The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar (12.12.2008)
Feb 22, 2016
The Large Hadron Collider
The 19th Sep 2008 incident
[R. Alemany][CERN AB/OP]
[Engineer In Charge of LHC]NIKHEF Seminar (12.12.2008)
Incident of September 19th 2008• During a few days period without beam• Making the last step of hardware commissioning of
dipole circuit in sector 34 to 9.3 kA 5.5 TeV• At 8.7 kA, a resistive zone developed in the dipole bus
bar splice between Q24 R3 and the neighboring dipole• Electrical arc developed which punctured the helium
enclosure• Helium released into the insulating vacuum• Rapid pressure rise inside the LHC magnets
• Large pressure wave travelled along the accelerator both ways
• Self actuating relief valves opened but could not handle all
• Large forces exerted on the vacuum barriers located every 2 cells
• These forces displaced several quadrupoles and dipoles
• Connections to the cryogenic line affected in some places
• Beam vacuum also affected: soot and superinsulation material
R.Bailey, DESY, December 2008 3
LHC cryodipole (1232 of them)7TeV• 8.33T• 11850A• 7MJ
R.Bailey, DESY, December 2008 4
All have to be interconnected (quads too)
5
Interconnections
Bus bar interconnection
Hypothesis
• Temperature increase due to an excessive resistance• Superconductor quenches and becomes resistive at high
current (temperature increase due to the resistance).• Up to a certain current, the Copper can take it (cooled by
the He II).• Beyond a certain current, ‘run-away’ of the temperature,
splice opens, electrical arc …
Splice insulation Length He II @ 1.9K, 1Bar
currentcurrent
Heat exchange with He IIBus Bar’s Insulation
R.Bailey, DESY, December 2008 8
! Considerable collateral damage over few hundred metres Contamination by soot of beam pipes Damage to superinsulation blankets Large release of helium into the tunnel (6 of 15 tonnes)
Consequences
Insulating vacuum barrier every 2 cells in the arc Some moved
R.Bailey, DESY, December 2008 9
!
Repair
• Present strategy assumes treating all magnets Q19 to Q31
• May have to treat slightly further outside this zone (to Q33)
• Nearly all the components are at CERN• Critical components are beam screens and SSS
bottom trays• Estimate for magnets (preliminary) November 08
to March 09• Then have to finish interconnection, cool down,
power test• 53 magnets to be removed (39 dipoles + 14
quadrupoles): they will be thoroughly inspected and either clean or repaired or substituted by a spare magnet.
Outside sector 34• All data from hardware commissioning
carefully scrutinized• Anomalous cryogenic behaviour found in
sector 12 at 7kA• Higher than nominal heat load in
cryogenic sector 15 R1• Controlled tests made late October at
different currents• Calorimetric measurements
• Measure temperature increase at XkA mK/h
• Derive rate of energy deposition J/s = W
• Fit Energy deposition vs current• Deduce equivalent resistance nΩ
y = 9.2E-08x2.0E+00
0
5
10
15
0 5000 10000
Addi
tiona
l loc
al
diss
ipati
on [W
]
Dipole current [A]
Nominaldissipation
R.Bailey, DESY, December 2008 11
Calorimetric results so far (November)
-10
-5
0
5
10
15
20
25
30
35
40
07R1
11R1
15R1
19R1
23R1
27R1
31R1
29L2
25L2
21L2
17L2
13L2
09L2
07R6
11R6
15R6
19R6
23R6
27R6
31R6
29L7
25L7
21L7
17L7
13L7
09L7
07R7
11R7
15R7
19R7
23R7
27R7
31R7
29L8
25L8
21L8
17L8
13L8
09L8
Spec
ific r
esisti
ve h
eatin
g [m
W/m
]
3000 A 5000 A 7000 A
S1-2 S6-7 S7-8
25 nW
50 nW
75 nW
100 nW
• 3 sectors, 4 suspicious cases
Electrical results so far (November)
• Electrical measurements• Dedicated electronics needed for inter-magnet splices• QPS system used for internal magnet splices• S12 15R1
• All inter-magnet splices measured to be similar, around 0.3nΩ
• Magnet B16.R1 measured to have 100nΩ !!!• S12 19R1
• Nothing found; traced to a feature of cryogenic system• S12 31R1
• Nothing found; calorimetric fit in any case is very poor• S67 31R6
• Magnet B32.R6 measured to have 45nΩ !!!• S78
• Nothing found
Other measures• From the analysis of the incident, the following modifications and
consolidations are under consideration:
• Upgrade of the quench protection system for protection against symmetric quenches (was already in the pipeline before Sector 34 incident)
• Upgrade of the quench protection system for precision measurements and protection of all interconnects
• Modifications of commissioning procedure to include calorimetric information and systematic electrical measurements
• Addition of pressure release valves on EVERY dipole cryostat• note that this probably requires warming up
Strategy for implementing this is not yet finalised
Timescales for restart will be determined by
• Efficiency of logistics of magnets removal / installation
• Efficiency of magnet repair• Efficiency of beam pipe repair / cleaning• Efficiency of interconnection activities• Strategy adopted to ensure no repeat is
possible• Time to cool down• Time to re-commission power circuits