1 TPM - The Pinch - Point Solution for Delivering Operational Excellence © S A Partners Total Productive Maintenance Article 7 Applying TPM to different Sectors & their specific Production Facilities Peter Willmott
1
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
Total Productive
Maintenance
Article 7
Applying TPM to different Sectors & their specific Production Facilities
Peter Willmott
2
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
TPM-The ‘Pinch-Point’ Solution for Delivering Operational Excellence The Need to recognise the different Characteristics of Various Sectors and
their Physical Assets when applying TPM
1.0 Recap and Focus for this 7th Article In Articles 3 through to 6 we described the SA Partners Enterprise Excellence Model
centring on the 3 x P’s of Purpose, Process and People- which, through alignment,
improvement and engagement, is capable of delivering sustainable business results
as outcomes.
We illustrated how the TPM System Model aligns with these 3 x P’s as shown in
Figure 1 below where:
The TPM program is applied via a defined introductory and deployment process within the business unit –called the Purpose (the focus of Article 3)
The application of the TPM model is then delivered through a defined sequence of team based ‘learning by doing’ activities as a 4 x Cycle 11 step Process (which was the focus of Article 4)
The outputs of this 11 step application are then aligned to a progressive and evidence based assessment process to assure the team’s progress through the model-as the essential People development part (which was the focus of the 5th & 6th Articles).
Figure 1: The TPM System Model
Over the last 25 years it has been my privilege to help apply the TPM principles and
philosophy across the complete spectrum of industry. Whether it is in the acquisition
of primary materials (Offshore Oil & Gas, Surface and Deep mining.), through to the
conversion of those primary materials (Chemicals, Metals, Paper), or Public Utilities
and Transport (Water, Gas, Electricity & Nuclear, Air, Rail and Sea-including OEM and
MRO). Or indeed in the more traditional manufacturing sectors, whether hardware
3
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
related output, or for example, food & drink, pharmaceutical and medical devices, and
whether they are 1st, 2nd or 3rd tier suppliers into those industries.
The one common denominator in all these differing scenarios is the essential need to
recognise the different dynamics, characteristics and nuances of the specific
production operation and manufacturing processes-both in terms of the physical
assets themselves and equally important, the differing human interaction with those
assets. We then need to adapt the TPM process and system to reflect these
fundamental differences.
Whilst it is a play on three English language words, there is a huge difference between
adopting the TPM Philosophy without thinking it through, as opposed to adapting it.
Please remember however, that there is also a huge difference between adapting
something without corrupting the founding principles. Sadly, in my experience there
are far too many corrupted applications of TPM that fail to sustain the gains.
(previously addressed in Article 6).
2.0 Recognising the Differences
Whilst visiting Japan on a TPM study tour in 1992, I vividly remember being told by the
Japanese Managing Director of a recognised world class manufacturer and exemplar
TPM award winning company, that “…In the ‘1950s and ‘60s we had “M” for
Manufacturing. In the ‘70s we had “I M” for Integrated Manufacturing. In the ‘1980s
we had “C I M” for Computer Integrated Manufacturing. He paused for a moment and
then added “…For the remainder of this decade and 2000 and beyond, my company
is going to be pursuing “C H I M”-Computer Human Integrated Manufacturing…. He
added’…We have decided to re-introduce the human being back into our workplace
!!”.
As figure 2 below suggests- CHIM is no dream –it is a pressing reality. Today, some
twenty-five years later my interpretation of that powerful message is that it certainly
represents a challenge for all of us to develop and harness people’s skills in parallel
with advancing automation.
The bottom line is that it’s your people at the sharp end of the business that make
difference.
4
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
31 October, 2016© S A Partners Slide 2
The Future Vision &
Impact of TPM on Operational Excellence
DEVELOPMENT
OF TECHNOLOGY
AND SKILLS
NOW FUTUREADVANCING AUTOMATION
TPM=Effective
Maintenance
AUTOMATION
OF
EQUIPMENTOPERATIONSEQUIPMENT
CHIM
Computer/Human Integrated Manufacture
Is No But is the Reality!Dream
Figure 2 The CHIM Reality
The biggest-and often false- assumption nowadays is that regular visible and physical
‘human’ inspections & maintenance are grossly undervalued and the technological tail
is left wagging the dog.
The tail is an important part of the dog- but in this analogy the dog is the human being.
