 1/1/2006 1/1/2036

74958047 NRG Power Marketing 17 1/1/2006 1/1/2036

74958048 NRG Power Marketing 17 1/1/2006 1/1/2036

75207302 (renewal) Entergy Services, Inc. (EMO) 1 7/1/2011 7/1/2016

75259845 South Miss Electric Power Assoc. 2 4/1/2012 1/1/2040

75265640 (renewal) South Miss Electric Power Assoc. 75 6/1/2011 6/1/2016

75299243 AECI 103 1/1/2012 1/1/2017

75342276 Cargill Power Markets 202 12/1/2012 12/1/2017

75460486 MOWR 103 4/1/2012 4/1/2037

75495258 (renewal) NRG Power Marketing 13 1/1/2017 1/1/2019

75564309 ETEC 50 5/1/2014 5/1/2044

75826033 CPWM 600 4/1/2014 4/1/2033

76120007 renewal CLECO Power Marketing 10 10/1/2012 10/1/2017

Page 45: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

45

OASIS PSE MW Begin End 76234876 Entergy Services (SPO) 1 6/1/2012 6/1/2042

76234879 Entergy Services (SPO) 194 6/1/2012 6/1/2042

76234889 Entergy Services (SPO) 256 1/1/2016 1/1/2043

76234897 Entergy Services (SPO) 35 1/1/2016 1/1/2043

76234904 Entergy Services (SPO) 1 6/1/2012 6/1/2042

76234916 Entergy Services (SPO) 140 6/1/2012 6/1/2042

76234922 Entergy Services (SPO) 1 5/1/2013 5/1/2042

76234951 Entergy Services (SPO) 5 5/1/2013 5/1/2042

76234980 Entergy Services (SPO) 1 1/1/2014 1/1/2043 76234993 76235000 76235003 Entergy Services (SPO) 475 1/1/2014 1/1/2043

