8/18/2019 Technical Code for Testing of Building Foundation Piles
1/105
National Standard of the People’s Republic of China
Technical Code for Testing of Building Foundation Piles
JGJ 106—2003
Approved by: Ministry of Construction, P.R.China
Implemented from July 1 of 2003
2003 Beijing
8/18/2019 Technical Code for Testing of Building Foundation Piles
2/105
2
Ministry of Construction, P.R.China
AnnouncementNo.133
Announcement on the Issuance of Technical Code for
Testing of Building Foundation Piles
This is to approve Technical Code for Testing of Building Foundation Piles as industrial
standard (refer. No. JGJ106 —2003) and implement it from July 1 of 2003. In this Code,
Clause 3.1.1, 4.3.5, 4.4.4, 6.4.6, 8.4.7, 9.2.3, 9.2.4, 9.4.2, 9.4.5, 9.4.15 are mandatory
stipulations, which shall be implemented strictly. the previous industrial standard Regulations
for High Strain Dynamic Testing of Foundation Piles (JGJ106 —97) will become invalid at the
same time.
This Code shall be published and distributed by China Architecture Industry Press organized
by the Standard Norm Research Institute of the Ministry of Construction.
Ministry of Construction, P. R. China
March 21, 2003
8/18/2019 Technical Code for Testing of Building Foundation Piles
3/105
3
Foreword
This Code is laid down the Code Compilation Team according to document (JB[2000]No.284)
issued by the Ministry of Construction after this team has carried out universal investigation
and research, has summed up practical experience and scientific research results of the testing
of foundation piles of domestic and international pipe foundation job, and has collected
universal opinions.
Main technical contents of this Code are as follows: general provisions, terms and symbols,
basic regulations, vertical compression resistance static test of single pile, single pile, vertical
uplift static test & horizontal static test of single pile, core drilling, low strain integrity
testing , high strain dynamic testing , crosshole sonic logging, etc.
The Ministry of Construction shall be responsible for management of this Code and
explanation of mandatory clauses, the compilation institutions shall be responsible for
explanation of technical contents.
Compilation institutions of this Code:: China Academy of Building Research address: 30#,
North Sanhuan Donglu, Beijing; Post Code: 100013
Institutions participating in compilation of this Code:
Guangdong Building Science Research Institute
Shanghai Gangwan Engineering Design & Research Institute
Metallurgical Industry Engineering Quality Supervision Station Testing Center
Wuhan Institute of Rock and Soil Mechanics of Chinese Academy of Sciences
8/18/2019 Technical Code for Testing of Building Foundation Piles
4/105
4
Shenzhen Survey Research Institute
Building Science Research Institute of Liaoning Province
Building Engineering Quality Examination & Testing Center of Henan Province
Building Science Research Institute of Fujian Province
Building Science Research Institute of Shanghai
Prepared by:
Chen Fan Xu Tianping Zhu Guangyu Zhong Dongbo
Liu Minggui Liu Jinli Ye Wanling Teng Yanjing
Li Dazhan Liu Yanling Guan Lijun Li Rongqiang
Wang Minquan Chen Jiuzhao Zhao Haisheng Liu Chun
Ji Cangjiang
8/18/2019 Technical Code for Testing of Building Foundation Piles
5/105
8/18/2019 Technical Code for Testing of Building Foundation Piles
6/105
6
8.1 Scope of Application ...............................................................................................56
8.2 Instrumentations....................................................................................................56
8.3 On-the-Spot Inspection............................................................................................57
8.4 Analysis and Determination of Measured Data.......................................................59
9. High Strain Dynamic Testing ...............................................................................................63
9.1 Scope of Application ..................................................................................................63
9.2 Equipments.................................................................................................................63
9.3 Site Test ......................................................................................................................64
9.4 Analysis and Determination of the Test Data .............................................................66
10. Cross-hole Sonic Logging..................................................................................................74
10.1 Scope of Apllication ..............................................................................................74
10.2 Equipments............................................................................................................74
10.3 Site Test ....................................................................................................................75
10.4 Analysis and Determination of the Test Data ...........................................................76
Appendix A Endogenetic Force Test on the Pile Body..........................................................84Appendix B Treatment of Pile Toe of Concrete Pile .............................................................91
Appendix C Static Load Test Record Form...........................................................................92
Appendix D Records of Core Extraction Test .......................................................................94
Appendix E Core Sample Processing and Measuring..............................................................97
Appendix F Installation of Stress Sensor .................................................................................99
Appendix G Trial Pile Driving and Monitoring of Pile Driving ............................................101
G.1 Trial Pile Driving .....................................................................................................101
G.2 Monitoring of Hammering Stress of Pile Body .......................................................102
G.3 Monitoring of Hammering Energy........................................................................103
Appendix H Points of Burying Sound Ranging Pipes.........................................................104
Terminology in the Code................................................................................................105
8/18/2019 Technical Code for Testing of Building Foundation Piles
7/105
7
1. General Provisions
1.0.1 In order to ensure work quality of testing of foundation piles, unify the testing of
foundation piles, provide reliable reference for design and construction acceptance,
make quality testing of foundation piles meet requirements of “safe, applicable,
advanced in technique, exact data and correct assessment, this Code is hereby drafted.
