Click to edit Master title style Click to edit Master subtitle style The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning Organizations
33

The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Dec 16, 2015

Download

Documents

Claire Murphy
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

The Cost of Status Quo

Governor’s Task Force on Modernizing Transportation Funding

in IdahoDecember 2, 2009

Presented by Idaho’s Metropolitan Planning Organizations

Page 2: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Presentation Outline

•What is a Metropolitan Planning Organization (MPO)? ▫Why do we exist? ▫What do we do?

•How do MPOs develop plans?•What is the funding situation?

▫What are the assumptions used?•What are the ramifications?

• Congestion• Financial

Page 3: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

What is a Metropolitan Planning Organization (MPO)?

•A regional planning entity responsible for transportation planning and approval of U.S. Department of Transportation funding for federally designated urbanized areas.

Page 4: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Why do MPOs exist?• Mandated by law:

▫ U.S. Government mandate in Title 23, U.S.C. Section 134(a)(2):

“Metropolitan Planning Organizations…shall develop transportation plans and programs for urbanized areas of the state.”

“Provide for the safe and efficient movement of people and goods.”

▫ Required by federal government for an urban area to receive federal aid transportation funds

Page 5: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

What is an MPO’s role?• Provide a forum that brings together all

aspects of the regional transportation system in order to achieve a unified voice▫Local and state▫Roadway, transit, non-motorized

• Provide coordination, collaboration, and collective decision-making on regional transportation system investments

Page 6: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

What do MPOs do?• Develop regional transportation plans

▫Long-range transportation plans 20+ years

▫Short range transportation plans 5 years “Transportation Improvement Program”

• Oversee the prioritization and allocation of U.S. Department of Transportation funds to▫ Address regional transportation needs▫ Improve the local economy▫ Maintain or improve air quality

Page 7: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Where do MPOs exist?Urban areas over 50,000 in population

Five MPOs in Idaho: □ Kootenai Metropolitan Planning Organization□ Lewis-Clark Valley Metropolitan Planning Organization□ Community Planning Association of Southwest Idaho□ Bannock Transportation Planning Organization□ Bonneville Metropolitan Planning Organization

Urban areas over 200,000 in populations□ Transportation Management Area (TMA)

Special designation with enhanced “rules”□ Northern Ada County□ Within the Community Planning Association planning area

Page 8: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Where are the MPOs in Idaho?

1

Page 9: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

What is the statewide relevance of MPOs?

•Planning areas encompass▫63% of Idaho’s population▫54% of Idaho’s civilian jobs▫815 lane miles of state roadways▫6,814 lane miles of local roadways▫32 cities▫6 counties▫9 highway districts

Page 10: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Who makes up an MPO?

Governed by a Board of Directors□Primarily elected officials

Cities Counties Highway districts

□Special members Idaho Transportation Department Local transit authorities Universities (Boise State, Idaho State) Tribes (Coeur d’Alene, Shoshone-Bannock, Nez Perce) Others

Page 11: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

How is a long-range plan developed?

•20+ year planning horizon▫Predicts travel growth based on future land use▫Plans for future transportation programs and projects

based upon the forecasts•Completed/updated every 4 to 5 years•Fiscally constrained

▫Can only include projects where there is a reasonable chance of funding

▫Other needed projects can be listed in the plan as unfunded (“illustrative”)

Page 12: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

How is a long-range plan developed?Rigorous modeling

□ Travel demand□ Population growth□ Economic growth□ Air quality

Data-based□ Census□ Traffic counts□ Population estimates and forecasts□ GIS

Public involvementRealistic future scenarios

Page 13: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

What is considered when making planning decisions?•Data and modeling results•Necessities to accommodate future growth

and travel demand•Fiscal realities•Regional dialogue on a vision of the future•Planning for level of service “C” or “D”

▫Pragmatic; not extravagant

Page 14: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

What is “level of service”?A = Free flow B = Reasonably free flowC = Stable flowD = Approaching unstable flowE = Unstable flowF = Forced or breakdown flow

Page 15: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Level of service

B D F

Page 16: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Planning for congestion – Kootenai MPO

Page 17: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Assumption: Population(20-year planning horizon)

