Top Banner
©The McGraw-Hill Companies, Inc. 2008 McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand
47

©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

Jan 05, 2016

Download

Documents

Dorthy Hill
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin

Chapter 14

Capacity: Matching Productive Resource to

Demand

Page 2: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-2

Learning Objectives

• Define capacity and distinguish it from capability.• Describe how capacity relates to value and profitability for B2C and B2B

transactions.• Describe how demand that varies from design capacity influences profitability.• Describe the role individual resources and constraints play in determining system

capacity.• Make the calculations necessary to create demand chase and level production

aggregate plans• Describe the information inputs and logic necessary for rough-cut capacity

planning.• Calculate required and available capacity for a rough-cut capacity plan.• Describe the information inputs and logic necessary for capacity requirements

planning.• Calculate required and available capacity for a capacity requirements plan.• Describe how yield management aids services in maximizing revenues.• Perform the calculations to determine the number of customers to overbook.

Page 3: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-3

• Capacity– The ability to produce at a given volume in a specified amount

of time.

– Being able to do “enough” of something to meet demand.

• When making products, capacity can be stored in the form of work-in-process and finished-goods inventory.

• For services, capacity usually can’t be stored.

Introduction: Matching Resource Availability to Market Demand

Page 4: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-4

• Capacity is defined in terms of a level of output per unit of time. – There must be enough capacity in each resource to meet demand.

Matching Resource Availability to Market Demand: Capacity Defined

Page 5: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-5

• Capacity can be provided in various ways– Mixing production and storage capacity

– Demand of 1,000 units is to be met in ten days

Matching Resource Availability to Market Demand: Capacity Defined

Page 6: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-6

• Capacity affects value. What value attributes do customers seek?

Cost Style/fashion

Quality Ethical issues

Response time Technology

Dependability of delivery Flexibility

Convenience Personalization

• When capacity can’t meet demand, customers may choose to go elsewhere rather than wait.

• A capacity shortage creates waiting lines and impacts response time, dependability of delivery, and flexibility.

• A backlog is a queue of orders waiting to be processed (another term for a waiting line).

Capacity and Value

Page 7: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-7

• Excess (protective) capacity can serve the same purpose as inventory– Protect against surges in demand.

– More flexible than buffering with finished goods

• Excess capacity is often in short supply– Viewed as an investment in resources that aren’t providing a financial

return.

– Yet it provides a long-term benefit because it improves various time-related value attributes

Capacity and Value

Page 8: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-8

• Design capacity– The capacity a facility is designed to accommodate on an ongoing

basis.

• Best operating level– The level of demand or “load” on a system that results in the lowest

cost per unit produced or processed.

– Going either above or below the best operating level for long periods has a negative financial impact

The Financial Impact ofCapacity Decisions

Page 9: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-9

• Below best operating level (A and E):– Lower revenue

– Underutilized capacity drives up unit costs and/or forces layoffs

Exhibit 14.3 Demand and Design Capacity Relationships

The Financial Impact ofCapacity Decisions

Page 10: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-10

• Above best operating level (C):– High revenue and lower unit cost (both good)

– Equipment could wear out as maintenance is postponed

– Have to pay overtime and/or hire and train temps

– Possible decline in quality, increase in safety problems

The Financial Impact ofCapacity Decisions

Exhibit 14.3 Demand and Design Capacity Relationships

Page 11: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-11

• The overall capacity of a system is dependent on all of the resources used to create it.

• Constraint– Anything that inhibits a system’s progress toward its goals.

– In a production system, a constraint is called a bottleneck.

• Constraint management– An integrative framework that attempts to maximize the

system’s accomplishment of its goals by managing the system’s constraint.

Individual Resource Influence onSystem Capacity

Page 12: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-12

• Step 3 is slower than the rest. It is the constraint in the system.• Characteristics of constrained systems

– Resources don’t set their own utilization rates

– Time lost by the constraint is lost (and can’t be made up) to the entire system

– Constraints must be utilized 100% of the time to maximize output

– If a constraint breaks down, the result is the same as shutting down the entire system.

