Technical File Page 1 READYKIT BUILDING SYSTEM TECHNICAL FILE PRODUCT OF DURACASA (PTY) LTD P.O. Box 335 Paarden Eiland 7420 TEL: +27 21 510 2233 FAX: +27 21 510 2273 E-MAIL: [email protected] WEBSITE: www.readykit.co.za
Technical File Page 1
READYKIT BUILDING SYSTEM
TECHNICAL FILE
PRODUCT OF DURACASA (PTY) LTD
P.O. Box 335
Paarden Eiland
7420
TEL: +27 21 510 2233 FAX: +27 21 510 2273
E-MAIL: [email protected]
WEBSITE: www.readykit.co.za
Technical File Page 2
Table of contents:
1. Introduction
1.1 Duracasa, the company and product
1.2 Readykit system and details
1.3 Business plan
2. Social and economic benefits
2.1 Social
2.2 Economic
3. Construction process
3.1 Setting out
3.2 Foundations
3.3 Base plate
3.4 Floor slab
3.5 Wall panels & fixing
3.6 Wall plates and trusses
3.7 Roofing
4. Wall panels manufacturing drawings
4.1 Panel Fabrication
5. Factory
5.1 Raw materials needed
5.2 Tools and equipment needed
5.3 Health and safety
5.4 Layout
Technical File Page 3
6. Tests
6.1 SABS Fire Resistance Test
6.2 SABS Structural and Rain Penetration Tests
6.3 Agrément Assessment of Thermal Performance, Energy Usage and condensation
6.4 Rational Design by HMG Structural Engineers
7. Approvals
7.1 Letter from Cape Town City Planner’s Department
7.2 Letter from Western Cape Provincial Administration
7.3 Letter from NHBRC
7.4 Letter from Standards Association of Zimbabwe
8. Photographs Previous Building
Technical File Page 4
1) INTRODUCTION:
1.1 Duracasa is a South African company contracted to develop and market the Readykit
tried and tested building system that delivers cavity walled structures, at an
unparalleled delivery speed and low cost without compromising quality. Easily learnt
site construction allows for rapid skills transfer and the emergence of trained
contractors and maximum job creation.
1.2 The essentials of the patented Readykit system involves timber panels onto which is
stretched a fiberglass mesh plus a taut underlay which on site receives a 25mm
render of a mixture of building sand, cement and lime. The panels are delivered to
site including windows, door frames and an electrical layout that includes the
distribution board, stove isolator, oosterzee box and plug / switch boxes with
uprising vertical conduits in accordance to the building plan.
Technical tests over the years since first developed in 1994 have ensured that the
system is
Durable
Waterproof
Bullet resistant
60 minute fire rating
Excellent thermal protection
Condensation performance
Our Agrement Certification is now in process. Meanwhile we have received building
rights from many municipalities including Cape Town and bonds from the major banks.
Although the Readykit system was originally designed to help alleviate South
Africa’s housing shortage, experience has taught us that the system is of equal value
Technical File Page 5
when applied to a wide range of buildings, such as the office block erected in Cape
Town Harbour in 1994 and a testing ward for Brooklyn Chest Hospital in 2009.
1.3 Our Business Model is to manufacture and sell building kits from our Cape Town
factory, train and license builders, and enter into franchise agreements with
entrepreneurs who wish to manufacture kits in their own area and also train and
license both established builders and emerging contractors.
Resulting in the use of ready-kit panels all over South Africa, resulting in the rapid
decrease in housing shortages and increase in skills transfer. Help Building a better
South Africa!
Technical File Page 6
2) SOCIAL AND ECONOMIC BENEFITS
It need not be emphasised the fact that the ever widening gap in South Africa between
rich and poor is beginning to threaten the fabric of our society. It is imperative that
private enterprise links with government in creating self-fulfilling projects that combine
job creation with easily attainable skills transfer.
Readykit technology has already been identified as a building system ideal for Africa.
On site construction has been refined so that for a 45sq m house, a team of 7 will have the
foundation built, house erected and with a tiled roof in place in 4 days. Mechanical
plastering is faster than manual application, but the latter is more appropriate to job
creation.
The equipment needed in setting up a manufacturing facility is simple and inexpensive
(see Section 8 below) and far cheaper than required for other alternative building
systems.
Factories can be quickly established close to where construction will take place, allowing
for maximum local employment.
For the emerging franchisee and contractor our aim is to establish Readykit training
schools across the country.
The main economic benefit is a sharp growth in home industry and an increase in job
creation as well as less dependence upon job migration resulting in local employment.
Therefore the economy in the specific area will grow and hopefully flourish at an
increased rate. As acceptance of the Readykit concept spreads so will productivity
increase, which helps support the value of our currency and combat inflation, promote
ongoing affordable home ownership, lessen the poverty gap and combat crime.
Technical File Page 7
People have an understandable suspicion of alternative building systems, although recent
experience is that the vast majority of failed “jerry built” houses are of 145mm block.
