Top Banner
Third Street Corridor Rehabilitation Community Meeting # 2 | March 15, 2018 Third Street Corridor Rehabilitation Community Meeting # 2 | March 15, 2018 City of San Rafael BKF with WRT + Parisi
54

Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Oct 14, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Third Street Corridor RehabilitationCommunity Meeting # 2 | March 15, 2018

Third Street Corridor RehabilitationCommunity Meeting # 2 | March 15, 2018

City of San Rafael BKF with WRT + Parisi

Page 2: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Third Street - Agenda

1.Welcome and Introductions

2. Project Presentation

3.Discussion

4.Wrap-Up/Next Steps

5. Adjourn 1.

Welcome and Introductions1:00

Introduction of Committee members, staff, and consultant teamwith each member outlining their interests in the process

2. Project Presentation1:15

What the project is and isn’t, timelines, work program

Page 3: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

IMPROVEMENTS

• Pavement repair and drainage

• Signal upgrades

• Sidewalk and crosswalk enhancement

• Street trees

Baseline Project Features

$12.5 MILLON AVAILABLE

FUNDING FOR MEASURE A

GOALS

• Traffic flow improvements for cars, transit,

and emergency response

• Safety for all users

• Multi-modal access

Page 4: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Available BudgetB

ase

lin

e I

mp

rove

me

nts

$3.5 M

$9M

Bio-retention facilities

Additional cost for 12’ Multiuse Path

Road repair between Grand & Hetherton

4th Street Intersection

Improvements at

key intersections

Tota

l b

ud

get

= $

12

.5 M

illi

on

A

dd

itio

na

l

Page 5: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Project Area

Page 6: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Draft Final

ReportReview and

Create Preferred

Alternatives

• Existing Conditions

• Opportunities &

Constraints

• Technical and

Community Working

Group Meetings

Community

Meeting #1

Summer 2017 November 2017 Winter 2017-2018 Spring 2018

We

Are

here

Final Report to

City Council

Project Design

and Construction

Late Spring 2018 2018-2021

Project Development Schedule

Page 7: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

3rd Street Now

Page 8: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Major East West Connector

Page 9: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Other Projects in Pipeline

Public Projects• Grand Avenue Pedestrian Bridge over the canal

• Bettini Transit Center relocation

• SMART track extension

• Cijos St- Currently under construction.

• Intersection improvements at A Street

• Heatherton Intersection at 101

• Parking and Way finding Study

• Traffic Signal Timing Study

Private Projects • BioMarin/Senior Housing at old (Between Lindaro &

Brooks)

• Shell Station at 4th &2nd/3rd

Page 10: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Overview

Congestion Pedestrian Safety

Accessibility Comfort

Page 11: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Source: Marin County, February 2015

Vehicle CongestionWeekday Westbound

6 8 10 12 PM 2 4 6 8 10 PM12 AM 42

15

MIN

10

5

P

L

A

N

N

I

N

G

T

I

M

E

ADT:

19,200 TO 24,700

Page 12: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Vehicle Speeds During Peak Hours

Source: Marin County, February 2015

Page 13: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Collision Types

Source: Marin County, February 2015

Page 14: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Injury Rate

Source: Marin County, February 2015

Page 15: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Bike and Pedestrian Involved

Source: Marin County, February 2015

Page 16: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing Bicycle, Pedestrian & Transit

Page 17: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Pavement Conditions

Page 18: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Sidewalk Width

Source: Marin County, February 2015

Page 19: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

On Street Parking

Page 20: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

What we heard from the

Community, TWG and

CWG

Page 21: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Community Meeting- Nov 13, 2017

Page 22: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

� Pedestrian and bike safety

� Vehicular congestion and speed

� Need for tree canopy and level of comfort

� Need to improve accessibility and sidewalks

� Congestion east of 101 highway

� Maintain parking in residential zones

� Improve wayfinding

� Improve community character + identity

� Improve bike and pedestrian crossing at the 4th street

at 2nd/3rd

� Accidents at Shaver St. intersection

� Safe access to schools

Improve Bicycle Access And Safety.

What we heard

Page 23: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Previous Community Prioritization

1. Street Trees

2. Widened Sidewalk

3. Curb Extension

4. Street Lights

5. Gateway/Civic Identity

Signalized Intersection

Vegetative Buffer

6. Sidewalk Paving

7. Painted Crosswalk

8. Wayfinding + Signage

9. Sidewalk Seating

10. On Street Parking

Improve Bicycle Access And Safety.

Page 24: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Concept Design

Page 25: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Corridor-wide Improvements

Conduits for Future Adaptive Signals

Bulb-outs Traffic Signal Upgrades

High Visibility Crosswalks

Page 26: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Corridor wide Improvements

Key School Routes/Sidewalks Pavement Rehabilitation

Street Trees ADA/ Curb Ramps

Page 27: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Zones

Page 28: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Commercial/ Downtown

Page 29: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Commercial/ Downtown

Issues:

• Traffic Congestion results in sudden speeding

• Long distance between cross walks

• Tree canopy

• Pedestrian visibility at intersections

• On Street parking V/S off street parking

Page 30: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Commercial/ Downtown

Page 31: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: Brook St

Page 32: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: Brook St

Page 33: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: A St & B St

Page 34: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: A St & B St

Page 35: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: A St Intersection

Page 36: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: A St Intersection

Page 37: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: E St

Page 38: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: E St

Page 39: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Residential

Page 40: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Zone: Residential

Issues:

• Speed issues

• Pedestrian Crossing along 3rd St

• Vertical curves and visibility issues

• Narrow sidewalk at the G St. intersection, along

the hill

• 4th Street Intersection

Page 41: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Zones- Residential

Page 42: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: Hayes St to Shaver St

Page 43: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: Hayes St to Shaver St

Page 44: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: Hayes St to Shaver St

Page 45: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: G St

Page 46: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: G St

Page 47: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

G Street Cross Section

Existing

Interim

Page 48: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: G St Safe Route to School

Page 49: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: G St Safe Route to School

Page 50: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Existing: 4th St to Ida St

Page 51: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Proposed: 4th St to Ida St

Page 52: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Available BudgetB

ase

lin

e I

mp

rove

me

nts

$3.5 M

$9M

Bio-retention facilities

Additional cost for 12’ Multiuse Path

Road repair between Grand & Hetherton

4th Street Intersection

Improvements at

key intersections

Tota

l b

ud

get

= $

12

.5 M

illi

on

A

dd

itio

na

l

Page 53: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

Draft Final

ReportReview and

Create Preferred

Alternatives

• Existing Conditions

• Opportunities &

Constraints

• Technical and

Community Working

Group Meetings

Community

Meeting #1

Summer 2017 November 2017 Winter 2017-2018 Spring 2018

We

Are

here

Final Report to

City Council

Project Design

and Construction

Late Spring 2018 2018-2021

Project Development Schedule

Page 54: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •

QuestionsQuestions