THE CAPIM BRANCO HYDROELECTRIC COMPLEX Flavio Dutra Doehler Executive Coordination Aimorés and Capim Branco May 13, 2005
THE
CAPIM BRANCO
HYDROELECTRIC COMPLEX
Flavio Dutra DoehlerExecutive Coordination
Aimorés and Capim Branco May 13, 2005
2
THE CAPIM BRANCO
HYDRO PLANTS
The complex is made up of the Capim Branco I andCapim Branco II hydroelectric plants.
A public concession. Auction: December 2000 (without environmental licence).
Build and commercially operate for 35 years.
Cnotract signed on Jan. 29, 2001.
3
ENTREPRENEURS
Stockholdings:
Company Stake (%)CVRD 48.42
Cemig Capim Branco Energia 21.05Comercial e Agrícola Paineiras 17.89Companhia Mineira de Metais 12.63
4
EPC – The Construction Consortium
The Capim Branco construction consortium is made up of the following companies:
• Engineering/Construction works: Construtoras Andrade Gutierrez, Norberto Odebrecht andQueiroz Galvão;
• Electromechanical supplies: Energ Power, VA Tech Hydro Brasil and Voith Siemens Hydropower Generation;
• Project planning: Leme Engenharia, Engevix Engenharia and Intertechne Consultores Associados S/C.
5
CEMIG’S PARTICIPATION
The Capim Branco Energy Consortium (CCBE),composed of the private-sector companies CVRD,Votorantim, Suzano and Camargo Correia, andCemig, associated to bid at the Aneel auction.
Since Cemig had the environmental and engineering studies and has experience in building hydroelectric plants, it received a 20% stake inreturn for these studies, and for Quality and O&Msupervision services to be provided during and after construction.
6
THE AGREEMENT
The understanding was made by a Letter Agreement between the fourcompanies of CCBE and Cemig.
Above a certain budget limit for socio-economic and environmental costs, Cemig is committed to contributing to the company financially.
Camargo Correia left the project, and Cemig acquired a stake proportional toits own, of 1.0526% - resulting in its present stake of 21.0526%.
7
Construction and quality
Cemig’s Quality Supervision services certify that the product contracted through the global price contract is delivered at contracted levels. Project approvals, field supervision, releases of payment and certifications of acceptance of the plants are made by Cemig.
Management of the construction, including the environmental control plan (“PCA”), is carried out by a team of professionals hired by theCCBE consortium, with head office in Araguari.
The consortium members take part in management through amanagement board, which decides by majority vote, on which Cemighas a seat.
9
CAPIM BRANCO I
Rotor chamberSubstation Power
channel
Potential chamber
Diversion tunnel
Spillway
Dyke
Dam
10
Capim Branco I hydro plant: dataLocationLocationAraguari River between Municipalities of Uberlândia and Araguari
Reservoir Reservoir Area flooded: 18.66 km²Water level variation: zeroFilling time: 5 daysInstalled power: 240 MW (3 Francis rotors)Flooding quota: 624.00 mAssured energy: 1,357,800 MWh/year
DamDamType: Earth and rock fillHeight: 55 metersLength: 610 meters
12
Capim Branco II hydro plant: Data
LocationLocationAraguari River between municipalities of Uberlândia and Araguari
ReservoirReservoirArea flooded: 45.11 km²Water level variation: zeroFilling time: 14 daysInstalled power: 210 MW (3 Francis turbines)Flooding quota: 565.00 mAssured energy: 1,147,560 MWh/year
DamDamType: Earth and rock fillHeight: 60 metersLength: 800 meters
13
MAIN DATA
• Start dates:- Capim Branco I : September 1, 2003- Capim Branco II: March 1, 2003
• Start of generation:- Capim Branco I : January 31, 2006 (1st Unit)- Capim Branco II: December 15, 2006 (1st Unit).