FINAL PROJECT Business Analysis Final Paper DeVry University Thomas J Rones FINAL PROJECT
FINAL PROJECT
Business Analysis Final Paper
DeVry University
Thomas J Rones
FINAL PROJECT
FINAL PROJECT 2
Executive Summary_____________________________________________________________2
Business Problem Review________________________________________________________3Figure 1: U.S. Recoverable Oil vs Foreign______________________________________________________3
Analytical Plan_________________________________________________________________4
Elicitation Techniques________________________________________________________________4Schedule of activities_______________________________________________________________________4
Figure 2: Inputs, Tasks, & Outputs___________________________________________________________5
Survey Description and Question(s)_____________________________________________________5Questions________________________________________________________________________________6Survey Conclusion__________________________________________________________________________6
Requirements Communication____________________________________________________7Internal Stakeholders:_______________________________________________________________________7External Stakeholders:______________________________________________________________________7
Enterprise Analysis______________________________________________________________7Figure 3: Production Equation______________________________________________________________8Figure 4: Exploration Equation______________________________________________________________9Figure 5: Techniques for Information Gathering________________________________________________9
Requirements Analysis_________________________________________________________10Figure 6: To Drill or Not To Drill (Cap Rate is KPI)_______________________________________________11
Solution Assessment and Validation_______________________________________________12
Techniques________________________________________________________________________12
Recommendations & Conclusion__________________________________________________12
FINAL PROJECT 2
FINAL PROJECT 3
Executive Summary
This project began with a focus on how oil refineries are adapting to the new business
environment brought on by the United States oil shale revolution, but shifted scope to exploration and
production of oil, due to the results found during elicitation. As a result, this paper is of use to vertically
integrated firms and firms considering integrating either up or downstream. Producers looking
downstream need to be aware of the complexities in the refining arena and patient so as not to invest in
the wrong technologies. Upstream integrators can use the information found here as a starting place for
deciding if exploration and production makes financial sense – i.e. before obtaining expertise brought
through acquisition or consultation.
Business Problem Review
In June 2008 all the major oil benchmarks hit highs between $145 & $147/barrel. We recently hit
a low of $27/barrel. Many analysts and amateurs have tried to predict the ebb and flow of the supply and
demand for oil --- making statements such as “Oil prices doubled last year, even if people did not see the
price of their petrol double. The reason for this is simple: global demand for oil, particularly from
developing countries like China and India, is rapidly catching up to global supply (Our World, n.d.)” If
only it were that simple --- we would all be trading futures. The reality is that there are a myriad of
variables affecting the price and supply of oil.
FINAL PROJECT 3
FINAL PROJECT 4
Figure 1: U.S. Recoverable Oil vs Foreign
U.S. oil shale estimates definitely played their part. This project began with a focus on how oil
refineries are adapting to this new business environment, but shifted scope to exploration and production
of oil, due to the results found during elicitation.
Analytical Plan
The plan was originally to send surveys to subject matter experts and collect the responses to
come up with a solution for refineries. The solution ended up being patience, let the oil majors eat the
R&D costs. This is when the analytical plan turned to focusing on another portion of the supply chain,
analyzing it, and mapping out the thought process so that firms can create standard operating
procedures for decision making. I chose to focus on exploration and production, but we could also
analyze the chain from the refinery to the end user – known as midstream and downstream.
FINAL PROJECT 4
FINAL PROJECT 5
Elicitation TechniquesSchedule of activities
A. Stakeholder Selection – Decision makers (C-suite) at US oil refineries. If possible,
attempt to obtain a relatively even number of respondents per region and based on
refinery size. At a minimum, notate refinery size, location, and respondent’s position
within company so that the results can be filtered for analysis with a more specific
focus.
B. Analysis Techniques - The respondents will be contacted by email and/or phone. A
survey will be administered.
C. Timeline
Jan 17th- Design Survey
Jan 17th- Send survey through email
Jan 18th - Jan 27th – Collect additional responses over phone
Jan 28th – Analyze responses
FINAL PROJECT 5
FINAL PROJECT 6
Figure 2: Inputs, Tasks, & Outputs
Survey Description and Question(s)
(For a full description of the rationale behind each question see week 3 Survey Monkey Essay.)
The goal behind the survey is twofold:
1. Use quantitative questions to gain insight into the change/risk management policies of domestic oil
refineries and..