We have all these highly qualified control room operators spinning around on swivel
chairs watching all these mimic screens flashing with green and occasional red lights
flashing on and off –whilst out there in the real world of the physical asset with a critical
prime-mover, such as a pump or motor- is going drip, drip, hiss and eventually bang!
Maybe like CHIM in figure 2 above, we need to rediscover some old behaviours and
start walking the talk!
We in S A Partners aspire to help Manufacturing and Process Industry to realise its full potential in terms of Customer Service, Cost, Quality, Safety and Morale. TPM is a powerful enabling tool to help deliver this potential. Our experience suggests that- In the right hands-TPM is capable of unlocking your installed productive capacity by unlocking the potential of your people. This statement is of course subject to some vital pre-requisites. Among which are two main ones Hardware Considerations
When applying TPM to various Industry sectors we need to take account of the type
of Manufacturing Processes involved and whether for example, it’s a labour intense or
capital intense scenario; bulk processing or piece part manufacturing and so on….
People Considerations
5
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
We also need to recognise the differing impacts and hence the ideal behaviours the
Operator, the Maintainer and the Leader need to exhibit in those different scenarios.
With this in mind, we are going to consider here a matrix of seven types of facility
groups and six main factors that will impact the application of TPM
The seven groupings are
A) Process/Bulk Manufacturing (often Capital Intense)
B) Classic Manufacturing (Cell &/or linked Assets)
C) Packaging (sometimes Labour Intense)
D) Assembly (often Labour intense & / or Automated)
E) Utilities & General Services (often Capital Intense)
F) Warehousing (Pick and Place +Automation)
G) Remote & Dispersed Assets (ie Windfarms, Phone Masts, Reservoirs)
The six main factors we are going to consider are:
The OEE Measure (and other relevant KPI’s)
Operator Impact
Maintainer Impact
5S –WPO & Visual Management
Changeovers & Set-ups
Standard Work
We are also then going to consider in more detail the further ‘Human Factor’ impact
on these same seven A) to G) groupings in terms of
A Comparison of Potential impact on the ability to make Sound Decisions or
Judgements, whether you are an Operator, Maintainer or Leader
The Ideal behaviours to be exhibited by those same three job roles
2.1Seven Facility Types and Six Characteristics
The 2 x figures 3a) and 3b) below illustrates a matrix of the 7 types of facilities and the
6 main factors.
Each of the above are now described in more detail below
6
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
Type of Facility OEE Measure Operator
Impact
Maintaine
r Impact
5S –WPO &
Visual Man’
Change
overs
& Set-ups
Standard
Work
A)Process/Bulk
Manufacturing
(Capital
Intense)
Campaign or
Batch OEE as
a Fixed
Repeating
Schedule
Significant.
-Other than
being
Control
Room
based
Major Significant -
contamination
Control
+yields
Significa
nt +
Cleaning
In
Process
& use of
VSM &
ECRS
Major
B)Classic
Manufacturing
(Cell &/or
linked Assets)
Running
Clock OEE
Major -can
be labour
controlled-
rather than
machine
controlled
Major Major -to
create Flow
Major +
use of
VSM &
ECRS
Major
C)Packaging
(Often Labour
Intense +some
Automation)
Running
Clock OEE
Major -can
also be
labour
partly
controlled
Major Major -to
create Flow
Major Major
Figure 3a - Recognising the differences when applying TPM (1 of 2)
Type of Facility OEE Measure Operator
Impact
Maintainer
Impact
5S –WPO &
Visual Man’
Changeovers
& Set-ups
Standard
Work
D)Assembly
(Often Labour
intense & / or
Automated)
Running Clock
OEE
Major
Cycle or
Pulse rate
often
labour
controlled
Major Major to
create Flow
Significant
(&Pre-Kitting
,VSM &
ECRS
Major
E)Utilities &
Gen. Services
(Often Capital
Intense)
? Relevance of
OEE v.