The track record of Duracasa shows the durability of the houses, as you will see later in
this document.
One of the hidden scourges that hit our productivity is sickness, often the result of
overcrowded tiny units that are difficult to insulate against heat and cold, and which
sweat. Under such conditions diseases such as TB thrive. It is important that we move as
quickly as possible to housing our population in healthy structures of adequate size.
Technical File Page 8
3) CONSTRUCTION PROCESS
STAGE 1 – SETTING OUT
1. Remove vegetation and top soil
2. Set out the house using the centre lines of external walls as the centre lines of
foundations. Ensure all corners are square by checking the diagonal
measurements between opposing corners.
STAGE 2 – FOUNDATIONS
1. The depth of the foundations is determined by the top of the screed level which
must not be less than 150mm above the highest level of the finished ground
around the house perimeter. The trenches must therefore be 638mm below the top
of the screed level. (See figure 2 below)
Figure 1
Technical File Page 9
2. Foundations consist of 450 x 200 mass concrete footings of strength 15 Mpa - the
contractor is given the choice of using stone aggregate of between 13 and 26mm
for all work.
3. A plinth wall consisting of two courses of minimum 7MPa, SABS approved
concrete blocks (190 high by 190 wide by 390 long) is built on top of the
foundation strip. Cement mortar mix ratios for laying the block plinth must be
mixed according to SABS standards of 50 kg cement to 0 – 40 litres lime
(optional) to 200 litres sand graded to SABS Standard Method 829/SANS 201. If
Builders sand already has lime incorporated, then the ratios must be adjusted
accordingly.
4. Y10 Reinforcing Bar is used to connect the footing to the block plinth. The
bottom end should be bent 90° and be 200mm long. The vertical end should be
475mm long and 75mm from the top of the plinth. The bars are to be cast in to the
footing at 800 centres to coincide with the centres of the first void of every third
block.
5. Blocks may be placed off-centre on the footing, but external block edges shall be
no closer than 75mm to the edge of the footing. Refer to figure 3.
Figure 2
Technical File Page 10
6. For sloping sites, the plinth wall height may be increased to accommodate the site
conditions. If the plinth needs to be greater than 3 blocks high, then a non-
standard retaining wall to engineer's design is to be built.
Fill is then placed and compacted up to 75mm below the top of the plinth level to
allow for a 76mm surface bed which is then level with the top of the plinth.
7. If tapered cavity blocks are used then these must be laid with flat side down for all
courses (wider opening facing upwards). Blocks to be built one course at a time
and all cavities filled one course at a time. Block plinth to be filled with minimum
strength 20MPa concrete and aggregate size used will be according to builder’s
choice. Concrete must be well compacted by either rodding (manual) or vibrating.
(see Figure 4 and point 4 below).
Figure 3
Technical File Page 11
8. All foundations are to be inspected and signed off by the appointed engineer and
the City Planning department before casting concrete.
The City Planning department may opt to waive this requirement but the
appointed engineer must still sign off all foundations.
STAGE 3 – BASE PLATE
1. Treated SAP timber base plates of size 76 x 38mm are placed in the centre of the
block plinth and wrapped with a minimum 250 micron Damp Proof Course(DPC).
End-to-end joints to be wrapped individually with DPC when laid.
2. Once the base plates have been accurately positioned, using temporary diagonal
timber corner stays, the plates are fastened to the plinth wall with an M10, 100mm
thunderbolt masonry screw per every 750mm. The pre-drilled holes in the base
plates must be used as guides for drilling 150mm deep holes in the block plinth
which will accommodate the thunderbolts. The pre-drilled holes are further
counterbored (25 mm diameter) to a depth of 10mm to ensure that bolts do not
protrude above the surface of the base plate. The height of the bolt head =
(0.7xM10) = 7 mm. M10 washers (external diameter = 21mm, thickness = 2mm)
are to be used with the bolts.
3. A bitumen based product is used to seal bolt holes penetrating DPC when fitting
bolts. The bolt head must not protrude above the base plate upper face.
4. Back fill and compaction of the trenches can now take place and the ground inside
the plinth walls is trimmed or filled and compacted to a level 76 mm below the
top of the plinth walls. The Engineer is to be called in at this point to test the
compaction of the ground under the surface bed.
Technical File Page 12
STAGE 4 – CONCRETE SURFACE BED
1. Once the compaction of the ground has been approved, a 250 micron Damp Proof
Membrane (DPM) is placed on the compacted fill. The DPM must continue
vertically against the block plinth wall for 76mm, to the top of the plinth wall,
then horizontally along the top of the blockwork and again vertically against the
base plate so as to protrude 20mm or so above the top of the base plate, running
adjacent to the vertical portion of brickgrip wrapped around the base plate (see
figure 5 below). This will later be cut level with the top of the screed.
