Page | 1 MONTHLY PROGRESS REPORT Through June 2017 Strong Schools Bond Capital Improvement Projects Prepared by fs3|Hodges
45

Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

May 18, 2018

Download

Documents

vuquynh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 1  

 

  

MONTHLY PROGRESS REPORT  

Through June 2017 

  

Strong Schools Bond Capital Improvement Projects 

Prepared by  

 fs3|Hodges 

   

Page 2: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 2  

 

TABLE OF CONTENTS  

Executive Summary                  page 3   Attachment 1 – Consolidated Expenditure Report          Capital Projects   

Gunn High School – Central Building Project           page 7 Palo Alto High School – Science Building Addition          page 8 Palo Alto High School – Indoor PE and Athletic Facilities        page 9 Palo Alto High School – Building 500 Renovation          page 10 Addison Elementary School – New Library, Administration and Multipurpose Building  page 11 El Carmelo Elementary School – New Multipurpose Building        page 12 Escondido Elementary School – New Multipurpose Building        page 13 Hays Elementary School – New Multipurpose Building        page 14 Hoover Elementary School – New Library, Administration and Multipurpose Building  page 15 

 

Completed Capital Projects  

Gunn High School – New Classroom Building and World Languages Building    page 16 Gunn High School – New Gymnasium             page 17 Gunn High School – Existing Gymnasium Modernization        page 18 Gunn High School – E and K (L31 and MS) Buildings Renovation      page 19 Gunn High School – Traffic Signal Replacement (Phase I‐ Improvements)    page 20 Palo Alto High School – Athletic Stadium Improvements        page 21 Palo Alto High School – Haymarket and Tower Building Improvements      page 22 Palo Alto High School – New Classroom Building and Media Arts      page 23 Palo Alto High School – Performing Arts Center          page 24 Jordan Middle School                page 25 J.L. Stanford Middle School              page 26 J.L. Stanford Middle School – Landscape and Site Improvements      page 27 Terman Middle School                page 28 Duveneck Elementary School – New Classroom Buildings and Modernization    page 29 Fairmeadow Elementary School – New Classroom Buildings and Modernization    page 30 Ohlone Elementary School               page 31 Property Acquisition – 525 San Antonio Rd             page 32 Jordan Middle School – Interim Classrooms            page 33 Gunn High School – Air Conditioning of Existing Buildings        page 34 J.L. Stanford Middle School – Interim Classrooms          page 35 Fairmeadow Elementary School – Portable Relocation        page 36 Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System  page 37 Palo Alto High School – Multi‐use Field            page 38 Gunn High School – Industrial Arts Renovation          page 39 Gunn High School – Aquatic Center             page 40 Middle School Pre‐Design                page 41 Technology                   page 42 

 

Inactive Capital Projects  

Garland Elementary School              page 43 High School Master Plan                page 44 

   

Page 3: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 3  

EXECUTIVE SUMMARY  CURRENT CAPITAL PROJECTS  

Gunn High School – Central Building Project Demolition of the Music building is complete, and work is in progress on the old Library building removal. Demolition and waste removal for Spangenberg Theater is also in progress. Site clearing and rough grading will begin in July.  Palo Alto High School – Science Building Addition  DLM continued work on construction documents, and plans to submit to DSA for review in July.  Palo Alto High School – Indoor PE and Athletic Facilities  Work on the interior and exterior of the building is substantially complete, and punch list corrections are in progress. The glass guardrail, outdoor basketball courts and the pool fence installation are in progress. Vance Brown will turn over the building to the District on July 17. District movers have begun moving furniture and equipment into the building from the 700 building this month.  Palo Alto High School – Building 500 Renovation (Library) The Board approved award of a contract to Sausal Corp on May 9, and preconstruction work has begun on submittals and procurement of materials. Demolition and construction will begin on August 1. Renovation of the 700 building is nearly complete, and will be completed by July 7th. Movers have finished vacating the 700 building, and have begun moving materials from the library to their interim spaces.  Addison Elementary School – (Donor Funded Project) Gelfand Partners  is working on development of construction documents  for  submittal  to DSA over  the summer. Value engineering was finalized during May, and the project is now back within budget after incorporating some cost savings measures. The board has approved applying for a grant for a Magical Bridge type playground, which the district will match if granted.  El Carmelo Elementary School – New MP Building The Board approved beginning work on conceptual design for planning a new MP building for El Carmelo in January. The scope of work incorporates a new MP building adjacent to the newer classroom wing along Ramona Ave. The old MP building will be  renovated  into another  flex  classroom and a  space  for  reading,  speech and educational specialists, while the old specialist’s rooms will be renovated back into a classroom. Staff will present the cost for the three MP projects to the Board in August for their input, since they are cumulatively over budget.  Escondido Elementary School – New MP Building The Board approved beginning work on conceptual design for planning a new MP building for Escondido in January. The recommended scheme includes a new MP building in the location of the existing building adjacent to the parking lot. The old MP building will be renovated into two classrooms, and the Kindergarten wing will be expanded with two new classrooms. Staff will present the cost for the three MP projects to the Board in August for their input, since they are cumulatively over budget.  Hays Elementary School – New MP Building The Board approved beginning work on conceptual design for planning a new MP building for Hays in January.  A new MP  building  is  being  proposed  in  the  location  of  the  three  Kindergarten  portable  classrooms.  The  old MP building will be renovated into two classrooms. The project will also demolish half of the old classroom wing near the parking  lot  to allow expansion of  the parking and drop off area. Staff will present the cost  for  the three MP projects to the Board in August for their input, since they are cumulatively over budget.     

Page 4: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 4  

 Hoover Elementary School Gelfand refined the final schematic design plans with the Hoover Advisory committee in April, and a cost estimate was done in mid‐May, which showed the project to be over budget. Gelfand has developed some recommended cost reduction items for the Advisory committee’s approval. The schematic design presentation to the board is on hold for now, pending budget discussions.  COMPLETED CAPITAL PROJECTS  

Gunn High School – New Classroom Building and World Languages Building The new Math and English Building was occupied by staff and students on August 15, 2013.  World Language Building classrooms were occupied in February, 2013.  Gunn High School – New Gymnasium The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.  The tennis courts were completed August 27, 2013.  Gunn High School – Existing Gymnasium Modernization The modernized Bow gym was occupied by the campus on November 4, 2013.  Gunn High School – E and K (L‐31 and MS) Buildings Renovation Students occupied E and K buildings on August 13, 2014, and building E was occupied on September 15, 2014.  Gunn High School –Traffic Signal Replacement (Phase I ‐ Parking and Drop‐Off Improvements) Columbia  Electric  installed  the  new  traffic  signal  pole  at  Arastradero  and  Miranda  Ave.  and  wiring  has  been completed. Concrete sidewalk work was also done in late July. Final landscape improvements were completed in August, and the first phase of this project is now complete.  

Palo Alto High School – Athletics Stadium Improvements 

The concessions building, track re‐surfacing, new ornamental fence, signage and entry lighting were completed for 

the 2013 football season. 

 

Palo Alto High School – Haymarket and Tower Building Improvements All Trusty Builders completed the installation of the new windows on August 9, 2013.  Palo Alto High School – New Math/Social Sciences Building and Media Arts Building Move  in and occupancy of both buildings occurred  in  July 2014.    Taisei has  completed  their work,  and contract closeout is complete, with DSA closeout in progress.  Palo Alto High School – Performing Arts Center (PAC) Students and staff occupied the new building in July, and DSA closeout was completed in September. Additional audio‐visual equipment, drapes and production lighting, and furniture installation was completed in September, in preparation for the Opening Night Gala on October 1.   Jordan Middle School Students occupied all new and modernized buildings in fall 2013.  J.L. Stanford Middle School Students occupied all new and modernized buildings in fall 2013.    

Page 5: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 5  

 J.L. Stanford Middle School – Landscape and Sitework Improvements   Scapes completed the project on schedule in the fall 2013.  Terman Middle School Students  occupied  the  new  instructional  spaces  and  modernized  buildings  in  fall  2013.    The  cafetorium modernization was completed in October 2013.  Duveneck Elementary School – New Classroom Buildings and Modernization All buildings were substantially complete and occupied on August 11, 2014.   Fairmeadow Elementary School – New Classroom Building and Modernization  Students occupied all new and modernized buildings in fall 2013.  525 San Antonio Road – Site Acquisition This site has been leased to Athena Academy.   Ohlone Elementary School – New Classroom Building and Modernization Students occupied the new building on January 3, 2012.   Jordan Middle School ‐ Interim Classrooms The portables were installed and moved into for fall 2011.  DSA closeout received November 19, 2012.  Gunn High School – Air Conditioning of Existing Buildings Best Contracting Services Inc. completed the installation of air conditioning units and roofing in the summer 2011.  J.L. Stanford Middle School ‐ Interim Classrooms Coulter Construction completed the work on the relocated portables in August 2011.    Fairmeadow Elementary School – Portable Relocation Relocation of the portable was complete and occupied on August 8, 2011.  Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems Installation  of  SmartBoards  and  Lightspeed  sound  assist  systems  were  completed  for  all  elementary  school classrooms and libraries in April 2011.    Palo Alto High School – Multi‐use Field The fields were available for play on February 1, 2011, and the project was completed on March 9, 2011.  Gunn High School – Industrial Arts Addition & Renovation This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.  Gunn High School – Aquatic Center  This facility was available for use in July 2009, and has been closed out with DSA.  Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman These projects for pre‐design work have been closed.  Technology Equipment orders have arrived and were deployed to the various campuses for use during the 2014/15 school year.    

