Top Banner
The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019
43

The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

Oct 03, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

The ERCOT Grid

and Beyond

Joel Mickey Senior Director, Market Design & Operations

UEDA Winter Forum

Fort Worth

March 13, 2019

Page 2: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

The ERCOT Region

2

The interconnected electrical system serving most of Texas, with limited external connections

• 90% of Texas electric load; 75% of Texas land

• 73,473 MW peak, July 19, 2018

• More than 46,500 miles of transmission lines

• 600+ generation units

ERCOT connections to other grids are limited to ~1,250 MW of direct current (DC) ties, which allow control over flow of electricity

600 MW with SPP

30 MW with CENACE

at Eagle Pass

100 MW with CENACE

at Laredo 300 MW with CENACE at McAllen

220 MW with SPP

Texas RE

Page 3: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

What is ERCOT?

The Texas Legislature

restructured the Texas electric

market in 1999 and assigned

ERCOT four primary

responsibilities:

• System reliability

• Competitive wholesale

market

• Open access to

transmission

• Competitive retail market

ERCOT is a nonprofit organization that is regulated by the Public Utility Commission of

Texas, with oversight by the Texas Legislature.

ERCOT is not a market participant and does not own generation or transmission/distribution

wires.

Page 4: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Texas Competitive Model

4

• Generating units are owned by

privately owned companies

o Except for municipal and

cooperative units

• Compete in ERCOT market to

serve load

o Market is overseen by

PUC.

• Transmission and

distribution lines and related

facilities are owned and

operated by regulated

utilities.

oUtilities are regulated by

PUC.

• Retailers compete to serve

consumers’ electric load in

~75% of state

o Except 25% in municipal

and cooperative utility

areas

• Active retail competition

• 92% have switched

• ~15% switches in a year

• Nearly 100% smart meters

The Texas Legislature restructured the Texas electric market in 1999:

Page 5: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

73%

27%

2 models within ERCOT

Non-Opt in Entities

(NOIEs) are still

vertically integrated

Many have existing

and developing smart

grid initiatives:

-- AMI

-- Smart thermostats

-- Demand response

Possible triggers:

Demand charge

avoidance, real-time

prices, congestion

management

‘Utility’ a mostly

obsolete term

Dozens of REPs

competing for

residential and

commercial accounts

Terms typically range

from 3-24 months

Some pre-paid,

renewable options

>99% advanced

metering

Competitive Choice Municipals & Cooperatives (NOIEs)

Share of total ERCOT Load

The two worlds have very

different smart grid incentives

(more on this later)

5

Page 6: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Power Supply (Generation) Must Match Load (Demand)

6

• The fundamental concept behind ERCOT operations is that

generation has to match load at all times.

• In other words, a 1 MW reduction in load has the same effect on the

grid as a 1 MW increase in generation.

Page 7: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Energy Market

• Market participants bring generation on-line; ERCOT may start additional

generation needed to maintain reliability.

• Market participants submit offers for generation output.

• ERCOT clears the market every five

minutes, using the generation with

the lowest bids to serve the load,

subject to transmission constraints.

• Prices received by generators

signal whether more or less

output is needed from generators

in that area at that time.

• In general, the set of generator

output levels produced by this

process is the lowest cost way that

doesn’t overload the transmission system

to meet the system load for each five minute interval.

7

• Market participants bring generation on-line; ERCOT may start additional

generation needed to maintain reliability.

• Market participants submit offers for generation output.

• ERCOT clears the market every five

minutes, using the generation with

the lowest bids to serve the load,

subject to transmission constraints.

• Prices received by generators

signal whether more or less

output is needed from generators

in that area at that time.