Exhibit 14.4 Example of a Constrained System

Individual Resource Influence onSystem Capacity

Page 13: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-13

– Increasing output of a non-bottleneck doesn’t help the system. It just builds up inventory at the bottleneck.

- A system can be thought of as analogous to a chain. A chain is only as strong as its weakest link.

Individual Resource Influence on System Capacity: Constraints

Page 14: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-14

• A business can constrain an entire supply chain. The supply chain can be thought of as a “chain of chains”.

Exhibit 14.7 Weakest Link in a Supply Chain

• Constraints don’t have to be in production resources or machines. They can occur in transportation, distribution, or storage.

A Broader View: Supply Chain Capacity

Page 15: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-15

• Aggregate demand– The total demand for all products and services– Often utilizes a “pseudoproduct” or fictional “representative” product

• Two Alternatives for Aggregate Planning:– Demand Chase: Adjusting capacity to meet varying demand; hiring and

firing workers– Primary cost is hiring and firing costs– Loss of labor quality

• Level Production: Building up and using from inventory, while keeping workforce level– Primary cost is inventory carrying cost

The Demand-Capacity Match in Manufacturing

Page 16: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-16

• Step-by-Step: Demand Chase Aggregate Planning– Convert units required for each time period to labor hours by multiplying

number of units by labor hours required per unit.

– Compute number of workers required per period by dividing number of labor hours by the number of hours worked by each worker (rounding up).

– Hires are required if the number of workers needed in a time period is greater than the number of workers needed in the previous period. The difference between the two is the number of hires.

– Fires or layoffs are required if the number of workers needed in a time period is less than the number needed in the previous time period. The difference between the two is the number of fires.

– Calculate hiring costs by multiplying number of workers hired by cost of hiring a worker. Calculate firing costs the same way.

– Calculate total plan costs by summing hiring and firing costs.

The Demand-Capacity Match in Manufacturing

Page 17: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-17

• Example 14.1:

– Labor per unit = 1.2 hours

– 40 hour week (160 hours per month)

– Hiring cost = $475

– Firing cost = $400

– Initial staffing = 11 employees

The Demand-Capacity Match in Manufacturing: Demand Chase Example

Page 18: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-18

1,400 * 1.2 = 1,680 hours required

Example 14.1:

Labor per unit = 1.2 hours

40 hour week (160 hours per month)

Hiring cost = $475

Firing cost = $400

Initial staffing = 11 employees

The Demand-Capacity Match in Manufacturing: Demand Chase Example

Page 19: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-19

The Demand-Capacity Match in Manufacturing: Demand Chase Example

1,680 / 160 = 10.5 workers requiredRound to 11 workers in order to meet demand

Page 20: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-20

Total hiring cost = $6,650 Total layoff cost = $4,400Total plan cost = $11,050

The Demand-Capacity Match in Manufacturing: Demand Chase Example

Page 21: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-21

• Step-by-Step: Level production aggregate planning.– Divide total expected demand for the planning horizon by the number

of days to get number of units to produce each day

– Multiply the number of units produced each day by the number of labor hours per unit to get labor hours required per day

– Divide labor hours required per day by number of hours each worker works in a day to get number of workers required

– Get average level of inventory for each month by averaging beginning and ending inventory.

– Get inventory carrying cost by multiplying monthly average inventory by monthly carrying cost per unit

– Total cost is the sum of the monthly inventory carrying costs plus any initial hiring and firing costs

The Demand-Capacity Match in Manufacturing

Page 22: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-22

Example 14.2• Labor = 1.2 hours per unit• 40 hour week (8 hours per day)• Hiring cost = $475• Layoff cost = $400• Initial staffing = 11 employees • 253 working days per year• Total forecast production = 21,320 units• Carrying costs = $12 per unit per month

(85 units * 1.2 hours)/8 hours per day

12.75 13 workers on staff

85 units per day

The Demand-Capacity Match in Manufacturing: Level Production Example

Page 23: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-23

Hire two workers for $950 Carrying cost = $91,890Plan cost = $92,840

The Demand-Capacity Match in Manufacturing: Level Production Example

Page 24: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-24

• It is unlikely that either the demand chase or level production aggregate plan will be totally acceptable.

