Railway Equipment ACIM – Advanced Catenary Installation Method Systems & Technologies
Railway Equipment
ACIM – Advanced Catenary Installation Method
Systems & Technologies
2/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
Index
ACIM - Advanced Catenary Installation Method
Phases of the catenary stringing
Advantages of ACIM
3/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
ACIM - Advanced Catenary Installation Method - is the
working system for stringing the conductors (ropes -
wires) of an overhead contact line for electrification of
railway infrastructure.
This method allows to carry out simultaneously and in the
shorter time possible all the working phases.
It is used both for the electrification of "new railway lines“
and for the "renewal of the catenary".
The Advanced Catenary Installation Method has been used
with success for over 25 years in Europe. During this
period the equipment have been designed and
manufactured to develop and improve this method, each
of them dedicated to a specific working phase.
ACIM represents the best available working system for
stringing the catenary at the final operating tension force.
ACIM - Advanced Catenary Installation Method
4/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The complete system is composed by:
A. Traction Unit (self propelled rail truck): it has the function to tow the Constant Tension
Stringing Wagon.
Tesmec Traction Unit can operate at constant speed controlled by a PLC system. This
provides the best working condition to the Constant Tension Stringing Wagon and to the
operators.
B. Flat wagon for goods transport
C. Self propelled wagon with (crane and) platform for cable droppers installation: it has
the function to apply the droppers between the conductor and the contact wire.
Tesmec unit can perform these operations easily due a flexible working platform.
ACIM - Advanced Catenary Installation Method
5/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
D. Constant Tension Stringing Wagon (also bidirectional type): it has the function to
string with constant tension simultaneously all the cables of the lines at the same time.
The conductors should be strung according to the mechanical tensions indicated by the
manufacturers and with the maximum accuracy. The stringing system shall guarantee the
same individual stringing force applied to the conductors from the beginning to the end of
the operations without stressing the conductors.
Tesmec Constant Tension Stringing Wagon assures the highest tension accuracy even in
case of variation of towing direction, speed, air temperature and slope; world-class in case
of computerised automatic models.
E. Self propelled wagon with MAT and platform (advanced machine for cable
positioning): it is a specifically designed self propelled truck, that working in combination
with the Stringing Wagon, allows the stringing of the catenary on the cantilevers placed on
the poles. It has the function to easy positioning of the cable to the posts. Tesmec unit can
perform these operations easily due a flexible working platform and high performing MAT
system.
F. Multipurpose self propelled wagon equipped with developable working platform,
hydraulic derricks and line pantograph to perform electrical and dynamic final tests
ACIM - Advanced Catenary Installation Method
6/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The following drawing shows the system with a possible combination of equipment:
A - Traction Unit (self propelled rail truck)
D - Constant Tension Stringing Wagon
C - Self propelled wagon with (crane and) hydraulic platform
E - Self propelled wagon with MAT and hydraulic platform
Stringing a new catenary 25 kV with n.1 messenger wire and n.1 contact wire
7/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
Index
ACIM - Advanced Catenary Installation Method
Phases of the catenary stringing
Advantages of ACIM
8/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
“Catenary stringing" consists in a series of operations
carried out in sequence, to install the contact line
ready to operate.
We take into consideration only the technical
operations, leaving out the civil works (excavations
and foundations); from the poles installation to the
catenary final test.
The operations can be grouped into 5 different phases
which are listed below:
1st phase - poles installation on basements previously built
2nd phase - cantilevers installation on poles
3rd phase - cable(s) stringing (messenger wires - contact wires)
4th phase - droppers installation
5th phase - catenary final test
Introduction
9/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
1st PHASE - POLES INSTALLATION 2nd PHASE - CANTILEVERS INSTALLATION ON
POLES
3rd PHASE - CABLE(S) STRINGING
4th PHASE - DROPPERS INSTALLATION 5th PHASE - CATENARY FINAL TEST
Phases layout
10/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The 1st phase consists in poles installation on basements previously built.
It is carried out by a traction unit (self propelled rail truck - A) equipped with hydraulic crane
for the poles handling which are transported on a suitable flat wagon (B).
1st Phase - Poles installation on basements
11/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The 2nd phase consists in the cantilevers installation on poles.
A self propelled wagon with platform (C), equipped with hydraulic crane is normally used to
carry out this operation. A suitable flat wagon (B) is used to transport the pole cantilevers.
These are fixed to the poles by the crane directly operated from the working platform. The self
propelled wagon with hydraulic platform works also as traction truck of the flat wagon which
transports the pole cantilevers.
2nd Phase - Cantilevers installation on poles
12/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The 3rd phase consists in the cable(s) stringing, messenger wires - contact wires.
The constant tension stringing system guarantee the installation of the conductors at the final
operating tension. This system allows the operators to carry out the next phase (droppers
installation) in shorter time because the conductors are already properly positioned on their
cantilevers. The system also allows to save time because more than one operation is carried out at
the same time. This phase is performed by a traction unit (self propelled rail truck, A), a constant
tension stringing wagon (D) and a self propelled wagon with MAT and hydraulic platform (E).