• In general, the set of generator

output levels produced by this

process is the lowest cost way that

doesn’t overload the transmission system

to meet the system load for each five minute interval. -$250 $9,000

Prices

Page 8: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Nodal Energy Market

• ERCOT clears the real-time energy market every five minutes,

dispatching generation with the lowest offers to serve the load,

subject to transmission constraints

• Locational marginal prices (LMPs) are

produced every ≤5 minutes at >11,000 nodes,

including >600 Generation Resource Nodes

• If there is no congestion on the

system, all LMPs will be equal

(set by the marginal unit)

• Generators are paid the LMP at

their specific Resource Node

• Load Serving Entities are

billed the weighted-average

price at the Load Zone

8

Page 9: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Energy-Only Market & Scarcity Pricing Mechanism

• Features of the Energy-Only Market Design:

– No forward capacity market

• Energy and AS revenues are the incentives for future investment

– System-Wide Offer Cap of $9,000/MWh

• Highest in northern hemisphere

• Applies to energy and Ancillary Service offers

• Energy market cleared at the SWCAP for two 5-minute intervals in

Spring of 2018

– Operating Reserve Demand Curve

• Assigns values to reserve capacity based on Loss of Load Probability

• System-wide Price Adders increase as reserves decline

9

Page 10: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Peaker Net Margin (PNM)

Source: Potomac Economics (ERCOT Independent Market Monitor) 2017 State of the Market Report

• The PNM is a calculation

designed to measure the

annual net revenue of a

hypothetical peaking unit

• If the PNM for a year

reaches a cumulative

total of $315,000, the

system-wide offer cap is

then reduced to the

higher of $2,000 per

MWh or 50 times the

daily natural gas price

index

• This threshold (defined in

PUC Subst. Rule

§25.505) has never been

met

2018 PNM

= $62,293

10

Page 11: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Real-Time Energy Prices 2016-2018

11

-1,000

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

1/1 2/1 3/1 4/1 5/1 6/1 7/1 8/1 9/1 10/1 11/1 12/1 1/1

$/M

Wh

2016 SPP 2017 SPP 2018 SPP

Prices exceeded $75/MWh in

1.6% of intervals over 3 years

Intervals 2016 2017 2018

<$0 569 235 160

$0-$30 31,562 30,568 27,446

>$30-$75 2,605 3,685 6,691

>$75 400 552 743

HUB Avg. 15-min. Settlement Point Prices

Page 12: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Current Records

1

2

Peak Demand Record: 73,473 megawatts (MW)

July 19, 2018, 4-5 p.m.

Weekend Peak Demand Record: 71,445 MW

Sunday, July 22, 2018, 5-6 p.m.

Winter Peak Demand Record: 65,915 MW

Jan. 17, 2018, 7-8 a.m.

Wind Generation Records (instantaneous)

Output: 19,672 MW

‒ Jan. 21, 2019, 7:19 p.m.

Penetration (load served): 56.16%

‒ January 19, 2019, 3:10 a.m.

‒ Total MW Served by Wind = 17,406 MW

Recent Monthly Peak Demand Records

2018 • January: 65,915 MW (Jan. 17, 7-8 a.m.)

• May: 67,265 MW (May 29, 4-5 p.m.)

• June: 69,123 MW (June 27, 4-5 p.m.)

• July: 73,473 MW (July 19, 4-5 p.m.)

• November: 56,247 MW (Nov. 14, 7-8 a.m.)

2017

• April: 53,486 MW (April 28, 4-5 p.m.)

• October: 62,333 MW (Oct. 9, 4-5 p.m.)

Page 13: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Annual Energy and Peak Demand (2008-2018)

13

Page 14: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

13.3%

23.0%

26.0%

42.6%

32.5%

13.6%

14.8%

12.6%

16.5%

20.1%

17.1% 17.5%

14.3% 13.8% 14.3%

17.0%

18.2% 18.9%

11.0%

8.1%

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

45.0%

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

Pla

nn

ing R

ese

rve

Marg

in (

%)

Historic Summer Reserve Margins (May CDR Reports)

14

December 2018 update: 8.1%

Since release of the Dec. update,

unofficially revised to 7.4%

Page 15: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

0

20,000

40,000

60,000

80,000

100,000

1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

Nuclear Coal Other Gas CC Gas Steam Gas CT/IC Wind Solar

ERCOT Installed Capacity (1999-2018)

