Top Banner
BATHINDA GURU NANAK DEV THERMAL PLANT
38

Thermal Plant Project Ppt.

Oct 27, 2014

Download

Documents

menyu1989
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Thermal Plant Project Ppt.

BATHINDAGURU NANAK DEV THERMAL PLANT

Page 2: Thermal Plant Project Ppt.

HISTORY

• Foundation stone of G.N.D.T.P. at bathinda was laid on 19th November 1969

• First unit commissioned Sept, 1974• Second unit commissioned Sept, 1975• Third unit commissioned Mar, 1978• Fourth unit commissioned Jan, 1979• Each unit have capacity of 110MW

Page 3: Thermal Plant Project Ppt.

INTRODUCTION

• It is a coal-based plant

• combustion of coal Heat convert water in pipes into steam steam run the turbine Rotates generator three phase electric supply is produced

Page 4: Thermal Plant Project Ppt.

Hence basic requirements are :

• Fuel (coal)• Boiler• Steam turbine• Generator• Ash handling system• Unit auxiliaries

Page 5: Thermal Plant Project Ppt.

PLANT LAYOUT

Page 6: Thermal Plant Project Ppt.

DIFFERENT CELLS OF PLANT

• CHP(Coal Handling Plant) • Coal is unloaded from wagons using wagon

tippler• When coal reaches the plant, normal size of coal is

about 500mm primary crusher 120mm secondary crusher 25mm coal mill pulverized coal feeded in boiler.

Page 7: Thermal Plant Project Ppt.

Wagon tippler

Page 8: Thermal Plant Project Ppt.

• BOILER

• Coal burnt heat (15000 C) Superheated Steam(high P & T) in boiler pipes Turbine(power obtained)

Page 9: Thermal Plant Project Ppt.

•TURBINE

• steam rotates turbine at 3,000 rpm Rotates power generator electricity produced

Page 10: Thermal Plant Project Ppt.

•CIRCULATING WATER PUMP

• Two nos. of circulating water pumps provided for each unit.

• One for steam cycle in turbine-condenser-boiler

• 2nd for condenser-cooling tower water cycle

• Each have capacity of 17200 T/hr

Page 11: Thermal Plant Project Ppt.

•COOLING TOWER

• These are massive ferro-concrete structure having hyperbolic profile creating natural draught of air responsible for achieving the cooling effect.

• Height -- 120 m• Cooling capacity – 18000 T/hr for every 100c

Page 12: Thermal Plant Project Ppt.

•ASH PRECIPITATORS

• Fly ash carried by outgoing flue gases is arrested at two stages

a) Mechanical precipitators ash particles are separated out by centrifugal action.

b) Electrostatic Precipitators ash particles pass through high voltage electric field, particles get ionized and are attracted towards the collecting electrodes.

Page 13: Thermal Plant Project Ppt.

ELECTROSTATIC PRECIPITATOR

Page 14: Thermal Plant Project Ppt.

PROJECT

• WATER TREATMENT to prepare boiler

friendly feed water • COAL TESTING to calculate the grading

of coal

Page 15: Thermal Plant Project Ppt.

WATER TREATMENT

Natural water is available in abundance, but it contains impurities in many forms which are as :

• Cationic• Anionic• Undissolved (suspended)• Gaseous

Page 16: Thermal Plant Project Ppt.

TYPES OF IMPURITIES

Cationic Anionic Un-Dissolved Gaseous

Calcium Bicarbonate Turbidity, silt, mud, dirt and other suspended matter

Carbon dioxide

Magnesium Carbonate colour Hydrogen Sulphide

Sodium Hydroxide Organic matter Ammonia

Potassium Sulphate Colloidal silica Methane

Ammonium Chloride Oil Oxygen

Manganese Phosphate Corrosion products (condensate)

Chlorine

Iron Silica

Page 17: Thermal Plant Project Ppt.

HARDNESS AND SCALING

• Bicarbonates or carbonates of Ca and Mg form soft scale Temporary Hardness Deposits as soft scale in boiler pipes.

• Non-Carbonates of Ca and Mg (e.g.- Sulphates ,Chlorides) permanent hardness Deposits as hard scale in boiler pipes, which is difficult to remove.

Page 18: Thermal Plant Project Ppt.

When pH of feed water to boiler is below the recommended range chances of corrosion increases, and when it is above recommended value then chances of scaling increases.

Corrosion Scaling

Page 19: Thermal Plant Project Ppt.

NEGATIVE EFFECTS OF SCALING

• Decrease operating efficiency• Thermal damage• Reduced working life of a boiler• Increased cleaning time and cleaning costs

Page 20: Thermal Plant Project Ppt.

