Helmholtz Centre for Ion Research D. Krämer, FAIR Technical Director, Bucharest, July10, 2007 The FAIR Project • Motivation • The Project Scope • International Structure • Technical Systems and Challenges • FAIR Work Packages
Helmholtz Centre for Ion Research
D. Krämer, FAIR Technical Director, Bucharest, July10, 2007
The FAIR Project
• Motivation• The Project Scope• International Structure• Technical Systems and Challenges• FAIR Work Packages
• Motivation• The Project Scope• International Structure• Technical Systems and Challenges• FAIR Work Packages
FAIR: Motives and Objectives
∙ Provide physics research communitiy with a world-leading scientific infrastructure for nuclear and hadron research
∙ Build on the experience of GSI, the German competence center for hadron and nuclear physics
∙ Realize FAIR in an international cooperation
High Intensity Precision Beams of Heavy Ions and Antiprotons
Fundamental Research into the microscopic structure of matter
Creation of matter nuclear astrophysics and the evolution of the universe
Matter in extreme states and material studies & applications
Structure andfundamental properties of anti-matter
&
• Motivation• The Project Scope• International Structure• Technical Systems and Challenges• FAIR Workpackages
The Pillars of the FAIR Complex
Antiprotonproduction
100 TmSynchotron
SIS100
Collector & CoolerRing
AccumulatorRing
Deceleration
Rare isotopeProduction &
separator
HighEnergy
Storage Ring
HESR&
PANDA
NewExperimentalStorage Ring
CompressedBarionicMatter
experiment
NESR
300 TmStretcher
Ring
SIS300
From existing GSIUNILAC & SIS18& new proton linac
+ Experiments:E-I colliderNuclear PhysicsAtomic PhysicsPlasma PhysicsApplied Physics
Technical Realization of FAIR
100 m
UNILACSIS 18
SIS 100/300
HESR
SuperFRS
NESR
CR
RESR
FLAIR
Accelerator Components & Key CharacteristicsRing/Device Beam Energy Intensity
SIS100 (100Tm) protons 30 GeV 4x1013
238U 1 GeV/u 5x1011 (intensity factor 100 over present)
SIS300 (300Tm) 40Ar 45 GeV/u 2x109
238U 34 GeV/u 2x1010
CR/RESR/NESR ion and antiproton storage and experiment rings
HESR antiprotons 14 GeV ~1011
Super-FRS rare-isotope beams 1 GeV/u <109
Radioactive Ion Production Target
Anti-Proton Production Target
Existing facility: provides ion-beam source and injector for FAIR
New future facility: provides ion and anti-matterbeams of highest-intensity and up to high energies
100 m
UNILACSIS 18
SIS 100/300
HESR
SuperFRS
NESR
CRRESR
ESR
Planned Experimental Facilities
Unprecedented System Parameters at FAIR(a unique multi-purpose facility)
Beam Intensity: - primary heavy-ion beam intensity increases by x 100 – x 1000 - secondary beam intensity increases by up to x 10000
Beam Energy: - heavy-ion energy : x 30
Beam Variety: - antiprotons - protons to uranium & radioactive ion beams
Beam Precision:- cooled antiproton beams
- intense cooled radioactive ion beams
Beam Pulse structure: - optimized for experiments: from dc to 50 ns
Parallel Operation: - full accelerator performance for up to four different and independent experiments and experimental programs
• Motivation• The Project Scope• International Structure• Technical Systems and Challenges• FAIR Work Packages
2000 2002 2004 2006
Wor
ksho
ps /
Whi
te P
aper
s: e
xplo
ratio
n of
sci
ence
opp
ortu
nitie
s
Wis
sens
chaf
tsra
t-Eva
luat
ion
BM
BF
Pre
ss R
elea
se
CD
R S
ubm
issi
on
Preparation of CDR700 scientists
WR – ESAC – ETAC – EMAC -- EAC
Inte
rnat
iona
l Ste
erin
g C
omm
ittee
ISC STI PAC's / TAC / miniTACs CORE-A / CORE-E AFI (LFI / FCI )
Inte
rnat
iona
l MoU
Accelerator R & D coordinated by GSI