1.0.2 This Code is applicable for testing and assessment of the bearing capacity and the pile
integrity of foundation piles of construction projects.
1.0.3 Method for testing of foundation piles shall make reasonable selection and allocation
after considering such factors geologic condition, pile type and reliability of
construction quality, requirement for use according to features and applicable scopes
of all kinds of testing methods. Result of testing of foundation piles shall be
analyzed and determined according to the aforesaid factors.
1.0.4 Quality testing of foundation piles of construction projects shall execute this Code and
shall meet regulations of the state’s existing relevant compulsory standards.
8/18/2019 Technical Code for Testing of Building Foundation Piles
8/105
8
2. Terms and Symbols
2.1 Terms
2.1.1 Foundation Pile
Individual pile in pile foundation.
2.1.2 Pi1e Integrity
It reflects relative change of overall stationarity indices of shaft section size,
compactness of shaft material and continuity.
2.1.3 Pile Defects
a general designation of some phenomena such as shaft break, split, ;necking effect ,
slurry clamp sundries , hollow hole, honeycomb, unconsolidation, which can
deteriorate shaft integrality and cause reduction of shaft structure strength and
durability.
2.1.4 Static loading test
Vertical pressure or vertical upward pulling force or horizontal thrust shall be exerted
stage by stage on pile top, operator shall observe sedimentation occurring on the pipe
top along with the time, lift up displacement or horizontal displacement, in order to
determine test methods for vertical compression resistance bearing capacity of
relevant single pile, vertical uplift bearing capacity of single pile or horizontal bearing
capacity of single pile.
2.1.5 Core drilling method
A method to test the pile length, shaft defect, dreg thickness of pile toe, strength,
compactness and continuity of shaft concrete through drilling core sample by driller,
8/18/2019 Technical Code for Testing of Building Foundation Piles
9/105
9
in order to determine rock and soil characters of pile end.
2.1.6 Low strain integrity testing
A testing method, in which, operator shall carry out an excitation on pile top by using
a low energy transient state or stable state excitation mode, measure velocity time
interval curve or velocity admittance curve of pile top, in order to determine shaft
integrality through wave movement theory analysis or frequency domain analysis.
2.1.7 High strain dynamic testing
A testing methods, in which, operator shall shock pile top by using thumper, measure
velocity and time interval curve of force of pile top, in order to determine vertical
compression resistance bearing capacity and shaft integrality of single pile through
wave movement theory analysis.
2.1.8 Crosshole sonic logging
A testing methods, in which, testing is carried on shaft integrality by transmitting and
accepting the sound wave among the embedded sound logging pipe through relative
changes of some acoustic parameters actually measured sound time, frequency and
amplitude attenuation, which is spread by sound wave in medium of concrete.
8/18/2019 Technical Code for Testing of Building Foundation Piles
10/105
10
2.2 Symbols
2.2.1 Resistance and material property
c ——Unidimensional stress velocity of wave spread of shaft abbr. wave velocity of
shaft ;
E ——elastic modulus of shaft materials;
cu f ——compressive strength of concrete core sample;
m —— proportion factor of horizontal reaction coefficient of foundation soil;
uQ ——ultimate bearing capacity of vertical compression resistance of single pile;
a R ——characteristic value of vertical compression resistance bearing capacity of single
pile;
c R ——vertical compression resistance bearing capacity of single pile determined by
Case Method;
x R —— test estimated value of soil resistance of the aforesaid parts;
v ——sound velocity of concrete shaft;
Z ——mechanical impedance of shaft section;
p ——shaft material mass density;
2.2.2 Action and action effect
F ——hammer force;
H ——horizontal force acting on the ground in horizontal static test of single pile;
p —— failure load measured from compression resistance test of core sample;
8/18/2019 Technical Code for Testing of Building Foundation Piles
11/105
11
Q ——Vertical load and shaft axis in static test of vertical compression resistance of
single pile;
s ——vertical sedimentation of pile top and vertical displacement of shaft;
U ——upwards withdrawing load exerted in static test of vertical anti-withdraw of single
pile;
V ——movement velocity of particle ;
oY ——horizontal displacement of horizontal forceaction point ;
δ ——uplift volume of pile top;
sσ ——reinforcement stress.