15

Wind and solar values are based on nameplate

capacity (not adjusted for peak capacity contribution)

4.8%

51.6%

0.3%

35.4%

12.1%

21.4%

Page 16: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CELLRANGE] [CELLRANGE] [CELLRANGE] [CELLRANGE] [CELLRANGE] [CELLRANGE] [CELLRANGE]

[CELLRANGE] [CELLRANGE]

[CELLRANGE]

[CELLRANGE] [CELLRANGE]

[CELLRANGE] [CELLRANGE]

[CELLRANGE]

[CELLRANGE]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CE

LL

RA

NG

E]

[CELLRANGE] [CELLRANGE] [CELLRANGE]

[CELLRANGE] [CELLRANGE] [CELLRANGE] [CELLRANGE]

[CELLRANGE]

[CELLRANGE] [CELLRANGE]

[CELLRANGE] [CELLRANGE]

[CELLRANGE] [CELLRANGE] [CELLRANGE]

[CELLRANGE]

[CELLRANGE] [CELLRANGE]

[CELLRANGE]

-

50,000,000

100,000,000

150,000,000

200,000,000

250,000,000

300,000,000

350,000,000

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

MW

h

Nuclear Coal Other Natural Gas Water Net DC/BLT Wind Solar

Energy Fuel Mix 2003-2018

16

*Source: Historical ERCOT Demand and Energy Reports

8.5

%

9.2

%

9.9

%

10

.6%

11

.7%

15

.1%

17

.4%

Page 17: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Ancillary Services

• Load and generation are

constantly changing, due to:

– Daily load patterns

– Instantaneous load variation

– Changes in variable

generation output

– Generators tripping offline

• Ancillary Services are procured

in the Day-Ahead Market to

ensure extra capacity is

available to address variability

that cannot be covered by the

five-minute energy market.

Ancillary Service Products

• Regulation Service

ERCOT sends a signal every four seconds

to increase or decrease output to the

generators providing Regulation.

• Responsive Reserve Service

Capacity from generators or load resources

that is readily available to respond to

frequency events

• Non-Spin Reserve Service

Capacity that can be started in 10 or 30

minutes to cover forecast errors or ramps

17

Page 18: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Wind Generation Capacity – December 2018

18

• Steady growth continues, with some spikes.

• Largest annual increase: 3,294 MW in 2015

(A close second: 3,220 MW in 2008)

• Incentives, uncertainty and other factors affect

construction decisions and schedules.

• Not all planned projects will get built.

• Texas continues to lead U.S. in wind capacity.

Future outcomes uncertain

Page 19: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Utility Scale Solar Generation Capacity – December 2018

19

Future outcomes uncertain

Page 20: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

CREZ Transmission

20

Source: Oncor

Page 21: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Distributed Energy Resources

Page 22: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Distributed Energy Resources

22

• Distributed Energy Resources (DERs) include solar photovoltaic (PV)

installations, small wind turbines, batteries, small generators, and

advanced demand response.

• Identify potential future impacts of DERs on ERCOT’s functions –

including but not limited to load forecasting, network modeling, real-

time grid operations, metering and settlement.

• Identify and, when possible, eliminate barriers to DER participation in

ERCOT markets, including developing ways for appropriate

wholesale market price signals to be delivered to DERs

Page 23: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Examples of Distributed Energy Resources (DERs)

23

Capable of Providing:

– Backup (emergency) power

– Demand charge reduction (e.g., 4CP)

– Response to wholesale market prices

– ERCOT Emergency Response Service

– An offset to energy consumption

– Ancillary Services

Photos courtesy Acclaim Energy

Page 24: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

NPRR 917 pricing proposal

• NPRR 917 would extend applicable nodal pricing to SODGs and SOTGs

– This would provide incentives for behavior consistent with Nodal market design and the reliability needs of the ERCOT system