Proto-Collaborations international community
Civil Construction Planning / Regulatory Processes / UVS
Preparation of FBTR 2400 scientists
FBTR
Sub
mis
sion
The International Committee Structure(for XFEL & FAIR)
PAC QCD
PAC NUSTAR
PAC APPA
TAC
Observes:
FCIFull Cost Issues
AFI Working GroupAdministrative + Funding Issues
LFILegal Framework Issus
STI Working GroupScientific + Technical Issues
ISCInternational Steering Committee
Delegates from partner states
CORECost Review Groups
Reviews• Cryogenics• Warm magnets •Cold magnets• Power Supplies• Beam Instrumentation• p-Linac
Austria China Finland France Germany Greece India Italy Poland Spain Sweden Russia Great Britain Romania
• Baseline Technical Report - accelerator TR's - experiment proposals - civil construction plans (~ 3500 pages)
• PAC & TAC Review Reports
• Cost Book
• Cost Review Reports - accelerator & civil construction (CORE-A) - experiments (CORE-E)
• Convention
• Articles of Association
• By-Laws
• Final Act Document
• Legal Framework Report (LFI)
• Full Cost Structure Report (FCI)
FAIR Project
All documents are ready
The FAIR Baseline Technical Report
FAIR Baseline Technical Report
Volume 1: Executive Summary Volume 2: Technical Report Accelerators and Scientific Infrastructure Volume 3: Techn. Experiment Proposals on QCD physics Volume 4: Techn. Experiment Proposals on Nuclear Structure and Astrophysics Volume 5: Techn. Experiment Proposals on Atomic Physics, Plasma Physics and Applied Physics Volume 6: Techn. Report Civil Constructions
http://www.gsi.de/fair/reports/btr.html
Handed to ISC in April 2006
accepted as „The Project“
ISC FAIR – Roadmap: Establishment of FAIR GmbH as Project Owner
Contracting Parties
Share-holders
Bylaw Subgroup
AFI
ISC
STI
IKAB
Joint Core-Team
07/06 08 09 10 11 12 01/07 02 03 04 05 06
Nomination of Shareholders + Completion
of negotiations
Completion of draft Bylaws
Signature of Convention and Final
ActSignature
AoA
STIAFI AFI
joint meeting ISC/SHISC ISC
Bylaws, draft FAIR GmbH structure and
kick-off staffing
Convention, Final Act, AoA;
Joint Core Team
Technical evaluation of potential in-kind contributions (ongoing process up to the formation of FAIR GmbH)
Mandate for IKAB
Monitoring of technical planning and project costs (ongoing process up to the formation of FAIR GmbH)
Elaboration of the Bylaws (ongoing)
Convention Final Act AoA
First meeting: start senior
staffing
Constitutive Meeting of the
Council
Convention, Final Act, AoA;
draft Bylaws
Bylaws, draft FAIR structure
Technical project decisions (follow up design changes) / FAIR preparation tasks (ongoing process up to the formation of FAIR GmbH)
Formation FAIR GmbH
Negotiations (ongoing, 'till end of 2006)
meetings
.. Roadmap is behind schedule ... but …
hard working for an International Project Owner
in 2008
Master Schedule - Accelerators
Assumed project start in late 2006, first experiments in 2012,
staged commissioning of machines up to 2015.
Schedule needs revision - civil construction is the critical path.
Project Costs
Accelerator investment costs 533 M€Civil construction costs 289 M€Baseline experimental facilities( incl Super-FRS ) 180 M€Investment budget 1002 M€Manpower (2400 person-years) 185 M€
Total Construction Costs 1187 M€
Commissioning Costs 28 M€Operation Costs up to 2025 1485 M€Sum 2700 M€
Germany committed part of funding
25% of funds have to come from non-German partners
Scrutinized by CORE, TAC, STI …
Announcement by German Minister Ms. Schavan:
Start of the International FAIR Project
on November 7, 2007
together with all partners that have expressed their commitment on FAIR, as Romania.