Figure 4
Another option is that of having the DPM continue horizontally along the top of the block
work, below the base plate, in which case a bitumen-based sealing product must be used
to seal the DPM to the DPC of the base plate. The DPM must then extend 20mm past the
base plate as in figure 6. The base plate would then be installed only once the DPM is in
place.
If the folding of the DPM leaves the top of the block work of the four corners of the
plinth wall exposed, the exposed concrete needs to be treated with Hydroflex or a similar
cement waterproofing agent. The waterproofing agent will replace the DPM at the
Technical File Page 13
xposed areas and needs to overlap the DPM by at least 150mm.
Figure 5
2 If the DPM is too short to extend all the way past the base plate, the exposed
blockwork must be treated with Hydoflex or a bitumen-based or similar cement
waterproofing agent and the remaining DPM folded over onto the treated plinth
wall as in figure 7:
Figure 6
3 Cast the 76 mm thick concrete floor slab, using a 20MPa concrete and screed off
level with the top of the plinth wall. The concrete for the floor slab is to be of a
suitable slump and consistency for proper compaction, tamping and levelling.
Technical File Page 14
4 Once the surface bed has been cast, tamped off level and has cured for 24 hours,
the floor screed can be applied so as to finish level with the top of the base plate.
STAGE 5 – WALL PANELS
The wall panels are constructed in the factory in accordance to the specific panel
specifications. The fabrication is described later in the file. Additionally all the
information on the factory is also later in the technical file.
Technical File Page 15
STAGE 6 – WALL PANEL INSTALLATION
Method for fixing panels to each other and the base plate
Please find below the directive for fixing Duramesh panels to each other as well as to the
base plate.
Tools and Materials required:
Hurricane Clips: Timbalok
or equivalent
Nails: Clout nails with anti-
corrosion treatment/coating
Claw Hammer
Technical File Page 16
Tools and Materials required:
Staple Gun
Panel Alignment Device
Spirit Level
Four Inch Nails
Technical File Page 17
In-line Panel Fixing Required:
Hurricane clips
Hammer
Staples & staple gun
Panel Alignment Device
Spirit level
Four inch nails
Precautions: Ensure that the panels are lined upright at 90 degrees using spirit level. If
necessary start with bracing on the first two panels to ensure accurate alignment of the
panels. The use of long 4 inch nails may also help to sure up the panels with one anther
and the base plate. Start with panel one and work around the building n both directions
to ensure speed and efficiency.
NOTE: If care is taken with the erection of the panels to ensure straightness and
plumb, it saves an enormous amount of time, effort and money later when it comes to
plastering, fitting skirting, ceilings, facias, tiling etc.
All panels must be checked after to ensure fixing and alignment.
Three hurricane clips and respective
number of clout nails used to fix the
panels to the base plate. Along the
bottom of the panels.
Four additional hurricane clips per
panel used to fix the panel to each
other.
Each clip positioned roughly one third
(600-800 mm) from the top and the
bottoms of the panels respectively.
Technical File Page 18
In-line Panel Fixing Required:
Hurricane clips
Hammer
Staples & staple gun
Panel Alignment Device
Spirit level
Four inch nails
Two on the inside and two on the
outside of the panels.
Starting in the corner ensures the
accuracy of alignment of the panels.
Start fixing panels in both directions
using teams of three carpenters. You
may use the four inch nails to help fix
panels and base plate together.
The internal and external panels are
also skew-screwed to the base plate,
each other along their lengths (with 4
M6, 75mm coach screws per length,
but only from the inside face). Screws
are inserted in holes that have been
pre-drilled in the factory.
Technical File Page 19
STAGE 7 – WALL PLATES
1. Wall plates of 76 x 38mm are secured to the top of all wall panels with galvanised
clout nails at 1m intervals at panel uprights. A second layer of wall plates is nailed to
the wall plates on the external panels only, using galvanised clout nails, also at 1m
intervals as shown:
Figure 11 Figure 12
Prior to nailing the wall plates in position, 680mm lengths of light gauge roof bracing are
inserted between panel top and wall plate at 750mm centres. The bracing will be used to
fix the trusses to the wall plate and the wall panels where the trusses do not coincide with
a panel upright i.e. every 1.5m.
Where the trusses do coincide with the panel uprights (at every third upright) the bracing
must go from the upright across the top of the “truss-fill-in” panel down the inside. The
brace is to overlap the panel upright by at least 150mm on either side of the panel, with a
total length of approximately 680mm.
All bracing is to be secured into the upright by at least 2 “serated” nails at 100mm
centres.
All corners where walls are longer than 1m are to receive a 38mm thick timber bracing of
1.41m which is set at 45˚ and forms part of the second wall plate layer. The bracing is
Technical File Page 20
fixed onto the first wall plate layer (similar to the second wall plate layer), 1m from the
corner, as illustrated in Figure 13 and Figure 14:
Figure 13
Figure 14
2. The roofs are all designed and erected on site by a qualified roofing sub-
contractor with the appropriate A19 certification. The roofs are to be braced
internally so as to act as horizontal diaphragms that carry transverse wind loads on the
walls to the orthogonal walls which act as shear walls.
