THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 0 1 /18/200 5 PROJECT LIFE CYCLE 1
Jan 05, 2016
THE PROJECT LIFE CYCLE
PROJECT MANAGEMENT LIFE CYCLE
LSU 01/18/2005
PROJECT LIFE CYCLE 1
GOAL OBJECTIVE
LSU 01/18/2005
PROJECT LIFE CYCLE 2
• To Understand project phase
• To mastering process flow during life cycle
• To implment Preliminary Design Review (PDR)
• To implment Critical Design Review (CDR)
• To implment Flight Readines Review (FRR)
THE PROJECT PHASES
All projects complete roughly the same phases from inception to completion
LSU 01/18/2005 PROJECT LIFE CYCLE 3
OPERATION
DESIGN PDR
DEVELOPMENT CDR
FABRICATION
INTEGRATION
TESTINGFRR
THE DESIGN PHASE
Little to no hardware testing or prototypingDefine science goals and objectivesSystem level design (subject of Lecture 3) System requirements derived from goals and objectives Identify major subsystems and interfaces
Concept hardware and software design Derived from system requirements and constraints Identify parts, costs & availability
Establish tasks, schedule, resource needs and plans for remaining phases of life-cycle
Develop preliminary risk assessment & management plan
Phase terminates with Preliminary Design Review (PDR)
LSU 01/18/2005
PROJECT LIFE CYCLE 4
“Paper” study of all issues to establish major concepts and plans
THE DEVELOPMENT PHASE - 1
Test concepts by prototyping Not building flight hardware Used to gain information necessary to refine or
finalize a design Applies to structure, electronics, sensors and
software
Finalize hardware & software design Complete system design Define interfaces and develop appropriate
Interface Control Documents (ICD) Complete detailed design
LSU 01/18/2005
PROJECT LIFE CYCLE 5
Design
Prototype
Test
Complete Design
Detailed in-depth study when all design components are finalized
THE DEVELOPMENT PHASE - 2
Purchase long lead items (identified at PDR)
Finalize plans for pre-flight phasesFabrication, integration, calibration and testingTasks, schedule, procedures, resource needs, costs
Update risk assessment & management plan
Preliminary plan should already be in use for tracking and mitigating risks during development
Develop preliminary mission operations & data analysis plan
Phase terminate with Critical Design Review (CDR)
LSU 01/18/2005
PROJECT LIFE CYCLE 6
THE FABRICATION PHASE
LSU 01/18/2005
PROJECT LIFE CYCLE 7
Training
Integration
Thermal Test
QA / QC Assembly
Order Parts
Inspect/Test
• Parts procurement– Test that parts satisfy flight
requirements before assembly
• Assemble hardware & software subsystems– Training may be required for particular assemblies
– Fabricate component with qualified parts
– If part fails initial inspection and testing, return to assembly for rework / fixing
– If part fails thermal testing return to assembly for rework / fixing
• Once complete move to integration
Implement construction of flight components
THE INTEGRATION PHASE
Make sure all parts fit together, if not then rework
Make sure power system is delivering proper voltage and current
Connect electronics and sensors
Install software and run
Fix issues before proceeding to system testing
LSU 01/18/2005
PROJECT LIFE CYCLE 8
Fit Check
System Testing
Integrate Fix
Test
Subassemblies are put together to make the final package
THE SYSTEM TESTING PHASE
Payload flight certification
LSU 01/18/2005
PROJECT LIFE CYCLE 9
Functional Test
FRR
Fix
Calibration
Thermal Test
Pressure Test
Shock Test
Check Calibration
• Integrated payload must first be fully functional
• Calibration values are determined– Sensors, ADC gain, timing
• Payload must function correctly during thermal, pressure & shock testing– If not, fix and begin again– If OK, then validate calibrations
• Test and test data must be documented
• Proceed to Flight Readiness Review
MISSION OPERATIONS & DATA ANALYSIS (MO&DA)
Mission Operations plan includes the following
Sequence of operations to prepare payload for vehicle integration
Sequence of operations to prepare payload for launch Flight profile requirements Operations, commanding, contingencies during flight Recovery handling and operations
Data Analysis plan describes what happens to the flight data
Flight data handling, processing and analysis sequence Specify data required from vehicle
LSU 01/18/2005
PROJECT LIFE CYCLE 10
Operate payload during flight & obtain science results
PROCESS FLOW DURING LIFE CYCLE
Effort focus changes as a function of phase Design can be highly theoretical involving simulations and
calculations Development involves “experiments” and testing concepts
to gain information necessary for the design Fabrication, Integration, and System testing requires skilled
technical help to realize the design in hardware and software
MO&DA requires “scientists” to direct the proper use of the payload and to turn the data into science results
Resource needs and costs changes as a function of phase
Design requires no hardware and few personnel Development costs increase a bit with some prototyping Major cost in personnel and hardware is in fabrication,
integration and testing MO&DA drops down to no hardware and few personnel
LSU 01/18/2005
PROJECT LIFE CYCLE 11
PROJECT RISK MANAGEMENT
“The essence of project management is risk management”
LSU 01/18/2005
PROJECT LIFE CYCLE 12
• Probability of a disaster decreases during the life of a project
• Cost to recover from a problem increases during the project
Catch & correct problems early!
PROJECT MILESTONES
There are three major reviews during the project
Preliminary Design Review (PDR)Follows design phase
Critical Design Review (CDR)Follows development phase
Flight Readiness Review (FRR)Prior to flight
The team must prepare written documents and oral presentations for each review
LSU 01/18/2005
PROJECT LIFE CYCLE 13
PRELIMINARY DESIGN REVIEW (PDR)
The PDR should cover results from your design phase including:
Goals & objectives Preliminary System design Concept hardware & software design Tasks, schedule, resource needs, long-lead items Preliminary risk assessment & management plan
Should show that you have “thought the problem through”
Include written document and oral presentation Format of document will be discussed in Lecture 8
A member of the LA ACES Project will attend and participate in the PDR
LSU 01/18/2005
PROJECT LIFE CYCLE 14
CRITICAL DESIGN REVIEW (CDR)
The CDR should cover results from your development phase including:
Resolving issues identified during the PDR Prototyping results and “proven” designs Completed system design and defined interfaces Finalize tasks, schedule, procedures and costs Updated risk assessment & management plan Preliminary MO & DA plan
Determines whether you are ready to begin building your payload
Include written report and oral presentation
Precise date for CDR should be identified during PDR
LSU 01/18/2005
PROJECT LIFE CYCLE 15
FLIGHT READINESS REVIEW (FRR)
The FRR reviews all aspects of your payload Documentation of as-built configuration Is payload safe? Will payload perform properly? Does payload satisfy the flight constraints?
The FRR will determine whether you are allowed to attach your payload to the flight vehicle!
Written FRR document sent to LA ACES Project 2 weeks before flight
Oral FRR presentation during the launch tripDetails about what is expected during the
FRR are provided in Ballooning Unit, Lecture 5
LSU 01/18/2005
PROJECT LIFE CYCLE 16
PRELIMINARY LSU 2005 SCHEDULE
Payload Concept January 25
PDR February 17
CDR (specify at PDR) (March 24)
FRR Document May 9
Launch Trip May 22 – 26FRR Defense May 23Launch, Flight Ops May 24Data Analysis May 25Science Presentation May 26
LSU 01/18/2005
PROJECT LIFE CYCLE 17