Phase Location of Phase What do the works entail? Anticipated start date and end date Impacts and restrictions 1b Left half of Berkeley Square (inner square) Installation of Granite sett motorcycle bays, new Yorkstone footway slab and Mackenzie lighting columns COMPLETED 2a Opposite Bruton Place The removal of the traffic island opposite Bruton Place COMPLETED 3a 18-22 Berkeley Square Installation of new Granite kerb and Yorkstone footway creating a larger pedestrian area outside 18-22 Berkeley Square. Installation of two parking bays finished in Granite Setts, and five cycle stands. COMPLETED 1c Right half of Berkeley Square (inner circle) Installation of new Yorkstone footway and seven Granite sett parking bays Nov 2018 – Jan 2019 Temporary parking bay suspensions and footway closures during works. 1d Outside the Phillips Gallery (30 Berkeley Square) Installation of a new pedestrian crossing outside Phillips, connecting the northern entrance to Berkeley Square Jan - Feb 2019 A temporary give way line will be installed for duration of works. Parking suspensions in place outside 30 Berkeley Square to allow traffic movement 2b Motorcycle island in the corner of Berkeley Square and Davies Street Permanent removal of the motorcycle island Jan 2019 Permanent removal of motorcycle parking bays in island. The loss of parking at this location is compensated by bays being re-provided elsewhere around the square 2c Traffic island at the Davies Street and Mount Street junction Permanent removal of the traffic island Feb 2019 Cycle stands will be removed. 3b Davies Street carriageway Construction of a new carriageway including new pedestrian crossing Feb - Apr 2019 There will be no access to Davies Street from Berkeley Square throughout these works. A diversion will be in place via Mount Street (see page 3). Taxi and motorcycle bays outside 40 Berkeley Square will be suspended The table below details the phasing plan for public realm improvements to Berkeley Square north. Please note that the dates below are approximate and could be subject to change. This document will be updated if any changes are made. (Document is accurate as of January 2019)
3
Embed
The table below details the phasing plan for public realm ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Phase Location of Phase What do the works entail? Anticipated start date and end date
Impacts and restrictions
1b Left half of Berkeley Square (inner square)
Installation of Granite sett motorcycle bays, new Yorkstone footway slab and Mackenzie lighting columns
COMPLETED
2a Opposite Bruton Place The removal of the traffic island opposite Bruton Place
COMPLETED
3a 18-22 Berkeley Square Installation of new Granite kerb and Yorkstone footway creating a larger pedestrian area outside 18-22 Berkeley Square. Installation of two parking bays finished in Granite Setts, and five cycle stands.
COMPLETED
1c Right half of Berkeley Square (inner circle)
Installation of new Yorkstone footway and seven Granite sett parking bays
Nov 2018 – Jan 2019 Temporary parking bay suspensions and footway closures during works.
1d Outside the Phillips Gallery (30 Berkeley Square)
Installation of a new pedestrian crossing outside Phillips, connecting the northern entrance to Berkeley Square
Jan - Feb 2019 A temporary give way line will be installed for duration of works. Parking suspensions in place outside 30 Berkeley Square to allow traffic movement
2b Motorcycle island in the corner of Berkeley Square and Davies Street
Permanent removal of the motorcycle island
Jan 2019 Permanent removal of motorcycle parking bays in island. The loss of parking at this location is compensated by bays being re-provided elsewhere around the square
2c Traffic island at the Davies Street and Mount Street junction
Permanent removal of the traffic island
Feb 2019 Cycle stands will be removed.
3b Davies Street carriageway Construction of a new carriageway including new pedestrian crossing
Feb - Apr 2019 There will be no access to Davies Street from Berkeley Square throughout these works. A diversion will be in place via Mount Street (see page 3). Taxi and motorcycle bays outside 40 Berkeley Square will be suspended
The table below details the phasing plan for public realm improvements to Berkeley Square north. Please note that the dates below are approximate and could be subject to change. This document will be updated if any changes are made. (Document is accurate as of January 2019)
Construction of a new Yorkstone footway with Granite setts creating a wider pedestrian area.
Apr - Aug 2019 No road closures. Traffic will run on a new carriageway set up. Existing parking and motorcycles bays will be suspended during works then relocated to new bays
4b Outside 31 - 41 Berkeley Square
Construction of a new Yorkstone footway with Granite setts creating a wider pedestrian area.
Sept - Nov 2019 No road closures. Traffic will run on a new carriageway set up. Existing parking and motorcycles bays will be suspended during works then relocated to new bays
5 Carriageway at the Davies Street and Mount Street junction
Construction of a new carriageway
Oct 2019 - Jan 2020 A diversion will be in place during this period. Local businesses and residents will be advised beforehand
6a Outside the Porsche garage Installation of a new Yorkstone footway with Granite setts
Nov - Dec 2019 No major impacts
6b Small section of carriageway on Mount Street
Construction of new carriageway at the entrance to Mount Street
Nov - Dec 2019 A diversion will be in place during this period. Local businesses and residents will be advised beforehand
7 Outside 25 Berkeley Square Construction of a new Yorkstone footway with Granite setts
Aug- Oct 2019 Bruton Place will not be accessible whilst the works are underway
8 Full northern half of Berkeley Square
Resurfacing the carriageway
Jan 2020 Overnight road closures will be in place for the duration of works