Efficiency &
other KPI’s
Ranges
from Very
Little to
Major
Major Housekeepin
g resulting in
‘Maintenance
Pride’
Rarely
Applicable
Relevant
F)Warehousing
(Pick and Place
+Automation)
Running Clock
OEE
Major Major Major to
create Flow
Pre-Kitting
VSM & ECRS
Relevant
G)Remote &
Dispersed
Assets ie
Windmills,
Phone masts,
H20Reservoirs
Alarms freq
Callout freq
MTBF
MTTR&R
Very Little Major Limited
application
Rarely
applicable
Relevant
Figure 3b - Recognising the differences when applying TPM (2 of 2)
Each of the above are now described in more detail below
2.2 Process / Bulk Manufacturing
This type of facility which can include the acquisition and conversion of primary
materials –for example metals & chemicals (both liquid and / or powder) and paper
making-often comprise major physical stand alone and /or sequentially linked assets-
7
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
which are spread over big acreage and /or multi storey buildings. It is often capital
intense and highly automated and employing relatively few staff with a central hub
Control Room environment, often working on a 24 hour, 7 days a week with a 365
days per year shift patterns.
Rather than jumping in with a classic running clock 24 hour OEE, it is often more logical
to consider a batch or campaign OEE as a standardised time and sequence. This can
then be monitored & tracked through the standard lead time cycle time gates according
to the manufacturing logic for that specific batch. This is sometimes referred to as a
Fixed Repeating Schedule OEE
One of the central tenants of the TPM process and philosophy is that it encourages
‘Equipment Consciousness’. (ie this is how this process or mechanism is meant to
work and these are the typical phenomena that negate against that actually
happening).The key learning points of the Criticality Assessment (Step 4 in the 11 Step
TPM Process) is that it highlights the Impact of Safety, Reliability, Environment and
APQ (ie the OEE).The Criticality Assessment also provides a focus on the parts that
need to be kept in Optimum Condition as part of Steps 6-the Future Total Asset Care-
and Steps 7 & 8-Root Cause Analyses, Problem Resolution and Standardised Best
Practice
Perhaps our over dependency on technology means we has lost the will and common
sense to walk around the site / facility or plant and use our god –given senses of look,
see, smell and touch- In other words, we have lost the ability for catching the status
quo of an item early (as in a pump, motor, mechanism) due to over-heating, or perhaps
a leak, or vibration before it becomes catastrophic. Often these out of sight / out of
mind assets are also surrounded by unacceptable levels of 5S / Work-place
organisation, which result in poor contamination control, spillage (and hence yields).
The principle of Autonomous Maintenance- or as I prefer to call the first part of Step 6
-Front Line Operator Asset Care –recognises that the best condition monitor ever
invented is the Operator using their God-given senses of look. listen and discuss with
their Maintenance colleagues.
The above comments are also largely true of the other six types of facilities mentioned
in 2.2 to 2.7 below
A really good example of adopting a mind-set based on knowledge and understanding
is the adaptation of the OEE metric to suit an offshore oil platform in a hostile North
Sea environment. Here the set of metrics developed by the TPM driven Asset
Reliability Team were as shown in figure 4 below
8
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
2 August, 2016© S A Partners
OEE Measurement & Responsibility
FREQUENCY PARAMETER MEASURE RESPONSIBILITY PERSON
Monthly 1 Subsea Wells & Reservoir (ORE) APQ Owner Reservoir Engineer
Monthly 2 Field Management Effectiveness (OFE)
APQ Owner Reservoir Engineer
Weekly `3 Effectiveness of Oil Plant (OPE) APQ Operator OIM
Weekly 4 Separation AQ Operator Production Supervisor
Weekly 5 Flare Minimisation P Operator Production Supervisor
Weekly 6 Gas Compression APQ Operator Production Supervisor
Weekly 7 Overall Gas Compression System
APQ Operator Production Supervisor
Weekly 8 LP Eductor Equipment P Operator Production Supervisor
Weekly 9 Produced Water AQ Operator Production Supervisor
Weekly 10 Fuel Gas System APQ Operator Production Supervisor
Weekly 11 Boilers A Operator Chief Engineer
Weekly 12 Water Injection APQ Operator Production Supervisor
Where the OEE =
A = Availability x P = Performance Rate When Running x Q = Quality Rate Produced
Figure 4. Adapting the OEE measure to reflect the Operating Environment
In the Process / Bulk Manufacturing industries, Changeovers are often significant and
in many cases involve a ‘Cleaning in Process’ cycle between batches which is both
lengthy and complex. Here the tool of Value Stream Mapping -or if you prefer, Brown
Paper Mapping the Current State in order to develop the Future State, where there is
only ‘One Best Way’-which is then Standardised and trained out.