2.2.3 Geometric Parameter
A——shaft section area;
B——margin of rectangular pile;
ob ——calculation width of shaft;
D——shaft diameter outer diameter ;
d ——average diameter of core sample;I——conversion section moment of inertia of shaft;
l ′——clear distance of outer wall of both sound logging pipes of each testing section;
L—— length of lower pile at survey point;
x——distance between sensor installation point and shaft defect;
z——depth of survey point
2.2.4 Calculation coefficient
c J ——damp coefficient of Case Method;
α ——horizontal deformation coefficient of pile;
8/18/2019 Technical Code for Testing of Building Foundation Piles
12/105
12
β ——shaft integrity coefficient of high strain dynamic testing;
λ ——coefficient corresponding to different statistical quantity in sample;
yv ——horizontal displacement coefficient of pile top;
ξ ——conversion coefficient of compressive strength concrete core sample.
2.2.5 Other
m A ——sound wave amplitude average value;
p A ——sound wave amplitude value;
a ——value voltage of head wave peak of signal;
oa —— peak value voltage of zero decibel signal;
mc ——average value of wave velocity of shaft;
f —— basic frequency of frequency and sound wave signal;
n ——quantity and sample quantity;
xs ——standard deviation;
T ——signal cycle;
t ′ ——corrected value of sound logging pipe and coupling the sound time of water layer;
ot ——delay time of instrumentations system;
1t —— time corresponding to the first peak of velocity;
ct ——sound time;
it ——measured value of time and sound time;
r t ——ascending time of hammer force;
8/18/2019 Technical Code for Testing of Building Foundation Piles
13/105
13
xt —— time corresponding to defect echo peak;
ov ——abnormal judgment value of sound velocity;
cv ——critical value of abnormal judgment of sound velocity;
Lv —— lower limit value of sound velocity;
mv ——average value of sound velocity;
f Δ —— lower limit among neighboring resonance peaks of pile toe on amplitude
frequency curve;
f ′Δ ——frequency difference among defect neighboring resonance peaks on amplitude
frequency curve;
T Δ —— time difference among the first peak of velocity wave and echo wave peak of
pile toe;
xt Δ —— time difference between the first peak of velocity wave and defect echo wave
peak.
8/18/2019 Technical Code for Testing of Building Foundation Piles
14/105
14
3. Basic Regulations
3.1. Testing Methods & Contents
3.1.1 Bearing capacity& shaft integrity sampling testing of single pile shall be carried
out on engineering piles.
3.1.2 Testing methods for foundation pile shall be chosen according to 3.1.2. on the basis of
testing aim.
Form 3.1.2 Testing Method & Testing Aim
Testing Method Testing Aim
Vertical compressionresistance static testof single pile
Determine vertical compression resistance ultimate bearing capacity ofsingle pileDetermine whether vertical compression resistance bearing capacitymeets requirement of design.Determine resistance of pile side and pile end through shaft internalforce and deformation testing;Verify vertical compression resistance bearing capacity testing results ofsingle pile of high strain dynamic testing.
Vertical uplift statictest of single pile
Determine vertical anti-draw ultimate bearing capacity of single pileDetermine whether vertical uplift bearing capacity can meet design.Determine uplift friction resistance of pile through shaft internal forceand deformation testing,
Horizontal static testof integrity
Determine horizontal critical and ultimate bearing capacity of single pile to conclude soil resistance parameters.Determine whether horizontal bearing capacity can meet design.
Determine bending moment of shaft through shaft internal force anddeformation testing.
Core drilling Test cast-in-place pile length, shaft concrete strength, dreg thicknessof pile toe, judge or identify rock and soil character of pile end,determine shaft integrity type.
8/18/2019 Technical Code for Testing of Building Foundation Piles
15/105
15
Low strain integritytesting
Testing shaft defect and its position, determine shaft integrity type
High strain dynamictesting
Determine whether vertical compression resistance bearing capacity ofsingle pile can meet design;
Test the shaft defect and its position, determine shaft integrity typeAnalyze pile side and soil resistance of pile end
Crosshole soniclogging
Test the shaft defect of cast-in-place pile and its position, determineshaft integrity type.