3rd Phase - Cable(s) stringing
13/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The 4th phase consists in installation of vertical wires called droppers. They connect the contact
wire to the messenger wire and the job is completed. This phase starts after the self propelled
wagon with MAT and platform fixes the messenger wire to the pole cantilevers. This is possible
because the conductors are tensioned at the final operating tension. The messenger wire on the
pole cantilevers will not vary its position as well the pole cantilevers will be kept orthogonal to the
poles. This phase is carried out by is a self propelled wagon with hydraulic platform (C) able to
carry at least two operators and a certain number of droppers. Normally more than one self
propelled wagon are required.
4th Phase - Droppers installation
14/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The 5th phase consists in the catenary final test, in order to check the right position of the
contact wire (height and wires off-set) and eventually carry out the necessary adjustments.
A dedicated machine called “multipurpose self propelled wagon" (F) is used to carry out this
operation. It is equipped with developable working platform, hydraulic derricks to support and
move away the catenary from the pole cantilevers and allow the adjustment of the position,
line pantograph to perform electrical and dynamic final tests and to draw up documents
showing the correct position of the contact wire, for own use as well as for client use.
5th Phase - Catenary final test
15/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
Index
ACIM - Advanced Catenary Installation Method
Phases of the catenary stringing
Advantages of ACIM
16/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
The aims of the “ACIM” is the construction of the Electrified Catenary for Railway Lines with the
most accurate tension in the shorter time possible.
Accuracy
This system is in continuous development. Actually the construction of high speed train
increase again the tension accuracy requirement for contact and messenger wires.
It is essential that the tension applied on them is constant all times during the stringing
operations, from the beginning to the end of one complete section (approx. 1400-1600
meters).
Performance
With the latest Equipment designed by Tesmec and its partners and a well trained working
team it possible today to complete a line section of 1400-1600 meters in less than two hours.
Anyone in Railways construction knows how the time factor is important for a new line and
crucial in case of maintenance of existing line.
Advantages of ACIM
17/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
In particular, the advantages of the ACIM are due to the specific characteristics of:
A. The Traction Unit (self propelled rail truck)
It is a railway engine expressly designed for
this operation.
It has a relevant traction force, suitable for
towing the constant tension stringing wagon
with the wires tensioned, at a very low speed
and with a system which allows the variation of
the translation speed in a soft way, according to
different working requirements, without
having to stop during the stringing
operations, only increasing and reducing the
translation speed.
Advantages of ACIM
18/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
D. The Constant Tension Stringing Wagon
It is provided with the equipment for the constant tension stringing of the catenary
conductors (wires and ropes), either simultaneously and individually, at the final operating
tension. The Tesmec constant stringing wagon systems has very compact dimensions, high
reliability and low maintenance costs and offer the following main features and advantages:
Automatic control of the pre-set stringing
tension forces on the cables with high accuracy
for both contact and messenger wires without
causing any cable rotation or twisting.
The high accuracy allows the installation of the
droppers at the same time in the same
working section with considerable time saving
No effect on the tension force values due to
the profile of the line or due to speed changes
while stringing.
All functions are controlled by one operator
from a central control console.
Advantages of ACIM
19/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
If we could measure the mechanical tension on the conductors when the constant tension
stringing wagon starts moving (instantaneous phase), we could see the physical phenomenon
which leads to an instantaneous increase of the mechanical tension on the conductors. Then,
once the translation speed is achieved, the mechanical tension stabilizes at the set value.
Advantages of ACIM
It is extremely important because it allows the
installation of the conductors to the pole cantilevers
without stopping the traction unit and the constant
tension stringing wagon and the coming out of the
conductors tensioned at the final operating tension
from the capstan tensioner. In fact, different stops
and restarts of the constant tension stringing system
cause different mechanical tensions on the
conductors when the constant tension stringing
wagon moves on again, following the physic
principle which says that the static friction is two
times the kinetic one.
E. The Self Propelled Wagon with MAT and Hydraulic Platform
20/20 Tesmec Presentation-RE-SY-ACIM-EN-Rev 02 12/10/2010
In conclusion, ACIM (constant tension without stops), is
the best system available for the catenary stringing,
without stressing the conductors (stops and restarts) and
with relevant advantages in terms of accuracy,
performance and timing saving.
The Tesmec System is the result of three important
factors:
The consolidated capability of Tesmec in construction of
Stringing Machines and Stringing Operation Procedures
The collaboration with important experience partners in
construction of Railway Ancillary Equipment
The Feedback experience by our customers, Railways
Bureaux as well construction companies.
Advantages of ACIM
TESMEC S.p.A - Headquarters
via Zanica, 17/O - 24050 Grassobbio (BG) - Italy
Tel. +39.035.423 2911 - Fax +39.035.4522444 Management and Administration
Fax +39.035.4522445 Stringing Equipment Division - Fax +39.035.335664 Trencher Division
www.tesmec.com - [email protected]