We do this by getting the right people (especially the Operators and Maintainers)
involved in that process of defining each elemental activity of the Current State via a
systematic E, C, R, S challenge process of which steps can we
Eliminate? -and if we can’t eliminate it, can we…
Combine it? with another activity upstream or downstream, & if not, can
we…
Replace it? with something smarter or at least …
Simplify it?
And then Standardise that ‘One Best Way’ and train it out as Standard
Work.
2.3 Classic Manufacturing
These physical assets can either be Singular (one Machine / one Operator) or Cellular
(more than one Machine but only one Operator), and / or coupled into a Value Stream
comprising several linked assets and their associated dependency and inter-
dependencies. Again it is vital to fully understand and then assimilate those
dependencies. For example, one Operator looking after more than one asset can
become labour controlled in certain machine loading and changeover configurations
9
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
rather than using the standard M/c cycle time or nameplate performance rate when
running. Line balancing becomes critical in these situations to optimise OEE
considerations-whether a running clock OEE or Batch OEE. The point being that the
lost opportunity elements of the OEE are not always due to the classic 6 x equipment
losses, but can be based on a manning level decision (and hence a ‘Management’ or
‘Door to Door’ loss). The figure 5 below attempts to illustrate some of these issues that
need to be fully understood, otherwise a corrupted performance measurement system
will give misleading information which is based on erroneous assumptions and
standards.
1 August, 2016© S A Partners
Machine Cycle
Lost quality
Lost performance
Lost availability
Working time available
Equipment Effectiveness
M/C #1
M/C #2
M/C #3
M/C #4
M/C #5
To focus on the worst OEE (Machine
#3) will miss the point (because
capacity is available)
Machine #5 is the pinch point even though it has
moderate OEE and comfortable machine
cycle time (Capacity is restricted throughout the Value Stream by this M/C)
Productive Capacity
Non-Productive Capacity
Available Capacity
To focus on the longest cycle time (Machine #2) may miss the point as it
is not the ‘pinch point’ within the line of 5 x M/cs
Where to focus the TPM Effort?
Figure 5 –Where to Focus the TPM efforts
It is important to also note that the OEE says nothing about schedule adherence. It is
pointless having a high OEE if you are making the wrong products.
OEE can be improved in good and bad ways. Good ways are to reduce unplanned
breakdowns, minor stoppages and changeover times. Bad ways are simply to do fewer
changeovers, or avoid making products with high defect rates or more difficult
adjustments.
As such, OEE should not be used in isolation, but alongside such measures as
customer request date, manufacturing promise date, schedule attainment, WIP and
inventory levels.
Similarly, your TPM efforts and the associated need for Asset Performance
Improvement (ie the OEE) needs to take account of the top level Business Drivers and
Imperatives for the next say 12 to 18 months.
10
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
IT is also a worthwhile exercise to stimulate discussion and more detailed analysis, by
first setting down a simple but effective A, B, C categorisation of the Physical Assets
where
A) Assets are critical all of the time
B) Assets are critical some of the time
C) Assets are never or rarely critical
2.4 Packaging
Similar to Classic Manufacturing in the sense that both Operators and their
Maintenance colleagues can have a major impact on asset effectiveness because all
6 classic equipment losses come into play. Many packaging lines have a combination
of labour controlled elements as well as islands of automation (conveying, weighing,
filling, inserts, sealing, palletising and shrink wrap). Minor stoppages corrected by the
Operator are often more significant as lost time / lost opportunity than breakdowns
requiring the presence of a Maintainer. Similarly, Changeovers can be significant as
can the need for 5S / workplace organisation to create flow around those assets
together with the judicious use of equipment based visual indicators
2.5 Assembly
This can range from a stationary but complex physical asset into which are fed several
components often at high speed, using innovative and ingenious tracking, sequencing,
insert and pressing devices with high levels of automation.
Alternatively, it may comprise a moving line or pulse line assembly for larger more
complex products (Home Entertainment Goods, White Goods and Vehicles). Again
the man / machine interface and interaction may be more labour controlled than
machine controlled.
In both cases internal and external supply chain co-ordination will be crucial. Also the
resultant internal pre-kitting, kan-bans and line balancing will be just as important as
the equipment reliability issues themselves.
