THE UNIVERSITY OF MICHIGAN REGENTS COMMUNICATION ITEM FOR INFORMAnON Subject: Plant Extension Background and Summary: Construction activities on University projects continued as scheduled during the month of October 2008, except as indicated by footnotes. The attached schedules update information concerning projects in planning and projects under construction. The projects listed below have been completed, except for specific items, and will no longer be included in this report. Newberry Hall Kelsey Museum Addition and Renovation UMHHC Medical Professional Building Heating, Ventilation and Air Conditioning Unit Replacement Respectfully submitted, November 2008 Attachment
12
Embed
THE UNIVERSITY OF MICHIGAN · Construction activities on University projects continued as scheduled during the month of October 2008, ... Central Campus Area 2008 Utility Tunnel $
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
THE UNIVERSITY OF MICHIGANREGENTS COMMUNICATION
ITEM FOR INFORMAnON
Subject: Plant Extension
Background and Summary:
Construction activities on University projects continued as scheduled during the month ofOctober 2008, except as indicated by footnotes.
The attached schedules update information concerning projects in planning and projectsunder construction.
The projects listed below have been completed, except for specific items, and will nolonger be included in this report.
Newberry Hall Kelsey Museum Addition and RenovationUMHHC Medical Professional Building Heating, Ventilation and Air ConditioningUnit Replacement
Respectfully submitted,
November 2008Attachment
cshankle
November 20, 2008
Project
PROJECTS IN PLANNINGNovember 2008
ProposedProject Budget
Status as of October 24, 2008
Source of Funds
Ann Arbor
ARCHITECT APPOINTED
Wall Street Office Building, East Parking Structure, and $
Transit Center
Walker Parking Consultants and the S/L/A/M Collaborative
48,600,000 Parking resources, Hospitals andHealth Ccnters' resources, and
investment procecds
WORKING DRAWINGS IN PREPARATION
Art and Architecture Building Addition
The MillerlHul1 Partnership, LLP
Camp Davis Rocky Mountain Field StationCabin Replacement and Infrastructure Improvement
Strout Architects, Inc.
William W. Cook Legal Research LibraryElevator Replacement
UM-AEC
W.K. Kellogg Institute and Dental Building
Information Technology Infrastructure Upgrade
UM-AEC
W. K. Kellogg Eye Center
Chiller ReplacementUM-AEC
$
$
$
$
$
13,000,000
1,350,000
1,800,000
4,500,000
1,950,000
Taubman College of Architecture andUrban Planning resources andinvestment proceeds
College of Literature, Sciencc, and theArts resources
Investment proceeds
Investmcnt proceeds
Investment procecds
Project
PROJECTS IN PLANNINGNovember 2008
ProposedProject Budget
Status as of October 24, 2008
Source of Funds
WORKrNG DRAWINGS IN PREPARATION
Law School Academic Building andHutchins Hall Law School Commons Addition
Hartman-Cox in association with Integrated DesignSolutions, LLC
Life Sciences Institute Building
Cryo-Eleetron Microscopy SuiteSmithGroup
Medical Science Unit IIMicrobiology and Immunology Departments Renovations
UM-AEC
Michigan Wrestling CenterJiekling Lyman Powell Associates, Inc.
Modern Languages BuildingChilled Water Plant Expansion
UM-AEC
Molecular and Behavioral Neuroscience Institute Building
First Level Laboratory Renovations
UM-AEC
Earl V. Moore BuildingInfrastructure Improvements
SI-IW Group
$
$
$
$
$
$
$
102,000,000
1,800,000
1,600,000
5,500,000
3,400,000
1,600,000
5,000,000
2
Gifts, investment proceeds, and LawSchool resources
Resources from the Office of theProvost, Medical School and the LifeSciences Institute
Medical School resources
Athletic Department resources andgifts
Utility and General Fund resources
Medical School rcsources
Investment proceeds and Utilityresources
Projcct
PROJECTS IN PLANNINGNovember 2008
ProposcdProject Budget
Status as of October 24,2008
Source of Funds
WORKiNG DRAWINGS iN PREPARATION
North Campus Switch StationTransformer Upgrades
DTE Energy
Thompson Strect Parking Structurc AdditionCarl Walker Inc.