• In the Real-Time Market, a nodal price is calculated for each electrical bus in the system at every SCED run

– There are ~13,100 electrical buses in the system

• The NPRR would establish nodal pricing as follows:

– SODGs (distribution-connected generators) would be paid the time-weighted price created at the Load point (electrical bus) to which the unit is mapped, per NPRR 866

– SOTGs (transmission-connected generators), which are already fully modeled, would be paid the time-weighted price at the electrical bus determined by ERCOT in review of the meter location in the Model

• There are 4 SOTG units with a total of 35.5 MW on the system today

24

Page 25: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Settlement Only DG in ERCOT 2010-2018

25

Accumulated

Count

0 MW

100 MW

200 MW

300 MW

400 MW

500 MW

600 MW

700 MW

800 MW

900 MW

0 Units

50 Units

100 Units

150 Units

200 Units

250 Units

Renewables

Non-renewables

Accumulated

Count

SODG formerly known as Registered DG

SODGs No. of Units MW

Non-Renewable 160 498

Renewable 55 320

TOTALS 215 818

73 units totaling 148 MW

added since 1/1/18

Page 26: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Demand Charges

Page 27: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC 27

Summer Weather Impacts on Load by Customer Type

• Customer class breakdown

is for competitive choice

areas; percentages are

extrapolated for municipals

and co-ops to achieve

region-wide estimate

• Large C&I are IDR Meter

Required (>700kW)

• 15-minute demand values

Thursday, July 19, 2018

5:00 p.m.

ERCOT Load: 73,539 MW

Temperature in Dallas: 108°

Thursday, March 1, 2018

5:00 p.m.

ERCOT Load: 37,997 MW

Temperature in Dallas: 62°

>35,000 MW of

weather-sensitive

load -- 48% of peak

Residential

48.8%

Small

Commercial

24.7%

Large

Commercial and

Industrial

26.4%

Residential

27.7%

Small Commercial

27.1%

Large

Commercial and

Industrial

45.2%

Page 28: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Demand Charge Avoidance (4CP Response)

• The Four Coincident Peaks (4CP) in ERCOT are the highest system-wide

load 15-minute settlement intervals in each of the four summer months:

June, July, August, September

• These intervals are the basis of various Transmission & Distribution (T&D)

charges for:

– Non-Opt In Entities (municipally-

owned utilities and electric cooperatives),

at the boundary meter level

– Retail choice customers with

peak demand ≥700 kW (Interval

Data Recorder Meter required)

Combined, more than

47% of total ERCOT

load is subject to 4CP

charges

Chart represents percentages of load at

IE 1700 on June 27, 2018, ERCOT’s

all-time system peak at the time

“Large C&I” = IDR Required

Retail

choice

load

Residential

34.4%

Small Commercial

18.2%

Large C&I

20.3%

NOIE

27.0%

28

Page 29: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Transmission Charge Increases

29

• Final 2019 postage stamp rate is $54.57 per 4CP kW

Most CREZ projects

came online 2013-2014

Major factors:

1. CREZ

2. Natural load

growth

3. Far West load

growth

Coming soon:

1. Freeport

Master

Project

2. Lubbock

Power & Light

Integration

Page 30: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Advanced Metering & Retail DR

Page 31: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Advanced Metering Origins

• 2005 Texas legislation enabled TDSPs to receive accelerated cost

recovery (via surcharge) for Advanced Metering Infrastructure (AMI)

• PUC rule implemented the law in 2007, with these purposes:

– Implement the legislation by authorizing the surcharge

– Increase the reliability of the regional electrical network

– Encourage dynamic pricing and demand response

– Improve the deployment and operation of generation, transmission and

distribution assets

– Provide more choices for electric customers

• Key elements of the rule:

– Applies to investor-owned TDSPs only (NOIEs not affected)

– AMI meters must measure consumption in 15-minute intervals

– Interval data shall be used in wholesale market settlement at the ESI ID

level

31

Page 32: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

15-Minute Metering

Pre-AMI AMI

Energy data points per month

Applies to residential premises without on-site distributed generation.