3.1.3 Shaft integrity testing shall adopts two kinds or many kinds of proper testing method.
3.1.4 Foundation pile testing shall be executed before and after construction, and shall meet
testing method in this Code or other testing method in processional acceptance code,
testing shall be done during pile foundation construction process, quality control of
construction process shall be strengthened.
8/18/2019 Technical Code for Testing of Building Foundation Piles
16/105
16
3.2 Testing Procedures
3.2.1 Procedure of testing work shall be executed according to Fig 3.2.1:
Fig. 3.2.1 Diagram of Testing Procedure
3.2.2 Investigation, data collection phase shall include the following:
1 Collect rock engineering survey data, pipe foundation design drawings and construction
records of the testing job; understand abnormal situation occurring in construction
Receiving the entrust
InvestigationData collection
Prepare testingscheme
Preparation in earlierstage
On-the-spotInspection
Calculation analysis and resultsappraisal
Testing report
Verification ofinstrumentations
Reinspection, verification, expansionof testing
8/18/2019 Technical Code for Testing of Building Foundation Piles
17/105
17
process.
2 Further explicate concrete requirement of the entrusting party.
3 Feasibility for implementation of the testing project on site.
3.2.3 According to investigation results and determined testing aim , operator shall choose
testing method, lay down testing scheme. Testing scheme shall contain the following
contents: job summary, standard for testing method and its reference, sampling scheme,
machines or labor needed, test cycle.
3.2.4 Instruments shall be checked and debugged before testing.
3.2.5 Measuring instruments for testing must be in validity period of metrological
verification .
3.2.6 The starting time for testing shall meet the following regulations:
1 When low strain integrity testing or crosshole sonic logging testing is adopted,
concrete strength of testing pile shall amount to at least 70% of design strength, and
shall not be less than 15MPa.
2 When core drilling testing is adopted, concrete age of the testing pile shall be 28d or
strength of preset curing sample under same conditions shall meet the designed
strength.
3 Quiescent time of the bearing capacity testing shall meet concrete strength stipulated in
the above Clause 2, if no mature local experience, time shall not be less than the time in
Form 3.2.6.
8/18/2019 Technical Code for Testing of Building Foundation Piles
18/105
18
Form 3.2.6 Quiescent Time
Type of Soil quiescent time d
Sandy soil 7
Silty soil 10
Non-saturated 15Glutinous soil
Saturated 25
Note: for mortar-wall cast-in-place pile, quiescent time shall be delayed properly.
3.2.7 After construction, shaft integrity testing of job pile shall be done firstly, then bearing
capacity testing shall be followed. When foundation buried depth is bigger, shaft
integrity testing shall be done at the time of excavation of foundation pit up to
elevation of base.
3.2.8 Testing on site shall follow this Code and stipulations of safe production of the state. If
operational environment on site is not in conformity with requirements for use of
instrumentations, effective protection measures shall be taken.
3.2.9 When abnormal testing data are found, reasons shall be searched for re-testing .
3.2.10 Further verification or testing shall be confirmed by authorities concerned and shall be
executed according to Clause 3.4.1-3.4.7 of this Code.
3.3 Testing Quantity
3.3.1 If required by design, or in case of one of the following conditions, static test shall be
adopted before construction for confirmation of bearing capacity characteristic value of
vertical compression resistance of single pile:
8/18/2019 Technical Code for Testing of Building Foundation Piles
19/105
19
1 Pipe foundation with design grade A or B;;
2 Complicated geographical conditions and low reliability of construction quality of
pile;
3 New pile type or new technology adopted in this region.
Testing quantity shall not be less than 3 pieces under same conditions, and shall not be
less than 1% of total quantity of pile; and shall less than 2 pieces when total quantity of
job pile is below 50 pieces.
3.3.2 If driven prefabricated pile meets one of the following conditions, high strain dynamic
testing shall be adopted for the purpose of process monitoring of trial piling:
1 Control the shaft stress during piling process;
2 Choose instrument for driving pile and confirm technology parameters;
3 Choose end bearing layer of pile.
With same construction technology and similar geographical conditions, piling
quantity shall not be less than 3 pieces.
3.3.3 The testing pile selection for single pile bearing capacity and shaft integrity
acceptance sampling testing shall meet the following regulations:
1 Pile with defective construction quality;
2 Important pile, in designer’s opinion;
3 Pile with abnormal partial geographical conditions;
4 Pile with different construction technology;
5 In case of bearing capacity acceptance testing, type- Ⅲ pile determined in properly
chosen integrity testing ;
6 Besides the aforesaid regulations, pile of the same type shall be distributed uniformly
at random.