Page 6: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 6  

 INACTIVE CAPITAL PROJECTS   Garland Elementary School Renovation The Board of Education has put new development for Garland on hold until a growth plan  is established for the elementary schools.    High School Master Plan The Board of Education (BOE) approved the master plans for both high schools, and these projects have been closed.  

Board Items in June 

June 6, 2017: 

Consent 3.I: Authorization to Award Contracts for Inspector of Record and Construction Management Services for the Palo Alto High School Library Renovation Project 

Consent 3.J: Resolution No. 2016-17.13: Resolution Requesting the Board of Supervisors of the County of Santa Clara to Establish the Tax Rate for Bonds of the Palo Alto Unified School District Expected to be Sold During the Fiscal Year 2017-18 

Consent 3.K: Authorization to Transfer $562,663 from the Paly Reserve to the Paly Athletic Center Project 

Consent 3.L: Movement of Budgeted Funds to the Change Order Allowance for the Paly Athletic Center 

Consent 3.M: Extension of the Following Site Leases 1. The Lease of the Garland Site to Stratford Schools 2. The Lease of the 525 San Antonio Site to Athena Academy 

Discussion  6.G:  Design  Update  and  Submittal  to  DSA  for  Addison  Elementary  School  and Magical  Bridge Playground  

Discussion 6.R:  Hoover Elementary School Schematic Design Approval (Pulled)  June 20, 2017: 

Consent 3.F: Approval of Strong Schools Bond Change Orders 

Action  5.D:  Design  Update  and  Submittal  to  DSA  for  Addison  Elementary  School  and  Magical  Bridge Playground  

Discussion/Action  5.H: Approval  of  Adjusted  Contract  Amounts  for  Inspection  Consultants  for  the  Peery Family Center at Palo Alto High School 

Discussion/Action 5.I: Authorization to Contract for 2017‐18 with fs3|Hodges for Bond Program Management Services 

  

   

Page 7: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

A B C C / A B - C C / B A - B

Measure A Fund

Gunn High School - High School Master Plan 172,390 166,328 147,706 86% 18,622 88.80% 6,062

Gunn High School 1 - Aquatic Center 4,862,530 4,862,530 4,862,530 100% 0 100.00% 0

Gunn High School 2 - I.A Building 5,065,128 5,065,128 5,065,128 100% 0 100.00% 0

Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100% 0 100.00% 0

Gunn High School 4 - New classroom Buildings 24,808,489 24,776,633 24,776,633 100% 0 100.00% 31,856

Gunn High School 5 - Parking & Drop Off improvements 3,939,998 2,085,755 1,855,723 47% 230,032 88.97% 1,854,243

Gunn High School 6- New/Auxiliary Gymnasium 12,450,948 12,440,998 12,440,998 100% 0 100.00% 9,950

Gunn High School 7- A/C 2,092,366 2,092,366 2,092,366 100% 0 100.00% 0

Gunn High School 8 - MS & L-31 Buildings 1,629,176 1,623,174 1,623,174 100% 0 100.00% 6,002

Gunn High School 9 - Central building 24,887,216 24,148,408 2,301,982 9% 21,846,426 9.53% 738,808

Gunn High School - Reserved 3,390,796 0 0 0% 0 0.00% 3,390,796

Palo Alto High Schools - High School Master Plan 172,999 167,759 161,616 93% 6,143 96.34% 5,240

Palo Alto High School 1 - Stadium Field 4,758,037 4,758,037 4,758,037 100% 0 100.00% 0

Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609,680 100% 0 100.00% 0

Palo Alto high School 3 - New classroom & Media Art Building 36,938,516 36,824,295 36,824,295 100% 0 100.00% 114,221

Palo Alto High School 4 - New Theater 27,481,465 27,231,463 26,972,021 98% 259,442 99.05% 250,002

Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,260,933 1,260,933 1,260,933 100% 0 100.00% 0

Palo Alto High School 6- Science Addition 5,532,205 929,613 648,234 12% 281,379 69.73% 4,602,592

Paly 7- Paly Athletic Center (Two Funds) 17,671,556 17,356,770 15,802,796 89% 1,553,974 91.05% 314,786

Paly 8-Library 14,161,140 12,559,756 847,319 6% 11,712,437 6.75% 1,601,384

Palo Alto High School - Reserved 1,121,584 0 0 0% 0 0.00% 1,121,584

Jordan Middle School -Program Management- MS Pre-Design 17,826 17,826 17,826 100% 0 100.00% 0

Jordan Middle Schools 1- Interim Classrooms 488,033 488,033 488,033 100% 0 100.00% 0

Jordan Middle School 2- Improvements 19,109,345 18,947,062 18,947,062 99% 0 100.00% 162,283

Jordan Middle School - Reserved 0 0 0 0% 0 0.00% 0

J.L.S Middle School - Program Management- MS Pre-Design 18,408 18,408 18,408 100% 0 100.00% 0

J.L.S Middle School 1 - Interim Classrooms 422,500 422,500 422,500 100% 0 100.00% 0

J.L.S Middle School 2- Improvements 15,670,128 15,535,784 15,535,784 99% 0 100.00% 134,344

J.L.S Middle School - Reserved 0 0 0 0% 0 0.00% 0

Terman Middle School - Program Management- MS Pre-Design 18,423 18,423 18,423 100% 0 100.00% 0

Terman Middle School 1- Improvements 13,051,488 13,003,128 13,003,128 100% 0 100.00% 48,360

Terman Middle School - Reserved 0 0 0 0% 0 0.00% 0

PAUSD Elementary Schools - Program Management- Elem. Growth Plan 308,000 93,480 87,290 28% 6,190 93.38% 214,520

Addison Elementary School 1-Phase I 21,267 21,267 21,267 100% 0 100.00% 0

El Carmelo Multi-Use Building 77,000 26,300 11,485 15% 14,815 43.67% 50,700

Escondido Multi-Use Building 73,000 22,100 6,860 9% 15,240 31.04% 50,900

Walter Hays Multi-Use Building 150,000 48,701 4,813 3% 43,888 9.88% 101,299

Hoover Elementary School 1-Phase I 23,207,165 1,697,101 386,560 2% 1,310,541 22.78% 21,510,064

Duveneck Elementary School 1-Phase I 9,230,464 9,229,952 9,229,952 100% 0 100.00% 512

Fairmeadow Elementary School 1- Phase I 7,590,515 7,590,496 7,584,495 100% 6,001 99.92% 19

Ohlone Elementary School 1- Phase I 10,528,254 10,528,254 10,528,254 100% 0 100.00% 0

Garland Elementary School 1- Phase I 280,113 280,113 280,113 100% 0 100.00% 0

Elementary Schools 1 - Elementary Classroom Improvements 1,879,695 1,879,695 1,879,695 100% 0 100.00% 0

Multi-Use Builindg - Reserved 36,832,808 0 0 0% 0 0.00% 36,832,808

PAUSD - Program Management 16,163,405 13,447,174 12,998,311 80% 448,863 96.66% 2,716,231

PAUSD - Technology 11,685,056 11,231,602 10,292,188 88% 939,414 91.64% 453,454

PAUSD - Technology -Reserved 2,222,312 0 0 0% 0 0.00% 2,222,312

PAUSD - Reserved 0 0 0 0% 0 0.00% 0

525 San Antonio -Property Acquisition 8,500,000 8,500,000 8,500,000 100% 0 100.00% 0

Transfer out to Planned Maintenance Fund* 17,758,557 6,330,628 6,330,628 36% 0 100.00% 11,427,929

Bond Issuance Cost 3,043,618 2,972,933 2,972,933 98% 0 100.00% 70,685

Measure A Fund Total 393,360,309 303,316,362 264,622,955 38,693,407 90,043,947

* Planned Maintenance Fund Total 6,330,629 6,166,411 5,611,631 89% 554,780 164,218

*$17,758,557 from Measure A fund to Planned Maintenance fund was approved. The budget for Planned maintenance fund will be increased about $2 M every year in 9 years.

Prepared by: Business Services Department based on QSS accounting System

Palo Alto Unified School District

Strong Schools Bond

5/31/2017

Percent of Expended

Contract Balance

Expenditures Budget BalanceCommittedBudgetSchool Name - Project NamePercent of

Budget Expended

Page 8: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 7  

Gunn High School 

Central Building Project 

A. PROJECT STATUS 

 Demolition  of  the Music  building  is  complete,  and work  is  in  progress  on  the  old  Library  building removal.  Demolition  and  waste  removal  for Spangenberg Theater is also in progress. Site clearing and rough grading will begin in July.          

B. BUDGET & SCHEDULE SUMMARY  

                    

  C. BOND PROJECT LIST REFERENCE: 5.5  D. PROJECT OVERVIEW: 

Demolition work is in progress. 