3. Each gable overhang must be one tile wide.
Technical File Page 21
4. Roof eaves must have an overhang of two tiles each side subject to the distance
between houses which may require that the eave overhang be shortened.
5. Trusses, which are exposed to the elements, are treated with creosote.or similar
wood preservative.
STAGE 8 – ROOFING
1. Readykit system is compatible to any roofing system.
2. The pitched tile roof is the recommended system to use with the Readykit panels.
This will require the double wall plate and the standard purlin and batten process.
Tiles or sheeting are done in accordance with the SANS 1082.
3. If an iron or lightweight roof sheeting used the trusses must be at 1m centres and
can have a single wall plate.
4. Roof trusses must be braced across and fixed with hurricane clips fully nailed.
Technical File Page 22
4) WALL PANEL MANUFACTURING
PANEL FABRICATION
1. The system involves the fabrication of wall panels in a factory. Panels have the
window frames, door frames and electrical conduit, switch and plug boxes
installed in the factory this also includes the J2 shallow connection box and
distribution board. Although fabrication is simple, the process requires precise
management of the numbering of each panel so that the correct house is sent to
site.
2. Panels are made of SA Pine of dimension 76mm x 38mm. All panels have an
external width of exactly 1m, or 1.5m, or 2m, and an overall height of 2.476m.
This height can vary according to specifications for higher ceilings and may be
increased up to 3.076m high.
3. As per figure 8 above, each panel comprises three long uprights of 2.4m and a top
and bottom horizontal member nailed to each end plus horizontal bracing at about
260mm intervals. Steel jigs are made from welding angle iron about 30mm x
30mm with the flat side inwards and used to construct the panels to exact size.
4. Window frames are inserted and nailed into position leaving 25mm protruding
beyond the panel timber. A Sondor closed cell foam strip is compressed between
the panel and the window frame.
5. Door frames are similarly nailed into position..All wire nails to be 75mm long.
The following description sets out the manufacturing procedure of door and
window panels
Technical File Page 23
PROCEDURE FOR DOOR AND WINDOW PANELS
1. The full width of the wall panels (and thus the window and door reveals) is
126mm (76 + 25 + 25).
2. In order to increase the overall width of the frames to 126mm to match the plaster
reveals, sub-frames are attached to the window frames.
3. These composite frames are installed into the wall panels such that the window
frames project 25mm beyond the outer faces of the timber wall panels and the
sub-frames project 25mm beyond the inner faces of the timber wall panels. A
116mm x 5mm Sondor closed-cell foam strip (SPX 33 PSA) is glued to the outer
perimeter of the composite frame which is then fitted into the framed opening in
the wall panel. The wall panel opening is 2,5mm wider than the composite frame,
(i.e. 2.5mm on each side of the window), resulting in a 50% compression of the
closed-cell foam strip. This ensures a good waterproof seal between window
frame and wall panel. When the walls are plastered, the protruding frames
provide a template against which to plaster and the Sondor strips form flexible
edges to allow for movement between window or door frames and plaster.
Technical File Page 24
4. Doors are similarly treated.
Figure 9
5. External open-in doors must be fitted with a weather bar similar to the one shown,
attached to the outside of the door:
Figure 70
Technical File Page 25
6. All wall panels have a sheet of Marley underlay sheeting on both faces of the
panels. The next step is to affix the Marley sheeting to both sides of the panel
with the staple gun. The sheeting then serves as a waterproofing layer as well as
for strength and to plaster on.
7. The Marley sheeting is fixed onto the Noggins via 1010 Staples (10mm in length,
and 10mm crown width) and pneumatic staple guns, as used in the upholstering
industry. The staple guns are powered by a small compressor. Two additional
strips of mesh (76mm wide) are fixed to the left side of a Panel and serves to
overlap the junction with adjacent panels.
8. Those panels that are to receive electrical conduits will have 25mm holes to allow
the conduit to protrude about 150mm above the panel and go down low enough to
the light switch, external light fitting, or wall plug as per the house design. Four
short conduits are required near the top of the panel that will contain the
distribution board, J2 shallow connections box.
9. Once completed and quality checked, each panel is numbered for according to
position house and placement in the wall, to ensure for easy erection on site.
Technical File Page 26
5) FACTORY DOCUMENTATION
This document contains all necessary information to start manufacturing of
Readykit panels. It furthermore contains requirements for all the tools, materials,
health and safety, manufacturing process and proposed layout necessary to start up
a factory and produce panels.
All the materials and tools listed are examples taken from the factory or a better
alternative is proposed. Any alternatives are used at your own discretion.
Raw Materials:
The following table of materials does not contain recommended quantitative, since
this is dependent on the rate of supply versus consumption which is unknown. The
rule for defining the raw material buffers is that the buffer must be equal to the
maximum estimated consumption within the reliable time to replenish the buffer.