3.3.4 Selective examination quantity of shaft integrity testing of concrete pile shall meet the
8/18/2019 Technical Code for Testing of Building Foundation Piles
20/105
20
following regulations:
1 Pile quantity for selective examination of pile cap of three piles under column or
below the three pipes shall not be less than one piece.
2 For cast-in-place pile with design grade- A, or complicated geographical conditions, or
lower reliability of pile quality, selective examination quantity shall not be less than
30% of total pile quantity, and shall not be less than 20 pieces; selective examination
quantity of other pipe foundation job shall not be less than 20% of total pile quantity,
and shall not be less than 10 pieces.
Note: 1.For end-support-type big-diameter cast-in-place pile, operator shall choose core
drilling or crosshole sonic logging within the scope of aforesaid selective
examination pile quantity to carry out shaft integrity testing on some testing piles.
Selective examination quantity shall not be less than 10% of total pile quantity.
2. For piles with artificially excavated bores on pile end bearing layer above
groundwater level and after telotremata, which have been examined and verified,
and, for single section of concrete-prefabricated pile, selective examination quantity
can be reduced properly, but it shall not be less than 10% of total pile quantity, shall
not be less than 10 pieces.
3. When pile quantity meeting stipulation of paragraph 1-4 of Clause 3.3.3 is more, or
in order to understand shaft integrity situation of the whole job foundation pile,
selective examination quantity shall be increased properly.
3.3.5 If job pile within unit job and under same condition meets one of the following
conditions, static test of vertical compression resistance bearing capacity of single
pile shall be adopted for the purpose of acceptance testing :
1. Pipe foundation with design grade A;
2. Complicated geographical conditions, low reliability of pile construction quality;
8/18/2019 Technical Code for Testing of Building Foundation Piles
21/105
21
3. New pile type or new technology adopted in this region;
4. Construction of soil-compacting pile group produces compacting effect.
Selective examination quantity shall not be less than l% of total pile quantity, and shall
not be less than 3 pieces; and shall not be less than 2 pieces when total pile quantity is
within 50 pieces.
Note: For job pile out of the aforesaid Clause 1-4, when vertical compression resistance static test is
adopted for the purpose of acceptance of bearing capacity testing, selective examination quantity shall be
executed according this regulation.
3.3.6 For prefabricated pile out of Clause 3.3.5 and for cast-in-place pile which meets
applicable testing scope of high strain dynamic testing, high strain dynamic testing can
be adopted for the purpose of acceptance testing of vertical compression resistance
bearing capacity of single pile. When compared verification data under similar
conditions in local region are available, high strain dynamic testing can also become a
supplementation acceptance testing of vertical compression resistance bearing capacity
of single pile, as stipulated in Clause 3.3.5.Selective examination quantity shall not be
less than 5% of total pile quantity and shall not be less than 5 pieces.
3.3.7 For end-support-type big-diameter cast-in-place pile, when vertical compression
resistance bearing capacity of single pile fails to be tested due to limit by instrument or
site condition,, core drilling can be adopted for determination of dreg thickness at pile toe,
and core sample of pile end bearing layer can be drilled and taken for the purpose of
examination of pile end bearing layer. Selective examination quantity shall not be less
than 10% of total pile quantity and shall not be less than 10 pieces.
3.3.8 For pipe foundation that bears bigger pulling force and horizontal force, vertical
anti-pulling and horizontal bearing capacity testing of single pile shall be done. Testing
quantity shall not be less than l% of total pile quantity, and shall not be less than 3 pieces.
8/18/2019 Technical Code for Testing of Building Foundation Piles
22/105
8/18/2019 Technical Code for Testing of Building Foundation Piles
23/105
23
3.5 Testing Results Evaluation And Testing Report
3.5.1 Appraisal of shaft integrity testing results shall provide shaft integrity type of every
piece of testing pile. Classification of shaft integrity shall meet Form 3.5.1 and shall be
classified according to technical contents stipulated in Chapter 7-10 of this Code.
Form 3.5.1 Classification of Shaft Integrity
Type of Shaft Integrity Principles for Classification
Type-I pile Shaft in completeType-II pile Slight defect exists in shaft, which will not affect normal function
of shaft structure bearing capacity.
Type- Ⅲ pile Obvious defect in shaft has an influence on shaft structure bearing
capacity.
