Top Banner
TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to serve as a resource for Superintendents and Foremen when conducting training on Lockout/Tagout. Information contained in this manual should be used to enhance the instruction and delivery of PDI safety requirements. LEARNING OBJECTIVES Provide training to introduce/reinforce understanding of the following learning objectives: Understand the purpose and requirements of PDI’s Lockout/Tagout Policy How to conduct proper lockout/tagout procedures o Preparation for lockout/tagout o Sequence of lockout system procedures o Restoring equipment and/or electrical supply How to ensure safety on the jobsite TRAINING GUIDELINES Before Training Familiarize yourself with the content Assess trainee’s understanding of content (beginner, moderate, advanced) Plan your training approach accordingly (hands on, lecture/philosophy, etc.) During Training Utilize training references (trainer manual, policy, etc.) Ensure trainee is attentive and follows along with their iPad Facilitate training using the Tell, Show, Do & Ask Model o Tell: Communicate what the expectation is o Show: Demonstrate how to complete the activity/process o Do: Allow them to perform the activity while you direct and provide feedback o Ask: Follow up immediately to ensure they understood the expectation After Training Play the Lockout/Tagout training video to reinforce expectations Have trainee sign the Lockout/Tagout policy and issue hardhat sticker Remind trainee how to access the Lockout/Tagout policy on the training websites
7

TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

May 29, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7

TRAIN THE TRAINER | LOCKOUT/TAGOUT

PURPOSE

The purpose of this manual is to serve as a resource for Superintendents and Foremen when conducting training on Lockout/Tagout. Information contained in this manual should be used to enhance the instruction and delivery of PDI safety requirements.

LEARNING OBJECTIVES

Provide training to introduce/reinforce understanding of the following learning objectives: Understand the purpose and requirements of PDI’s Lockout/Tagout Policy How to conduct proper lockout/tagout procedures

o Preparation for lockout/tagout o Sequence of lockout system procedures o Restoring equipment and/or electrical supply

How to ensure safety on the jobsite

TRAINING GUIDELINES

Before Training Familiarize yourself with the content Assess trainee’s understanding of content (beginner, moderate, advanced) Plan your training approach accordingly (hands on, lecture/philosophy, etc.)

During Training Utilize training references (trainer manual, policy, etc.) Ensure trainee is attentive and follows along with their iPad Facilitate training using the Tell, Show, Do & Ask Model

o Tell: Communicate what the expectation is o Show: Demonstrate how to complete the activity/process o Do: Allow them to perform the activity while you direct and provide feedback o Ask: Follow up immediately to ensure they understood the expectation

After Training Play the Lockout/Tagout training video to reinforce expectations Have trainee sign the Lockout/Tagout policy and issue hardhat sticker Remind trainee how to access the Lockout/Tagout policy on the training websites

Page 2: TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 2 of 7

TABLE OF CONTENTS

OVERVIEW PDI Lockout/Tagout Policy pg. 3

Purpose Requirements

LOCKOUT/TAGOUT PROCEDURES Preparation for Lockout pg. 3

Disconnecting means Power interruption Isolation of power

Lockout/tagout devices Other work activity hazards Voltage testers Proper PPE Grounding

Sequence of Lockout System Procedures pg. 5 Lockout/tagout system and electrical hazards Disconnecting means and stored energy locations De-energization Lockout/tagout procedures Devices Hasp locks PPE Voltage testing Grounding

Restoring Equipment and/or Electrical Supply pg. 7 Task completion Cleanup Grounding Quality Control Lockout/Tagout removal Worker notification Disconnecting means

JOBSITE SAFETY Responsibilities pg. 8 Safety Resources

Page 3: TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 3 of 7

TRAINING CONTENT

OVERVIEW |Lockout/Tagout

REMEMBER: SAFETY IS PRIORITY #1!