   

Funding State Funds  $0 Strong Schools Bond Funds  $ 24,887,216 Other Funding  $0 Total  $24,887,216  Budget Salaries and Benefits  $4,098 Supplies  $421 Contracts & Services  $3,811,130 Construction & Equipment  $21,010,351 Soft Costs Contingency  $61,216 Total  $24,887,216  Percent of Budget Expended  9.25%  Change Order Contingency 

Starting Contingency Balance  $1,966,300 

Remaining Contingency Balance  $1,919,572 

Percent of Changes  0.1% (Change Orders + Construction Change Directives. Original Contract) 

 

Current Phase:  Construction  

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  February 25, 2014 BOE Approval  March 11, 2014 

 Schematic Design (2)  June 3, 2014 BOE Approval  June 17, 2014 BOE Approval of Program Change  December 9, 2014  

Submit to DSA  February 15, 2016  

Authorize to Bid (2)  September 27, 2016 BOE Approval  October 18, 2016    

Approval by DSA  February 7, 2017  

Bid Opening  March 21, 2017  

Award of Contract (1)  March 28, 2017  

Notice to Proceed  May 15, 2017  

Substantial Completion  December 15, 2018*  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 9: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 8  

Palo Alto High School 

Science Building Addition 

 A. PROJECT STATUS  

DLM  continued  work  on  construction  documents,  and plans to submit to DSA for review in July.         

B. BUDGET & SCHEDULE SUMMARY  

                    

    

C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3  D. PROJECT OVERVIEW: 

DLM continued construction documents design efforts to submit into DSA.   

    

Funding State Funds  $0 Strong Schools Bond Funds  $5,532,204 Other Funding  $0 Total  $5,532,204  Budget Salaries and Benefits  $0 Supplies  $60,309 Contracts & Services  $842,825 Construction & Equipment  $4,628,294 Soft Costs Contingency  $776 Total  $5,532,204  Percent of Budget Expended  11.72%   

Current Phase: Construction Documents 

Schedule: Architect Contract (2)  March 12, 2013 BOE Approval  March 19, 2013  

Conceptual Design (2)  March 12, 2013 BOE Approval  March 19, 2013  

Schematic Design (2)  September 10, 2013 BOE Approval  October 8, 2013  

Submit to DSA  February 14, 2017 BOE Approval  February 28, 2017    

Authorize to Bid (2)  March 13, 2018* BOE Approval  March 27, 2018*  

Approval by DSA  March 15, 2018*  

Bid Opening  May 1, 2018*  

Award of Contract (1)   May 8, 2018*  

Notice to Proceed  June 1, 2018*  Substantial Completion  August 1, 2019*  Planned Occupancy  October 1, 2019*  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 10: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 9  

Palo Alto High School 

Indoor PE and Athletic Facilities  

 A. PROJECT STATUS  

 Work on the  interior and exterior of the building  is substantially  complete,  and  punch  list  corrections are  in  progress.  The  glass  guardrail,  outdoor basketball courts and the pool fence installation are in progress. Vance Brown will turn over the building to the District on July 17. District movers have begun moving  furniture  and  equipment  into  the  building from the 700 building this month.  

    B. BUDGET & SCHEDULE SUMMARY 

                     

   

C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3  D. PROJECT OVERVIEW: 

Project is substantially complete, and move‐in is in progress.   

Funding State Funds  $0 Strong Schools Bond Funds  $17,671,555 Other Funding (Deseret Trust Co.)  $23,443,720 Total  $41,671,555  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $2,991,039 Construction & Equipment  $38,500,516 Soft Costs Contingency  $180,000 Total  $41,671,555  Percent of Budget Expended *  87.98% (Above % of budget expended is against bond funds of $17,671,555)  Change Order Contingency 

Starting Contingency Balance  $1,822,167 

Remaining Contingency Balance  $214,261 

Percent of Changes  4.41% (Change Orders + Construction Change Directives. Original Contract) 

 

Current Phase:   Construction  

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  March 12, 2013 BOE Approval  March 19, 2013  

Schematic Design (2)  September 10, 2013 BOE Approval  October 8, 2013  

Submit to DSA  December 4, 2013 Re‐Submit to DSA  January 27, 2014    

Approval by DSA  September 22, 2014  

Lease Leaseback Agreement (1)  May 26, 2015 Award of LLB Contract (1)  June 23, 2015  

Notice to Proceed  August 1, 2015  

Substantial Completion  May 7, 2017  

Planned Occupancy  July 21, 2017*  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 11: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 10  

Palo Alto High School  

Building 500 Renovation (Library) 

 A. PROJECT STATUS  

 The Board approved award of a contract to Sausal Corp  on  May  9,  and  preconstruction  work  has begun  on  submittals  and  procurement  of materials. Demolition and construction will begin on  August  1.  Renovation  of  the  700  building  is nearly complete, and will be completed by July 7th. Movers  have  finished  vacating  the  700  building, and have begun moving materials from the library to their interim spaces.     

  B. BUDGET & SCHEDULE SUMMARY 

                     

  C. BOND PROJECT LIST REFERENCE: 4.8  D. PROJECT OVERVIEW: 

Sausal has begun preconstruction activities, and will mobilize on July 31. 

   

Funding State Funds  $0 Strong Schools Bond Funds  $14,161,140 Other Funding  $0 Total  $14,161,140  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $2,283,420 Construction & Equipment  $11,728,800 Soft Costs Contingency  $148,920 Total  $14,161,140 Percent of Budget Expended  5.98%   

Current Phase:   Construction  

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  September 23, 2014 BOE Approval  October 14, 2014  

Schematic Design (2)  March 24, 2015 BOE Approval  April 21, 2015  

Submit to DSA  December 15, 2015    

Approval by DSA  March 14, 2017*  Authorize to Bid (1)  February 28, 2017  

Award of Contract (1)  May 23, 2017  

Construction Start  August 1, 2017  

Substantial Completion  November 15, 2018*  

Planned Occupancy  January 2019*  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 12: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 11  

 Addison Elementary School (Donor‐Funded Project) New Library, Administration and Multipurpose Building 

A. PROJECT STATUS 

Gelfand  Partners  is  working  on  development  of construction  documents  for  submittal  to  DSA  over the summer. Value engineering was finalized during May, and the project is now back within budget after incorporating  some  cost  savings  measures.  The board has approved applying for a grant for a Magical Bridge type playground, which the district will match if granted. 

   

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10  D. PROJECT OVERVIEW: 

Project is currently in Construction Documents phase, with DSA submittal planned for July 2017.     

Funding State Funds  $0 Strong Schools Bond Funds  $0 Other Funding – Donation  $1,330,000 Total  $1,330,000  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $1,330,000 Construction & Equipment  $0 Soft Costs Contingency  $0 Total  $1,330,000  Percent of Budget Expended  22.4% 

Current Phase:   Construction Documents  

Schedule: Conceptual Design (2)  February 23, 2016   March 8, 2016  

Schematic Design (2)  September 13, 2016 BOE Approval  September 27, 2016  

Submit to DSA  July 30, 2017*    

Approval by DSA  February 15, 2018*  

Authorize to Bid (2)  February 1, 2018* BOE Approval  February 15, 2018*  

Bid Opening  April 15, 2018*  

Award of Contract (1)  May 1, 2018*  

Notice to Proceed  May 15, 2018*  

Substantial Completion  September 15, 2019*  

Planned Occupancy  December 20, 2019*  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 13: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 12  

El Carmelo Elementary School 

New Multipurpose Building 

A. PROJECT STATUS 

The Board approved beginning work on conceptual design for planning a new MP building for El Carmelo in January. The scope of work incorporates a new MP building adjacent to the newer classroom wing along Ramona Ave. The old MP building will be renovated into another flex classroom and a space for reading, speech  and  educational  specialists,  while  the  old specialist’s  rooms  will  be  renovated  back  into  a classroom. Staff will present the cost  for  the  three MP projects to the Board in August for their  input, since they are cumulatively over budget.   

 B. BUDGET & SCHEDULE SUMMARY 

                      C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10 

 D. PROJECT OVERVIEW: 

Conceptual Design planned for board approval in September 2017.   

    

Funding State Funds  $0 Strong Schools Bond Funds  $0 Other Funding  $0 Total  $0  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $0 Construction & Equipment  $0 Soft Costs Contingency  $0 Total  $0  Percent of Budget Expended  0.00% 

Current Phase:   Conceptual Design  

Schedule: Conceptual Design (2)  August 22, 2017 BOE Approval  September 12, 2017  

Schematic Design (2)  TBD BOE Approval  TBD   

Submit to DSA  TBD    

Approval by DSA  TBD  

Authorize to Bid (2)  TBD  

Bid Opening  TBD  

Award of Contract (1)  TBD  

Notice to Proceed  TBD  

Substantial Completion  TBD  

Planned Occupancy  TBD  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 14: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 13  

 Escondido Elementary School New Multipurpose Building 

A. PROJECT STATUS 

The Board approved beginning work on conceptual design for planning a new MP building for Escondido in  January.  The  recommended  scheme  includes  a new  MP  building  in  the  location  of  the  existing building  adjacent  to  the  parking  lot.  The  old  MP building will be renovated into two classrooms, and the  Kindergarten  wing  will  be  expanded  with  two new  classrooms.  Staff will  present  the  cost  for  the three MP projects  to  the Board  in August  for  their input, since they are cumulatively over budget. 