Technical File Page 27
Material: Description: Sizes/purpose:
Timber Tanalith Treated Grade 5 SA
Pine, Dried and Sawn
38 x 76mm
Noggins
Tanalith Treated Grade 5 Sa
Pine, Dried and Sawn
16 (minimum) x 76mm
Door Frames Order form supplier Open-in
door frame 895 x 2116mm or
open-out door frame 895 x
2103mm for external doors.
Internal doors 870 x 2050mm
Window Frames; Swartland Customized
Winsters for Readykit panels
or alternatively WINKLIK
from Cipco (Pty) Ltd.
600mm (615 x 920mm)
900mm (920 x 920mm)
1200mm (1160 x 920mm)
Meranti wood from a supplier 70 x 22 x 3000mm planed
meranti – is used on top of
doorframe to increase size
Marley Underlay Marley sheet waterproofing
tile membrane
Standard roll of underlay
Electrical Conduit piping UPVC 25mm thick/diameter
Electrical outlet box Standard box 105 x 105 x 40 mm
Distribution Board Mod- 12- econ-5 Only one size with that type
J2 shallow connection box Standard box 105 x 105 x 40 mm or
equivalent
Staples Standard staples for staple gun 10/13/16mm long staples
Technical File Page 28
Material: Description: Sizes/purpose:
Nails Standard for nail gun you have Box details of T38 & T64
Timber treatment Maxi Care – mahogany (or
equivalent)
5 l
Bitumen Paint Super Laykold bitumen black
paint as a waterproofing
system
Used on base plates only not
needed for the panels
Silicon Standard Black silicon from
penny pinchers
For waterproofing corners of
walls In tube( only one size) to
fit sealant gun
Waterproofing Rubber foam from Sondor
Industries
115 x 5 mm
Masking tape Standard 24mm- to number base plates
on top of the bitumen
Spray paint Any standard paint – Red or
Black, or both
Used to mark the panels
Stencils for numbering Custom made or bought
numbers 1 to 9, to number
panels
Made out of A5/A4 sizes card
Timber/steel Storage bins/shelves Hand made storage bins to
store the cut timber pieces.
Extra shelves or tool racks if
necessary
Technical File Page 29
Material: Description: Sizes/purpose:
Glue Alcolin, Water based glue
(wood glue)
Alcohol water proofing ultra
water based glue
Screws Drywall screws 9 x 30 mm
Technical File Page 30
Tools:
Tool
Description
Size/designation: Minimum
Recommended
QTY
Recommended
brand (reliable
products):
Picture
Pneumatic
Nail Guns
Standard
compressed air nail
gun
Fit nails 22-64mm
2 Testo – t-type
Technical File Page 31
Pneumatic
Staple Guns
Standard air stapler
Fit staples 6 –
22mm
2 Raco air tools
6. 22mm s - type
Air
Compressor
Standard
1 No
recommendation
Technical File Page 32
Compressor
piping
Standard – to fit
your specific
compressor and
nail/ staple gun
2 pipes +
Connection to
use two tools at
once
No
recommendation
Radial Arm
Saw
Minimum blade size
of 300mm
1 Dewalt
Technical File Page 33
Cross cut
Hand saw
700 x 525 mm or
bigger
1
Stanley
G clamps 4 – 7+ adjustable
clamps
4 Irwin
Sash clamps 2000mm long
4 Sealey
Technical File Page 34
Rubber
mallets
Minimum size of
200mm long
1 No
recommendation
Hand Drills Standard electric
drill
1 Makita
Technical File Page 35
Flat steel
wood drill
bit
Standard set – steel
1 set – most
important a
25mm bit
Most likely come
with the drill or
buy the same
brand as drill
Craft knife Standard 2 Stanley
Side
cutter/Cuttin
g pliers or
combination
pliers
Standard 1 Stanley
Technical File Page 36
Square
measure
Standard (500 and
over)
1 Stanley
Claw hammer
Standard - used
more for taking
nails out
2 Any
Tables or
pine boards
2440 x
1220working tables
2 No
recommendation
(good quality
required though)
Technical File Page 37
Spindles for
Duramesh
and
Undertile
membrane
Minimum of
2000mm
2 – 1 for each No
recommendation
Toggle
clamps
Minimum of 4
inches
6 Irwin/sealey
Technical File Page 38
Measuring
tape
2 x 5m 2 Stanley
X amount of
Leads/cords
Dependent on
factory size
Dependant on
layout and plug
points
No
recommendation
Technical File Page 39
Circular
table saw
Minimum of
300mm blade
1 Dewalt
Drill press Standard
With a 13mm
capacity chuck
1 Dewalt
Technical File Page 40
Sealant gun Standard 1 Stanely
Screw driver
set
Star and flat for
work on the factory
machinery
One star and flat
or ideally a set
Bosch
Small tool Set as required
Technical File Page 41
Health and safety Equipment and Requirements:
The health and safety in any factory is very important and of a high priority. The
following merely serve as a few guidelines. It is the franchisee’s responsibility to ensure
that they are aware of and meet all the health and safety requirements in terms of the law.