▫Idaho population growth = 1.3% annually

2000 2005 2010 2015 2020 2025 20300

500,000

1,000,000

1,500,000

2,000,000

2,500,000

20001,293,953

20081,523,816

20101,517,291

20151,630,045

20201,741,333

20251,852,627

20301,969,624

Idaho PopulationCensus Bureau Estimate and Forecast

Source: Census BureauApril 21, 2005

Page 18: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Assumption: Population(20-year planning horizon)

• Percent of populations in MPO planning areas

1990 Current 203050%

60%

70%

80%

52%

63%

75%

Page 19: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Assumption: Funding (20-year planning horizon)

• Federal: 1.5% annual increase• State fuel usage = 0.9% annual increase• State vehicle registration = 2% annual increase• Property tax = 3.9% annual increase• Impact fees = 2% annual increase• Local option tax registration fee = 4% annual

increase

Page 20: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Assumption: State funding (20-year planning horizon)

•No increases based upon Legislative changes▫No change in fuel tax rates▫No change in Highway Distribution Account

sources (fuel tax, registration fees)▫No change in Highway Distribution Account

formulas

Page 21: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Assumption: Inflation (20-year planning horizon)

•Roadway construction inflation rates▫Short-term inflation (2010 – 2014)

2.8%

▫Long-term inflation (2015 – 2030) 4.0% Consistent with Federal Highway Administration

guidance

Page 22: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Annual revenues per year; 2009 to 2030 (MPO planning areas)

$-

$50,000,000

$100,000,000

$150,000,000

$200,000,000

$250,000,000

$300,000,000

$350,000,000

$400,000,000

Total Revenues

Page 23: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

OPR vs. ExpansionWhat is “OPR”? Short for “operations, preservation, restoration.”

All non-capacity maintenance projects.

The same as the following ITD categories:

What is “Expansion”?

All capacity projects.

The same as the following ITD category:

Operations Preservation Restoration Expansion

Snowplowing Striping Patching potholes Signal/sign repair Crack sealing Guard rail repair Grading gravel

Seal coating Overlays Bridge deck

seals Bridge deck

replacement Grading gravel

surfaces

Rebuild old roads and bridges

NOT adding lanes or widen roads

• Adding lanes or widen roads

or bridges

Page 24: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Average annual shortfall

OPR Expansion OPR Expansion M & O ExpansionState Local Transit

$0

$10,000,000

$20,000,000

$30,000,000

$40,000,000

$50,000,000

$60,000,000

$70,000,000

Average annual shortfall based on current dollars over the next 20 years within MPO planning areas

Overlap MPO Only

Page 25: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Total projected shortfall (MPO planning areas)

•Total average annual projected shortfall based on current dollars over the next 20 years within MPO planning areas

$169.9 Million

Page 26: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

The cost of status quo

•Cost of doing nothing exceeds the cost of doing something.▫Increased congestion → increased costs

Page 27: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Cost of congestion: Time

2009 2030 -

100,000

200,000

300,000

400,000

500,000

600,000

199,238

478,036

Bannock Transportation Planning Organization Annual Hours of Delay

Page 28: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Cost of congestion: FinancialValue of time = $24

2009 2030 $-

$500,000,000

$1,000,000,000

$1,500,000,000

$2,000,000,000

$2,500,000,000

$3,000,000,000

$224,640,000

$2,513,390,88

0

COMPASS – Annual Financial Cost of Congestion

Page 29: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Cost of congestion: Personal•Opportunity costs

▫Time with family vs. time stuck in traffic

vs.

Page 30: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

Future challenges facing MPOs

•Potential changes in federal transportation bill▫Donee state vs. donor state▫Solvency of the federal Highway Trust Fund▫More emphasis on transit to decrease vehicle

miles traveled ▫Without dedicated funding for transit, Idaho may not be

able to meet new goals

•Air quality issues▫Potential federal changes to air quality standards

Page 31: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

In summary•MPOs play a key role in transportation planning

and investment in Idaho•MPOs’ transportation plans…

▫Are based on solid data and mathematical modeling▫Use significant public involvement▫Are pragmatic and realistic

“Family sedan” type of plans; not luxury models

•Financially, Idaho’s transportation picture is grim and unsustainable if we want to meet public expectations.

Page 32: The Cost of Status Quo Governor’s Task Force on Modernizing Transportation Funding in Idaho December 2, 2009 Presented by Idaho’s Metropolitan Planning.

The bottom line…

The cost of doing nothing is greater than the cost of repairing the system.