TCWS Design and Centralized procurement for ITER Piping Information Day
� Each Supplier or Subcontractor providing equipment or servicesto the ITER Organization must provide a dedicated Quality Plan.
� A Quality Plan covers the whole scope of the contract anddescribes the operational quality system (based on ISO 9001 orequivalent) to ensure that:� Contract requirements will be met� Evidence of such compliance is maintained
� Work shall not start until the relevant Quality Plan has beenaccepted by ITER.
4 - Quality Assurance requirements
Page 7
TCWS Design and Centralized procurement for ITER Piping Information Day
� The Quality Plan is contract specific and shall identify:
• the specific allocation of resources, duties, responsibilities andauthority;
• details of all suppliers/subcontractors and how interfaces will bemanaged;
• the specific procedures, methods and work instructions to beapplied;
• the specific methods of communication, both formal and informal,to be established between working groups.
� Much of the generic documentation needed to prepare the Quality Planwill normally already exist as part of the Supplier/Subcontractor’squality management system and supporting procedures. The QualityPlan need only refers to this documentation and shows how it is to beapplied to the particular contract.
4 - Quality Assurance requirements
Page 8
TCWS Design and Centralized procurement for ITER Piping Information Day
Manufacturing and Inspection Plan (reference ITER_D_22MDZD)
� Each Supplier and sub-contractor shall supply the DA with a MIPlisting the sequence of manufacturing operations encompassing thewhole scope of the contract (review of drawings, verification ofmaterials, manufacture, inspection and test to delivery…).
� MIP allows supplier, DA and IO to mention control points (NP, HP,WP…).
4 - Quality Assurance requirements
Page 9
TCWS Design and Centralized procurement for ITER Piping Information Day
Deviations and Non Conformances (reference ITER_D_22F53X)
� Deviation: A planned alternative to a specified requirement.
When a deviation to IO specifications is anticipated theSupplier/Contractor shall discuss it with the IO/DA responsible officer asappropriate for that ITER work activity. If the proposal is consideredbeneficial, the Deviation Request shall be sent to IO for approval.
� Non-Conformance: Any condition, which does not comply with a
specified requirement.
When a non-conformance is identified the Supplier/Contractor shall:• Identify, and segregate when practical, the non-conforming item• stop any further work on the item until a decision is made• record and report the occurrence by raising a Non-conformance
Report• Minor Non-conformances are sent to IO for information• Major Non-conformances are sent to IO for approval
4 - Quality Assurance requirements
Page 11
TCWS Design and Centralized procurement for ITER Piping Information Day
• IO recognizes the basic principles of competition, fair andequal treatment of Tenderers
• These principles shall ensure that the IO can obtain the bestvalue for money by soliciting participation of a number ofqualified firms.
� Procurement and Contracts Division (PCD) :
• PCD primary objective and responsibility is to protect the IO’sinterest while procuring supplies, services, and works to meetits organizational requirements.
• PCD in charge of the management of tendering processesand then administrating the contracts
5 - TCWS&CP Procurement general strategy/program
Page 19
TCWS Design and Centralized procurement for ITER Piping Information Day
� Ensure that offers are sought only from suppliers who have thefinancial capabilities as well as requested skills, equipmentand experience to perform works or services as described inthe technical summary (and later in the technicalspecifications).
� The PQ form includes :• Questionnaire with Pre-Qualification criteria (pass/ fail)• Technical Summary of the scope • Administrative forms
5 - TCWS&CP Procurement general strategy/program
Page 21
TCWS Design and Centralized procurement for ITER Piping Information Day
� Contractual document signed between the IO and Supplier(s)which sets the terms and conditions under which anyDomestic Agency or their contractors may procure identifiedsupplies
� Concluded and signed by the IO to ensure standardization ofsupplies for the ITER Project
5 - TCWS&CP Procurement general strategy/program
Page 25
TCWS Design and Centralized procurement for ITER Piping Information Day
� Contemplated selection process in most of the cases:
� Call for Tender with Call For Nomination and Pre-Qualification
� Award criteria based on Lowest Price Technically Compliant approach where the Technical Compliancy for each Requirement is to be justified in the Tender.
5 - TCWS&CP Procurement general strategy/program
5.2 - TCWS General Contractual Strategy (cont’)
Page 27
TCWS Design and Centralized procurement for ITER Piping Information Day
� Regulatory requirement to have two separate contracts, but could be awarded to one single Contractor
� Each Contract will cover the needs of TCWS and potentially ITER Systems needs with regards to the Centralized Piping Procurement approach
� For these two contracts : �Contract Type should be Framework Contract with Tasks Orders. �Selection process should be Restricted Solicitation to companies
agreed Notified Body by ASN (French Nuclear Safety Authority)
No Scope of Work
TCWS/NB/1 Contract for Technical assistance in the field of Pressure Equipment and Nuclear Pressure Equipment.
