JSEM 2006 – Transforming DERP Panel 1 of 7 14 Feb 06
Mr. Rick NewsomeOffice of the Deputy Assistant Secretary of the Army
(Environment, Safety and Occupational Health)
March 22, 2006
JSEM 2006 – Transforming DERP Panel 2 of 7 14 Feb 06
TopicsTopics
• Military Munitions Response Program
• Performance-Based Contracting
• Formerly Used Defense Sites Program
• BRAC 2005 & Army Transformation
JSEM 2006 – Transforming DERP Panel 3 of 7 14 Feb 06
Military Munitions Response ProgramMilitary Munitions Response Program
FY2005 FY2006 FY2007 FY2008 FY2009 FY2010 FY2011
Dol
lars
• Inventory completed as required by Congress• DoD Goals:
– Complete Preliminary Assessments by EOY 2007; Sites Inspections by EOY 2010
• Munitions Response Prioritization Protocol:– Used to assign relative priority; sequencing for
responses– Involves stakeholders in process
• Cross-over of Army IRP to MMRP in POMIRP
MMRP
JSEM 2006 – Transforming DERP Panel 4 of 7 14 Feb 06
MMRP Site InspectionsMMRP Site Inspections
• DoD goal: complete SIs by FY2010– Active Sites SI Schedule (154 total) funded by
FY08– FUDS Program SI Schedule (765 total) with
funding thru FY10 at $25M/year
• Need for State involvement in review of SIs and application of Munitions Response Site Prioritization Protocol
JSEM 2006 – Transforming DERP Panel 5 of 7 14 Feb 06
What is PBC?What is PBC?• Performance-Based Contracting (PBC) -
mechanism that solicits bids on basis of what RESULTS that you want achieved rather than what ACTIVITIES you want conducted:– Contract for “What,” not “How”
• Characteristics of PBC:– Clearly defined performance expectations and measures
(baseline vs. expected results)– Clearly defined due dates & milestones– Use of incentives for performance– Flexibility in exchange for accountability for results
• Army retains Environmental Liability• Regulators concur with remedy selection and
response complete
JSEM 2006 – Transforming DERP Panel 6 of 7 14 Feb 06
Army PBC ResultsArmy PBC Results
PBC Accomplishments (F01 – FY05)• 36 installation at 541 sites
Total Number of Properties Requiring Response Action: 2,965Data: FY05 Defense ENV Program Annual Report to Congress
JSEM 2006 – Transforming DERP Panel 21 of 7 14 Feb 06
BRAC 2005 (Major Closures)
Reserves • Charles E. Kelly Spt Ctr, PA• Vancouver Barracks, WA
• Lease – Army Judge Advocate General Agency, VA
• Lease – Crystal City Complex, VA • Lease – Headquarters Army Test and Evaluation Command, VA
• Lease – Hoffman Building, VA • Lease – Rosslyn Complex, VA • Lease – Army Personnel Center, MO
• Ft Gillem, GA • Ft McPherson, GA • Ft Monmouth, NJ • Ft Monroe, VA • Walter Reed Army Medical Center, DC• Kansas Army Ammunition Plant, KS • Lone Star Army Ammunition Plant, TX • Mississippi Army Ammunition Plant, MS • Riverbank Army Ammunition Plant, CA • Umatilla Chemical Depot, OR • Deseret Chemical Plant, UT • Newport Chemical Depot, IN • US Army Garrison – Selfridge, MI
JSEM 2006 – Transforming DERP Panel 22 of 7 14 Feb 06
BRAC 2005 (Major Re-alignments)
• Fort Knox, KY• Fort Jackson, SC
• Watervliet Arsenal, NY• Fort Huachuca, AZ• Tobyhanna Army Depot, PA• Fort Hood, TX• Soldier Systems Center, Natick, MA• Fort Eustis, VA• Sierra Army Depot, CA• Fort Dix, NJ• Rock Island Arsenal, IL• Fort Campbell, KY• Redstone Arsenal, AL• Fort Buchanan, PR• Lima Tank Plant, OH• Fort Bragg, NC• Fort Wainwright, AK• Fort Bliss, TX• Fort Sill, OK• Fort Benning, GA• Fort Sam Houston, TX• Fort Belvoir, VA• Fort Rucker, AL• Detroit Arsenal, MI• Fort Richardson, AK• Corpus Christi Army Depot, TX• Fort McCoy, WI• Bailey’s Crossroads Lease Site, VA• Fort Lewis, WA• Anniston Army Depot, AL• Fort Leonard Wood, MO• Adelphi Laboratory, MD• Fort Lee, VA• Aberdeen Proving Ground, MD
JSEM 2006 – Transforming DERP Panel 23 of 7 14 Feb 06
RABS for BRAC 2005
Reserves Charles E. Kelly Spt Ctr - NOVancouver Barracks – NO
Property Transfer RealignmentsRed River Army Depot – YESWatervliet Arsenal - NO
Ft Gillem - NO Ft McPherson – NO Ft Monmouth - YESFt Monroe - NO Walter Reed Med Ctr - NO Kansas AAAP – NO Lone Star AAP – NOMississippi AAP – NO Riverbank AAP – NO Umatilla Chemical Depot - YESDeseret Chemical Depot - YESNewport Chemical Depot - YESArmy Garrison Selfridge – NO
JSEM 2006 – Transforming DERP Panel 24 of 7 14 Feb 06
Installation Restoration ProgramInstallation Restoration Program
• Focus on DoD goals of Remedy-in-Place/ Response Complete targets
• Efficiency initiatives:– Performance Based contracting focusing on cost
and time savings• Environmental liabilities:
– Chief Financial Officer Act of 1990 requires federal agencies to report liabilities
– Supporting documentation and supervisory controls are key