The purpose of PDI’s Lockout/Tagout policy is to establish the minimum requirements to control hazardous electrical energy on all PDI jobsites* *Reference: PDI Lockout/Tagout Policy

PDI’s Lockout/Tagout policy should be used to ensure conductors and circuit parts are: disconnected from sources of electrical energy locked (tagged) tested before work begins where employees could be

exposed to dangerous conditions

All team members are expected to abide by the policy:

PDI employees ITR Team employees Vendors and/or Subcontractors while on the jobsite

LOCKOUT/TAGOUT PROCEDURES

PREPARATION FOR LOCKOUT

Review current drawings, tags, labels, and signs to identify and locate all disconnecting means

Determine power is interrupted by a physical break (disconnect, switch, breaker) and not de-energized by remote means such as a push button or photo cells

Review disconnecting means to determine isolation of power and if a visible open point is available for verification

Select lockout/tagout devices that will effectively prevent

disconnecting means from operation

(continued on next page)

According to OSHA, following proper lockout/tagout procedures prevents an estimated 120 fatalities and 50,000 injuries each year!

Page 4: TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 4 of 7

LOCKOUT/TAGOUT PROCEDURES, cont. |Lockout/Tagout

PREPARATION FOR LOCKOUT, cont.

Review other work activity to identify where and how other employees might be exposed to sources of electrical energy hazards

Ensure an adequately rated voltage tester is available to verify that the equipment is de-energized Establish a method to determine that the voltage tester is

operating satisfactorily

Verify that properly rated PPE per NFPA 70E is available

Ground the phase conductors or circuit parts before touching them where the possibility of induced voltages or stored electrical energy exists

Most equipment installed by PDI only requires an arc flash PPE category of 2

Reference current construction schedule and discuss conflicts with the GC

Page 5: TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 5 of 7

LOCKOUT/TAGOUT PROCEDURES, cont. |Lockout/Tagout

SEQUENCE OF LOCKOUT SYSTEM PROCEDURES

Notify affected workers of lockout/tagout system and hazards associated with electrical energy

Confirm the location of the disconnecting means for all sources of electrical energy and the location of all sources of stored energy

Lockout/tagout all disconnecting means with lockout/tagout devices

Use a hasp for additional locks if more than one person is working on the de-energized equipment

Attempt to operate the disconnecting means to determine if operation is prohibited

(continued on next page)

REMEMBER: SAFETY IS PRIORITY #1!

Page 6: TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 6 of 7

LOCKOUT/TAGOUT PROCEDURES, cont. |Lockout/Tagout SEQUENCE OF LOCKOUT SYSTEM PROCEDURES, CONT.

Wear PPE as required per NFPA 70E

Install grounding equipment/conductor device where required to eliminate induced voltage or stored energy

Ensure function of the tester by using a known live circuit

Test locked out equipment to ensure it is de-energized

Confirm tester functionality using a known live circuit

Begin work once the equipment and/or electrical source is locked out/tagged out

RESTORING EQUIPMENT AND/OR ELECTRICAL SUPPLY TO NORMAL CONDITION

Visually verify that the job or task is complete

Remove all tools, equipment, and unused materials and perform appropriate housekeeping

Remove any grounding equipment/conductors/devices

Perform any quality control tests on the equipment and/or electrical supply

(continued on next page)

Most equipment installed by PDI only requires an arc flash PPE category of 2

REMEMBER: Follow 5S procedures!

Verify proper torque values of all nuts, bolts, and lugs

Page 7: TRAIN THE TRAINER | LOCKOUT/TAGOUT · Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 1 of 7 TRAIN THE TRAINER | LOCKOUT/TAGOUT PURPOSE The purpose of this manual is to

Rev. 1/23/16 TRAIN THE TRAINER MANUAL | LOCKOUT/TAGOUT Page 7 of 7

LOCKOUT/TAGOUT PROCEDURES, cont. |Lockout/Tagout RESTORING EQUIPMENT AND/OR ELECTRICAL SUPPLY TO NORMAL CONDITION, CONT.

Remove any lockout/tagout devices Return LO/TO to Lockout/Tagout kit for future use

Notify affected workers that the equipment and/or electrical supply is ready to be returned to normal operation

Return the disconnecting means to their normal condition

JOBSITE SAFETY

Enforce safety requirements daily in order to: reduce injuries/time lost increase productivity ensure quality installations

All PDI employees, ITR crew members, and 3rd party subs must: abide by PDI’s Jobsite and Lockout/Tagout policies

wear proper PPE at all times

notify management of unsafe conditions

Be sure to lead by example with all PPE and safety standards!

REMEMBER: Safety on the jobsite is everyone’s responsibility!

All safety resources are available on the Super and Foreman websites