This is where a broader view of the OEE is worth exploring
Figure 6a) Below illustrates 3 x levels of measurement focus
The Floor to Floor OEE, which focuses the core Team’s TPM efforts onto the
classic 6 x Equipment based losses, (by tackling breakdowns, changeover
times, running at reduced speed, minor stops, scrap. yield, rework losses-
plus start-up losses every time we get a breakdown, changeover or minor
stop). This is where a product and / or raw material is fed to a ‘value adding’
machine, physical asset or process and them placed on a pallet or conveyor
for onward routing.
The Door to Door Effectiveness which is within Management’s control (and is not an equipment related loss). Typically, these losses might be
11
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
* Labour Co-ordination losses (i.e. no Operator available, or the Maintainer is diverted to other priority) * Product Supply Starvation * No Work Order * No Packaging Materials * Consumable Stock outs * Awaiting QA Clearance Instructions * NPI Trials * Machine Upgrade and hence out of production service.
The Value Chain Effectiveness embracing Suppliers through to Customer
Delivery
1 August, 2016© S A Partners
The Value Stream
and the OEE as an Enabler
65% M/C OEE(90%)
Classic 6 x Losses
FLOOR-TO-FLOOR
OEE
55% DOOR-TO-DOOR
EFFECTIVENESS (85%)
CustomersExternal Suppliers
45% “VALUE CHAIN” EFFECTIVENESS (80%)
Where (x%) = Target
y% = Actual
Figure 6a-The OEE as an Enabler through the Value stream
In the above example, the current and target levels of effectiveness are shown at each
level. The rationale being that there is little merit in increasing the F2F OEE from 65%
to 90% if the D2D effectiveness stays at 55%. Likewise, there is little merit in getting
the D2D effectiveness up to say 85% if we are getting inconsistent Supplier responses
and we are making product that sits in the finished goods warehouse for 6 months.
The point is that by concentrating on the F2F losses we will also be highlighting the
D2D losses and in turn the Supply chain effectiveness
This 3 x Level Model can then be aligned to the Plant organisation structure to reflect
accountabilities and expectations as illustrated in figure 6b.
12
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
1 August, 2016© S A Partners
General
Manager
Unit Operations
Manager
Manufacturing
Area T/L
& Team
Overall Supply Chain Efficiency
Factory “Door-to-Door” OEE
Machine/
Line
OEE
The OEE as an Enabler for a
Site Performance Contract
Site Performance “Contract”
Top Down Target Driven Management,
Bottom-Up Shift Team - Based Activity
Maximize Value Added & Eliminate Waste
Through OEE Measurement To Direct/
Focus Action/ Improvement
In
Order
To
Top
Down
Bottom
Up“Floor To
Floor”
Figure 6b-A Three Level Site Performance ‘Contract’
This approach allows us to pin-point commitment and accountability at the right level
in a Plant organisation such that, in this example:
The General Manager is the SPONSOR of the TPM routines (making TPM a
non-optional part of ‘the way we do things here’)
The Unit Operations Manager -through their Shift based Section Leaders, are
the FACILITATORS of the TPM routines (ensuring that the routines are
carried out to the required standard at the right time and frequency)
The Operators and Maintainers, who CARRY OUT the TPM routines that they
themselves have designed and specified during the TPM pilot project phase.
All of the above becomes a key part of the application of Standard Work which will be
central to the TPM activity.
2.6 Utilities & General Services
This grouping range from the large public utilities such as Water, Gas, Electricity and
Nuclear, and can also include Docks & Airports in this category
Likewise, In-plant local services for any of the above four A) to D) facilities such as on-
site CHP Energy raising (Steam, Gas, Electricity and Air) and its distribution to the
point of use. Also Effluent control and disposal.
There is often a very significant element of outsourcing the Maintenance activity. This
can range from specialist Condition Monitoring services to the total outsourcing of the
Maintenance activity. Here the TPM Philosophy becomes attractive as the moves
13
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
towards Partnership Agreements become a reality. (as opposed to purely Service
Level Agreements-which often tend to generate the wrong behaviours- even to the
extent of them eroding over time to become both adversarial and confrontational)
In terms of measurement, the classic OEE is not always relevant and other KPI’s need
to be thought through and used. A few examples that I have seen in this category are
Airport Baggage Handling System-Number of lost bags per day. Number of false sensor alarm resets per shift
Mail Sorting Office-Number of miss-sorted items per shift. Number of Interventions per day
Water Treatment Plant-Mean Time Between Failures & Mean Time to Respond & Repair. Maintenance cost per 1,000 litres of processed clean water.
