Page 1: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

The Path to Running CLAS12 BONuS12

Latifa ElouadrhiriAugust 21, 2015

Page 2: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

2

Outline

• CLAS12 Construction Status

• Project Schedule and Tentative Run plan

• The path to running BONuS12

Page 3: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

3

12 GeV Upgrade Project

New Hall

Add arc

Enhanced capabilitiesin existing Halls

Add 5 cryomodules

Add 5 cryomodules

20 cryomodules

20 cryomodules

Upgrade arc magnets and supplies

CHL upgrade

Completion of the 12 GeV CEBAF Upgrade was ranked the highest

priority in the 2007 NSAC Long Range Plan.

Upgrade is designed to build on existing facility: vast majority of accelerator and experimental equipment have continued use.

Maintain capability to deliver lower pass beam energies: 2.2, 4.4, 6.6….

Project Scope (~95% complete): •Doubling the accelerator beam energy - DONE•New experimental Hall D and beam line – DONE•Upgrades to Experimental Halls B & C (89% & 86%)

TPC = $338M

Page 4: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

4

CLAS12Base equipmentForward Detector (FD)

- TORUS magnet (6 coils)- HT Cherenkov Counter - Drift chamber system - LT Cherenkov Counter - Forward ToF System- Pre-shower calorimeter - E.M. calorimeter

Central Detector (CD)- SOLENOID magnet - Barrel Silicon Tracker - Central Time-of-Flight

Beamline- Targets- Moller polarimeter - Photon Tagger

Upgrade to base equipment - MicroMegas

- Central Neutron Detector - Forward Tagger - RICH detector (1 sector)- Polarized target (long.)

- BONus12

MM

CND

http://www.jlab.org/Hall-B/clas12-web/4

Page 5: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

5

CLAS 12 - Central Detector

Integration of BoNus in CLAS12/CD requires early coordination with technical team.

Page 6: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

6

Status of Hall B

Forward CarriageFTOF1a, FTOF1b, PCAL and EC essentially operational 2+ years prior to scheduled beam commissioning.

Beam Line InstrumentationCommissioned during HPS run up to Faraday cup, BPMs, harps, halo counters.Additional beam line components to be installed beginning 10/2015

TORUS Magnet Installation6 coils and 6 pairs of hex beams installed in Hall Spare coil cryostated and factory disassembledFull Torus commissioned and field mapped 7/2016. SOLENOID Magnet 2nd of 5 coils in fabricatedDelivery of Magnet to JLab ~5/2016Expected to be operational ~8/2016

Page 7: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

CLAS Collaboration Meeting 6/17/2015 Page 7

Hall B: Detector Progress

FTOF 1-a, 1-b Installed(USC)

Drift Chambers(ODU, ISU, JLab)

Assembled CTOF Counters Being Tested

PCAL Installed(JLab, OU, W&M, NSU)

SVT (Jlab and FNAL)

Complete

Complete

Complete

LTCC-1 with First Set of Mirrors

SVT-Mechanical integration completed!

Page 8: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

CLAS Collaboration Meeting 6/17/2015 Page 8

SVT- Integration and Alignment Complete

Page 9: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

9

Key Dates

Hall Key Event Projected Date

B Torus 1st Coil Cold Mass Arrived November 2014

B Torus 6th Coil in Cryostat Done June 2015

B Torus Installation October 2014 (‘spit’) – May 2016

B Solenoid Coil Winding March 2015 – November 2015

B Solenoid Arrives May 2016

B Detector Commission with Beam December 2016

Page 10: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

10

Hall B Schedule

Torus Assembly, Install + Test

Solenoid Install + Test

8 months to CD-4B(as of 2-June)

Software readyCalibration readyDocumentation readyCommissioning readyFirst experiment ready

Today

Page 11: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

11

Proposal Physics Contact Rating Days Group New equipment Energy Run Group Target

E12-06-108 Hard exclusive electro-production of π0, η Stoler B 80

139

RICH (1 sector)Forward tagger

11

A

F. Sabatié

liquidH2

E12-06-112 Proton’s quark dynamics in SIDIS pion production Avakian A 60

E12-06-119 Deeply Virtual Compton Scattering Sabatie A 80

E12-09-003 Excitation of nucleon resonances at high Q2 Gothe B+ 40

E12-11-005 Hadron spectroscopy with forward tagger Battaglieri A- 119

E12-12-001 Timelike Compton Scatt. & J/ψ production in e+e- Nadel-Turonski A- 120

E12-12-007 Exclusive φ meson electroproduction with CLAS12 Stoler, Weiss B+ 60

E12-11-005a Photoproduction of the very strangest baryon Guo NR (120)

E12-07-104 Neutron magnetic form factor Gilfoyle A- 30

90

Neutron detectorRICH (1 sector)Forward tagger

11 B

K. Hafidi

liquidD2 target

PR12-11-109 (a) Dihadron DIS production Avakian

E12-09-007a Study of partonic distributions in SIDIS kaon production Hafidi A- 30

E12-09-008 Boer-Mulders asymmetry in K SIDIS w/ H and D targets Contalbrigo A- 56

