Tempe Town Lake Downstream Dam Replacement ALTERNATIVES EVALUATION UPDATE IRS Tempe City Council September 22, 2011
Jun 13, 2015
Tempe Town Lake Downstream Dam Replacement
ALTERNATIVES EVALUATION UPDATE
IRS Tempe City Council September 22, 2011
Timeline Alternatives Evaluation – June thru November Project Update with Council – September 22 Phase 1 Validate Concept & Select Dam Technology –
November Phase 2 Design New Dam – August 2012 Acquire Permits – July 2013 Bid and Procure Construction Contract – October 2013 Fabricate New Dam – November 2014 Construction Complete – December 28, 2015*
* Per current agreement with Bridgestone.
Town Lake: Part of a River System
Granite Reef Dam Watershed Map
Town Lake: Part of a River System
Salt River Watershed Schematic Diagram
Tempe Town Lake Dam
Current Level of Flood Protection
Designed to maintain or improve current levels of flood protection – 210,000 cubic feet per second (cfs.)
This is consistent with the rest of the river system.
Maintain Waters of Town Lake Handle Flows from Storms,
Regular Water Sources Return Lake to Normal After
Floods Handle Water from Extreme
Flood Events Smaller Than 210,000 cfs
Meet Regulatory Requirements
Be Safe
Dam Must
1. Maintain or Improve Current Level of Flood Protection 2. Maintain Full Lake Quickly After Flood Event3. Raise, Lower and Operate Reliably at Normal Lake
Levels 4. Be Cost Efficient – Capital, Lifespan, O&M 5. Have Parts Easily Available 6. Be Compatible with Pedestrian Bridge, Existing
Structures7. Meet Regulatory Requirements8. Perform Well in this Climate
Dam Design Criteria
Regulatory Conditions
Regulatory Agency Concerns
U. S. Army Corps of EngineersWater quality, channel conditions, 404 permitting
Flood Control District of Maricopa County Flood control, levee maintenance
Federal Emergency Management Agency (FEMA) Flood control, levees
Arizona Department of Water Resources Dam Safety
Flood Control Criteria
Flood Control District of Maricopa County:
Use 200-Year Discharge for Design as it’s Close to Capacity of Area Bridges (like Mill Ave, Rural Rd)
West Dam 200-Year Discharge: 204,000 cfs
East Dam 200-Year Discharge: 207,000 cfs
Tempe Town Lake Capacity Discharge: 210,000 cfs
Current Alternatives Evaluation
About 20 Dam Options Studied:
Radial (tainter) Gates Bascule or Bottom-Hinged Leaf
Gates Inflatable Rubber Dams
(water and air-filled) Ogee Crest Weirs Labyrinth Weirs Many Styles of Fuse Plugs Several Styles of Pneumatically-
Operated Hinged Crest Gates (Obermeyer)
Hydraulic Hinged Crest Gates Dyrhoff Rubber Dams (Sumitomo) Vertical Lift Gates Swing Gates Fusegates (Hydroplus) Earth Embankment/Fuseplug Several Styles of Mixed-type Spans Cable-Operated Hinged Crest Gate Others
Mixed Type Alternatives:Concrete Sections and Gates
Different technologies in the different spans between the existing piers
Concrete dams in outer spans and gates in inner spans Gate section atop concrete section each span
Concrete Section Concrete SectionGate SectionGate Section
Gate SectionConcrete Section
Gate SectionConcrete Section
Gate SectionConcrete Section
Gate SectionConcrete Section
Results of Restricted Flow
Results of alternative that requires additional piers
Results of Restricted Flow
Results of Mixed Type Alternative that Impedes Two Spans
Earthen (Fuseplug) Embankment
Typically located within an auxiliary spillway channel. Zoned earth and rockfill embankment with a sloping impervious core
Designed to wash out in a predictable and controlled manner.
Alternative not carried forward due to uncertain performance, potential to increase upstream flooding, inability to maintain lake after storm and permitting issues
Pros Cons
Lower cost for initial constructionCannot catch end of flood to reestablish lakeCannot reliably meet flood protection/flood impact criteria
Permitting uncertain
Long reconstruction time after flood event
Extensive economic impacts after large flows
Earthen (Fuseplug) Embankment
1. Obermeyer Crest Gates
2. Fusegates
3. Hinged Crest Gates
4. Inflatable Rubber Dams
Alternatives Carried Forward
1
3
2
4
Inflatable Rubber Dams
Rubber body fixed to a reinforced concrete foundation Inflated by pumping air or water until height is reached Deflated by allowing the air or water inside the rubber
body to escape
Inflatable Rubber Dams
Pros ConsRelatively low construction cost Performance in site environment uncertain
Known operation Long term cost may by highCan catch end of flood to reestablish lake Manufacturer support and warranty uncertain
Does not require additional piers Vulnerable to vandalism
Lake could be maintained during construction
Fusegates (Hydroplus)
Consists of a bucket, a base, and an intake well connected to a chamber in the base Designed to breach and wash out when overtopped
Pros ConsDoes not require additional piers Long term costs may be high
SimpleCannot catch end of flood to reestablish lake
Reliable Permitting requirements uncertain
Lake can be maintained during construction
Fusegates (Hydroplus)
Obermeyer Crest Gates
Steel gate panels supported on their downstream side by inflatable air bladders Water elevation maintained by controlling the pressure in the bladders
Pros ConsDoes not require additional piers Higher construction cost than rubber dam
SimpleBladders have similar limitations as rubber dam
ReliableLake can be maintained during constructionCan catch end of flood to re-establish lake
Obermeyer Crest Gates
Hinged Crest Gates (Hydraulic Operation)
Steel gate panels hinged at the bottom Operated with overhead pier-mounted hydraulic cylinders
Pros ConsSimple Would require additional piers
Reliable May require lake to be drained to construct
Durable Complicated operation and maintenanceCan catch end of flood to reestablish lake Would require periodic opening
Less vulnerable to vandalism than rubber dams
Hinged Crest Gates (Hydraulic Operation)
Steel gate panels hinged at the bottom Operated with wire rope electric motor hoist
Hinged Crest Gates (Electric Operation)
Pros ConsSimple Would require additional piers
Reliable May require lake to be drained to construct
Durable Complicated operation and maintenance
Can catch end of flood to re-establish lake Would require periodic opening
Less vulnerable to vandalism than rubber dams
Hinged Crest Gates (Electric Operation)
Dam Budget
Minus $367,000 Gannett Fleming Contract for
Dam Technology Analysis
Preliminary Capital Cost Estimates: $25 - $35 Million
Includes Design, Materials, Construction
Does Not Include East Dam or Pump System
Finance Options Include: Use Remaining $3,633,000 Seek Voter Approval for Bond
Authorization for Dam Replacement Capital Costs
Sale of City Properties Combinations
Dam Financing
Public Meeting on Oct. 17, 6 p.m. Tempe Center for the Arts
Failure Modes and Effects Analysis
Third Party Review Gannett Fleming, Staff Will
Recommend Dam Technology Review Financing Options Bring Selected Dam System
to Council in November
Next Steps
Want more information? Visit www.tempe.gov/lake and
Click on Town Lake Dam Replacement in the Blue Box