The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Mar 31, 2015

Download

Documents

Arely Hoo
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 2: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

The PREM project, Tranylvania.2003-2006.

INTBAU participation and contribution.

The genesis of INTBAU Romania.

Page 3: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 4: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

The fortified church.

Viscri - Deutch Weiskirch, 1280. © Riksantikvaren.

Page 5: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Copsa Mare –Grosköpisch 1320-1400. © Riksantikvaren

Page 6: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Overview of Biertan - Bierthälm, © H. Fabini, Saxon Churces.

Biertan - Bierthâlm, 16th century, UNESCO World heritage site. © Riksantikvaren

Page 7: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Törzburg - Bran

© Riksantikvaren

Page 8: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Törzburg - Bran

http://members.chello.at/freshminds/sbneu/index.htm

Page 9: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

PREM project – 3 tracks

• Track 1• 32 houses finished. Another 15 houses have

been partially repaired or the work is in progress. 8 training courses were held and 31 workers trained. A training venue is established (INTBAU).

• Track 2.• Model farm Laslea. Fully renovated, equipped,

staffed and operational as of 2005. Courses and training as of 2004.

Inner Laslea valley. © Riksantikvaren

• Track 3.• 3 working seminars, cum architect student competition, organised by the

municipality of Medias. • In the Municipality of Laslea 2 workshops were organised by INTBAU Scandinavia

and was the start of INTBAU Romania. The first concerned development and plans for Laslea village The second focused on the wish to develop agro tourism by offering accommodation and sightseeing in the municipality and the close environment (which includes the 2 UNESCO World Heritage Sites, Biertan and Sigishoara).

Page 10: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

THE MUNICIPALITY OF LASLEA. THE LASLEA VILLAGE.

Page 11: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 12: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 13: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Houses completely restored / repaired in project periodHouses completely restored / repaired in project period

Del 1.

Page 14: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Del 2.

Page 15: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 16: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 17: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 18: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Village workshop - charrette

• Why did we need a village workshop?– Things were moving slowly at the Town Hall– If we could get no input from the municipality we

would get it by our own.

• Why did we invite INTBAU Scandinavia to organise this work shop?– The project architect was Mr. Arne Sødal, member of

INTBAU Scandinavia.– Intbau Scandinavia proposed to organise the WS. It

was good value for money.– The quality turned out to be excellent.

Page 19: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

The long term consequences of involving INTBAU?

• Mr. Sødal and Mr. A. Engh organised the workshop.• The need for a training venue and office became

evident.• The first steps towards a rental agreement for House

344 was made. Mr. A. Sødal, Mr. A. Engh, A. Neag, have the contract with the owner.

• The paperwork to start INTBAU Romania was set in montion. The genesis of INTBAU Romania was started.

• Many students were recuited from the Medias workshops / architect competitions.

• Mr. A. Sødal, Mr. A. Engh pushed this project forward on their own initiative.

Page 20: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

The traditional house

Page 21: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

The modern but traditional house.

Page 22: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

A Roma settlement, Laslea.

Page 23: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

A Roma settlement, Laslea.

• Figure 5. Proposed development low cost social housing - overview.

• Development of Node 2. • Northern side of village, at entry from turnoff from main road.• Presently site is makeshift gypsy settlement. To the right a run down

former workers housing block. Can with minor financial means be brought up to minimum standard.

• Plan for low cost communal houses for the socially disabled as presently set in motion by the by Municipality. Target, bring social hosing, improved sanitary conditions; i.e. washing facilities.

• Figure 6. Detailed view of upgraded workers flats at north end of social housing village proposed development

Page 24: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

A Roma settlement, Laslea.

Page 25: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Proposals for upgrade and safeguard of buildings; court between Hospital and the new Saxon church.

One of the nodes is the complex of House of Culture (behind church), the Saxon Church; the old tower and the hospital.

Results to be achieved with a minimum of investments and use of local manpower.

Page 26: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

court between Hospital and the new Saxon church.

Renovation of place outside the church.

Page 27: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

court between House of Culture and 12 century fortified

tower.