  

 B. BUDGET & SCHEDULE SUMMARY 

                      C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10 

 D. PROJECT OVERVIEW: 

Conceptual Design planned for board approval in September 2017.   

    

Funding State Funds  $0 Strong Schools Bond Funds  $0 Other Funding  $0 Total  $0  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $0 Construction & Equipment  $0 Soft Costs Contingency  $0 Total  $0  Percent of Budget Expended  0.00%  

Current Phase: Conceptual Design  

Schedule: Conceptual Design (2)  August 22, 2017 BOE Approval  September 12, 2017  

Schematic Design (2)  TBD BOE Approval  TBD   

Submit to DSA  TBD    

Approval by DSA  TBD  

Authorize to Bid (2)  TBD  

Bid Opening  TBD  

Award of Contract (1)  TBD  

Notice to Proceed  TBD  

Substantial Completion  TBD  

Planned Occupancy  TBD  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 15: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 14  

 Hays Elementary School New Multipurpose Building 

A. PROJECT STATUS 

The  Board  approved  beginning  work  on  conceptual design  for  planning  a  new  MP  building  for  Hays  in January.  A new MP building is being proposed in the location  of  the  three  Kindergarten  portable classrooms. The old MP building will be renovated into two classrooms. The project will also demolish half of the old classroom wing near the parking  lot to allow expansion of the parking and drop off area. Staff will present  the  cost  for  the  three  MP  projects  to  the Board  in  August  for  their  input,  since  they  are cumulatively over budget.     

 B. BUDGET & SCHEDULE SUMMARY 

                      C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10 

 D. PROJECT OVERVIEW: 

Conceptual Design planned for board approval in September 2017.   

  

Funding State Funds  $0 Strong Schools Bond Funds  $0 Other Funding  $0 Total  $0  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $0 Construction & Equipment  $0 Soft Costs Contingency  $0 Total  $0  Percent of Budget Expended  0.00%   

Current Phase: Conceptual Design  

Schedule: Conceptual Design (2)  August 22, 2017 BOE Approval  September 12, 2017  

Schematic Design (2)  TBD BOE Approval  TBD   

Submit to DSA  TBD    

Approval by DSA  TBD  

Authorize to Bid (2)  TBD  

Bid Opening  TBD  

Award of Contract (1)  TBD  

Notice to Proceed  TBD  

Substantial Completion  TBD  

Planned Occupancy  TBD  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 16: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 15  

  Hoover Elementary School New Library, Administration and Multipurpose Building 

E. PROJECT STATUS 

 Gelfand refined the final schematic design plans with the Hoover Advisory committee  in April, and a cost estimate  was  done  in mid‐May,  which  showed  the project  to  be  over  budget.  Gelfand  has  developed some  recommended  cost  reduction  items  for  the Advisory committee’s approval. The schematic design presentation to the board is on hold for now, pending budget discussions.   

  

 F. BUDGET & SCHEDULE SUMMARY 

                      

G. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10  

H. PROJECT OVERVIEW: 

Schematic design will go to the Board for approval in September 2017.   

Funding State Funds  $0 Strong Schools Bond Funds  $23,207,165 Other Funding  $0 Total  $23,207,165  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $4,848,277 Construction & Equipment  $18,358,888 Soft Costs Contingency  $ Total  $23,207,165  Percent of Budget Expended  0.84% 

Current Phase:   Schematic Design  

Schedule: Conceptual Design (2)  December 13, 2016 BOE Approval  January 10, 2017  

Schematic Design (2)  August 22, 2017* BOE Approval  September 12, 2017*  

Submit to DSA  January 2018*    

Approval by DSA  September 2018*  

Authorize to Bid (2)  September 2018*  

Bid Opening  November 2018*  

Award of Contract (1)  December 2018*  

Notice to Proceed  January 2019*  

Substantial Completion  March 2020*  

Planned Occupancy  April 2020*  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 17: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 16  

Gunn High School  

New Classroom Buildings A & B   A. PROJECT STATUS 

The  new  Math  and  English  Building  was  occupied  by  staff  and students on August 15, 2013.  World Language Building classrooms have been in use since February, 2013.           

 B. BUDGET & SCHEDULE SUMMARY 

                     

  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4  D. PROJECT OVERVIEW: 

The World Languages building move‐in occurred on February 8, 2013, and was occupied with staff and students on February 11, 2013.  The Math & English building move‐in occurred on July 15, 2013, and was occupied with staff and students on August 15, 2013.  The project was completed within budget.  

   

Funding State Funds  $0 Strong Schools Bond Funds  $24,808,488 Other Funding  $0 Total  $24,808,488  Budget Salaries and Benefits  $24,948 Supplies  $308,194 Contracts & Services  $3,789,909 Construction & Equipment  $20,685,160 Soft Costs Contingency  $277 Total  $24,808,488  Percent of Budget Expended  99.9%  Change Order Contingency 

Starting Contingency Balance  $ 1,763,200 

Remaining Contingency Balance  $ 99,232 

Percent of Changes  9.3% (Change Orders + Construction Change Directives vs. Original Contract) 

 Project Savings Realized = $226,713  

Current Phase:  Occupancy – August 15, 2013  

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  September 8, 2009 BOE Approval  September 22, 2009  

Schematic Design (2)  January 12, 2010 BOE Approval  January 26, 2010  

Submit to DSA  August 4, 2010    Authorize to Bid (2)  March 8, 2011 BOE Approval  March 22, 2011  

Approval by DSA  May 27, 2011  

Bid Opening  July 13, 2011  

Award of Contract (1)  July 22, 2011  

Notice to Proceed  August 24, 2011  

Substantial Completion  July 15, 2013  

Planned Occupancy  August 15, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 18: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 17  

Gunn High School  

New Gymnasium  

A. PROJECT STATUS 

The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.  The tennis courts surfacing and striping was installed and completed August 27, 2013. 

  

    

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13  D. PROJECT OVERVIEW: 

The new gym was occupied on June 7, 2013.    

Funding State Funds  $0 Strong Schools Bond Funds  $ 12,450,946 Other Funding  $0 Total  $12,450,946  Budget Salaries and Benefits  $0 Supplies  $19,706 Contracts & Services  $2,461,402 Construction & Equipment  $9,936,883 Soft Costs Contingency  $32,955 Total  $12,450,946  Percent of Budget Expended  99.9%  Change Order Contingency 

Starting Contingency Balance  $834,700 

Remaining Contingency Balance  $7,909 

Percent of Changes  9.9% (Change Orders + Construction Change Directives vs. Original Contract) 

 Project Savings Realized = $463,854 

Current Phase:    Occupancy – June 7, 2013  

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  September 8, 2009 BOE Approval  September 22, 2009  

Schematic Design (2)  January 12, 2010 BOE Approval  January 26, 2010  

Submit to DSA  August 4, 2010  

Authorize to Bid (2)  March 8, 2011 BOE Approval  March 22, 2011  

Approval by DSA  May 27, 2011  

Bid Opening  July 13, 2011  

Award of Contract (1)  July 20, 2011  

Notice to Proceed  August 1, 2011  

Substantial Completion  May 1, 2013  

Planned Occupancy  June 7, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 19: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 18  

Gunn High School  

Existing Gymnasium Modernization 

A. PROJECT STATUS 

The  modernized  Bow  gym  was  occupied  by  the  campus  on November 4, 2013.     

    

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13  D. PROJECT OVERVIEW: 

The project was completed on‐schedule and within budget. Occupancy by the school occurred on 

November 12, 2013. 

  

   

Funding and Budget This project is funded by the New Gymnasium project budget.  See that project budget for status.  Change Order Contingency 

Starting Contingency Balance  $99,800 

Remaining Contingency Balance  $51,455 

Percent of Changes  4.8% (Change Orders + Construction Change Directives vs. Original Contract) 

 

Current Phase:  Occupancy – November 12, 2013  

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  September 8, 2009 BOE Approval  September 22, 2009  

Schematic Design (2)  January 12, 2010 BOE Approval  January 26, 2010  

Submit to DSA  August 4, 2010  

Authorize to Bid (2)  February 12, 2013 BOE Approval  February 26, 2013  

Approval by DSA  January 23, 2013  

Bid Opening  April 2, 2013  

Award of Contract (1)  April 9, 2013  

Notice to Proceed  May 31, 2013  

Substantial Completion  October 28, 2013  

Planned Occupancy  November 12, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 20: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 19  

Gunn High School  

E and K (MS and L‐31) Buildings Renovation  

A. PROJECT STATUS 

Students  occupied  E  and  K  buildings  on August  13, 2014, and the flex room in building E was occupied on September 15, 2014.     

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13  D. PROJECT OVERVIEW: 

Construction was completed on schedule and within budget.  Occupancy took place on August 13, 2014.  