1 2,880

32

Page 33: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Advanced Metering benefits

• >7 million advanced meters now active in the

competitive choice areas of ERCOT

– >99% of ERCOT Load is now settled on 15-

minute interval data

• includes AMI, competitive IDR, and

NOIE IDR

• TDSP benefits:

– Reduced meter-reading costs

– Advanced outage detection

– Faster switching and move-ins/move-outs

33

Page 34: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Advanced Metering benefits

• Retail Electric Provider (REP) benefits:

– Settlement accuracy (no more load profiles; see next slide)

– Real money if customers reduce load during high-priced periods

• ISO benefits:

– Settlement timeliness & accuracy

• Customer benefits:

– Access to granular energy usage data

– A wider selection of REP products to choose from

34

Page 35: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Why settlement is important

• In settlement, LSE purchases are reconciled with

generators’ sales

• Prior to the AMI implementation, REP obligations for

residential and small commercial customers were

based on Load Profiles

– Profiles are estimates of average individual usage, based

on statistical samples of data from ‘like’ customers

– A Profile for each customer type was created for each

Operating Day, using weather & other inputs

– Interval-level values were then assigned to each customer

according to their Profile type, scaled based on monthly

kWh usage

35

Page 36: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Profile example

• A profile assumes customers of this type on average have the

profiled Load shape

– The load magnitude is adjusted (scaled) based on the

customer’s monthly kWh consumption

• Prior to AMI, REP Load was settled based on this estimate

Residential High Winter Ratio Profile Type for

North Central Weather Zone, July 23, 2018

36

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

1.10

1.20

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kW

h

Hour

Page 37: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Why settlement is important

• Settlement based on Load Profiles would be accurate at

the REP aggregate load level only if its customers were

not deviating from the profiled shapes

– REP must accept the settlement outcome even if its customers

were making significant changes to their load shapes

• In other words…

– Profiles are oblivious to intelligent load management

– Profiles are hard barriers to price elasticity of demand

– Profiles kill demand response

37

Page 38: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Why settlement is important

• Settlement on actual 15-minute data

cures this problem

– When customers are settled on their

actual usage, the benefits of any action

taken to reduce Load during a period of

high wholesale prices will accrue directly

to the LSE

– This gives the LSE (in this case, the

REP) an incentive proportional to real

time prices to promote intelligent load

management and demand response for

its customers

38

Page 39: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Retail Price/Demand Response

• If retail DR and price response penetration are a key metric in

measuring the success of the ERCOT retail market and the AMI

investment, how are we doing?

• Leveraging this rule language, ERCOT has worked with REPs since

2013 to collect data on various product offerings, including: – Time-of-Use

– Peak rebates

– Real-Time pricing

– Block & Index pricing

– Other load control products

• REPs take snapshots of their customer base on Sept. 30 each year

39

PUC Subst. R. 25.505 (e)(5)

Load serving entities (LSEs) shall provide ERCOT with complete

information on load response capabilities that are self-arranged or

pursuant to bilateral agreements between LSEs and their customers.

Page 40: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Examples of Product Options

40

Page 41: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

ERCOT Communications

Page 42: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

ERCOT Communication Channels

42

ERCOT website – www.ercot.com

• Today’s Outlook and grid conditions

• Daily and seasonal weather

• Market information, prices and more

Social media – join us!

• Twitter: @ERCOT_ISO

• Facebook: Electric Reliability Council

of Texas

• YouTube: ERCOTISO

ERCOT mobile app

• Real-time updates

• Wholesale pricing

• Information sharing

Page 43: The ERCOT Grid and Beyond...The ERCOT Grid and Beyond Joel Mickey Senior Director, Market Design & Operations UEDA Winter Forum Fort Worth March 13, 2019

PUBLIC

Questions?