UMHHC C. S. Molt Children's and Women's Hospitals
Replacement ProjectShell Space Complction Project
HKS Architccts, P.c.
UMHHC Domino's Farms Leasehold Improvements for theDivision of Mctabolism, Endocrinology and Diabetes
UMHHC A. Alfred Taubman Hcalth Centcr
Lcvel B I Medical Obscrvation Unit
Intcgrated Design Solutions, LLC
UMHHC University Hospital
Inpaticnt Adult Psychiatry Rcnovation
Hobbs and Black Associates, Inc.
$
$
$
$
$
$
3,800,000
15,700,000
23 I,000,000
4,500,000
5,900,000
3,150,000
3
Utility resources
Parking resources and investmentproceeds
Hospitals and Health Centers'resources
Hospitals and Health Centers'resourccs
Hospitals and Health Centcrs'
rcsources
Hospitals and Health Centers'
resources
NEW CONSTRUCTION PROJECTSNovember 2008 Status as of October 24, 2008
Date Original CUlTcnt
Construction Completion Completion
NEW CONSTRUCTION PROJECTS Project Budget Started Date Date Source of Funds
Ann Arbor
Alumni Memorial Hall $ 41,900,000 Nov-06 lLlI1-08 Dee-08 Gifts, Museum of ArtMuseum of Art Addition resources, General Fund
Allied Works Architecture resources and investmentproceeds
Central Campus Area 2008 Utility Tunnel $ 6, I00,000 Mar-08 Mar-09 Mar-09 Utility resourcesReplacements
Fishbeck, Thompson, Carr and Huber, Inc.
Celllral Power Plant $ 2,000,000 J,II-08 Dee-09 Dec-09 Utility resources
Replacemelll Steam TurbineUM-AEC
Central Power Plant $ 4,200,000 Mar-05 .lun-06 Dec-08 Utility resources
Two Replacement Steam TurbinesUM-AEC
Central Power Plant $ 2,550,000 Apr-08 Sep-09 Sep-09 Utility resources
2AkV Switchgear UpgradeCDA Associates
Central Power Plant $ 1,550,000 Aug-08 Mar-09 Mar-09 Utility resources
Water Treatment System ImprovemelllsBlack & Veatch
4
NEW CONSTRUCTION PROJECTSNovember 2008 Status as or October 24, 2008
Date Original CUITentConstruction Completion Completion
NEW CONSTRUCTION PROJECTS Project Budget Started Date Date Source or Funds
William W. Cook Legal Research Library and $ 6,500,000 Feb-08 Mar-09 Mar-09 Gift to the Law School and
Hutchins Hall investment proceeds
Lighting Improvements
Lord Aeek & Sargent, Inc.
Dental Building and W. K. Kellogg Institute $ 1,500,000 Aug-07 Mar-09 Mar-09 Investment proceeds
Elevator Replacement
UM-AEC
W. K. Kellogg Institute and Dental Building $ 1,600,000 Oet-08 Sep-09 Sep-09 Investment proceeds
2008 Exterior RepairsUM-AEC
East University Chiller Plant $ 2,700,000 Aug-08 Sep-09 Sep-09 Investment proceeds
New Chiller
UM-AEC
Engineering Programs Building $ 1,200,000 Jlil-08 Mar-09 Mar-09 College of Engineering
First Floor Instructional Learning Center resourcesUM-AEC
Indoor Practice Facility for Intercollegiate Football $ 26,100,000 Dee-O? Dee-09 Dec-09 Athletic DepartmentJickling Lyman Powell Associates, Inc. resources and gi fts
Institute for Social Research $ 2,000,000 Jan-08 Sep-08 Mar-09 Investment proceedsHeating, Ventilation and Air Conditioning Upgrades