 

 

 

   

Funding State Funds  $0 Strong Schools Bond Funds  $1,629,173 Other Funding  $0 Total  $1,629,173  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $428,000 Construction & Equipment  $1,198,886 Soft Costs Contingency  $2,287 Total  $1,629,173  Percent of Budget Expended  98.2%  Change Order Contingency 

Starting Contingency Balance  $122,800 

Remaining Contingency Balance  $114,946 

Percent of Changes  1.0% (Change Orders + Construction Change Directives vs. Original Contract) 

 Project Savings Realized = $491,666 

Current Phase:       Occupancy – August 15, 2014  

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  September 8, 2009 BOE Approval  September 22, 2009  

Schematic Design (2)  June 11, 2013 BOE Approval  June 18, 2013  

Submit to DSA  November 25, 2013  

Authorize to Bid (2)  March 25, 2014 BOE Approval  April 22, 2014  

Approval by DSA  March 27, 2014  

Bid Opening  April 29, 2014  

Award of Contract (1)  May 20, 2014  

Notice to Proceed  May 27, 2014  

Substantial Completion  August 11, 2014  

Planned Occupancy  August 15, 2014  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 21: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 20  

Gunn High School 

Traffic Signal Replacement 

Phase I – Parking and Drop‐off Improvements  

A. PROJECT STATUS 

Columbia Electric  installed the new traffic signal pole at Arastradero and Miranda Ave. and wiring has been completed. Concrete sidewalk work was also  done  in  late  July.  Final  landscape improvements  were  completed  in  August,  and the first phase of this project is now complete.  

   

   B. BUDGET & SCHEDULE SUMMARY 

                     

  

C. BOND PROJECT LIST REFERENCE: 5.5  D. PROJECT OVERVIEW: 

The Miranda Ave. parking and drop‐off was phase one of a multi‐phase project for various parking and drop off improvements. Future phases will be coordinated with the Central Building project, which will develop a new drop off area and entry plaza in the main parking lot. 

   

Funding State Funds  $0 Strong Schools Bond Funds  $3,940,000 Other Funding  $0 Total  $3,940,000  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $919,858 Construction & Equipment  $2,919,840 Soft Costs Contingency  $100,302 Total  $3,940,000  Percent of Budget Expended  47%  Change Order Contingency 

Starting Contingency Balance  $121,380 

Remaining Contingency Balance  $77,492 

Percent of Changes  3.6% (Change Orders + Construction Change Directives vs. Original Contract) 

 

Current Phase:  Closeout  

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  June 19, 2012 BOE Approval  June 26, 2012 

 Schematic Design (2)  December 18, 2012 BOE Approval  January 15, 2013  

Authorize to Bid (2)  June 11, 2013 BOE Approval  June18, 2013  

Submit to DSA  July 17, 2013    

Approval by DSA  October 2, 2013  

Bid Opening  November 12, 2013  

Award of Contract (1)  November 19, 2013  

Notice to Proceed  December 4, 2013  

Substantial Completion  August 15, 2014   

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 22: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 21  

Palo Alto High School  

Athletic Stadium Improvements  

A. PROJECT STATUS 

The  concessions  building,  track  re‐surfacing,  new  ornamental fence, signage and entry lighting were completed for the Fall 2013 football season.         

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 4.13  D. PROJECT OVERVIEW: 

The ornamental fence was completed on schedule in August 2013.  The concessions building was occupied September 10, 2012.  The bleacher replacement work was completed on schedule in June 2013. 

 

 

   

Funding State Funds  $0 Strong Schools Bond Funds  $4,758,036 Other Funding  $0 Total  $4,758,036  Budget Salaries and Benefits  $882 Supplies  $2,746 Contracts & Services  $818,716 Construction & Equipment  $3,935,692 Soft Costs Contingency  $0 Total  $4,758,036  Percent of Budget Expended  100%  Change Order Contingency 

Starting Contingency Balance  $310,200 

Remaining Contingency Balance  $364,338 

Percent of Changes  ‐1.7% (Change Orders + Construction Change Directives vs. Original Contract)  

Project Savings Realized = $331,964  

Current Phase:  Occupancy – August 1, 2013  

Schedule: Architect Contract (2)  January 26, 2010 BOE Approval  February 9, 2010  

Conceptual Design (2)  June 1, 2010 BOE Approval  June 22, 2010  

Schematic Design (2)  February 22, 2011 BOE Approval  March 8, 2011  

Submit to DSA  April 4, 2011  

Authorize to Bid (2)  June 28, 2011 BOE Approval  July 19, 2011  

Approval by DSA  July 26, 2011    

Bid Opening  December 1, 2011  

Award of Contract (1)  December 13, 2011  

Notice to Proceed  January 4, 2012  

Substantial Completion ‐ Concession   August 31, 2012 Planned Occupancy ‐ Concessions  September 10, 2012 Bleachers  March 31, 2013 Fence Completion  August 1, 2013 * Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings

Page 23: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 22  

Palo Alto High School 

Haymarket and Tower Building Improvements  

 A. PROJECT STATUS  

All  Trusty  Builders  completed  the  installation  of  the  new windows  on  August  9,  2013,  on  schedule  and  within budget. 

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3  D. PROJECT OVERVIEW: 

The project completed on schedule and within budget.    

Funding State Funds  $0 Strong Schools Bond Funds  $1,260,933 Other Funding  $0 Total  $1,260,933  Budget Salaries and Benefits  $0 Supplies  $62,844 Contracts & Services  $179,000 Construction & Equipment  $1,019,092 Soft Costs Contingency  $0 Total  $1,260,933  Percent of Budget Expended  100%  Change Order Contingency 

Starting Contingency Balance  $39,200 

Remaining Contingency Balance  $33,930 

Percent of Changes  1.3% (Change Orders + Construction Change Directives vs. Original Contract) 

 Project Savings Realized = $239,067 

Current Phase:  Occupancy – August 9, 2013  

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  May 25, 2012    

Authorize to Bid (2)  April 24, 2012 BOE Approval  May 6, 2012  

Approval by DSA  August 24, 2012  

Bid Opening  January 17, 2013  

Award of Contract (1)  January 29, 2013  

Notice to Proceed  February 21, 2013  

Substantial Completion  August 9, 2013   

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 24: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 23  

Palo Alto High School  

Classroom Building and Media Arts   A. PROJECT STATUS  

Move in and occupancy of both buildings occurred in July 2014.    Taisei  has  completed  their  work,  and  contract closeout is complete. 

   

          

 B. BUDGET & SCHEDULE SUMMARY 

                     

  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3  D. PROJECT OVERVIEW: 

Furniture installation and occupancy of the Media Arts and Math/Social Sciences buildings completed.  

   

Funding State Funds  $0 Strong Schools Bond Funds  $36,938,515 Other Funding  $0 Total  $36,938,515  Budget Salaries and Benefits  $18,448 Supplies  $1,325,333 Contracts & Services  $6,261,915 Construction & Equipment  $29,236,995 Soft Costs Contingency  $95,826 Total  $38,415,001  Percent of Budget Expended  99.6%  Change Order Contingency 

Starting Contingency Balance  $2,515,000 

Remaining Contingency Balance  $34,288 

Percent of Changes  * 9.9% (Change Orders + Construction Change Directives vs. Original Contract) * Does not include $570,000 settlement agreement with Taisei for release of any and all claims 

 Project Savings Realized = $1,476,486 

Current Phase:  Occupancy – August 1, 2014   

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  September 8, 2009 BOE Approval  September 22, 2009  

Schematic Design (2)  January 12, 2010 BOE Approval  January 26, 2010  

Submit to DSA  August 4, 2010    

Authorize to Bid (2)  March 8, 2011 BOE Approval  March 22, 2011  

Approval by DSA  April 28, 2011  

Bid Opening  June 30, 2011  

Award of Contract (1)  July 12, 2011  

Notice to Proceed  August 4, 2011  

Substantial Completion  April 15, 2014  

Planned Occupancy  August 1, 2014  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 25: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 24  

Palo Alto High School Performing Arts Center (PAC) 

A. PROJECT STATUS 

Students and staff occupied the new building in July, and DSA closeout was completed in September. Additional audio‐visual equipment, drapes and production lighting, and furniture installation was completed in September, in preparation for the Opening Night Gala on October 1.      

 

 

 

B. BUDGET & SCHEDULE SUMMARY  

                    

  

 

C. BOND PROJECT LIST REFERENCE: 4.11  

D. PROJECT OVERVIEW: 

Occupancy occurred over the summer break.  

   

Funding State Funds  $0 Strong Schools Bond Funds  $29,370,049 Other Funding  $0 Total  $29,370,049  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $4,377,871 Construction & Equipment  $24,845,000 Soft Costs Contingency  $147,178 Total  $29,370,049  Percent of Budget Expended  90.19%  Change Order Contingency 

Starting Contingency Balance  $2,184,400 

Remaining Contingency Balance  $1,065,582 Percent of Changes  5.12% 

(Change Orders + Construction Change Directives vs. Original Contract) 

 

Current Phase:  Occupancy – July 1, 2016  

Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  

Conceptual Design (2)  June 1, 2010 BOE Approval  June 22, 2010  

Schematic Design (3)  June 14, 2011 BOE Approval  December 13, 2011 BOE Approval  January 17, 2012  

Submit to DSA  March 28, 2013    

Approval by DSA  January 16, 2014  

Authorize to Bid (2)  January 14, 2014 BOE Approval  January 28, 2014  

Bid Opening  May 13, 2014  

Award of Contract (1)  June 3, 2014  

Notice to Proceed  June 23, 2014  

Substantial Completion  May 5, 2016  

Planned Occupancy  July 1, 2016  

 ( ) Denotes number of Board of Education Readings 

Page 26: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 25  

Jordan Middle School  

Classroom Wing, Cafetorium and  Campus Improvements  A. PROJECT STATUS 

Students occupied all new and modernized buildings  for the start of school in fall 2013. 