© Riksantikvaren / INTBAU

The complex of the old tower, Saxon church and House of Culture is proposed restored and a new building added. New building in same emplacement as old demolished church. Site of demolished church picture on left above, new building drawing to the right.. The new building and the whole complex could house a youth hostel, a restaurant, activity rooms for youth activities, a booking service for agro-tourism, etc. The new building also serves as support to the tower, which is badly in need of restoration.

Page 28: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Figure 9. River crossing and junction.

Bridge, open air water delivery and washing / facilities improved.

Communal / public shower, permanent market with stalls are new elements .

Area cleaned up. Market stalls above bridge on right bank. Market area presently a vacant lot. Such facility requested by population.

© INTBAU , Riksantikvaren.

Page 29: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Figure 11. Proposal 2. New building matching in proportions in empty lot

Comments: On the traditional but modern.

Page 30: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Municipality of Medias - Mediasch

Page 31: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

The historic urban planning seminars with the Municipality

• 2003 – the historic center square and the new market• 2004 – historic court yards and facades, • 2005 – The historic centre; the old monastery, the

medieval walls

Page 32: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Winning model from architect student competition Franz

Ferdinand place, Medias, May 2003

Page 33: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Area of East tower and fortification wall. Medias, May 2005.

© T. Nypan / Riksantikvaren

Page 34: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

What we did not like or want

Page 35: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

More from the INTBAU work.

Page 36: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Typoplogy and intervention studies.

Example of typoplogy and intervention studies. © INTBAU, Riksantikvaren

Page 37: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Typoplogy and intervention studies

Example of typoplogy and intervention studies. © INTBAU, Riksantikvaren

Illustrations from planning: Map Neudorf and Floresti with house types indicated in colours. © INTBAU, Riksantikvaren

Page 38: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Typoplogy and intervention studies.

Page 39: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 40: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Building rehabilitation.

Page 41: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

INTBAU, establishing a permanent training venue

• Laslea House 344 future training centre, MET INTBAU joint restoration works started fall 2005.

•© Riksantikvaren

Page 42: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

INTBAU training venue, 2006.

Page 43: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

INTBAU training venue, 2006.

Now used for INBAU training seminars. Last in September 2007.

Page 44: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Rehabilitation method - Work priority definitions

Developed by Riksantikvaren and architect. Mr. A. Sødal

category

Starting condition house / property

Relevant interventions – order of priority

C 1. Good maintenance condition. Only normal yearly maintenance work needed

Front facades, drainage, down pipes, gate, stucatures,

C 2. poor maintenance condition, but suffer no structural damages.

1. Damaged building elements: roofs, drainage, down pipes, gate, side walls, windows etc.

2. Esthetical elements: painting facades, restoring front façade stucature.

C 3. poor maintenance condition and suffer from structural damages.

1. Repair of structural damages (fallen down roof, falling out of fundaments, caving in of cellar vaults, cracking of facades and long term damages caused by moisture and root).

2. Repair of other damaged building elements: : roofs, drainage, down pipes, gate, side walls, windows etc.

3. Restoration of esthetical elements (painting of facades, front façade stucature).

C 4. in bad need of attention and maintenance to arrest the (rapid) and advanced decay through existing damages to the house.

Only ‘arresting actions’ are applied. The objective is to arrest further decay of the building fabric to safeguard house for future repairs; C3.intervention.

Page 45: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Building rehabilitation.

Training and creating employment. Creating skilled manpower for building rehabilitation.Distributing income and fostering local development. © Riksantikvaren

Page 46: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Right: Courtyard before work. Left: A finished court-yard. © Riksantikvaren

Page 47: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Priests house.

Before work May 2002 © MET September 2003 © Riksantikvaren New gate and entry door. Down pipes repaired, 2006.

Page 48: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Street row traditional houses.

Page 49: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Street row traditional houses.

Page 50: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

New tendencies

Page 51: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

New tendencies

Page 52: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

INTBAU Workshop on eco-tourism and cultural heritage

1. The trekking group

2. A group mapping interesting events

3. A group mapping interesting sites

4. A group looking at cultural and natural heritage sites and documenting a village profile based on the findings

Page 53: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

Walking routes drawn up during the workshop; illustrates the need for detailed topographical

maps.

Page 54: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.
Page 55: The PREM project, Tranylvania. 2003-2006. INTBAU participation and contribution. The genesis of INTBAU Romania.

E N D.