Type-Ⅳ pile Serious defect exists in shaft
3.5.2 Type- Ⅳ pile shall be subject to job treatment.
3.5.3 Evaluation of bearing capacity testing results of job pile shall give testing value of
bearing capacity for each piece of testing pile, and give results whether bearing
capacity characteristic value of single pile of unit job under same condition design
meets requirement.
3.5.4 Testing report shall contain exact results and standard words and expresses.
3.5.5 Testing report shall include the following contents:
1. Name of the entrusting party, name of job, place, construction, survey, design,
supervising unit and construction unit, foundation, structure type, quantity of layer,
8/18/2019 Technical Code for Testing of Building Foundation Piles
24/105
24
design requirement, testing aim, testing reference, testing quantity, testing date;
2. Description of geographical conditions;
3. Pile serial number, pile position and relevant construction records of testing pile;
4. Statement of testing method, testing instrumentations, testing process;
5. Testing data, measurement and calculation/analysis curve, form and summary result of
testing pile;
6. Testing results relating to testing contents.
3.6 Testing Institution & Testing Personnel
3.6.1 Testing institution shall be subject to measurement certification and have qualification
of foundation pile testing.
3.6.2 Testing personnel shall be qualified after being trained and have relevant qualification.
8/18/2019 Technical Code for Testing of Building Foundation Piles
25/105
25
4. Static Test of Vertical Compression Resistance of Single
Pile
4.1 Scope of Application
4.1.1 This method is applicable for vertical compression resistance bearing capacity of
testing pile.
4.1.2 If sensor or displacement pole for measurement of shaft stress, strain, pile toe
counterforce is embedded, layered side resistance and end resistance of pile or
displacement of shaft section can be measured.
4.1.3 If test pile is provided as a reference for the design, the pile shall be loaded until being
destroyed; bearing capacity of pile is controlled by shaft strength, the loading volume
required in the design shall be applicable.
4.1.4 When job pile sample is tested, loading volume shall not be less than design the
required bearing capacity characteristic value of single pile by 2.0 times.
4.2 Instrumentations and Installation
4.2.1 Test loading shall adopt oil jack. When two and more sets of jacks are used for loading,
parallel connection and synchronous work are required, and the following regulations
shall be met.
8/18/2019 Technical Code for Testing of Building Foundation Piles
26/105
26
1. Jack mode and specification to be used shall be the same.
2. Composite force of jack shall be superposed with pile axes.
4.2.2 Loading counterforce device may be crossbeam counterforce device of anchor pile
according to site condition, mould weight platform counterforce device, mould weight
counterforce device of anchor pile, earth anchor counterforce device, and shall meet
the following regulations:
1. Counterforce that can be provided by the loading counterforce device shall not be less
than maximum loading volume by 1.2 times.
2. Operator shall carry out a strength and deformation calculation on all members of
loading counterforce device.
3. Operator shall calculate anchor pile anti-pulling force foundation soil, uplift
reinforcement, pile joint ; when job pile is used as anchor pile, anchor pile quantity
shall not be less than 4 pieces, and shall monitor uplift volume of anchor pile.
4. Mould weight shall be enough before testing and shall be placed on platform stably .
5. Stress of mould weight exerted on substrate shall not bigger than 1.5 times of bearing
capacity characteristic value of substrate, if applicable, job pile shall be used as stacking
pivot.
4.2.3 Load measurement can be determined directly by load sensor which is put on the jack;
or pressure meter or pressure sensor which is in parallel connection with jack oilway
shall be adopted to determine oil pressure, curve conversion load shall be determined
according to jack rate. Measurement error of sensor shall not be more than 1%,
accuracy of pressure meter shall be superior or equal level 0.4. Pressure of pressure
meter, oil pump, oil tube used for test in case of maximum loading shall not exceed
80% of specified working pressure.
4.2.4 Sedimentation measurement shall adopt displacement sensor or wide range dial
8/18/2019 Technical Code for Testing of Building Foundation Piles
27/105
27
indicator, and shall meet the following regulations:
1. Measurement error shall not be more than 0.1% FS, resolution is superior to or equal to
0.01mm.
2. Pile with diameter or margin of more than 500 mm shall be equipped with four
displacement testing meters symmetrically on its two directions, Pile with diameter or
margin of less than or equal to 500mm shall be equipped with two displacement testing
meters.
3. The testing surface of sedimentation shall be at a position 200mm below the pile top,
survey point shall be fixed on shaft firmly.