• Motivation• The Project Scope• International Structure• Technical Systems and Challenges• FAIR Work Packages
R&D on Key-Components during Preparatory Phase by GSI & Partner Institutes since 2001
IHEP Protvino
SIS300 sc magnets
Variable frequencyMA&ferrite loaded cavities
BINP Novosibirsk
SIS100 rapidly cycling sc magnetsCEA
NESR Electron Cooling
German BMBF provides 60 M€ for FAIR preparatory phase
300 kV septum power converter
Charge state separator
Projects funded by the European Communityunder the “Structuring the European Research Area” Specific Programme
Research Infrastructures action
SIS h=2 cavity
EU provides > 10 M€ for FAIR preparatory phase in FP6
R&D at GSI funded by EU
SIS100/300 Design Parameters
First Stage: Second Stage:
Acceleration + Acceleration +
Compression Stretching
1083 m1083 mCircumference
3 · 1011 /s1 · 1010 /s
5 · 1011
5 · 1013
Number of Particles
2.7 GeV/u34 GeV/u
2.7 GeV/u29 GeV
Energy
d.c.slow ext.
25 – 90ns 50 ns
Beam time structure
4.5 T2 TDipole flux density
1 T/s4 T/sRamp Rate
U28+ U92+
U28+
pReference Ions
300 Tm100 TmMagnet. rigiditySIS300SIS100
SIS300SIS100
SIS100 Dipole under Construction
Other on-going sc magnet activities: Super-FRS: quadrupole (Toshiba) radiation resistant magnets (BINP) superferric dipole (IMP)
MoU on prototype R&DSIS300 bending magnet
Progress in SIS 300 Magnet R&D
GSI001, first 4 T prototype by BNL6 T protoype under construction at DubnaCurved 4.5 T dipole magnetunder fabrication at INFN
INFN develops a 4.5 T SIS 300 dipole magnet
Capital cost financing: 4,7 M€ by INFN (1 M€ GSI)
Layout of Super-FRS
Bρmax =20 Tm
SuperferricMultiplet
SuperferricMultiplet
3 x 9.75° Dipole Unit MF2
MF1
SuperferricMultiplet
SIS
Main-SeparatorPre-Separator
Low-Energy Cave
CR complex
NESR
Energy Buncher
High-EnergyCave
Super-FRS eA-Collider
gas target
Production Target
Beams p - U1500 MeV/u10 ions /s12
Super-FRS20 Tm
from S
IS10
0
Center of Advanced TechnologyIndore
Saha Institute of Nuclear Physics, Kolkata
Variable Energy Cyclotron Center, Kolkata
Superconducting dipoles for Super-FRS energy buncher
from SIS 18
Study on large aperture quadrupoleContract for prototype ready for signature
The Superconducting Fragment Separator
CR-RESR Complex
CR
RESRFrom Super-FRS,
antiproton separator
Tasks of the CRTasks of the CR
1. Cooling of secondary beams of radioactive ions (RI)
ε⊥=200 mm mrad
∆p/p=3 % 1.5 sec
ε ⊥ ≤ 0.5 mm mrad
∆p/p ≤ 0.05 %
CRFinal RI beam
• 2. Cooling of antiproton beams (Pbar)
ε⊥ =240 mm mrad
∆p/p=6 %
ε ⊥ ≤ 5 mm mrad
∆p/p ≤ 0.1 %
Initial antiproton beam Final Pbar parameters
10 sec
CR
• 3. Mass spectrometer of radioactive ions RI (TOF)
ε ⊥ =100 mm mrad
∆p/p=1 %
RI beam CR
few turns
ff
mm
tr∆=∆ 2γ
Initial RI beam
From Super-FRS to the NESR
From antiproton separator to the RESR
From Super-FRS
The assembly of die First lamination punched
IMP LanzhouIPP HefeiIEE Beijing
CAS
CR Dipole Prototype Development in China
Coil fabrication Magnet design
The New Experimental Storage Ring Experiments with radioactive and stable ions at gas-jet or pellet targetPreparation of the low energy antiproton beams Electron scattering on radio-active nuclei (collider mode)Ion-electron interaction studies
• Injection energy: Radioactive Ion Beams (RIB) 100 – 740 Mev/uAntiproton beams (Pbar) 3 GeV• Lowest extraction energy: RIB 4 MeV/uPbar 30 MeV• Emittance: RIB 0.1 – 1 mm mradPbar 1 mm mrad• Momentum spread: < 10-4
design by BINP, Novosibirsk
• high voltage up to 500 kV• fast ramping, up to 250 kV/s• magnetic field quality
Issues:
Cooler Parametersenergy 2 - 450 keVmax. current 2 Acathode radius 1 cmbeam radius 0.5-1.4 cmhollow cathode option
magnetic field gun up to 0.4 T cool. sect. up to 0.2 T straightness ≤ 5×10-5
adiabatic expansion option
cool. section length 5 mmax. power in collector 15 kW vacuum ≤ 10-11 mbar
The NESR Electron Cooler
R&D Collaboration Partners cont‘d
Centro de Investigaciones Energéticas, Medioambientales y Technológicas
Madrid, Spain
on NESR magnets, vacuum system, power converters
High Energy Storage Ring
• Momentum: 1.5 – 15 GeV/c• Straights: Cooler and target section • Ring circumference: 573 m.