Appoint a safety officer for the factory. Such a person should preferably have
completed a first aid course.
A dust mask and a pair of safety goggles are to be issued to all workers, as well as
suitable clothing, i.e. overalls.
Suitable shoes, all factory workers must have closed shoes, preferably safety
boots.
All equipment and tools must have a suitable area in which to be stored, as
anything left lying around will be a health and safety hazard. There must be
suitable working area for each table/machine etc. as to ensure people are not
working on top of each other.
Demarcate safety zones around equipment
Post safety signs in suitable places
Ensure all equipment is kept in a good state of repair
Ensure all workers are properly trained to use their equipment safely – especially
circular saws – these units can very easily maim and/or kill workers! Be
particularly aware that loose clothing / long hair etc can become entangled in
rotating equipment and cause serious harm.
Gloves are recommended if rough wood (un-planed) is handled
Be careful when stacking / storing panels so as not to create a safety hazard (e.g.
toppling).
Fire safety requirements and standards have to be met in terms of the building.
Furthermore it is a requirement to have a fire hose and fire extinguisher – dry
powder serviced regularly. The local fire station can be a good source of
guidance and training.
There must be a well stocked first aid kit available and accessible in case of an
emergency/accident.
Technical File Page 42
Factory Layout
In order to ensure the best productivity and working environment with the best flow it is
important to ensure the factory layout is set out well. Therefore knowing the process of
what is going to happen in the factory is very important. All consideration in terms of
storage and movement of machinery and materials must be taken into account before the
layout is completed.
The process of the panel manufacturing needs to be considered. The wood is ordered in
and the radial/circle saw is used to cut the right lengths, this wood is then stored in the
bins. This means most of the work is then done on the jigs and the tables. The wood is
then moved from the bins to the jigs to start assembly. Once the frame construction is
complete, the panels move across to the wrapping tables. This is where the panels get
completed. The mesh underlay and any other material is added. Also to be considered is
where the tools are to be stored as they need to be in close proximity of the applicable
table. The timber door and window frames must also be situated close to the jigs, for
when built into the panels.
The numbering of the panels, using the spray paint should be done in a well ventilated
area.
It may be decided to produce panel to stock, in which case a stock room will be required
and the numbering of the panels will take place just prior to shipping.
A recommend factory layout is provided below.
Technical File Page 44
7) QUALITY TESTS
The Quality Tests follows in the following order:
SABS Fire Resistance Test
SABS Structural and Rain Penetration Tests
Agrément Assessment of Thermal Performance, Energy Usage and Condensation
Rational Design by HMG Structural Engineers
Technical File Page 64
DURACASA – READYKIT HOUSING – RATIONAL DESIGN
DESIGN OF BASIC UNIT
Basis of design
1. Internal walls not taken into account for lateral loads to allow for complete flexibility.
2. Roof to be designed to act as horizontal diaphragm so that lateral loads on a 6m x 2,5m wall panel
will be equally shared between foundation and roof and resisted by sheer capacity of side walls.
3. Wall panels orthogonal to the lateral loads to be designed to span foundation-to-roof (i.e. vertical
spanning)
Wind loads – SABS 0160 (table 5)
Assume Ter. Category = 2
Element class = B
Basic wind speed = 40m/s
Site altitude = 0 m A.S.L
Building height = < 5m
Wind speed multiplier kz = 0,92
Technical File Page 65
Therefore Vz = 0.92 x 40 = 36,8
qz = kp.v² where kp = 0,6 (0 m ASL)
qz = 0,6 x (36,8)² ÷ 10³ kN/m²
= 0,812 Kpa
Cpe (wall) = 0,7 or –0,2 Cpi = 0,0 or –0,3 Cpe (roof) = -0,9
Check wall panel for vertical spanning (excluding reinforced plaster)
Because of 25mm reinforced plaster attached to both sides of panel, the wind load will be equally shared
between the 3 vertical members.