             

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5  D. PROJECT OVERVIEW: 

The project was completed on schedule and within budget.    

Funding State Funds  $0 Strong Schools Bond Funds  $19,109,345 Other Funding  $0 Total  $19,109,345   Budget Salaries and Benefits  $6,111 Supplies  $86,265 Contracts & Services  $3,723,370 Construction & Equipment  $15,224,812 Soft Costs Contingency  $68,787 Total  $19,109,345  Percent of Budget Expended  99.2%  Change Order Contingency 

Starting Contingency Balance  $1,398,700 

Remaining Contingency Balance  $202,769 

Percent of Changes  8.6% (Change Orders + Construction Change Directives vs. Original Contract) 

 Project Savings Realized = $782,219 

Current Phase:  Close‐out / Occupancy – August 15, 2013  

Schedule: Architect Contract (2)  October 28, 2008 BOE Approval  October 30, 2008  

Conceptual Design (2)  June 23, 2009 BOE Approval  September 8, 2009  

Schematic Design (2)  March 23, 2010 BOE Approval  April 27, 2010  

Submit to DSA  December 21, 2010    

Authorize to Bid (2)  June 28, 2011 BOE Approval  July 19, 2011  

Approval by DSA  October 5, 2011  

Bid Opening  December 8, 2011  

Award of Contract (1)  December 13, 2011  

Notice to Proceed  December 27, 2011  

Substantial Completion  August 1, 2013  

Planned Occupancy  August 15, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 27: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 26  

J.L. Stanford Middle School Classroom Wing and Campus Improvements  A. PROJECT STATUS  

Students occupied all new and modernized buildings  for the start of school in fall 2013. 

           

 B. BUDGET & SCHEDULE SUMMARY 

                     

   

C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5  D. PROJECT OVERVIEW: 

The project completed on schedule and within budget.      

Funding State Funds  $0 Strong Schools Bond Funds  $15,670,127 Other Funding  $0 Total  $15,670,127  Budget Salaries and Benefits  $8,879 Supplies  $144,790 Contracts & Services  $3,545,843 Construction & Equipment  $11,970,665 Soft Costs Contingency  $0 Total  $15,670,127  Percent of Budget Expended  99.1%  Change Order Contingency 

Starting Contingency Balance  $1,057,800 

Remaining Contingency Balance  $911,677 

Percent of Changes  1.4% (Change Orders + Construction Change Directives vs. Original Contract) 

 Project Savings Realized = $1,514,522 

Current Phase:  Close‐out / Occupancy – August 15, 2013  

Schedule: Architect Contract (2)  October 28, 2008 BOE Approval  October 30, 2008  

Conceptual Design (2)  June 23, 2009 BOE Approval  September 8, 2009  

Schematic Design (3)  June 1, 2010 BOE Approval  June 22, 2010 BOE Approval (Sitework)  September 28, 2010  

Submit to DSA  May 6, 2011    

Authorize to Bid (2)  November 29, 2011 BOE Approval  December 13, 2011  

Approval by DSA  January 24, 2012  

Bid Opening  May 3, 2012  

Award of Contract (1)  May 8, 2012  

Notice to Proceed  May 30, 2012  

Substantial Completion  August 7, 2013  

Planned Occupancy  August 15, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 28: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 27  

J.L. Stanford Middle School  Landscape and Site Improvements 

 A. PROJECT STATUS  

Scapes completed the project on schedule in the fall 2013.  

           

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5  D. PROJECT OVERVIEW: 

The project completed on schedule and within budget.     

Funding and Budget This project is funded by the J.L. Stanford Middle School project budget.  See that project budget for status.  Percent of Budget Expended  100%  Change Order Contingency 

Starting Contingency Balance  $1,057,800 

Remaining Contingency Balance  $902,445 

Percent of Changes  2.8% (Change Orders + Construction Change Directives vs. Original Contract) 

 

Current Phase:  Close‐out / Occupancy – August 16, 2013 

Schedule: Architect Contract (2)  October 28, 2008 BOE Approval  October 30, 2008  

Conceptual Design (2)  June 23, 2009 BOE Approval  September 8, 2009  

Schematic Design (3)  June 1, 2010 BOE Approval  June 22, 2010 BOE Approval (Sitework)  September 28, 2010  

Submit to DSA  May 6, 2011    

Authorize to Bid (2)  November 29, 2011 BOE Approval  December 13, 2011  

Approval by DSA  January 24, 2012  

Bid Opening  May 3, 2013  

Award of Contract (1)  May 8, 2013  

Notice to Proceed  May 23, 2013  

Substantial Completion  August 16, 2013  

Completion  August 16, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 29: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 28  

Terman Middle School  Library Addition and Campus Improvements 

A. PROJECT STATUS 

Students  occupied  the  new  instructional  spaces  and modernized buildings for the start of school in fall 2013.  The cafetorium modernization was completed in October 2013.  

  B. BUDGET & SCHEDULE SUMMARY 

                     

   

C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12  D. PROJECT OVERVIEW: 

The project completed on schedule in August 2013, except for the Cafetorium, which was completed in November 2013.  The project has been completed within budget. 

   

Funding State Funds  $0 Strong Schools Bond Funds  $13,051,487 Other Funding  $0 Total  $13,051,487   Budget Salaries and Benefits  $4,153 Supplies  $75,747 Contracts & Services  $2,720,590 Construction & Equipment  $10,246,249 Soft Costs Contingency  $4,748 Total  $13,051,487  Percent of Budget Expended  99.6%  Change Order Contingency 

Starting Contingency Balance  $929,900 

Remaining Contingency Balance  $12,909 

Percent of Changes  9.4% (Change Orders + Construction Change Directives vs. Original Contract) 

 Project Savings Realized = $261,484 

Current Phase:  Close‐out / Occupancy – November 15, 2013 

Schedule: Architect Contract (2)  October 28, 2008 BOE Approval  October 30, 2008  

Conceptual Design (2)  June 23, 2009 BOE Approval  September 8, 2009  

Schematic Design (2)  May 11, 2010 BOE Approval  May 25, 2010  

Submit to DSA  December 21, 2010    

Authorize to Bid (2)  June 28, 2011 BOE Approval  July 19, 2011  

Approval by DSA  September 1, 2011  

Bid Opening  December 6, 2011  

Award of Contract (1)  December 13, 2011  

Notice to Proceed  December 27, 2011  

Substantial Completion  October 31, 2013  

Planned Occupancy  November 15, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 30: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 29  

Duveneck Elementary School  New Classroom Buildings and Modernization 

A. PROJECT STATUS  

The  fence  around  the  sod  for  the  field  area  to  establish growth was removed on September 19, 2014.  All buildings were  substantially  complete  and occupied on August  11, 2014. 

          

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10  D. PROJECT OVERVIEW: 

The project has been completed within budget, and was occupied on August 5, 2014.      

Funding State Funds  $0 Strong Schools Bond Funds  $9,277,534 Other Funding  $0 Total  $9,277,534  Budget Salaries and Benefits  $20,313 Supplies  $0 Contracts & Services  $2,098,650 Construction & Equipment  $7,154,178 Soft Costs Contingency  $4,393 Total  $9,277,534  Percent of Budget Expended  99.5%  Change Order Contingency 

Starting Contingency Balance  $703 ,772 

Remaining Contingency Balance  $304,029 

Percent of Changes  5.7% (Change Orders + Construction Change Directives vs. Original Contract) 

 Realized Project Savings = $500,824 

Current Phase:    Close‐out/Occupancy – August 5, 2014  

Schedule: Architect Contract (2)  April 27, 2010 BOE Approval  May 11, 2010  

Conceptual Design (2)  December 14, 2010 BOE Approval  January 11, 2011  

Schematic Design (2)  June 14, 2011 BOE Approval  June 28, 2011  

Submit to DSA  February 27, 2012    

Approval by DSA  December 10, 2012  

Authorize to Bid (2)  December 18 2012 BOE Approval  January 15, 2013  

Bid Opening  February 28, 2013  

Award of Contract (1)  March 12, 2013  

Notice to Proceed  March 25, 2013  

Substantial Completion  July 31, 2014  

Planned Occupancy  August 5, 2014  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 31: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 30  

Fairmeadow Elementary School  New Classroom Building and Modernization   A. PROJECT STATUS 

Students occupied all new and modernized buildings for the start of school in fall 2013. 

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10  D. PROJECT OVERVIEW: 

The project completed on schedule and within budget.    