76238089 Entergy Services (SPO) 20 1/1/2014 1/1/2043

76280552 (delist) Entergy Services (SPO) 1 6/1/2012 6/1/2042

76280558 (delist) Entergy Services (SPO) 1 5/1/2013 5/1/2042

76336174 (redirect) NRG Power Marketing 206 6/1/2013 6/1/2017

76449800 Arkansas Electric Cooperative Corp.

275 1/1/2013 1/1/2014

300 1/1/2014 1/1/2015

320 1/1/2015 1/1/2017

76449828 Arkansas Electric Cooperative Corp.

80 1/1/2013 1/1/2014

82 1/1/2014 1/1/2015

84 1/1/2015 1/1/2016

86 1/1/2016 1/1/2017

76513126 (delist) Constellation Energy Commodities Grp. 1 1/1/2012 1/1/2017

76513148 (delist) Constellation Energy Commodities Grp. 1 1/1/2012 1/1/2017

76513215 EWOM 60 11/1/2009 11/1/2014

76513304 (renewal) EWOM 60 11/1/2014 11/1/2019

76523750 SRMPA 180 6/1/2012 6/1/2018

76523753 SRMPA 30 6/1/2012 6/1/2016

76523754 EWOM 45 6/1/2012 6/1/2016

76533177 EWOM 25 4/1/2009 4/1/2014

76533260 (renewal) EWOM 25 4/1/2014 4/1/2019

76583976 Arkansas Electric Cooperative Corp. 660 9/1/2012 9/1/2017

76744580 (deferral) South Miss Electric Power Assoc. 2 1/1/2013 1/1/2040

76767669 NRG Power Marketing 103 6/1/2013 6/1/2017

76794133 NRG Power Marketing 1 1/1/2014 1/1/2022

76794134 NRG Power Marketing 1 1/1/2014 1/1/2022

76794135 NRG Power Marketing 1 1/1/2014 1/1/2022

76794138 NRG Power Marketing 1 1/1/2014 1/1/2022

76794140 NRG Power Marketing 309 1/1/2014 1/1/2019

76794150 NRG Power Marketing 1 1/1/2014 1/1/2019

76794151 NRG Power Marketing 309 1/1/2014 1/1/2019

76794321 NRG Power Marketing 10 1/1/2013 1/1/2025

76975184 Entergy Services (SPO) 28 1/1/2013 1/1/2033

76999226 SWCC 78 5/1/2013 5/1/2018

77020374 (renewal) Tennessee Valley Authority 73 9/1/2013 9/1/2023

77065320 (renewal) Entergy Services (SPO) 10 7/1/2012 7/1/2013

77161524 Entergy Services (SPO) 495 1/1/2014 1/1/2017

Page 46: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

46

OASIS PSE MW Begin End 77176931 NRG Power Marketing 525 6/1/2014 6/1/2024

10.0 PRE-888 TRANSACTIONS

OASIS # PSE MW Begin End

1332606 East Texas Electric Cooperative 55 1/1/2006 1/1/2017

1412155 Entergy Services, Inc. (EMO) 1718 1/1/2007 1/1/2038

1412156 Entergy Services, Inc. (EMO) 741 1/1/2007 1/1/2038

1412158 Entergy Services, Inc. (EMO) 1867 1/1/2007 1/1/2038

1412160 Entergy Services, Inc. (EMO) 1142 1/1/2007 1/1/2038

1412161 Entergy Services, Inc. (EMO) 59 1/1/2007 1/1/2038

1412162 Entergy Services, Inc. (EMO) 148 1/1/2007 1/1/2038

1412163 Entergy Services, Inc. (EMO) 194 1/1/2007 1/1/2038

1412164 Entergy Services, Inc. (EMO) 1157 1/1/2007 1/1/2038

1412165 Entergy Services, Inc. (EMO) 1219 1/1/2007 1/1/2038

1412166 Entergy Services, Inc. (EMO) 683 1/1/2007 1/1/2038

1412167 Entergy Services, Inc. (EMO) 140 1/1/2007 1/1/2038

1412168 Entergy Services, Inc. (EMO) 456 1/1/2007 1/1/2038

1412169 Entergy Services, Inc. (EMO) 739 1/1/2007 1/1/2038

1412170 Entergy Services, Inc. (EMO) 183 1/1/2007 1/1/2038

1412171 Entergy Services, Inc. (EMO) 64 1/1/2007 1/1/2038

1412172 Entergy Services, Inc. (EMO) 870 1/1/2007 1/1/2038

1412173 Entergy Services, Inc. (EMO) 129 1/1/2007 1/1/2038

1412174 Entergy Services, Inc. (EMO) 140 1/1/2007 1/1/2038

1412175 Entergy Services, Inc. (EMO) 130 1/1/2007 1/1/2038

1412176 Entergy Services, Inc. (EMO) 65 1/1/2007 1/1/2038

1412177 Entergy Services, Inc. (EMO) 947 1/1/2007 1/1/2038

1412178 Entergy Services, Inc. (EMO) 61 1/1/2007 1/1/2038

1412179 Entergy Services, Inc. (EMO) 304 1/1/2007 1/1/2038

1412180 Entergy Services, Inc. (EMO) 351 1/1/2007 1/1/2038

1412181 Entergy Services, Inc. (EMO) 692 1/1/2007 1/1/2038

1412182 Entergy Services, Inc. (EMO) 1641 1/1/2007 1/1/2038

1412183 Entergy Services, Inc. (EMO) 433 1/1/2007 1/1/2038

1412184 Entergy Services, Inc. (EMO) 1926 1/1/2007 1/1/2038

1412185 Entergy Services, Inc. (EMO) 946 1/1/2007 1/1/2038

1412186 Entergy Services, Inc. (EMO) 1233 1/1/2007 1/1/2038

1498278 Entergy Services, Inc. (EMO) 75 8/1/2007 1/1/2017

1498281 Entergy Services, Inc. (EMO) 86 8/1/2007 1/1/2017