Wind pressure on panel
= (Cpe + Cpi) x qz = 1,0 x 0,812 = 0,812 Kpa
Moment = 0,812 x 1,0 x (2,5)² = 0,634 kNm
8
Resistance
Permissible stress in timber = fb x k1 x k2 (k1 = duration of load)
Technical File Page 66
(k2 = sharing)
k1 = Wd + Ww
Cfd + Cfi Wi
But dead load not considered
Therefore k1 = Ww = 1 = 1 = 1,5
Cfi. Ww Cfi 0,66
k2 = 1,15 (Sharing due to spacing < 0,6m)
Therefore: For grade 5 timber:
Permissible stress fb = 5,0 x 1,5 x 1,15
= 8,6 Mpa
Resistance moment = Z x fb -6
= 38 x 3 x (76)² x 8,6 x 10 = 0,944 kNm
6 (< 0,634) Therefore Ok
Consider racking of shear walls
Technical File Page 67
Wr = Mass of half roof
Ww = Mass of wall
F = 0,812 x 2,5 x 6,0 = 3,04 KN
2 2
Mass of roof : (minimum)
A Roof sheeting = 0,08kPa x 3,0 = 0,240 kN/m
B Rafters = 5,0 x 0,22 x 0,038 x 3,0 = 0,125 kN/m
C Purlins = 5,0 x 0,076 x 0,05 x 1 = 0,016 kN/m
1,2
______
0,38 kV/m
Therefore Wr = 0,38 x 6,0 = 2,28kw
Mass of wall :
a) frame = 5,0 x 0,038 x 0,076 x ((2,5 x 3) + (1,0 x 6)) = 0,195 KN/m
b) plaster = 24 x 0,02 x 2 x 2,5 = 2,4 kw/m
2,59 kn/m
Technical File Page 68
Therefore Ww = 2,59 x 6,0 = 15,57kn
OTM = 3,04 x 2,5 = 7,6 knm
RM = (15,57 +2,28) x 3,0 = 53,55 knm
Therefore OK against racking
Principle Tensile Force (diagonal) = 3,04 x 1
Cos x
(Where x = arc tan 2,5 = 22,61º)
6,0
Therefore Principle tensile force = 3,04 x 1 = 3,3kn
Cos 22,61º
Tension in say 100 wide band of plaster/mesh each side
= 3 300 = 16,5 N/mm
2 x 100
Duramesh R080 strength = 160 N/cm or 16N/mm
Duramesh 155 strength = 360 N/cm or 36N/mm
Therefore either will have sufficient tensile strength – OK
Roof Uplift:
Wind uplift = (Cpe + 0,2) qz (allowance for dominant opening on windward wall
= (0,9 + 0,2) x qz
= 1,1 x 0,812 = 0,893 kPa
Therefore force on wall =0,893 x 3,0 = 2,68 kN/m
From page 3, Mass of (roof + wall ) = Wr + Ww =
2 = 2,28 + 15,57 = 17,85 kN/m
Therefore Mass of wall = 17,85 = 6,66 = F.O.S. (uplift)
Uplift 2,68
Technical File Page 69
Total length of timber in truss
= 6,0 + (6,0 x 1 ) + 1,5 + 1,5 + 0,35 = 15,44
cos 10º
Say 16m
Roof Trusses
@ 1000 c/c
W = Sheeting 0,08 kPa = 0,08 kN/m
Purlins 0,076, x 0,05 x 1,0 x 5 = 0,019 kN/m
Trusses 0,114 x 0,038 x 16 x 5 = 0,347 kN/m
(Ceiling) = 0,150 kN/m
L.L = 0,3 = 0,30
0,816 kN/m (or kPa)
Heel joint - F: 0,816 x 3,0 x 1 = 14,097 kN
Sin 10º
Stress in rafter = 14097 = 3,25 Mpa = σc
Technical File Page 70
114 x 38
L/b = 1000 = 26,3 Therefore Pc = 3,64 Mpa = therefore OK
38
Foundation (See construction manual)
Alternatively raft foundation as follows:
Technical File Page 71
STEP 1 450 X 450 X 50 CONCRETE PAVING SLABS
STACKED TOSUIT LEVELS PLACED AT EACH
CORNER OF 6M X 6M UNIT TO SUPPORT
NAILED-TOGETHER FRAMES
STEP 2 ERECT FRAMES
STEP 3 DIG TRENCH AND LEVEL OFF GROUND FOR
CASTING SLAB
STEP 4 WRAP SOLE PLATES WITH DPC
STEP 5 CAST SLAB AND THICKENING TOGETHER
Check on wall panels: (2,7m high)
From original calcs page 2 qz = 0,812
Cpe + Cpi = 1,0
Technical File Page 72
M = 1m0 x 0,812 x (2,7)² = 0,7399 kNm
8
6
fb = 0,7399 x 10 x 6 = 6,74 Mpa
3, (76)² x 38
Load duration coefficient =0,66 (wind load)
Therefore k1 = Wo + Ww
1,0Wo + 0,66 Ww
= Ww
0,66Ww (DL = 0 laterally)
= 1,51
Load sharing factor kz = 1,15
Therefore Pb = 5,0 x 1,5 x 1,15 = 8,6 MPa for grade 5
= both of these are greater
Technical File Page 73
than 6,74 therefore OK
= 4,0 x 1,5 x 1,15 = 6,9 MPa for grade 4
Therefore No shear connection required
Roof x Roof support (Cement tiles on battens on trusses)
All roofs are to be designed and erected on site by a qualified roofing contractor with the
appropriate A19 certification. The roofs are to be braced internally so as to act as
horizontal diaphragms that carry transverse wind loads on the walls to the orthogonal
walls, which act as shear walls
This clause is included in the Housing Construction Manual (submitted herewith and to be included in