2. Use qualitative questions to elicit information to guide the development of additional quantitative
questions for future surveys.
QuestionsQ1: Is the lift of the United States crude export ban a positive, negative, or inconsequential development
for your business?
Q2: Why or Why Not?
Q3: Is US storage capacity an issue you consider? (1-10)
Q4: How large of a factor is the 2016 election in your risk management strategy? (1-10)
FINAL PROJECT 6
Survey Results
Analysis of Survey Results
Recommendations for future studies
Outputs
Conduct Survey
Tasks
Document Analysis
Survey Timeline
Business Need/Solution
Scope
Inputs
FINAL PROJECT 7
Q5: Have you converted or do you plan to convert your refineries from overseas heavy crude to light
sweet (shale) oil?
Q6 :( If Yes to previous Q) What percentage of your refining capacity do you plan to convert?
Q7: Do you use a price per barrel break even analysis to justify new capital expenditures?
Q8: What is your price per barrel needed for profitability?
Q9: How much lower do you think the price of oil can go?
Q10: Comments – Any key items we missed?
Survey ConclusionAs of this time, the survey size is too small, and/or the survey respondents span to wide a
variety of job roles and refinery sizes & types to use this data to guide any business decisions.
Unfortunately many of the issues discussed in this survey are interrelated. For example, the choice to
convert refining facilities depends on the political and legal environment. One factor overlooked when
designing the questions was the industry structure. The majority of firms are vertically integrated, from
production through refining, distribution, and marketing. Questions such as “price per barrel for
profitability” would be ok for independent refiners, but irrelevant for vertically integrated firms because
productions costs are passed through all the way to end consumers. The survey results inform us that
we need to narrow our focus in future studies.
Requirements Communication
Requirements do not need to be communicated to stakeholders because the final output is this
document. If we were to execute the idea outlined in enterprise analysis and requirements analysis
below, then the stakeholders that would need to be kept informed would include:
FINAL PROJECT 7
FINAL PROJECT 8
Internal Stakeholders: the project manager, financial department, team operating the
actual well
External Stakeholders: any applicable regulatory agencies, landowners, and/or financial
institutions with a vested interest.
Enterprise Analysis
We conducted enterprise analysis twice. The first time (Refining) used document analysis to
prepare for elicitation. After elicitation, we found that requirements analysis would not be
recommended due to the current state of technological adoption. There’s a fine line between the
leading edge and the bleeding edge, in other words, first mover advantage only applies to the pioneers
who survive the winter. Elicitation confirmed the need to shift scope to another section of the value
chain, but which one? The shale revolution has resulted in major upstream integration – production
companies getting into refining and distribution. This is because the cost of pumping oil is much less
volatile than buying crude on the open market. Let us then focus on the exploration and production
section of the value stream.
Round two of enterprise analysis consisted of functional decomposition - Which variables affect
our decision to invest in exploration and production? For exploration we are concerned with the initial
cost to acquire/drill the well, the lifetime barrels per well, the cost to pump each barrel, and the price
we can get on the market for each barrel (or downstream at the pump). The decision whether or not to
run the pump requires all of the above except for the initial cost of the well and the other variables are
concerned with a much smaller time period (days, weeks, or months).
FINAL PROJECT 8
FINAL PROJECT 9
To make these decisions simple, we created some equations that reflect how changes in each of
these four variables affects the others.
Figure 3: Production Equation
FINAL PROJECT 9
FINAL PROJECT 10
Figure 4: Exploration Equation
These equations can be put into excel for rapid scenario development, but where do we obtain our
numbers from? Unfortunately these are only estimates, but we can use the following information to
inform our estimates.
Figure 5: Techniques for Information Gathering
Technique Information
Document Analysis Cost/Well Barrels/Well Cost/Barrel Market Price/Barrel
Geo-Modeling X
Industry Reports X X X X
Competitors Public Docs X X X X
Futures Market X
Historical data on price of oil X
This document analysis will also provide us with the information necessary to conduct a SWOT analysis.
We need a SWOT analysis in order to Assess Capability Gaps.