4. Datum beam shall have a certain rigidity, one end of beam end shall be fixed on datum
pile, another end shall be erected on datum pile simply.
5. Holder for fixing and supporting displacement meter dial indicator and datum beam
shall avoid influences caused by air temperature, vibration and other factors.
4.2.5 Center distance between testing pile, anchor pile supporting pier side of mould weight
platform and datum pile shall meet Form 4.2.5.
8/18/2019 Technical Code for Testing of Building Foundation Piles
28/105
28
Form 4.2.5 Center distance between testing pile, anchor pile(supporting pier side of
mould weight platform) and datum pile
Distance
counterforce
device
Testing pile center and
anchor pile center
(or supporting pier side of
mould weight platform)
Testing pile center and
datum pile center
Datum pile center and
anchor pile center
(or supporting pier side of
mould weight platform)
Anchor pile
crossbeam
≥ 4(3)D and 2.0m ≥ 4(3)D and 2.0m ≥ 4(3)D and 2.0m
Mould weight
platform
≥ 4D and 2.0m ≥ 4(3)D and 2.0m ≥ 4D and 2.0m
earth anchor device ≥ 4D and 2.0m ≥ 4(3)D and 2.0m ≥ 4D and 2.0m
Note: 1. D is testing pile, anchor pile or design diameter or margin of earth anchor, the larger value is bigger.
2. In case of testing pile or cap-shape guttate or multiple tray decoration, center distance of testing pile and
anchor pile shall not be less than 2 times of expanded end diameter.
3. Values in bracket can be used for such circumstance that designed pile center distance of several rows of piles
is less than 4D in case of job pile acceptance testing
4. For soft soil stockyard, when weight is enlarged, distance between support pier side and datum pile center and
testing pile center shall be increased, vertical displacement of datum pile shall be observed in experiment
process.
4.2.6 When testing of pile side resistance and pile end resistance is required, sensor
embedded in shaft shall be executed in Annex A of this Code.
8/18/2019 Technical Code for Testing of Building Foundation Piles
29/105
8/18/2019 Technical Code for Testing of Building Foundation Piles
30/105
30
measure and read once every 30 minutes.
2. Relatively stable standard of the testing pile sedimentation: sedimentation volume of
pile top within every one hour shall not exceed 0.1mm, and shall occur for twice
continuously from 30 th minute after the grading load is exerted, the result shall be
calculated according to sedimentation value observed for three times every 30 minutes
within 1.5 hour .
3. When sedimentation velocity of pile top has reached relatively stable, load of the next
grade can be exerted.
4. In case of unloading, load of every level shall be maintained for one hour, after operator
measures and reads sedimentation volume of pile top according to 15, 30 and 60
minutes, unloading of the next level can be executed. After unloading to zero, operator
shall measure and read the remaining sedimentation volume of pile top, maintenance
time is 3 hours, measuring and reading time shall be 15 and 30mins, operator shall
measure and read once every 30 minutes.
4.3.7 After construction of job pile, low-speed maintenance load testing method shall be
adopted for acceptance testing. When mature local experience is available, high-speed
maintenance load testing method can be used.
Maintenance time of high-speed maintenance load testing method of load of every level
shall be at least one hour, whether delay maintenance load time shall be determined
according to pile top sedimentation convergence situation.
4.3.8 In case of the following circumstances, loading can be terminated:
1. Under load action at a certain level, sedimentation volume of pile top is more than 5
times of sedimentation volume under load action of previous level.
Note: When sedimentation of pile top can be stable and total sedimentation volume is less than 40mm,
it shall be loaded till total sedimentation volume of pile top is more than 40mm.
8/18/2019 Technical Code for Testing of Building Foundation Piles
31/105
31
2. Under load action of a certain level, if sedimentation volume of pile top is more than 2
times of sedimentation volume under load action of previous level, and has not reached
relatively stable standard after 24 hours.
3. It has reached maximum loading volume required by design.
4. When job pile is used as a anchor pile, uplift volume of anchor pile has reached
allowable value.
5. When load sedimentation curve presents a slow change shape, it can be loaded till total
sedimentation volume of pile top reaches 60 80mm; under special circumstance, it
can be loaded according to detailed demands until the accumulated sedimentation
volume of pile top is more than 80mm.
4.3.9 Testing data shall be recorded according to format of Form C.0.1 of Annex c of this
Code.
4.3.10 When testing the pile side resistance and pile end resistance, measuring and reading
time of the testing data shall meet Clause 4.3.6 .