E12-11-003 DVCS on neutron target Niccolai A 90

E12-06-109 Longitudinal Spin Structure of the Nucleon Kuhn A 80

185

Polarized targetRICH (1 sector)Forward tagger

11 C

S. Kuhn

NH3ND3E12-06- 119(b) DVCS on longitudinally polarized proton target Sabatie A 120

E12-07-107 Spin-Orbit Correl. with Longitudinally polarized target Avakian A- 103

PR12-11-109 (b) Dihadron studies on long. polarized target Avakian

E12-09-007(b) Study of partonic distributions using SIDIS K production Hafidi A- 80

E12-09-009 Spin-Orbit correlations in K production w/ pol. targets Avakian B+ 103

E12-06-106 Color transparency in exclusive vector meson production Hafidi B+ 60 60 11 D Nuclear

E12-06-117 Quark propagation and hadron formation Brooks A- 60 60 11 E Nuclear

E12-06-113 Free Neutron structure at large x Bueltman A 40 42 Radial TPC 11 F Gas D2

E12-14-001 EMC effect in spin structure functions Brooks B+ 55 55 Pol. LiH target 11 G LiH

TOTAL run time 1466 (1586) 631

Hall B CLAS12 experiments – run groups

11

Page 12: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

12

Proposal Physics Contact Rating Days Group Equipment Energy Group Target

C12-11-111 SIDIS on transverse polarized target Contalbrigo A 110

110 Transverse target

11 G HDC12-12-009 Transversity w/ di-hadron on transvere target Avakian A 110

C12-12-010 DVCS with transverse polarized target in CLAS12

Elouadrhriri A 110

All transverse target proposals 330 110

C12-11-006 Heavy Photon Search at Jefferson Lab (HPS) Jaros A 180 180 New setup in alcove

2.2, 6.6

H Nuclear

E12-11-106 High Precision Measurement of the Proton Charge Radius

Gasparian A 15 15 Primex 1.1, 2.2

I H2 gas

Beam time request from CLAS12 C! experiments + non-CLAS12 experiments 525 305

Beam time from approved CLAS12 experiments (from previous page) 1466 631

TOTAL Beam time for all Hall B experiments 1991 936

C1 approved proposals & non-CLAS12

Optimistically, we may run 90 PAC days per year. To run all experiments as run groups with full beam time will require 936/90 ≈ 10 years.

12

Page 13: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

13

Run Group Schedule – Tentative 6/2015Run Group Days 2015 2016 2017 2018 2019 2020 2021 Remai

nAll Run Groups 936 CND MM

FTBONUS

RICHLong. PT Trans. PT 525 411

HPS 180* 3 5? 10 20 135

PRad 15* 15 ---

CLAS12 KPP 15

RG-A (proton) 139* 20 40 79*

RG-F (BoNuS) 42* 40 2

RG-B (deut.) 90* 40 50*

RG-C (NH3) 120 20 40 60

RG-C-b (ND3) 65 35 30

RG-E (Hadr.) 60 25 10 25

RG-G (TT) 110* 55 55

RG-D (CT) 60 35 25

RG-K (LiD) 55 55 ---

13

Page 14: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

14

Project Phases

• Science – Physics Requirements• R&D – Finalizing detector components choices• Conceptual Design - CDR• Engineering Design – TDR with well defined detector specifications• Project construction• Detector assembly • Commissioning • Operation and maintenance

Simulation & Reconstruction is an important part of every phase of the project.

Page 15: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

15

Project Execution

• Science document with well defined science requirements• Technical Design Report (TDR) and detector specification• Baseline cost and schedule – Resource loaded schedule with clear dependencies• Labor by skill• Procurement with BoE• Space & Infrastructure• Milestones• QA/QC• Risk and Risk mitigation document• Software: simulation, reconstruction & calibration• Geometry and commissioning document• Organization with well defined roles and responsibilities with Control Change board• Project Tracking/Reviews

– BoNus collaboration conducted reviews and meeting– Hall B reviews– Physics Division Experimental Readiness Reviews– Funding agencies-report/reviews

Page 16: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

16

Path Forward for CLAS12 BoNus12 Project

• Detector Technology choice: October 2015 to be presented at the CLAS12 workshop October 19-20, 2015

• Produce Conceptual Design Report with estimated cost and schedule, to be presented to Hall B management by December 2015.

• Hall B management to conduct first review December 2015/January 2016

• Form a run group of experiments: what other science can be done with BoNus12? Write the document - important for the final detector optimization

Page 17: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

17

Path Forward for CLAS12 BoNus12 Project

• Detector Technology choice: October 2015 to be presented at the CLAS12 workshop October 19-20, 2015

• Produce Conceptual Design Report with estimated cost and schedule, to be presented to Hall B management by December 2015.

• Hall B management to conduct first review December 2015/January 2016

• Form a run group of experiments: what other science can be done with BoNus12? Write the document - important for the final detector optimization

• BoNus 12 is CLAS12 detector, so having dedicated group from BoNus group involved with CLAS12 software and the preparation and running of the first CLAS12 experiment is critical to the success of BoNus12 Project.

Page 18: The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015.

18

Looking Forward to an Exciting Project

THANK YOU