FINAL PROJECT 10
FINAL PROJECT 11
Requirements Analysis
We will now process model the value chain and then functionally decompose our/competitors
costs. This should uncover any cost saving capabilities not found earlier. At this point we should have
enough information to conduct a MoSCoW analysis (Must have, Should have, Could have, and Would
like but won't get) on the capability gaps we have discovered. Our requirements are now organized and
prioritized. At this point, it would be nice to have Key Performance Indicator(s) for our Acceptance and
Evaluation Criteria. Essentially we want a definite answer to whether or not we should go ahead with
drilling. Our Key Performance Indicator (KPI) can be anything, and our swimlane diagrams will change
based on the KPI chosen. We will still use the same sources of information, and the equations
introduced in enterprise analysis will remain the same – the swimlane diagram just maps the options
available to change the values of those four variables.
My examples are using capitalization rate (the number of years it will take for income to reach
the cost of the capital expenditure at purchase). I chose this because after our capital expenditure is
paid off, our margin per barrel will be higher (no interest!).
(A full explanation of “To Drill or Not to Drill” can be found in the week 5 Visio assignment.)
FINAL PROJECT 11
FINAL PROJECT 12
Figure 4: To Drill or Not To Drill (Cap Rate is KPI)
FINAL PROJECT 12
FINAL PROJECT 13
Solution Assessment and Validation
The purpose of the Key Performance Indicator is solution validation. The Visio diagram shown
above is meant to be ever expanding, particularly under “Cut Costs”. For example, operational could be
sub-divided into categories – always remembering that a penny saved in a repetitive process is saved
every time the pump runs. The solution is thorough in that it reminds the oil producer to consider their
bargaining power, through five forces analysis - that penny saved might be as a result of being a major
customer of the local electric utility. To validate the solution further we would have to actually go
through the process of exploration and production.
TechniquesTechniques have been detailed all throughout this paper. One key technique is document
analysis. After elicitation yielded sub-par results, we used document analysis to find that as of now it
would be better to refocus our efforts on another section of the value chain --- production instead of
refining. Brainstorming and surveys were obviously used.
Recommendations & Conclusion
As recommended in the Executive Summary, patience is a virtue for refineries. Producers do not
have such an easy decision. If the equations indicate that it would be very profitable to acquire land and
drill, then do so. More work needs to be done to evaluate opportunity costs. In particular, a history of
drilling innovations with a focus on acquisition and operating cost would reassure producers that their
capital expenditures do not become sunk costs. It would also be prudent to gather information about
past deals and deal structure. Even if it does not make sense to drill in the current economic
FINAL PROJECT 13
FINAL PROJECT 14
environment, firms should always be aware of the supply of and demand for property sitting on shale
formations.
Oil majors may have more opportunity analyzing and transforming their downstream strategy.
Minor issues such as pricing and gas station accessibility could have dramatic consequences. This may be
anecdotal, but I usually end up at the same gas stations because they are conveniently located. This
might actually be a more interesting topic to research, but unfortunately we have reached the end.
FINAL PROJECT 14
FINAL PROJECT 15
References
Eberhart, D. (2014, February 14). Light on the Top, Heavy on the Bottom: A Crude Oil Refinery Primer - Canary, LLC. Retrieved January 16, 2016, from http://canaryusa.com/crude-oil-refinery-primer/
Levine, S., Taylor, G., Arthur, D., & Tolleth, M. (2014). Understanding Crude Oil and Product
Markets. Retrieved January 15, 2016, from http://www.api.org/~/media/Files/Oil-and-Natural-Gas/Crude-Oil-Product-Markets/Crude-Oil-Primer/Understanding-Crude-Oil-and-Product-Markets-Primer-Low.pdf
Obama rejects Keystone XL pipeline - CNNPolitics.com. (n.d.). Retrieved January 16, 2016, from http://www.cnn.com/2015/11/06/politics/keystone-xl-pipeline-decision-rejection-kerry
Oil Price Rises as Airline Fails - Our World. (n.d.). Retrieved January 16, 2016, from
http://ourworld.unu.edu/en/oil-price-rises-as-airline-fails
Oil Shale - IER. (n.d.). Retrieved January 16, 2016, from http://instituteforenergyresearch.org/topics/encyclopedia/oil-shale/
The Economics Of U.S Crude Oil Storage Capacity | Investopedia. (2015). Retrieved January 16, 2016, from http://www.investopedia.com/articles/investing/041015/economics-us-crude-oil-storage-capacity.asp
U.S. Oil Shales: Breakeven Oil Price Is A Tricky Concept. (2015, May 10). Retrieved January 16, 2016, from http://seekingalpha.com/article/3166446-u-s-oil-shales-breakeven-oil-price-is-a-tricky-concept
FINAL PROJECT 15