TCWS/NB/2Contract for mission of Notified Body and Agreed Notified Body for the manufacture of several Pressure and Nuclear Pressure Equipment
5 - TCWS&CP Procurement general strategy/program
5.6 - TCWS Contractual Strategy for Notified Body
Page 32
TCWS Design and Centralized procurement for ITER Piping Information Day
TCWS Final Design Centralized Procurement and Pre-
Assembly of Pipes
NO
NO
Conflict of
interest with CP
YES
TCWS/NB/2
Contract for mission of Notified Body and Agreed Notified
Body for the manufacture of several Pressure and Nuclear
Pressure Equipment
NO
Nota : � No conflict of interest between CP contracts stated in CP/1 CFN (issued)� No conflict of interest between FD contracts stated in FD/1 and 2 CFN
(issued)
No Scope of Work
TCWS/FD/1
Contract for Thermo-Hydraulic Analyses and
Calculations for Process and System
Engineering of TCWS
TCWS/FD/2Contract for Mechanical Analyses and
Calculations of TCWS piping
TCWS/FD/3Contract for Analyses and Calculations for
Mechanical Engineering of Equipment Design
TCWS/FD/4 Contract for Feasibility Studies
TCWS/FD/6 Contract I&C Engineering
TCWS/FD/7Contract for Agreed Notified Body Services during
Final Design
TCWS/FD/8 Final Design for TCWS: 1st plasma equipment
TCWS/FD/9 Final Design for TCWS: 2nd plasma equipment
YES
YES*
YES*
TCWS/FD/5 Optional : Contract for 2D-3D drawings
TCWS/NB/1Contract for Technical assistance in the field of Pressure
Equipment and Nuclear Pressure Equipment.
5.7 - TCWS Contracts Mapping and Conflict of Interest
YES* Conflict with only one CP/X contract
[FD/4 with CP/6 and FD/6 with CP/4]
TCWS Notified Body
NO
5 - TCWS&CP Procurement general strategy/program
Page 33
TCWS Design and Centralized procurement for ITER Piping Information Day
6 – Focus on Design contracts FD/1 : Contract for Thermo-Hydraulic Analyses and Calculations for Process and System Engineering of TCWS
Subject : Thermo-Hydraulic Analyses and Calculations for Process and System Engineering of TCWS
Main tasks / activities :
� Task 1: Thermo-hydraulic steady state analyses
� Task 2 : Thermo-hydraulic transient analyses
� Task 3 : Components sizing calculations
� Task 4 : Water Hammer analyses
� Task 5 : Design of overpressure protection systems
� Task 6 : Listing needed modifications to PFD and P&IDs
Particular skills:
� Experience in thermal-hydraulic design of nuclear systems or complex processing plants cooled by pressurised water.
� Computational analyses performed with Fathom and Arrow (or similar codes) for steady state analyses and Relap5 code for transient analyses. Experience in water hammer analyses.
� Experience in the design of overpressure protection systems.
� Knowledge of the requirements included in ESP/ESPN regulations.
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 3 years
Key sizing figures :
� Thermo-hydraulic analyses and components sizing (Task1-2-3) for 5 TCWS sub-systems (excluding IBED and VV PHTS).
� Water hammer analyses and over pressure protection system design for 7 TCWS sub-systems (including IBED and VV PHTS).
� 115 reports to be produced.
Conflict : No
Page 40
TCWS Design and Centralized procurement for ITER Piping Information Day
6 – Focus on Design contracts FD/2 : Contract for Mechanical Analyses and Calculations of TCWS piping
Subject : Mechanical Analyses and Calculations of TCWS piping
Main tasks / activities :
� Static and Dynamic stress analysis for Nuclear and Non – Nuclear class piping
� Postulation of Double End Guillotine Breaks for High Energy Lines, analysis of consequences and implementation of mitigating measures to cope with jet and whipping effect
� Detailed Design of Pipes and component supports and structures
� Thermal stratification studies and thermal fatigue analyses
Particular skills:
� Strong experience in the thermo mechanical analyses of nuclear piping
� Good knowledge of ASME B31.3 code and additional requirements of ESPN regulation
� Good knowledge of the Double End Guillotine Break problem and the associated effects
� Strong capacity to design a large amount of nuclear qualified supports and associated reports and drawings within a tight schedule
� Knowledge of Nuclear supports design codes, in particular AISC N690 / ASME III NF
� Proven capability to analyze the thermal stratification problem in piping systems
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 3 years
Key sizing figures :
� 3400 process lines grouped in 150 Engineering Problems for Stress analyses
� 6500 individual supports to be designed and 6500 drawings to be produced
� 1200 potential rupture DEGB locations
� 3 pressurizer lines and potentially several more lines to be address for thermal fatigue
� 100 Reports to be produced, 300 Deliverables (including software files) ;30 Work Packages
Conflict : With all Piping Procurement Contracts
Page 41
TCWS Design and Centralized procurement for ITER Piping Information Day
� Interface engineering for Instrument and Electrical systems
� Control Software Philosophy
� Electrical power engineering documents including load list revisions, single-line diagrams, power distribution equipment lists and specifications, etc….