In House Plant Services-Air Pressure distribution loss. Energy cost per unit of output
Obviously the possibilities are immense and it’s perhaps worthwhile setting down the
5 x Measurement principles within TPM to help you decide on the correct measures
to drive the right behaviours within your facility
The correct measures will:
Improve the quality of problem solving
Help set fast track priorities
Maintain Management commitment to the TPM approach
Help deliver the Business drivers
Focus on driving out non value adding waste in all its forms.
2.7 Warehousing
This category is again an opportunity to be creative by the careful tailoring and
adaptation of the more classic TPM application.
Here is an example of an ‘In-Plant’ highly Automated Storage and Retrieval System
(ASRS) which is characterised by
6 x Cranes servicing 12 Racks over 13 x Levels, 100 Spaces each
C.14,000 pallet spaces
1,200 pallet movements per month
100+ alarms per week caused by……
o Miss-aligned sensors
o Dirty sensors
o Twisted pallets (variety of reasons)
o Random Mixture of Plastic v. Wood pallets (Good & bad points)
Significant No. of Conveyors and transport Mobiles
‘Hundreds of Sensors
Very good Visual Process Flow Map (Photo’s +Graphic)
14
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
Many linked critical assets (GR→ Automated HL Storage → Retrieve
→ Convey → Kit → Convey →AGV → Production)
New Integrated Process Logic system bedding in
Need high Level Criticality assessment to focus improvement
opportunities via TPM & develop Future state via ECRS challenge &
then Standardise
The Future Vision and ‘Challenge’ developed across the Shift Team’s involvement in
applying relevant measures and TPM based Asset Care is articulated by the Team as
follows
Operates as it should-with the ASRS part of it as ‘lights-out’ operation
where Alarms are a rarity
Operations & Maintenance working as One Team to self-determined
Standards and then Sustaining those standards over the long term
Greatly improved understanding of how our physical Assets actually
work, through relevant Training in a Safe and fit for purpose
environment
Deliver our internal customer requirements (production) on time in full.
Early indications after 6 months’ application of the above ‘Statement of Intent’ are that
Alarms are now less than 10 per week and the Operators & Maintainers are proud of
their workplace and are far more ‘Equipment Conscious’. Internal customer demand
is being met without overtime and there is now a choice of flexibility to meet planned
future increase in demand.
In a more mature application of TPM in a Materials Handling environment of a highly
automated multi- sourced material stock feed system to c.60 moulding machines, the
following results- as articulated by the Team of Operators and Maintainers at Milestone
2 of their TPM journey (previously mentioned in article 5) has been as follows:
• ‘…. The Material Handling System Area has become an easier place to
work in and is presentable to both customers and suppliers. Safety is
now our number 1 Priority
• Current average alarms are 76 per Week which represents an 80%
reduction from 463 per Week before we started TPM
• Average Weekly Downtime as a result of the Material System
improvements & Feed delivery to all c.60 Moulding M/cs has gone from
68 Hours- down to just 3 Hours per week…’
2.8 Remote and Dispersed Assets
Typical, but not exhaustive examples would include Wind Farms, Telecommunications
masts, Water Reservoirs (both above & below ground) and their associated pumping
and metering stations.
Technically we might call these peripatetic maintenance assets, where the business
is responsible for multiple and geographically diverse assets which are largely
15
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
unmanned facilities requiring central 24-hour monitoring. The biggest-and often false-
assumption in this scenario is that regular visible and physical ‘human’ inspections &
maintenance are grossly undervalued and the technological tail is left wagging the
dog.
Maybe like CHIM in figure 2, we need to rediscover some old behaviours and start
walking the talk!
The OEE metric is not usually relevant in this category. More relevant Asset Reliability
metrics would include
Alarms frequency
Callout frequency
Mean Time Between Failure
Mean Time to Respond & Repair
Whilst Operator impact is minimal the Maintainer impact is major and Standard Work
will be very relevant
3.0 Human Factor Impact
We also need to consider the Human Factor impact on these same seven A) to G)
Facility groupings in terms of two considerations
A Comparison of the Potential impact on making Sound Decisions or
Judgements, whether you are an Operator, Maintainer or Leader (Figure 7a &
7b)
Ideal behaviours to be exhibited by those same three job roles (Figure 8)
These comparisons and statements as illustrated below are based on personal
experience and qualitative assessments (rather than absolute or quantified data).