Funding State Funds  $0 Strong Schools Bond Funds  $7,656,720 Other Funding  $0 Total  $7,656,720  Budget Salaries and Benefits  $32,377 Supplies  $98,962 Contracts & Services  $1,992,932 Construction & Equipment  $5,531,329 Soft Costs Contingency  $1,120 Total  $7,656,720  Percent of Budget Expended  99.1%  Change Order Contingency 

Starting Contingency Balance  $642 ,300 

Remaining Contingency Balance  $186,122 

Percent of Changes  7.1% (Change Orders + Construction Change Directives vs. Original Contract) 

 Realized Project Savings = $139,830 

Current Phase: Close‐out / Occupancy – August 15, 2013  

Schedule: Architect Contract (2)  October 13, 2009 BOE Approval  October 27, 2009  

Conceptual Design (2)  March 23, 2010 BOE Approval  April 6, 2010  

Schematic Design (2)  September 14, 2010 BOE Approval  September 28, 2010  

Submit to DSA  April 18, 2011    

Authorize to Bid (2)  October 11, 2011 BOE Approval  October 25, 2011  

Approval by DSA  November 14, 2011  

Bid Opening  December 5, 2011  

Award of Contract (1)  December 13, 2011  

Notice to Proceed  January 3, 2012  

Substantial Completion  August 5, 2013  

Planned Occupancy  August 15, 2013  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 32: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 31  

Ohlone Elementary School 

New Classroom Building and Modernization  A. PROJECT STATUS  

Move‐in to the new building and other existing classrooms occurred  in  December  2011.    Students  occupied  the  new building on January 3, 2012. 

    

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10  D. PROJECT OVERVIEW: 

Occupancy occurred on January 3, 2012.  Project completed on schedule and within budget.    

Funding State Funds  $0 Strong Schools Bond Funds  $10,556,389 Other Funding  $0 Total  $10,556,389   Budget Salaries and Benefits  $7,461 Supplies  $49,049 Contracts & Services  $2,180,418 Construction & Equipment  $8,319,461 Soft Costs Contingency  $62,598 Total  $10,556,389  Percent of Budget Expended  99.7%  Change Order Contingency 

Starting Contingency Balance  $748,400 

Remaining Contingency Balance  $459,113 

Percent of Changes  3.9% (Change Orders + Construction Change Directives vs. Original Contract) 

 Realized Project Savings = $41,481 

Current Phase:  Occupancy – January 3, 2012 

Schedule: Architect Contract (2)  September 30, 2008 BOE Approval  October 14, 2008  

Conceptual Design (2)  March 3, 2009 BOE Approval  March 17, 2009  

Schematic Design (2)  June 2, 2009 BOE Approval  June 23, 2009  

Submit to DSA  November 24, 2009  Authorize to Bid (2)  April 27, 2010 BOE Approval  May 11, 2010    

Approval by DSA  May 18, 2010  

Bid Opening  July 13, 2010  

Award of Contract (1)  August 3, 2010  

Notice to Proceed  August 19, 2010  

Substantial Completion  November 18, 2011  

Planned Occupancy  January 3, 2012  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 33: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 32  

Site Acquisition 525 San Antonio Rd  

A. PROJECT STATUS 

This site has been leased to Athena Academy.         

   

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10  D. PROJECT OVERVIEW: 

The site has been leased to Athena Academy.     

Funding State Funds  $0 Strong Schools Bond Funds  $8,500,000 Other Funding  $0 Total  $8,500,000  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $8,500,000 Construction & Equipment  $0 Soft Costs Contingency  $0 Total  $8,500,000  Percent of Budget Expended  100% 

Current Phase:    N/A  

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  N/A    

Approval by DSA  N/A  

Authorize to Bid (2)  N/A BOE Approval  N/A  

Bid Opening  N/A  

Award of Contract (1)  N/A  

Notice to Proceed  N/A  

Substantial Completion  N/A  

Planned Occupancy  N/A  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 34: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 33  

Jordan Middle Schools ‐ Interim Classrooms  A. PROJECT STATUS 

The portables were installed and moved into for fall 2011.  DSA closeout received November 19, 2012.     

      

 B. BUDGET & SCHEDULE SUMMARY 

                     

   

C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5  D. PROJECT OVERVIEW: 

This project completed ahead of schedule and under budget. 

Move in occurred on September 30, 2011.     

Funding State Funds  $0 Strong Schools Bond Funds  $379,811 Other Funding  $208,222 Total  $488,033   Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $180,286 Construction & Equipment  $306,983 Soft Costs Contingency  $764 Total  $488,033  Percent of Budget Expended  100%   

Current Phase:    Move‐in  

Schedule: Approval by DSA  June 16, 2011  

Authorize to Bid (2)  June 14, 2011 BOE Approval  June 28, 2011  

Bid Opening  July 14, 2011  

Award of Contract (1)  July 20, 2011  

Notice to Proceed  July 27, 2011  

Substantial Completion  September 20, 2011  

Occupancy  September 30, 2011  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 35: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 34  

Gunn High School Air Conditioning of Existing Buildings 

A. PROJECT STATUS 

Best  Contracting  Services  Inc.  completed  the  installation  of  air conditioning units and cool roof coating in the summer 2011.              

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 3.7  D. PROJECT OVERVIEW: 

Project has been closed‐out.  

Funding State Funds  $0 Strong Schools Bond Funds  $2,092,366 Other Funding  $0 Total  $2,092,366  Budget Salaries and Benefits  $1,919 Supplies  $0 Contracts & Services  $454,610 Construction & Equipment  $1,612,946 Soft Costs Contingency  $22,891 Total  $2,092,366  Percent of Budget Expended  100% 

Current Phase:    Completed  

Schedule: Architect Contract (2)  March 27, 2010 BOE Approval  April 6, 2010  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  October 20, 2010  

Approval by DSA  February 10, 2011  

Authorize to Bid (2)  February 22, 2011 BOE Approval  March 8, 2011  

Bid Opening  March 28, 2011  

Award of Contract (1)  April 8, 2011  

Notice to Proceed  April 11, 2011  

Substantial Completion  August 8, 2011   

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 36: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 35  

J.L. Stanford Middle School   Interim Classrooms  A. PROJECT STATUS 

Coulter  Construction  completed  the  work  on  the relocated portables in August 2011.             

 B. BUDGET & SCHEDULE SUMMARY 

                     

   

C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5  D. PROJECT OVERVIEW: 

Project completed on schedule and is currently in close‐out.      

 

  This portable relocation project funded by main JLS project.  Refer to pg. 14 

 

Current Phase:    Occupancy ‐ August 11, 2011  

Schedule: Approval by DSA  April 19, 2011 Jordan Project  June 16, 2011   

Authorize to Bid (2)  May 10, 2011 BOE Approval  May 24, 2011  

Bid Opening  June 1, 2011  

Award of Contract (1)  June 13, 2011  

Notice to Proceed  June 20, 2011  

Substantial Completion  August 8, 2011  

Planned Occupancy  August 15, 2011  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 37: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 36  

Fairmeadow Elementary School Portable Relocation Project 

A. PROJECT STATUS  

Relocation of the portable was complete and occupied on August 8, 2011.      

    

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 6.4  D. PROJECT OVERVIEW: 

Project completed ahead of schedule on August 8, 2011.          

   This portable relocation project funded by main JLS project.  Refer to pg. 14 

Current Phase:    Occupancy ‐ August 8, 2011  

Schedule: Architect Contract (2)  February 15, 2011 BOE Approval  N/A  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  March 3, 2011    

Approval by DSA  March 3, 2011  

Authorize to Bid (2)  May 11, 2011 BOE Approval  May 24, 2011  

Bid Opening  June 14, 2011  

Award of Contract (1)  June 14, 2011  

Notice to Proceed  June 20, 2011  

Substantial Completion  August 1, 2011  

Planned Occupancy  August 8, 2011  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 38: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 37  

Elementary Classroom Improvements Interactive Whiteboards and Sound Assist System Installation 

A. PROJECT STATUS 

Installation  of  SmartBoards  and  Lightspeed  sound  assist systems  were  completed  for  all  elementary  school classrooms and libraries in April 2011.             

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7  D. PROJECT OVERVIEW: 

All SmartBoards and Lightspeed sound systems installed.     

Funding State Funds  $0 Strong Schools Bond Funds  $1,879,695 Other Funding  $0 Total  $1,879,695  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $275,488 Construction & Equipment  $1,604,207 Soft Costs Contingency  $0 Total  $1,879,695  Percent of Budget Expended  100%  

Current Phase:  Complete ‐ May 15, 2011  

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  N/A    

Approval by DSA  N/A  

Authorize to Bid (2)  November 9, 2010 BOE Approval  November 23, 2010  

Bid Opening  February 25, 2011  

Award of Contract (1)  March 8, 2011  

Notice to Proceed  March 9, 2011  

Completion  May 15, 2011   

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 39: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 38  

Palo Alto High School  Multi‐Use Field  A. PROJECT STATUS 

The fields were available for play on February 1, 2011, and final  change order  negotiations  completed on March 9, 2011. 

        

  

 B. BUDGET & SCHEDULE SUMMARY 

                     

   

C. BOND PROJECT LIST REFERENCE: 4.14  D. PROJECT OVERVIEW: 

Field was open for use on February 1, 2011.    