� Electrical power distribution installation drawings including cable specification and diagrams, motor control centre (MCC/VFD) fabrication drawings, etc….
Particular skills: Instrumentation engineering for industrial plants, preferably water treatment systems or chemical plants. Experience in instrumentation installed in ionizing radiation and magnetic field, nuclear domain will be an added advantage
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 1 – 1,5 year
Key sizing figures :
� > 3000 components
� > 10.000 Inputs/outputs
� > 50 MW
Conflict : With CP/4 : Contract for procurement of instruments
Page 44
TCWS Design and Centralized procurement for ITER Piping Information Day
FD/8 : Final Design for TCWS: 1st plasma equipment
Subject : Final Design for TCWS: 1st plasma equipment
Main tasks / activities :
� Perform equipment associated calculations to support USDA and IO in the preparation of the component detailed design (Pressure Vessels, Heat Exchangers, Filters, Cyclones, Heaters, etc)
� Providing support to the USDA and IO during the preparation of the system’s 1st Plasma main component Technical Specification
� Providing expert support to the USDA and IO during the elaboration of the system’s 1st Plasma main components data sheets
� Providing support to the USDA and IO during the selection of 1st Plasma component supplier by giving expert advice on relevant technical issues
Particular skills: Systems engineering
Contract type : Framework Contract
Duration forecast : 9-11 months
Key sizing figures :
� 3 Compressors and 11 pumps
� 10 Heat exchangers and 4 electrical heaters
� 6 Pressure vessels and 3 separators
� 4 cartridge filters
Conflict : Potential conflict with the contracts for Supply of components under USDA scope
Page 45
TCWS Design and Centralized procurement for ITER Piping Information Day
FD/9 : Final Design for TCWS: 2nd plasma equipment
Subject : Final Design for TCWS: D - T plasma phase equipment
Main tasks / activities :
� Perform equipment associated calculations to support USDA and IO in the preparation of the component detailed design (Pressure Vessels, Heat Exchangers, Filters, Cyclones, Heaters, etc)
� Providing support to the USDA and IO during the preparation of the system’s D -T phase main component Technical Specification
� Providing expert support to the USDA and IO during the elaboration of the system’s D -T phase main components data sheets
� Providing support to the USDA and IO during the selection of D -T phase component supplier by giving expert advice on relevant technical issues
Particular skills: Systems engineering
Contract type : Framework Contract
Duration forecast : 10-12 months
Key sizing figures :
� 20 pumps.
� 22 Heat exchangers and 3 electrical heaters.
� 17 Pressure vessels
� 14 cartridge filters and 4 mixed bed filters
Conflict : Potential conflict with the contracts for Supply of components under USDA scope
Page 46
TCWS Design and Centralized procurement for ITER Piping Information Day
Subject : Manual, motorized, safety and control valves & valve actuators
Materials:
� Manual valves with ratings ranging from 150# to 900 #
� Pneumatic Actuators and Electric Motor including required accessories, spare parts and documentation to the IO
� Control valves including required accessories, spare parts and documentation to the IO
� Pilot operated relief valves and Spring operated relief valves
Particular requirements :
� Applicable Standards: ASME B16.34 (Valve Body), ASTM for all, ESP and ESPN partially, Machinery Directive (Control Valves and Actuators), and EMC Directive (Control Valves and Actuators)
� Seismic qualification required for most of the valves
� Most valves with rigorous leak tightness requirements
� Some valves with particularly low seat leakage requirements
Contract type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 4 years
Key sizing figures :
� Valve Size (DN): 15 to 500
� Approximately 2700 valves (Manual, operated), 100 Relief Valves, 100 Control Valves, 2200 actuators (Pneumatic and Motor operated)
CP/3 : Contract for procurement of manual, motorized, safety and control valves & valve actuators