They do however serve to help clarify roles, responsibilities, accountabilities and
expectations of the main players when implementing a TPM system in that industry
sector and facility type.
16
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
Type of
facility
Equipment Consciousness(How the Asset is meant to Work)
Initialtrouble Shooting &ProblemSolving-Before Issue Escalation
ProcessConsciousness(How the Process Works)
Preventative maintenance involvement
Process Plannedshutdown
Spares and stores processes
A)Process /
Bulk
O 3
M 3
L 3
O 2
M 3
L 2
O 3
M 3
L 3
O 3
M 3
L 1
O 1
M 3
L 3
O 1
M 3
L 3
B)Classic
Manufacture
O 3
M 3
L 2
O 3
M 3
L 2
O 3
M 2
L 3
O 3
M 3
L 1
O 2
M 3
L 2
O 2
M 3
L 3
C)Packaging O 3
M 3
L 2
O 3
M 3
L 2
O 3
M 3
L 3
O 3
M 3
L 1
O 2
M 3
L 2
O 2
M 3
L 2
D)Assembly O 3
M 3
L 2
O 2
M 3
L 2
O 3
M 3
L 3
O 3
M 3
L 1
O 1
M 3
L 3
O 2
M 3
L 3
Potential Impact Rating Scale 1= none, 2= some , 3= major .
Where job Role is O = Operator, M = Maintainer and L = Leader
Figure 7a) Comparison of Potential impact on making Sound Decisions or
Judgements
Type of Facility Equipment
Conscious
ness
(How the
Asset is
meant to
Work)
Initial
Trouble
Shooting &
Problem
Solving-
Before Issue
Escalation
Process
Conscious
ness
(How the
Process
Works)
Preventative
maintenance
involvement
Process
Planned
shutdown
Spares
and stores
processes
E)Utilities O 2
M 3
L 2
O 2
M 3
L 2
O 2
M 3
L 3
O 2
M 3
L 1
O 1
M 3
L 3
O 1
M 3
L 3
F)Warehouse O 3
M 3
L 2
O 3
M 3
L 2
O 3
M 3
L 3
O 3
M 3
L 1
O 1
M 3
L 3
O 1
M 3
L 3
G)Remote &
Dispersed
Assets
O 2
M 3
L 3
O 2
M 3
L 2
O 2
M 3
L 3
O 3
M 3
L 1
O 1
M 3
L 3
O 1
M 3
L 3
Where job Role is O = Operator, M = Maintainer and L = Lead
Potential Impact Rating Scale 1= none, 2= some , 3= major.
Figure 7b) Comparison of Potential impact on making Sound Decisions or
Judgements
17
TPM - The Pinch - Point Solution for Delivering Operational
Excellence © S A Partners
© S A Partners
Type of Facility Ideal Behaviours
Operator
Ideal Behaviours
Maintainer
Ideal Behaviours
Leader
A)Process/Bulk Take initial front line Ownership
Resolve and Prevent Recurrence
Trust to DelegateManage by Green
B)Classic Manu Take front line Responsibility
Proactive &Innovative
Trust to DelegateManage by Green
C)Packaging Take front line Responsibility
100 yr fix Mentality Trust to DelegateManage by Green
D)Assembly Take initial front line Ownership
Resolve and Prevent Recurrence
Regular, Visible support
E)Utilities An appetite & willingness to Learn
Pride of OwnershipWith TLC
Ask not Tell.Regular, Visible support
F)Warehouse Take initial front line Ownership
100 yr fix Mentality Create anEnvironment for Teamwork to thrive
G)Remote &
Dispersed Assets
Learn new skills,Go see the Asset with the Maintainer
Pride of OwnershipGo see the Asset,Resolve and Prevent Recurrence
Trust to DelegateManage by Green
Figure 8-Ideal Behaviours exhibited by job role in the seven Facility types
Our penultimate article in this series (No 8) will be published in March and will focus
on the Early Equipment Management founding pillar of the TPM philosophy.
Finally, in Article 9 (April), we will review a number of TPM case studies and conclude
with a signposted Summary of the Key Learning points from all 8 previous articles.
Meanwhile –your observations & contribution to this article and particularly to
challenge my observations and statements will be very welcome. Please contact me
at [email protected] .