Technical FORUM, 16.3.06 Peter G lässel, Heidelberg 1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Project leader: Peter Braun-Munzinger, GSI Darmstadt Darmstadt Deputy project leader: Deputy project leader: Johanna Stachel, Johanna Stachel, Heidelberg Heidelberg Technical coordinator: Technical coordinator: Peter Gl Peter Gl ä ä ssel, ssel, Heidelberg Heidelberg
36

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Jan 17, 2018

Download

Documents

Fay Sullivan

Technical FORUM, Peter Glässel, Heidelberg3 Status at last FORUM ROC mounting completed end Sept 05 Survey of end plate and ROCs: End plate conical by 2.6 mm Force needed to straighten: about 6000 N
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 1

TPC Progress

Project leader: Peter Braun-Munzinger, GSI DarmstadtProject leader: Peter Braun-Munzinger, GSI DarmstadtDeputy project leader: Deputy project leader: Johanna Stachel, HeidelbergJohanna Stachel, HeidelbergTechnical coordinator: Technical coordinator: Peter GlPeter Gläässel, Heidelbergssel, Heidelberg

Page 2: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 2

Outline

Survey of end plates, I-bar story Leak testsService Support Wheels (SSW)Installation of Front End ElectronicsLaser systemCooling systemGas systemPlanning, Summary

Page 3: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 3

Status at last FORUM

ROC mounting completed end Sept 05Survey of end plate and ROCs:

End plate conical by 2.6 mmForce needed to straighten: about 6000 N

Page 4: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 4

Straightening the end plate

Decision to use 2 I-barsForce needed for flat end plate: F= 2 x 2600 NIntegration problems with ITS solved (installation situation actually improved for ITS)2nd set of I-bars needed to allow changing between A and C-side (never again allow the endplate to go to its conical shape)2nd set already delivered

Page 5: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 5

Precision Shimming of the ROCs

Steps:surveytake out shimsmachine to correct lengthreinsert shims

Overall precision: 200 μm

end plateend plate

ROC bodyROC bodyMounting point,shim removed

Page 6: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 6

Survey result of ROCs, A-side

1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

0.2

0.1

0

0.1

0.2

A SIDE

SECTOR No

Dev

iatio

n (m

m)

zi is 0

zi is 1

zi is 2

zo is 0

zo is 1

zo is 2

zo is 3

is

0.30.2

0.10

0.105101520

A SID

E

Devia

tion (

mm)

yh

xh

Page 7: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 7

Survey, C-side

1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 180.2

0

0.2

C SIDE

SECTOR No

Dev

iatio

n (m

m)

ziis 0

ziis 1

ziis 2

zo is 0

zo is 1

zo is 2

zo is 3

is

0.20.1

00.1

0.20.3

0.405101520

C SI

DE

DEVI

ATIO

N (m

m)

yh

xh

peak-to-peak ± 200 μmrms < 100 μmone outlier each side

Page 8: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 8

After mounting ROCs

Sealing chambersLeak test

He-sniffingOne OROC and one seal exchanged

Argon test

End plate

ROCROCSeali

ng fo

il

Sealing bar

Page 9: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 9

Argon test

Flow 2.6 m3/h 4x less than with final system → 4x more sensitive11 ppm O2 reached 24.2.06, still not asymptotic extrapolated < 3 ppm for final flow

Page 10: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 10

A-side ROCs completed

Page 11: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 11

Laser system optics and mechanics

Safety tube

Most components installed on end plateAlignment and start-up Apr 06

Page 12: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 12

Service Support Wheels (SSW)

Used ‘bare’ in ITS-TPC integration testServices partially preinstalled

LV bus bars delayed due to quality problem, problem solved by now

Mounted on Delphi frame rail at end platesLoad FEC frames to simulate FEC weight (1.1 t each side)Alignment of FEC frames to ROCsDeformation of wheel < 0.1 mm

Page 13: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 13

SSW sector prototype

Page 14: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 14

Service Support Wheelsunequipped SSW for integration test

equipped with cooling + FEC frames

Page 15: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 15

SSW installation A-side

Page 16: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 16

SSW C-side

Page 17: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 17

SSW loaded

Page 18: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 18

Measurement of VCCA, VCCD, IA, ID and T

Test of all CSRs, Control & Readout path

FE Cards Installation 2/2

Readout of trigger related data (pulser)

Connection to the pad plane

During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface)

U2F Card

FEE installation

Page 19: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 19

TPC A Side(17th February ’06)

The FEE installation teamThe FEE installation team

Page 20: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 20

FEE installation highlights

Page 21: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 21

Sector A09 equipped with • backplanes • cooling circuit• LV power rods• LV PS + cables (4 x 40m)

FEE Test Sector A09

Page 22: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 22

sum of charges sum of charges, pad row 46

baseline noise rms (ADC counts)

Characterization of Sector A09 - IROCTest sector IROC results, preliminary

Page 23: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 23

sum of samples

baseline rms

Characterization of Sector A09 - IROC

baseline

Test sector IROC results, preliminary

Page 24: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 24

sum of charges sum of charges, pad row 11

Characterization of Sector A09 - OROC

baseline noise rms (ADC counts)

Test sector OROC results, preliminary

Page 25: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 25

sum of samples

Characterization of Sector A09 - OROC

baseline rmsbaseline rms

sum of samples

Test sector OROC results, preliminary

Page 26: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 26

Conclusion from Test Sector Results

Noise and electronic gain uniformity equal our most optimistic expectations!

Page 27: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 27

Cooling: Heat screens

Inner thermal screen installed, shields from ITS servicesReminder: no screen towards ITS

Outer thermal screen: Decision for active screenDesign completed, 1% Xo:

fixed to SF from TPC sideOffer receivedInstall July/Aug 06, if possible earlier

Page 28: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 28

Gas system

Previously commissioned with dummy volumesStart pre-commissioning with TPC in SXL2 with final gas mixture in a week

Control Backup Mixer Purifier CO2 Distr Analys Pump

Page 29: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 29

Pre-Commissioning plans, SLXL2

Commissioning of gas system from 20.3. to ~19.4.Commissioning of Field cage, FEE and ROCs

DCS systemDrift HV Laser ROC HVGatingReadout chainTrigger for cosmics, laserOnline monitoringVerify each sector, at least with laser tracksTracks (laser, cosmics) with 2 sectors (joining, opposite, …)Commissioning of temperature sensors

Move to UX25: 4.9.06

Page 30: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 30

TPC Summary

Survey: I-bar and Shimming ROCLeak testsFEE installation phase till mid Mar 065 ½ months pre-commissioningTPC installation in UX2 Sep 06

Page 31: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 31

-- Spares --

Page 32: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 32

TPC with 2 I-bars

During ITS installation, I-bars will be on A-side

Page 33: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 33

The Gain Variation Story

IROC 1 IROC 5

Problem traced to pad/anode distance variations of IROC 1Installed chambers are within specs

Page 34: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 34

Service Support Wheels (SSW)

Installation of services into SSW started mid Sep05Quality problem detected:

LV bus bars: some LV connectors damaged by flux residues and/or excessive temperature

Repair at company failed, connectors can’t be trusted anymoreNew production, will bring completion of SSW to Jan or even Feb06Partial recovery of schedule due to the possibility to install LV bus bars after FEE cards, would allow start of FEE installation on one side already late December, almost like foreseen previously

Page 35: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 35

Temporary I-bar

Page 36: Technical FORUM, 16.3.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,

Technical FORUM, 16.3.06 Peter Glässel, Heidelberg 36

C-side: loaded SSW