WHAT IS TOP DOWN CONSTRUCTION ?

In this method, basement concrete slabs act as lateral bracing for the perimeter wall system. Ground level and first basement slabs are poured, with access holes left to allow excavation beneath. As each subsequent subgrade level is completed, the floors act as lateral bracing for the perimeter wall system.

Page 3: Top down construction

TOP-DOWN CONSTRUCTION METHODo Use of diaphragm wall as the side support for the earth

o Construction progress upwards and downwards at the same time

o Savings in construction time

o Schematics and pictures give ideas on ongoing activit ies during construction

Page 4: Top down construction
Page 5: Top down construction

TOP-DOWN CONSTRUCTION METHOD

Page 6: Top down construction
Page 7: Top down construction
Page 8: Top down construction

TOP-DOWN CONSTRUCTION METHOD

Page 9: Top down construction

MAIN ADVANTAGE OF TOP-DOWN CONSTRUCTION

Page 10: Top down construction

DETAILS OF TOP-DOWN CONSTRUCTION METHOD

Page 11: Top down construction

EXCAVATION TO LEVEL -1

Page 12: Top down construction

EXCAVATE TO LEVEL -2

Page 13: Top down construction

COMPACTION AND LEVELING OF BASEMENT SLAB FOR REINFORCEMENT AND CONCRETE WORKS

Page 14: Top down construction

MORE EXCAVATION WORK IN PROGRESS

Page 15: Top down construction

CONCLUSIONo Need careful consideration for use in HCMC since method is new here

o Ideal for 5 basements or more

o May need some soi l improvement techniques and good dewatering system

o Equipment for these works may not be readily available in HCMC

o Handling of excavated soi l material require planning, keeping in mind marine clay at upper level and silty sand at lower level