The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008

Page 2: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Existing riffle constructed by ODOT

Conceptual Design

Illustration of

Restoration Site by Matt Horvat of TMACOG

At the request of

the Village of Ottawa Hills we did not work in

this bend even

though the

vertical bank is 7 ft tall and the water over 7 ft deep!!

US

Pro

ject

Lim

it

DS

Pro

ject

Lim

it

This project will

encompass the bends

immediately upstream

and downstream of the former

dam site

Page 3: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

The Ottawa Hills Dam Decommissioning Project

The dam was removed by Ohio-DOT in November 2007.

The project described in this PowerPoint is designed to reduce bank erosion and protect public

infrastructure (two roads), create aquatic & riparian habitat, improve streamside vegetation, assist with improving the riparian area, provide

benches & stepping stones for public stream enjoyment and access, and still have the existing

mowed floodplain recreation areas for public use!

Page 4: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.
Page 5: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

OHIO DOT REMOVING THE

SECOR ROAD DAM NOV-DEC 2007

Page 6: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking from left bank at the Secor Road dam.

OTTAWA R-DAM REMOVAL @ OTTAWA HILLS-PIX BY MATT HORVAT-2007

Page 7: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Typical condition US of the Secor Road dam.

OTTAWA R-DAM REMOVAL @ OTTAWA HILLS-PIX BY MATT HORVAT-2007

Page 8: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking from left bank @ trackhoe removing the dam.

OTTAWA RIVER-DAM REMOVAL @ OTTAWA HILLS-PIX-LAWRENCE-2007

Page 9: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US @ trackhoes removing dam

OTTAWA RIVER-DAM REMOVAL @ OTTAWA HILLS-PIX-LAWRENCE-2007

Page 10: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US. Dam out, right bank sheetpile out, concrete riffle in. Left bank sheetpile will stay.

OTTAWA RIVER-DAM REMOVAL @ OTTAWA HILLS-PIX-HORVAT - 2007

Page 11: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

PRE-PROJECT PHOTOS STARTING FROM

UPSTREAM TO DOWNSTREAMby Dave Derrick

AUGUST 20, 2008

Page 12: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS. High velocity current is eroding the right bank, then crosses over & erodes the left bank in the crossing. Note

how deep Matt is. Matt went in over his head when he ventured near the right bank. At the request of the Village of

Ottawa Hills, the right bank was not stabilized.

PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008

Page 13: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ left eroded bank in the crossing & the upper portion of the US project bend.

PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008

Page 14: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US @ the lower end of the US project bend

PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008

Page 15: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

At the former dam site, looking US into the US bend

PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008

Page 16: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ the DS project bend. Hill Ditch tributary comes in just US of the bend.

PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008

Page 17: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ the DS project bend & the Secor Road bridge.

PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008

Page 18: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS. The protection will tie into the existing bridge abutment protection right here.

PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008

Page 19: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

THE PLAN

Page 20: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.
Page 21: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Existing riffle constructed by ODOT

Conceptual Design

Illustration of

Restoration Site by Matt Horvat of TMACOG

At the request of

the Village of Ottawa Hills we did not work in

this bend even

though the

vertical bank is 7 ft tall and the water over 7 ft deep!!

US

Pro

ject

Lim

it

DS

Pro

ject

Lim

it

This project will

encompass the bends upstream

and downstrea

m of the former dam

site

Page 22: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

EQUIPMENT

Page 23: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

The Cat 330 tracked back hoe with a 4 ft wide bucket, 25 ft reach, weight about 70,000 pounds

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 24: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

STONE & STONE STAGING

Page 25: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

SUITABLE STONE

Stone used for keys and LPSTP was a well-graded, self-adjusting, self-filtering Class A Stone with a size of 18” to 36” on the “B” axis. Stone for the Bendway Weirs &

Traffic Control Stones was a specially produced armor stone that varied from 2’ by 2’ by 3’ to

4’ by 4’ by 5’.

Page 26: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Dumping “A”stone-18 to 36 inch sized stone

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 27: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Staged “A”-stone and armor stone

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 28: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

THE BEND IMMEDIATELY UPSTREAM OF THE FORMER

DAM LOCATION

Page 29: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Methodologies for the Upstream Bend

Traffic Control Stones with short Bendway Weirs

Vegetated keys

Transplanted clumps of shrubs

Hydraulic Cover Stones

Planned fall 2008: Container plantings of dogwoods, fast and slow growing shade trees, chokecherry, buttonbush, & other shrubs for food, pollinators, etc.

Page 30: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

A KEY HAS ONE MAIN JOB, TO CONNECT THE

RIVER TRAINING STRUCTURE TO THE REST

OF THE WORLD (DON’T LET THE STREAM GET BEHIND {FLANK} RIVER TRAINING STRUCTURES)

Page 31: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

CONSTRUCTION PHOTOS

by Dave Derrick & Matt Horvat

August 20-25, 2008

Page 32: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Detail for key

Cross-section for keywayFlow

Page 33: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking uphill at the dug key trench

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Flow

Page 34: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Detail for key

Place some stone & soil in the trench

Flow

Page 35: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Placing some graded “A” stone and soil in the trench

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Flow

Page 36: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Place Willow Poles against DS side of trench.