for antiprotons
PANDA Detector
• ±17 m free space between quadrupoles around the target• 10 m free space behind the target• Compensation dipoles between quadrupoles• Orbit deviation: 50 mrad, 400 mm (max)
-3,00
-2,00
-1,00
0,00
1,00
2,00
3,00
-3,00 0,00 3,00 6,00 9,00 12,00 15,00 18,00
X(m)
Y(m
)PANDAdipole
PANDAsolenoid
D1 D2
TSL
30 m cooling length
PelletronElectron energy 4 - 8 MeV
30 m cooling length
Collaboration
14 m
Working on planning and design of HESR
HESR Consortium FZ Jülich, TSL Sweden and the PANDA experiment collaboration
Main R&D Activities During Preparatory Phase
Amongst others:
BNL – SIS 300 superconducting ramped dipoleJINR – SIS100 s.c. ramped dipole & quadrupoleIHEP – SIS300 s.c ramped dipoleBINP – SIS100 curved dipoleBNN – SIS100 straight dipoleToshiba – Super FRS mulitpole tripletSpain consortium – NESR magnets, vacuum, power converterChinese consortium – CR superconducting dipoleBINP – RF cavityBINP – fast ramped power converter for ECOOLBINP – Feasibility studies/ Design studies on Septa, ER-Electron Ring, Electroncooling, Electron-Target at NESRACCEL – Feasibility study on injection/extraction at SIS100/300
Civil Construction
Legal conditions settled (Bebauungsplan)Study on civil construction work (BUNG)
- Designs have been frozen.- R&D on key components is well advanced, - Civil Construction planning aiming for start of execution work in early 2009.- Planning according to German ZBAU procedure.- CC Steering Co. awarded after European wide Call for Tender- CC Planning Co. Call for Tender in preparation.
Civil Construction
• Motivation• The Project Scope• International Structure• Technical Systems and Challenges• FAIR Work Packages
Work Packages have been Defined
∙ 94 WPs defined according to WBS, FBTR and Cost Book schematics
13 subprojects
15 te
chni
cal s
yste
ms
interest to take WP indicated
Internal Working Model:
FAIR Working Packages
No decision made yet
Partners have to commit their share first
and indicate their interest
FAIR GmbH and its committees will decide.
Specification of Work Packages
∙ WPs (independent of aggregation level) need to be specified - to allow proper realization of the contribution
which in general is a “hardware component” - basis: scope of work is FBTR and approved optimizations - technical detailing of specs under way, according to R&D results,
simulations and progress in enlarged planning depth
∙ FAIR machine and CC people aim for functional specs and/or full technical specs of components available late 2007
∙ Presently: CERN EDMS has been implemented also to spread specifications, follow-up and document evolution to final design,
production of components and life-cycle management of components (not only for accelerator components).
In-Kind Contracts 1 In-kind contributions will be contractually defined by FAIR GmbH and
representatives of the partner countries
2 Contracts will address:
2.1 Legal aspects (schedule, responsibilities ..)
2.2 Compliance to European/German laws - electrical rules, pressure vessel regulations etc. (necessary certifications are part of the work)
2.2 Specifications of components to deliverables- Technical specifications (parameters and tolerances)- functional specification (in general no detailed drawings!) to .