Funding State Funds  $0 Strong Schools Bond Funds  $2,609,680 Other Funding  $1,007,255 Total  $3,616,935  Budget Salaries and Benefits  $0 Supplies  $1,506 Contracts & Services  $698,293 Construction & Equipment  $2,916,682 Soft Costs Contingency  $454 Total  $3,616,935   Percent of Budget Expended  100.0%  Change Order Contingency 

Starting Contingency Balance  $269,300 

Remaining Contingency Balance  $230,579 

Percent of Changes  1.5% (Change Orders + Construction Change Directives vs. Original Contract) 

 

Current Phase:    Occupancy – February 1, 2011  

Schedule: Architect Contract (2)  September 30, 2008 BOE Approval  October 14, 2008  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  November 18, 2008 BOE Approval  December 09, 2008  

Submit to DSA  March 19, 2009    

Approval by DSA  September 30, 2009  

Authorize to Bid (2)  February 24, 2009 BOE Approval  March 17, 2009  

Bid Opening  March 16, 2010  

Award of Contract (1)  April 7, 2010  

Notice to Proceed  June 1, 2010  

Substantial Completion  January 31, 2011  

Planned Occupancy  February 1, 2011  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 40: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 39  

Gunn High School 

Industrial Arts Addition and Renovation 

A. PROJECT STATUS 

This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.  

   

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11  D. PROJECT OVERVIEW: 

The building occupied as scheduled, and the project completed within budget.

Funding State Funds  $0 Strong Schools Bond Funds  $5,065,128 Other Funding  $0 Total  $5,065,128  Budget Salaries and Benefits  $1,061 Supplies  $88,985 Contracts & Services  $984,783 Construction & Equipment  $3,990,300 Soft Costs Contingency  $0 Total  $5,065,128  Percent of Budget Expended  100%  Change Order Contingency 

Starting Contingency Balance  $349,000 

Remaining Contingency Balance  $141,967 

Percent of Changes  41.6% (Change Orders + Construction Change Directives vs. Original Contract) 

 

Current Phase:  Occupancy – January 4, 2010 

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  June 17, 2008    Approval by DSA  December 24, 2008  

Authorize to Bid (2)  October 14, 2008 BOE Approval  October 28, 2008  

Bid Opening  December 16, 2008  

Award of Contract (1)  December 24, 2008  

Notice to Proceed  January 6, 2009  

Substantial Completion  November 25, 2009  

Planned Occupancy  January 4, 2010  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 41: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 40  

Gunn High School Aquatic Center 

A. PROJECT STATUS 

This  facility was available  for use  in  July 2009.             

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 3.12  D. PROJECT OVERVIEW: 

This project completed within budget.

Funding State Funds  $0 Strong Schools Bond Funds  $4,862,530 Other Funding  $0 Total  $4,862,530  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $647,169 Construction & Equipment  $4,215,360 Soft Costs Contingency  $0 Total  $4,862,530  Percent of Budget Expended  100%  Change Order Contingency 

Starting Contingency Balance  $389,887 

Remaining Contingency Balance  $195,148 

Percent of Changes  49.9% (Change Orders + Construction Change Directives vs. Original Contract) 

Current Phase:    Occupancy – June 15, 2009  

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  December 11, 2007    Approval by DSA  April 24, 2008  

Authorize to Bid (2)  April 8, 2008 BOE Approval  April 22, 2008  

Bid Opening  May 28, 2008  

Award of Contract (1)  June 4, 2008  

Notice to Proceed  December 6, 2008  

Substantial Completion  June 15, 2009  

Planned Occupancy  June 15, 2009  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 42: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 41  

Middle School Pre‐Design Jordan, J.L. Stanford and Terman 

A. PROJECT STATUS 

AEDIS presented recommended concept plans for each campus to the Board of Education for approval on September 8, which became the program documents for the new projects at each campus.  These projects for pre‐design work have been closed, and  funds will be  transferred  to  the program contingency on June 14, 2011.        

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12  D. PROJECT OVERVIEW: 

This project has been completed. Board approval received on September 8, 2009.

Funding State Funds  $0 Strong Schools Bond Funds  $54,658 Other Funding  $0 Total  $54,658   Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $54,658 Construction & Equipment  $0 Soft Costs Contingency  $0 Total  $54,658  Percent of Budget Expended  100%  

Current Phase:    Complete  

Schedule: Architect Contract (2)  October 28, 2008 BOE Approval  October 30, 2008  

Conceptual Design (2)  June 23, 2009 BOE Approval  September 8, 2009  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  N/A    Approval by DSA  N/A  

Authorize to Bid (2)  N/A BOE Approval  N/A  

Bid Opening  N/A  

Award of Contract (1)  N/A  

Notice to Proceed  N/A  

Substantial Completion  N/A  

Planned Occupancy  N/A  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 43: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 42  

Technology Improvements  

A. PROJECT STATUS  Equipment orders have arrived and were deployed to the various campuses for use during the 2014/15 school year.    

  

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7  D. PROJECT OVERVIEW: 

Equipment has been installed for the 2014/15 school year.     

Funding State Funds  $0 Strong Schools Bond Funds  $10,485,054 Other Funding  $0 Total  $10,485,054  Budget Salaries and Benefits  $0 Supplies & Computers  $6,850,644 Contracts & Services  $539,269 Construction & Equipment  $3,095,142 Soft Costs Contingency  $0 Total  $10,485,054  Percent of Budget Expended  92.2%  

Current Phase:    N/A  

Schedule: Architect Contract (2)  N/A BOE Approval  N/A  

Conceptual Design (2)  N/A BOE Approval  N/A  

Schematic Design (2)  N/A BOE Approval  N/A  

Submit to DSA  N/A    

Approval by DSA  N/A  

Authorize to Bid (2)  N/A BOE Approval  N/A  

Bid Opening  N/A  

Award of Contract (1)  N/A  

Notice to Proceed  N/A  

Substantial Completion  N/A  

Planned Occupancy  N/A  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 44: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 43  

Garland Elementary School Campus Modernization 

A. PROJECT STATUS 

The  Board  of  Education  has  put  new  development  for Garland on hold until a growth plan is established for the elementary  schools.    The  board  voted  to  terminate  the lease with Stratford School in June 2011. Discussions with the  Board  on  future  plans  for  growth  at  the  elementary schools are ongoing.        

B. BUDGET & SCHEDULE SUMMARY  

                    

   

C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10  D. PROJECT OVERVIEW: 

This project has been placed on hold.

Funding State Funds  $0 Strong Schools Bond Funds  $22,178,544 Other Funding  $0 Total  $22,178,544  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $3,915,789 Construction & Equipment  $17,400,000 Soft Costs Contingency  $862,755 Total  $22,178,544  Percent of Budget Expended  1.3% 

Current Phase:    On Hold  

Schedule: Architect Contract (2)  October 28, 2008 BOE Approval  October 30, 2008  

Conceptual Design (2)  February 10, 2009 BOE Approval  February 24, 2009  

Schematic Design (2)  June 2, 2009 BOE Approval  June 23, 2009  

Submit to DSA  N/A    Approval by DSA  N/A  

Authorize to Bid (2)  N/A BOE Approval  N/A  

Bid Opening  N/A  

Award of Contract (1)  N/A  

Notice to Proceed  N/A  

Substantial Completion  N/A  

Planned Occupancy  N/A  

* Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings 

Page 45: Through June 2017 - Palo Alto Unified School Districtpausd-web.pausd.org/community/StrongSchoolsBond/... ·  · 2017-07-25Through June 2017 Strong ... Addison Elementary School –

Page | 44  

High School Master Plan 

Palo Alto HS and Gunn HS 

A. PROJECT STATUS 

The Board of Education (BOE) approved the master plans for both high schools, and these projects have been  closed,  with  funds  transferred  to  the respective campus reserve funds.       

   

B. BUDGET & SCHEDULE SUMMARY  

                    

 C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14  D. PROJECT OVERVIEW: 

Master planning effort complete.        

Funding State Funds  $0 Strong Schools Bond Funds  $285,387 Other Funding  $0 Total  $285,387  Budget Salaries and Benefits  $0 Supplies  $0 Contracts & Services  $285,387 Construction & Equipment  $0 Soft Costs Contingency  $0 Total  $285,387  Percent of Budget Expended  86.2% 

Current Phase:    Complete  Schedule: Architect Contract (2)  March 31, 2009 BOE Approval  April 14, 2009  Initial Master Plan Approval (2)  September 8, 2009 BOE Approval  September 22, 2009  Paly CEQA Approval (2)  February 9, 2010 BOE Approval  February 23, 2010  Gunn Master Plan Update (2)  March 23, 2010 BOE Approval  April 6, 2010  Gunn CEQA Approval (2)  April 27, 2010  BOE Approval  May 11, 2010   Master Plan Revision Approval (2)  September 14, 2010 Paly MP Revision Approval (2)  October 9, 2010 Gunn MP Revision Approval (2)  October 12, 2010  * Anticipated Dates – Subject to Change ( ) Denotes number of Board of Education Readings