WATER TREATMENT STEPS

1. Pre-Treatment of water Make water free from suspended, colloidal

and organic impurities.

process involved in pre-treatment are :- a)Settling and Coagulation(using Alum) b)Filtration-Clay ,Colloids ,algae etc.

Page 21: Thermal Plant Project Ppt.

SETTLING AND COAGULATION

• Alum is mixed in water to make solid particles settle down.

Water from lakes

Clear well

Page 22: Thermal Plant Project Ppt.

DEMINERALISATION SYSTEM

• It is an ion exchange process with following steps :-

i) Conversion of salts to their corresponding acids by hydrogen cat-ion exchanger

ii)Removal of acids by anion exchangers • Two exchangers are normally in series. Normally

cat-ion precedes the anion exchanger

Page 23: Thermal Plant Project Ppt.

WORKING OF DM PLANT

Page 24: Thermal Plant Project Ppt.

•Cation exchanger mainly removes Calcium, Magnesium, sulfates, chloride , nitrates and sodium salts alkalinity from raw water

Water from sand filters

Degasser

Page 25: Thermal Plant Project Ppt.

•Carbon dioxide generated by dissociation of carbonic acid at cation outlet water, is removed by degasser system

Cation Exchanger

Anion Exchanger

Page 26: Thermal Plant Project Ppt.

•Anion exchangers remove the highly dissociated acids (like H2So4, HNo3, Hcl ) from the effluent of cation exchanger

DegasserMixed bed Deioniser

Page 27: Thermal Plant Project Ppt.

CONDUCTIVITY AND pH READINGS

• Raw water [pH>7 ,conductivity=200-300 µ.mhos]• Effluent of cation exchanger [pH≈4 ,conductivity=400-800 µ.mhos ]• Effluent of anion exchanger [ 7<pH<10 ,conductivity=14-15 µ.mhos]

Page 28: Thermal Plant Project Ppt.

Mixed-bed Deionisation

• Effluent water after anion exchanger may still have some salts due to them its conductivity is around 14-15 micro.mhos. 7 < pH <10 , so it is further passed through Mixed-Bed Deioniser

• The mixed bed mixture of Cation and Anion resins is present there.(resin+Hcl+NaOH)

Page 29: Thermal Plant Project Ppt.

Mixed-Bed Resin Container

•Treated water has pH 6.8-7.2 ,conductivity < 1µ.mhos

•During charging 100kg each of Hcl and NaOH are injected.

Page 30: Thermal Plant Project Ppt.

EXHAUST OF DM PLANT INDICATION

• Conductivity of cation exchanger decreases• Conductivity of anion exchanger increases

• It means its time to charge the ion-exchangers

• Cation ex. Charged with Hcl injection• Anion ex. Charged with NaOH injection

Page 31: Thermal Plant Project Ppt.

DM PLANT SPECIFICATION

• GNDTP has 2 units of DM Plant, each having capacity of 40 T/hr

• DM water storage tank have capacity of 2456m3

• Max running hrs 5(one unit)

Page 32: Thermal Plant Project Ppt.

COAL TESTING

• Coal used is Bituminous Carbon = (60-70) % Ash = (30-40) % Moisture < (2) % Calorific Value = (3500-4500) Kcal/Kg

Page 33: Thermal Plant Project Ppt.

Moisture Content Test

1gm sample of powdered coal is weighed and taken in the silicon dish. Then this sample is heated in oven at 1100C for 1hr.then sample is taken out and again weighed. Loss of weight is the water content.

Page 34: Thermal Plant Project Ppt.

Ash Content Test

In this test 1gm sample of powdered coal is weighed and taken in the silicon dish. Then this sample is heated in oven at 8100c for 1hr.then Sample is taken out and again weighed. Remaining is the only ash content.

Page 35: Thermal Plant Project Ppt.

Volatile Matter Test

For this test 1gm sample of powdered coal is taken. This sample is taken in a silicon crucible dish and heated at 900C for 7 minutes. Then the remaining amount of sample is noted and the losses are noted.

• Volatile matters are Hg and NH3.

Page 36: Thermal Plant Project Ppt.

COAL GRADING FORMULATION

• Moisture content - M• Ash content - A

• UHV (useful heat value)=[8900-138(M+A)] Kcal/Kg

Page 37: Thermal Plant Project Ppt.

The results of the laboratory tests performed on the basis of the representative samples prepared by the sampling system are used for: •Calculating the payment due for each batch of coal supplied •Adjusting the coal flow to the mills •Calculating the amount of by-products from each batch of coal•Calculating the emissions from each batch of coal

Page 38: Thermal Plant Project Ppt.

THANKS ..!!