Detail for key

Flow

Page 37: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Placing willow poles in the key trench

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 38: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Key will be extended uphill where the hoe is parked

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Flow

Page 39: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Place the remainder of the stone in the trench

Detail for key

Flow

Page 40: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Placing “A” stone within 1 ft of the surface of the trench

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 41: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Choke stone with soil & water in.

Detail for key

Flow

Page 42: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Backfill with native soils.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 43: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Backfill and overfill with native soils, then compact

(some settling will still occur)

Detail for key

Flow

Page 44: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Compacting soil over key. Note poles on DS side of key

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 45: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

TRAFFIC CONTRO

L STONES

Page 46: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

WHAT IS THE LOWER LIMIT OF HARD

BANK PROTECTION?

AND MORE IMPORTANT, HOW

CAN WE REACH IT?

Page 47: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

TRAFFIC CONTROL STONES

(TCS) WITH SINGLE-STONE OR SHORT BENDWAY

WEIRS

Page 48: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Drawn by Matt Horvat, TMACOG

Traffic Control

Stones for the US project

bend

Page 49: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Drawn by Matt Horvat, TMACOG

Page 50: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Large stones (3 ft by 3 ft by 3 ft) designed to “kick” flow off the bank, must be keyed into the bed & bank, spaced 6 to 8 ft

apart, every 3rd one should be keyed into the bank. Every 3rd stone has a Single Stone or short Bendway Weir.

Traffic Control Stones with Single Stone Bendway Weirs

Key

Key

TCS

Key

TCS

SSBW

TCS

TCS

TCS

TCS

TCS

TCS

TCS

SSBW

SSBW

Page 51: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Willow, dogwood, & buttonbush Live Stakes & poles

were installed along with the TCS. Rooted stock plants will be installed this fall or spring

Traffic Control Stones with Single Stone Bendway Weirs

Key

Key

TCS

Key

TCS

SSBW

TCS

TCS

TCS

TCS

TCS

TCS

TCS

SSBW

SSBW

Page 52: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Track hoe digs a pit. Willow, dogwood, & buttonbush poles are placed around backside of pit

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 53: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ Traffic Control Stone being placed in pit

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 54: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ key, TCS, BW, & adventitious rooting poles

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

BW

TCS

TCS

TCS

TCS

TCS

Page 55: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.
Page 56: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

How Do Bendway Weirs Work? Water flowing over the weir is redirected at an angle

perpendicular to the longitudinal axis of the weir.

With weirs angled upstream the erosive flow (energy) is directed away from the outer bank and toward the inner part of the bend.

Strong secondary currents (helical flow) in bend are broken up.

A set of weirs are designed to act as a system to capture, control, and redirect current directions and velocities through the bend and into the downstream crossing.

Last weir in system can aim flow (and channel thalweg) where you need it.

Page 57: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ TCS. Hoe is stuck in unconsolidated muck

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 58: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ hoe filling tracks.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 59: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US @ the row of TCS @ the upper end of the bend.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 60: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US @ center of bend (impact area). No mature vegetation on bank, so TCS are placed closer together.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 61: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS toward the former dam location. Placing TCS

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 62: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US @ the TCS near the DS end of the bend.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 63: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US. Dense brush & trees make TCS placement difficult

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008

Page 64: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Resting rocks in the upper bend.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-2008

Page 65: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Raking, seeding, and spreading weed-free straw.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-2008

Page 66: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Spreading straw.

CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-2008

Page 67: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

THE UPSTREAM BEND

CONSTRUCTION IS COMPLETE

(let’s look from upstream to downstream)

Page 68: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

FROM THE OPPOSITE BANK

(inner bank), LOOKING AT THE

COMPLETED UPPER BEND

Page 69: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US @ US key, veg poles & transplants & TCS

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-08

Page 70: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking US @ TCS, Live Poles, Bendway Weirs, & Live Stakes

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08

Page 71: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking @ center of bend (impinging impact area)

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08

Page 72: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking across @ outer bend just DS of the apex (center).

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-08

Page 73: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ outer bank TCS, Bendway Weirs, & poles.

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08

Page 74: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS @ lower end of bend (dam sheetpile visible)

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08

Page 75: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08

Looking DS @ end of bend TCS, Poles, & Live Stakes.

Page 76: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

From the US crossing, looking DS into the project bend

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08

Page 77: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking DS into the impinging flow impact zone of the bend.

CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08

Page 78: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Ottawa River Dam Removal8-10-2009

UpdatePix & words by Matt Horvat, TMACOG

Page 79: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Increased public use

Pix & words by Matt Horvat, TMACOG

Page 80: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Pix by Matt Horvat, TMACOG

Page 81: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Left Bank in the spring

Bank protection stones and willow, dogwood, buttonbush stakes are visible

6-5-2009 photo, Horvat

Page 82: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

SIGNIFICANT PLANTING EFFORT

500 PLANTS INSTALLED THE WEEK OF JULY 27,

2009 ON BANKS & RIPARIAN AREAS

Photos & words by Matt Horvat

Page 83: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Another view of the same area - Left Bank in the spring

Bank protection stones and willow, dogwood, buttonbush stakes are visible

Pix & words by Matt Horvat, TMACOG

Page 84: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Close up, leafing of stakes is visible.

Stakes were installed when stones were placed in 8-2008

Pix & words by Matt Horvat, TMACOG

Page 85: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Materials to be used for restoration and stabilization

Photos taken week of 7-27-2009

Pix & words by Matt Horvat, TMACOG

Page 86: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Wetland and riparian species of shrubs will be placed to in-fill between the stabilization stones.

Nine-bark and buttonbush will be planted in the lowest areas.. They love having wet roots. Their roots will spread forming a dense network, holding the bank and soil during flood events.

Photos taken by Matt Horvat week of 7-27-2009

Page 87: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Some of the woody shrubs being staged for planting on a right bank. The shrubs will be staggered to maximize the benefit of their roots holding the soil.

Photos taken by Matt Horvat week of 7-27-2009

Page 88: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Floodplain area on the right bank being reforested.

The vegetated floodplain and riparian area will help to slow flood velocities and allow suspended soil to settle out as well as provide habitat and recreation opportunities.

Photos taken by Matt Horvat week of 7-27-2009

Page 89: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

An auger is used where possible to prepare the soil for the new plant. All bank areas will have to be hand planted.

Photos taken by Matt Horvat week of 7-27-2009

Page 90: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Site prep done with the 24” auger

Photos taken by Matt Horvat week of 7-27-2009

Page 91: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

One of the woody shrubs

Photos taken by Matt Horvat week of 7-27-2009

Page 92: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Photos taken week of 7-27-2009

Page 93: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Planting top of bank floodplain areas

Photos taken by Matt Horvat week of 7-27-2009

Page 94: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Looking downstream

Photos taken by Matt Horvat week of 7-27-2009

Page 95: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

LDB, just downstream of first key, new plantings of buttonbush, ninebark and elderberry visible at the bamboo stakes

Photos taken by Matt Horvat week of 7-27-2009

Page 96: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Ninebark

Photos taken by Matt Horvat week of 7-27-2009

Page 97: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Newly planted maple severely browsed, planting was only one day old

Photos taken by Matt Horvat week of 7-27-2009

Page 98: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Browsed Hackberry

Photos taken by Matt Horvat week of 7-27-2009

Page 99: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

One of the suspects

What deer like:•Opportunity•Maple•Hackberry•Everything else

Photos taken by Matt Horvat week of 7-27-2009

Page 100: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Smells bad enough, lets hope it works!

Photos taken by Matt Horvat week of 7-27-2009

Page 101: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

RDB, just upstream on the old dam on the inside bank. Note the buttonbush planted low along the bank

Photos taken by Matt Horvat week of 7-27-2009

Page 102: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

LDB, looking upstream toward key

Photos taken by Matt Horvat week of 7-27-2009

Page 103: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

LDB, looking upstream toward key

Stakes mark each plant location

Photos taken by Matt Horvat week of 7-27-2009

Page 104: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

RDB, upstream of dam and undercut high bank visible just beyond the sign at the locust tree.

Planted approx 750lf from dam upstream = 0.8 acre

Photos taken by Matt Horvat week of 7-27-2009

Page 105: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

RDB, nearest old dam

Photos taken by Matt Horvat week of 7-27-2009

Page 106: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

LDB, West of Secor Ave.

800 lf from dam upstream = 1 acre

Photos taken by Matt Horvat week of 7-27-2009

Page 107: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

LDB, looking upstream. Upstream key starts at big locust

Photos taken by Matt Horvat week of 7-27-2009

Page 108: The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008.

Documented watershed scale fish distribution changes due to dam mitigation/removal (first fish passage connectivity in 80+ years) !! Fish community above both Secor Dam (removed) and Highland Dam (mitigated) have significantly changed for the better. Least Darter are now distributed throughout the lower Ottawa River, presumably following the new conveyance of sand. I think I forwarded the picture of the juvenile Rainbow Trout we caught right? We caught the first juvenile Golden Redhorse I've found above the dam this fall. Furthermore, sunfish are abundant around Sylvania, which never happened before. The result of having sunfish and Redhorse has been a shift in dominance to less tolerant, lithophilic-spawning species.

I also talked to someone who lives by the Airport who has had white suckers in his ditch every spring since you put in the riffle at Highland. There have been other highlights, but you're probably all yawning with the fish talk by now :) Awesome part, most all this data was collected by undergraduates in our Ecology 3060 lab course (University of Toledo).Take home message: CONNECTIVITY = GOOD! From: Todd Crail