• Best solution is some hybrid of using inventory and adjusting the level of the workforce.– Adjust workforce levels periodically and level the production between

adjustments

The Demand-Capacity Match in Manufacturing

Page 25: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-25

• Capacity-demand relationships must be addressed on a detailed level in the short term.– Goal is to determine the load on firm resources– Capacity planning processes are typically integrated with dependent

demand inventory- with material requirements planning (MRP)

• Bill of capacity: A statement of the time required on each resource needed to produce a product.

• Rough-cut capacity planning: An approach used in manufacturing that uses the master production schedule to provide the quantity of units that must be produced.

Detailed Capacity Planning in Manufacturing

Page 26: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-26

• Step-by-Step: Rough-Cut Capacity Planning– Calculate capacity required (in hours) for each work center for each

week by multiplying the quantity of items to be produced in each week (from the master production schedule) by the time it takes on that particular work station to produce them

– Calculate available capacity (in standard hours) at each work center by multiplying the actual hours available in a week by the historical utilization and by the historical efficiency

– On a weekly basis, compare required capacity to available capacity, for each work station

Detailed Capacity Planning in Manufacturing

Page 27: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-27

• Example 14.3– A manufacturer of crates wants to create a rough-cut capacity

plan for one of their lines (model 2440). The utilization rate for all machines averages 93%. Efficiency is at 95%. Develop a rough-cut capacity plan using data from master production schedule and the bill of capacity.

Rough-Cut Capacity Planning Example

Page 28: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-28

• First, multiply the number of units you will produce in each week (from the MPS) by the time one unit takes at each work center (from the bill of capacity).

Exhibit 14.15 Bill of Capacity

Exhibit 14.14 Master Production Schedule

210 * 0.08 = 16.8

Do this for all the numbers to create a table

Rough-Cut Capacity Planning Example

Page 29: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-29

• The table below shows capacity required at each work center, each week.

Exhibit 14.16 Capacity Required

Rough-Cut Capacity Planning Example

Page 30: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-30

• Multiply actual hours available by the historical utilization rate for the work center and also by historical efficiency to get capacity available, in “standard hours”.

Exhibit 14.17 Capacity Available

Rough-Cut Capacity Planning Example

Page 31: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-31

• Combine the capacity required and capacity available tables for easy comparison.

Exhibit 14.18 Rough-cut Capacity Plan

Rough-Cut Capacity Planning Example

Page 32: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-32

• Rough-cut capacity planning is a quick but inaccurate analysis.– It is frequently used to check if the MPS is feasible

– Ignores on-hand inventory

– Ignores possibility of production occurring in weeks before the MPS shows a product to be due

• Capacity Requirements Planning is more accurate.– Uses the planned releases from MRP- timing of production is more

accurate

– Accounts for inventory

Detailed Capacity Planning in Manufacturing

Page 33: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-33

• Step-by-Step: Capacity Requirements Planning– Using MRP logic, compute planned order releases for all components

– For each department or work station, identify the components that will utilize that work station

– Compute required capacity for each work station by multiplying quantity of a component (from planned order releases) by the time required per unit on that work station. Do this for each week

– Compute total capacity required on a work station for a given week by summing the time required for each of the components using it

Detailed Capacity Planning in Manufacturing

Page 34: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-34

• Example 14.4– A fly rod manufacturer wants to use planned order releases from MRP

to help plan for capacity. The manufacturer has three departments: Handle assembly, wrapping department, and finishing. The product structure of a fly rod is given below:

Capacity Requirements Planning Example

Exhibit 14.19 Product Structure for 9-foot 5-Weight Fly Rod

Page 35: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-35

• MRP logic generates the planned order releases:

• All the bottom-level components are purchased, so assembling these components into the butt and tip sections is what needs capacity.