tender documents for builders wishing to be trained and certified as approved erectors of the houses)
Check wall panels for truss loads:
Trusses at 750 c/c
Span = 6,15m
Technical File Page 74
Worst case is when truss is mid span between panel edge and panel centre post (As A above)
NOTE! INTERNAL WALLS ARE NOT LOAD-BEARING
Roof loads: (Timber density = 5 kN/m³)
1 Roof tiles = 0,49 kPa
2 Battens (0,038)² x 5 x 1 = 0,029 kPa
0,25
3 Trusses 0,114 x 0,038 x 3,0 x 5 x 1 = 0,087 kPa
0,75
4 Ceiling = 0,15 kPa
5 Superimposed Load = 0,30 kPa Roof bed 1,056 kPa
= 1,056 kPa
Truss Span = 6,15 m
Therefore Point load on wall plate = 6,15 x 0, x 1,056 = 2,435 kN
2
Total DL = 0,756 kPa
Total LL = 0,300 kPa
Technical File Page 75
Pb = 5,0 x k1 (Where k1 = 0,756 + 0,3 = 1,103)
0,756 + (0,67 x 0,3
Therefore Pb = 5,0 x 1,103 = 5,517 MPa
-6
Therefore MR = 5,517 x (38)² x 75 x 10 = 0,0996 KNm
(75 x 38) 6
MR = 5,517 x (50)² x 75 x 10 = 0,172 kNm
(75 x 50) 6
From Prokon: (See attached Prokon output pages 01 – 06)
75 x 50 wall plate is continuous @ A and B
75 x 38 top plate is continuous @ A and simply supported @ B
Technical File Page 76
From Prokon Analysis (Pages 01 – 06, attached)
50 x 75 wall plate moments
Moment (wall plate) = 0,16 kNm (less than 0,172 kNm therefore OK)
Moment (top plate) = 0,06 kNm (less than 0,0996 kNm therefore OK)
Consider uplift
From page 5 uplift pressure = 0,893 kPa
DL = 0,756 kPa
Nett uplift = 0,137 kPa
Therefore nett uplift at truss end = 0,137 x 0,75 x 6,15/2
= 0,316 kN
Capacity of M10 coach screw (75 long) in tension
= 0,74 KN (for 25 penetration)
Technical File Page 79
Lintol moment = 2,435 x 1,0/4 = 0,6088 kNm
Fb = 0,6088 x 10 x 6 = 3,748 Mpa (OK)
(114)² x 75
Check side walls as shear walls
Consider the wall panels acting as shear walls
Technical File Page 80
Wind force P1 = 0,893 x 0,7 x 3,0 x 2,5 = 2,3 kN
2
Wind force P2 = 0,893 x 0,2 x 3,0 x 2,5 = 0,67 kN
2
P1 + P2 = 2,97 kN
2,97 8 (per panel)
Technical File Page 81
Mass of each panel = 2,59kN (from page 3)
Moms about A (Per panel)
OTM = 2,97 x 2,5 = 0,928 kNm
8
RM = (2,32 + 2,59) x 0,5 (ignoring F)
= 2,455
Therefore ignoring shear resistance between panels (F),
F.O.S = 2,455 = 2,645 (OK)
0,928
Therefore the mass of roof and individual wall panels is sufficient to overcome racking force of each panel
due to horizontal wind load.
Therefore the panel connections through nailing need only be nominal.
Technical File Page 82
In addition to this, there is a certain amount of shear connection between panels through the mesh-
reinforced plaster.
Therefore shear walls are sufficiently braced.
Each individual panel is stiffly braced by the diaphragm effect of the mesh-reinforced plaster connected to
the timber frame.
In summary:
The above calculations prove the stability of the system under dead, live and wind loading.
The Housing Construction manual provides additional information regarding the erection procedure, which
is to be strictly adhered to, and monitored by an appointed professional engineer,
The roof is to be designed and constructed by a suitable A19 certified roofing company and braced to form
a diaphragm between walls.
The Housing Construction Manual is to be read as part of this rational design.
Technical File Page 83
8) APPROVALS
The approval documents follows in the following order
Letter from Cape Town City Planner’s Department
Letter from Western Cape Provincial Administation
Letter from NHBRC
Letter from Standards Association of Zimbabwe
Technical File Page 88
9) PREVIOUS BUILDINGS
1994: 8 Mqaai St, Makana Sq, Langa, Cape Town
Erected after 2 days
Completed – 17 days later
1995: 9 Protea Circle, Ocean View
First day
Completed – 22 days later
1994: Offices for Portnet Container Port, Cape Town Harbour
Technical File Page 89
2005: Show house, Erf 52808, Weltevreden, Parkway, Highlands Village, Cape Town
2 Bedrooms, 52m2 plus car port