1 The Greek Energy System: A brief overview The Greek Energy System has historically always been in close interplay with the national electricity vendor.The Public Power Company (PCC), which was founded in the 1950s, has been a vertically integrated monopoly in power generation and supply for more than 50 years, possessing all the facilities for the generation, transmission and distribution of electrical energy in the whole Greek region. Following the relevant European Directives for the liberalization of the Electricity Market, the PCC has turned from a public company to an S.A. status in 2001. Independent parties were subsequently allowed to generate and sell energy, and the public is allowed to freely choose its energy supplier. Following the further reform of the energy sector in a free market for electricity, the PCC was obliged to separate its transmission and distribution sectors, forming two daughter companies, the Independent Power Transmission Operator S.A. (IPTO) and the Hellenic Electricity Distribution Network Operator S.A. (HEDNO) in 2011, which retain the role of a TSO and DSO respectively. It is underlined that those companies are supposed to operate in a fully independent status in their economic and administrative part, according to the relevant European directive of 2009. Additionally, the Hellenic Electricity Market Operator S.A. (HEMO) was created in 2011, with the task to perform the daily energy programming, market audit and final transactions for all the participants in the daily energy market. A state-maintained independent Regulatory Authority for Energy (RAE) was also sustained to oversee the Greek energy market. The Grid System in Greece consists of the interconnected electric grid system in the mainland and the isolated facilities of the Greek islands. As of 2011 the system was supplying 53 TWh yearly with a peak load of 10.1 GW. [6] The participation of different technologies in the capacity and energy production mix of the interconnected system for 2013 can be shown in Figure 1. [1][3] The interconnected Greek grid is dominated from thermal power plants (mainly coal), while the significant existing hydroelectric capacity offers a relatively small percentage of the totally generated energy. Figure 1 Installed Power (MW) and yearly Energy Production of the Greek Interconnected Grid System (2012) 10238 3017 1446 1404 348 Installed Power (MW) of the Greek Interconnected Grid System in 2012 Thermal Hydro W/F PV Other RES 46,47 3,89 3,16 1,51 1,01 Energy Production (TWh) of the Greek Interconnected Grid System in 2012 Thermal Hydro W/F PV Other RES
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1
The Greek Energy System: A brief overview
The Greek Energy System has historically always been in close interplay with the national electricity
vendor.The Public Power Company (PCC), which was founded in the 1950s, has been a vertically
integrated monopoly in power generation and supply for more than 50 years, possessing all the
facilities for the generation, transmission and distribution of electrical energy in the whole Greek
region. Following the relevant European Directives for the liberalization of the Electricity Market, the
PCC has turned from a public company to an S.A. status in 2001. Independent parties were
subsequently allowed to generate and sell energy, and the public is allowed to freely choose its
energy supplier. Following the further reform of the energy sector in a free market for electricity, the
PCC was obliged to separate its transmission and distribution sectors, forming two daughter
companies, the Independent Power Transmission Operator S.A. (IPTO) and the Hellenic Electricity
Distribution Network Operator S.A. (HEDNO) in 2011, which retain the role of a TSO and DSO
respectively. It is underlined that those companies are supposed to operate in a fully independent
status in their economic and administrative part, according to the relevant European directive of
2009. Additionally, the Hellenic Electricity Market Operator S.A. (HEMO) was created in 2011, with
the task to perform the daily energy programming, market audit and final transactions for all the
participants in the daily energy market. A state-maintained independent Regulatory Authority for
Energy (RAE) was also sustained to oversee the Greek energy market.
The Grid System in Greece consists of the interconnected electric grid system in the mainland and
the isolated facilities of the Greek islands. As of 2011 the system was supplying 53 TWh yearly with a
peak load of 10.1 GW. [6] The participation of different technologies in the capacity and energy
production mix of the interconnected system for 2013 can be shown in Figure 1. [1][3] The
interconnected Greek grid is dominated from thermal power plants (mainly coal), while the
significant existing hydroelectric capacity offers a relatively small percentage of the totally generated
energy.
Figure 1 Installed Power (MW) and yearly Energy Production of the Greek Interconnected Grid System (2012)
10238 3017
1446 1404 348
Installed Power (MW) of the Greek Interconnected Grid System in 2012
Thermal
Hydro
W/F
PV
Other RES
46,47
3,89 3,16 1,51 1,01
Energy Production (TWh) of the Greek Interconnected Grid System
in 2012
Thermal
Hydro
W/F
PV
Other RES
2
Within this report, the main aspects of the Greek electricity system and market will be analyzed. This
is to be achieved with a targeted reference to a series of features. More specifically, the topics
presented will cover the recent developments in the Greek electricity market, the present changes
regarding the generation and consumption sectors, the state and development of the Transmission
and Distribution network, the integration of RES in the system, the regulatory framework and
relevant legislation related to the RES, and finally the prospects of the integration of storage
technology.