Exhibit 14.20 Planned Order Releases

Capacity Requirements Planning Example

Page 36: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-36

• Multiply the time each section takes at each department by the planned order releases from MRP.

Exhibit 14.21 Routings for Components48 * 0.08 = 3.84

Exhibit 14.20 Planned Order Releases

Capacity Requirements Planning Example

Page 37: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-37

• Add butt and tip section capacities to get total required capacity per week per department.

Exhibit 14.22 Capacity Requirements Plan

Capacity Requirements Planning Example

Page 38: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-38

• Relationships between material and capacity planning within a generic production planning and control system:

Exhibit 14.23 Generic Manufacturing Planning and Control System

Detailed Capacity Planning in Manufacturing

Page 39: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-39

• For services, the load on capacity can’t be leveled by inventory. We must often smooth demand to smooth the load on capacity.– We use appointments, reservations, or pricing strategies to level demand.

• Services that have high fixed costs and little marginal cost for additional customers have developed more sophisticated approaches, such as yield management.

The Demand-Capacity Match in Services

Page 40: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-40

• Yield Management: An approach used in capital-intensive services that attempts to obtain maximum revenues through differential pricing, reservation systems, and overbooking.– Used in services with high fixed costs, low variable costs.

– Requires segmenting the customer base, using multiple price levels

The Demand-Capacity Match in Services: Yield Management

Page 41: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-41

• Overbooking: Taking more reservations than you have capacity.– Minimizing costs associated with “no-shows” when

reservations are used• Balance these costs with costs of not being able to serve a customer

(or having to serve them differently) when too many show up

– Common issue in high fixed cost service businesses and where “no-shows” are a problem

• Airlines

• Hotels

The Demand-Capacity Match in Services: Overbooking

Page 42: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-42

• Step-by-Step: Determining the Low-Cost Overbooking Policy.– Calculate percentage of the time each no-show condition occurs– Determine the cost of walking or bumping a customer and the

opportunity cost of a vacant room or seat– Identify an overbooking policy to evaluate. For each scenario under the

policy, determine the cost of the no-shows or bumping. If there are empty rooms, calculate the expected cost of that condition by multiplying the number of empty rooms by the cost per empty room by the probability of this condition occurring. Similarly, multiply number of customers bumped by the cost of bumping, by the probability of it happening. The cost of the plan is the sum of all bumping and empty room costs

– Repeat last step for any overbooking policies being evaluated, and pick the one with the lowest cost

The Demand-Capacity Match in Services: Overbooking

Page 43: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-43

• Example 13.5:– A hotel wants to use overbooking to minimize the cost of no-shows.

Over the past year it has had an average of 1.56 no-shows per day, at a cost of $89 each. It has calculated the cost of bumping a customer to be $110. No-show probabilities are given below. Find the best overbooking policy.

Exhibit 14.24 No-show History

The Demand-Capacity Match in Services: Overbooking Example

Page 44: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-44

• Overbooking by one results in a total cost of $101.38

Exhibit 14.25 Expected Costs of Overbooking by One

The Demand-Capacity Match in Services: Overbooking Example

Page 45: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-45

• Overbooking by two results in a total cost of $143.72

Exhibit 14.26 Expected Costs of Overbooking by Two

The Demand-Capacity Match in Services: Overbooking Example

Page 46: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-46

• Overbooking by one is the best policy: Expected cost is less than no overbooking, and less than overbooking by two.– There is no need to try policies where you overbook by three or more,

as costs will only increase

The Demand-Capacity Match in Services: Overbooking Example

Page 47: ©The McGraw-Hill Companies, Inc. 2008McGraw-Hill/Irwin Chapter 14 Capacity: Matching Productive Resource to Demand.

14-47

• The goal is flexibility– Temporary workers

– Contract manufacturers

– Outsourced components

• All of these have negative aspects, as far as quality, reliability, and increased transportation time, but there are tradeoffs in all capacity decisions.

Current Trends in Capacity Management