………allow industries for optimum production
In-Kind Contracts
3. Scope of Work and Responsibilities of WP-taker Production of fabrication drawings Procurement of materials Production of components according specification Testing (FAT) and Documentation Packing and transportation to FAIR site Unpacking, testing (SAT) and installation Functionality tests without beam
In-Kind Contracts
4. Communication and Reporting - Regular reviews (CDR, FDR, PRR ..) by FAIR with the help of external experts (e.g. GSI, CERN..)
- includes access to production site for FAIR representatives - Testing & documentation
FAT, SAT (requires a defined and approved QA and QC …..prior and during project)
WP-Costs
• WP-taker covers all costs to deliver the contribution (see scope of WP)
• WP-costs (for shares in FAIR) are defined in Costbook (independent of real costs)
• Purchasing Rules will be defined by AFI ..(e.g. GSI has to follow German and EU regulations and allow industries from
FAIR partner countries to bit in tender process)
Matrix of the 94 Work Packages
Invitation to all partner stateaccelerator labs to participatein workshop on detailing realizationof commitments (Oct. 1, 2007)
• Finland: looking into appropriate contributions - first meeting in Nov. 06• France: Technical discussions on proton source and SIS300 dipole magnets – various meeting with
CEA/IN2P3• FAIR China: prototype of CR and Super FRS dipole magnets R&D - meeting in Dec. 06• Germany: Continuous work on HESR, GSI active on all fields• Greece – no contacts• India: production of 4 sc dipoles for energy buncher, discussions on p-linac • Italy: R&D work on SIS300 has started (INFN) – MoU signed in Dec. 06 • Poland: looking into appropriate Polish contributions – first meeting • Russia: R&D contracts with BINP (Novosibirsk) on • radiation resistant nc dipoles & quadrupoles (SFRS target area)• design of ER ring• antiproton target• sc septum magnets• production of components for SIS18 upgrade (chambers, collimator)• design of ferrite loaded cavities (and prototype)• with JINP (Dubna)• development of low loss rapid cycling dipoles and quadrupoles for SIS100• with IHEP (Protvino)• study on SIS300 dipoles – meeting with ROSATOM• Romania: looking into appropriate contributions • Spain: NESR magnets, power supplies, vacuum – meetings by ministry in Dec. 06 and March 07• Sweden: Cryring for FLAIR experiments • UK: involved in various experiments (NuSTAR, PANDA), plans for active participation of accelerator experts• from Cockcroft Institute
Status of Technical Negotiations
AT CN FI FR GE GE IN IT PL ES SE RU GB RO
with tandem and cyclotron groupscould easily identify and support
Items of common interest
TSL
30 m cooling length
PelletronElectron energy 4 - 8 MeV
30 m cooling length
14
mAlternative Approach:
∙ Commitment(s) of partner countries to (share) financing of a complete experiment : including building, technical equipment (as beam-line, part of accelerator providing the beam, infrastructure ..)
The International Facility for Antiproton and Ion Researchin 2015/2016
Austria China Finland France Germany Greece India Italy Poland Spain Sweden Russia Great Britain Romania
Acknowledgements
GSI FAIR Technical DivisionP. Spiller, M. Steck, I. Hofmann, G. Moritz et. al.GSI Accelerator DivisionH. Eickkhoff et. al.FZ JülichR. Maier et. al.German universities: Darmstadt, Dresden, Frankfurt, Fulda, Kassel, Jena Collaborating laboratories:BNL, CERN, DESY, FZ Karlsruhe, KVI Groningen, MSU.FAIR member states:China: IMP, IEE, IPPFrance: INP Orsay, CEA SaclayGreat Britain: CLRC Daresbury, Cockcroft InstituteIndia: VECC CalcottaItaly: INFN GenoaPoland: Uni CracowRussia: BINP, IHEP, ITEP, IHCE, Uni Moscow and JINRSpain: CIEMATSweden: TSL Uppsala, MSL Stockholm
and many individuals that helped: 2400 worldwide
Thank you
and thanks to
Prof. Zamfir