1498283 Entergy Services, Inc. (EMO) 68 8/1/2007 1/1/2017

1498284 Entergy Services, Inc. (EMO) 78 8/1/2007 1/1/2017

1498285 Entergy Services, Inc. (EMO) 11 8/1/2007 1/1/2044

1498286 Entergy Services, Inc. (EMO) 69 8/1/2007 1/1/2044

1498287 Entergy Services, Inc. (EMO) 14 8/1/2007 1/1/2044

1528114 Entergy Services, Inc. (EMO) 1523 1/1/2008 1/1/2038

1528115 Entergy Services, Inc. (EMO) 1039 1/1/2008 1/1/2038

1528116 Entergy Services, Inc. (EMO) 1834 1/1/2008 1/1/2038

76120467 Renewal Entergy Services, inc. (EMO) 61 1/1/2038 1/1/2045

Page 47: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

47

OASIS # PSE MW Begin End for 1412178

76120472 Renewal

for 1412172 Entergy Services, inc. (EMO) 870 1/1/2038 1/1/2045

76120479 Replaces 1412155

Entergy Services, Inc. (EMO) 1738 1/1/2012 1/1/2045

76234797 Renewal

for 1412163 Entergy Services, Inc. (EMO) 194 1/1/2038 1/1/2043

76234817 Renewal

for 1412174 Entergy Services, Inc. (EMO) 140 1/1/2038 1/1/2043

76234827 Renewal

for 1412170 Entergy Services, Inc. (EMO) 183 1/1/2038 1/1/2043

76234836 Renewal

for 1412180 Entergy Services, Inc. (EMO) 351 1/1/2038 1/1/2043

76292988 Replaces 1412155

Entergy Services, Inc. (EMO) 190 1/1/2012 1/1/2043

76292990 Replaces 1412155

Entergy Services, Inc. (EMO) 144 1/1/2012 1/1/2043

76292992 Replaces 1412155

Entergy Services, Inc. (EMO) 210 1/1/2012 1/1/2043

76292993 Replaces 1412155

Entergy Services, Inc. (EMO) 324 1/1/2012 1/1/2043

76528782 Constellation Energy Commodities Grp. 5 7/1/1988 7/1/2027

Page 48: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

48

11.0 STUDY QUEUE

OASIS # PSE MW Begin End 74846159 AEPM 65 1/1/2015 1/1/2020

75206836 ETEC 125 1/1/2015 1/1/2020

76744419 SMEPA 280 1/1/2014 1/1/2025 SPP 74240998_1004_

1007_1231_1265 AEP 20-116 1/1/2011 1/1/2020

76902738 CPWM 80 1/1/2013 1/1/2018

77272292 Entergy Services (SPO) 9 1/1/2013 1/1/2033

77272300 Entergy Services (SPO) 4 1/1/2013 1/1/2033

77289977 NRG Power Marketing 1 6/1/2014 6/1/2024

77289995 NRG Power Marketing 309 6/1/2014 6/1/2024

77289999 NRG Power Marketing 1 6/1/2014 6/1/2024

77290002 NRG Power Marketing 309 6/1/2014 6/1/2024

77355706 Horizon Wind 100 1/1/2015 1/1/2020

Page 49: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

49

12.0 ATTACHMENTS

12.1 Table of Acronyms

Acronym Description ACSR Aluminum Conductor Steel Reinforced ACSS Aluminum Conductor Steel Supported ADEQ Arkansas Department of Environmental Quality ADSS All dielectric self supporting AFUDC Allowance for Funds Used During Construction ATC Available Transfer Capability BAB Bus air break CYDS Cubic Yards EES Entergy Control Area EHV Extra-High Voltage ERIS Energy Resource Interconnection Service ICT Independent Coordinator of Transmission IPO Independent Pole operated JSA Job Safety analysis KCMIL Kilo circular mil kV Kilo-Volt MCM (M) Thousand Circular Mils MCOV Maximum Continuous operating voltage MDOT Mississippi Department of Transportation MVA Mega-Volt Amp MW Mega-Watt NPDES National Pollution Discharge Elimination System NOI Notice of Intent NRIS Network Resource Interconnection Service OASIS Online Access and Same-time Information System OATT Open Access Transmission Tariff POD Point of Delivery POR Point of Receipt SES Steam Electric Station SOC System Operations Center SHV Super High Voltage SW Switch Station TOC Transmission Operations Center

12.2 Substation one lines

Attached pdf files

Page 50: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

50

One lines

• Hot Springs

Page 51: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

51

• Haskell

Page 52: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

52

• Butterfield

Page 53: TRANSMISSION SERVICE FACILITIES STUDY · The Haskell-Woodlawn 115 kV transmission line upgrade has been committed to by a previously confirmed transmission service request for this

AECC OASIS 77494473 Facilities Study

53

• Carpenter Dam