1. The electricity market in Greece
Although the liberalization of the energy markets of the member states was clearly introduced in the
European Directives of 1996, 2003, 2009, the liberalization of the Greek market is still in progress. In
an effort to promote competition and avoid unfair market asymmetries, the electricity industry of
Greece has been unbundled in the Sectors of Generation, Transmission, Distribution and Supply.
However, there has been limited success in the effort for an increase of market participants. More
specifically, although between 2004 and 2014 numerous participants have been introduced in the
generation area, as of today the PPC still holds 68% of the installed capacity. The prospect is even
worse in the supply sector. Two major supply companies that had managed to gain access to a high
number of end customers were suspended from the market in 2012 after participating in major
scandals. At this point of time several other companies are engaged in the supply sector, but
maintain a minor share of the supply market (1.5%). Recently, the retail tariffs have been effectively
unbundled, separating charges for monopolistic and competitive activities to the end user, adding
some transparency into the competition of the market. [7]
On the other hand, the Market Operator established operates effectively a wholesale (mandatory
electricity pool) market where a Daily Energy Planning takes place, after the producers/importers and
suppliers/exporters submit offers for their total generation/demand, forming the System Marginal
Price. No individual contracts between generators and suppliers are allowed. [10] Specific HV
costumers are reported to be allowed to take part in the Daily Energy Planning to cover their own
demand directly. Apart from the PCC, three major independent energy firms and two industrial firms
possess generation plants and participate with 9 generating units in the HEMO records. The
independent suppliers possess only gas fired power plants which, although cost efficient, allow the
PCC to be the only company in possession of low cost coal plants, maintaining its predominant
position in the market. At this point of time, HEMO is still under the complete ownership of the
Greek government. [7] In real time conditions, the HEMO is of course not responsible for real time
dispatch, emergency dispatch and import and ancillary services. The TSO is responsible for those
actions along with measurement and definition of deviations from the supposed Daily Planning.
Those deviations are transferred also to HEMO, who is responsible for the necessary corrections in
predefined transactions. [11]
The Regulatory Authority for Energy, although initially having only a consulting character, has
gradually gained independency from the ministry control (2011), and is currently related to the
licensing procedure for new generation units. It is also considered the referee guaranteeing the
proper operation of the electricity market, especially when it comes to fair competition and safety of
energy supply. The State cannot interfere with its decisions, but RAE is financed and manned by the
relevant Ministry of Environment, Energy and Climate Change (MEECC).
3
The Greek government has a high involvement in the electricity market through the actions of
MEECC. The ministry has often participated in regulatory decisions for the electricity market that
would normally not be under its jurisdiction, making the electricity market susceptible to political
influence. In the past, the publicly owned utility has constituted an important tool in the hands of the
government, used for the application of social policies, through the application of low retail tariffs for
specific social teams. The PPC often sets retail prices really low for specific customer categories
making competition very difficult, and existing suppliers are active into the supply of very small
profitable parts of the market, leaving the other market segments to the PPC. In general, the PCC’s
objectives have many times not led by the concepts of profit and value maximization, rather the
application of social and political aims. At this point of time, the liberalization process is seen by the
government as a clash between EU agenda and local Unions of Workers, with the Greek government
being rather reluctant to promote it, in fear of losing significant political power.
As of 2014, significant changes are promoted for the electricity market in Greece. The privatization of
the transmission operator is currently in process with 66% of its share capital being offered for sale in
April 2014. The privatization of the PCC has also taken a significant turn, with the PCC being forced by
law to complete a privatization of 30% of its generation capacity until March 2015. The plants to be
privatized contain coal and hydropower plants, as well as proportional mines and customer share, a
step which will largely open up the market and encourage competition. For the remaining state
owned PCC, a transfer of 17% of its shares to private investors is also planned, leaving public shares
under 35% in the near future. The shareholding structure of the Greek PPC will be then the following:
Figure 2 Future Shareholder structure of the Greek PCC [4]
2. Generation and Consumption
As mentioned, the large majority of the conventional power plants belongs to the national power
company PCC and consists of groups of lignite coal plants in the region of northern Greece (5GW).
Many of those plants have been established in the early 70s and are characterized by very high
environmental burden. After investments of many decades, the lignite exploitation in Greece is
characterized by high productivity and competitiveness, and the excavation costs are very low even
in comparison to industrialized countries [4]. However, the low calorific value of the Greek lignite is
affecting the total electricity generation costs negatively. The construction of new coal powered