4.4 Analysis and Determination of Testing Data
4.4.1 Clearing-up of testing data shall meet the following regulations:
1. When determining vertical compression resistance bearing capacity of single pile,
operator shall draw relation curve of vertical load vs sedimentation Q-S),
sedimentation vs logarithm of time t s lg− , if necessary, operator shall also draw
curve necessary for other auxiliary analysis.
2. When carrying out shaft stress, strain and pile toe counterforce, operator shall clear up
8/18/2019 Technical Code for Testing of Building Foundation Piles
32/105
32
record form of relevant data, and draw shaft axis distribution diagram according to
Annex A of this Code, and calculate layered side friction resistance and end resistance
value of different soil layer.
4.4.2 Limit bearing capacity uQ of vertical compression resistance of single pile can be
determined according to the following method after comprehensive analysis:
1. It can be determined according to characteristics that sedimentation changes along with
load: For rapid-rise Q-s curve, operator shall take load value corresponding to starting
point and ending point where obvious rapid rise occurs.
2. It can be determined according to characteristics that sedimentation changes along with
time: operator shall take load value of previous level where obvious downward bend
occurs at t s lg− curve tail.
3. In case of circumstances occurring in Paragraph 2 of Clause 4.3.8 , operator shall take
load value of previous level.
4. For slowly changed Q-s curve, operator shall load value corresponding to S 40mm
according to sedimentation volume; when pile length is more than 40m, elastic
compression of shaft shall be considered; For pile with diameter more than or equal to
800mm, load value corresponding to s=0.05D D is pile end diameter shall be taken.
Note: when vertical compression resistance bearing capacity which is used for determining the pile
according to the aforesaid Clause IV does not reach limit, maximum test load value shall be taken
for limit bearing capacity of vertical compression resistance of pile.
4.4.3 The counting value limit bearing capacity of vertical compression resistance of single
pile shall be determined according to the following regulations:1. For the testing pile results participating in counting, when its range does not exceed
30% of average value, average value shall be taken as limit bearing capacity of vertical
8/18/2019 Technical Code for Testing of Building Foundation Piles
33/105
33
compression resistance of single pile.
2. When range exceeds 30% of average value, reason of oversize range shall be analyzed,
the result shall be determined according to situation of job, if necessary, the testing pile
quantity can be increased.
3. For pile cap under column with pile quantity of 3 pieces or below, selective
examination quantity of job pile is not less than 3 pieces, lower value shall be taken.
4.4.4 Value of the bearing capacity characteristic value a R of vertical compression
resistance of single pile in unit job under same condition shall be taken according to 1/2
(0.5 times) of the counting value of limit bearing capacity of vertical compression
resistance of single pile.
4.4.5 The testing report shall include contents of Clause 3.5.5 of this Code and shall include:
1. Geologic log corresponding to pile position of testing pile;
2. Size of testing pile and anchor pile, material strength, anchor pile quantity,
reinforcement arrangement;
3. The loading counterforce type and stacking method shall indicate stacking weight,
anchor pile testing method shall have counterforce beam layout;4. Load/download method, load grading;
5. Curve and relevant data form; and curve and data for determining the bearing capacity,
required by this Code 4.4.1
6. Reference for determining the bearing capacity;
7. In case of testing the hierarchical friction resistance, sensor type installation position,
axis calculation method, change curve of shaft axis under all levels of loads, pile side
limit friction resistance and pile end resistance of each soil layer shall be available,
8/18/2019 Technical Code for Testing of Building Foundation Piles
34/105
8/18/2019 Technical Code for Testing of Building Foundation Piles
35/105
35
2. When natural substrate is adopted to provide counterforce, stress exerted on substrate
shall not exceed 1.5 times of bearing capacity characteristic value of substrate; pivot
center of gravity of counterforce beam shall be superposed with pedestal center.
5.2.3 Technical requirement of load measurement and instrumentations shall meet Clause
4.2.3 of this Code.
5.2.4 Technical requirement uplift volume measurement of pile top and its apparatus shall
meet Clause 4.2.4 of this Code.
Note: Observation point of uplift volume of pile top can be fixed on shaft concrete of pile top
surface.
5.2.5 Center distance among test pile, pedestal and datum pile shall meet Form 4.2.5.
5.2.6 When uplift friction resistance distribution of pile side or uplift displacement of pile
end is required to be tested, sensor embedded in shaft or displacement pole embedded
at pile end shall be executed according to Annex A of this Code.
5.3 On-the-spot Testing
5.3.1 For concrete cast-in-place pile and prefabricated pile with joint, low strain
integrity testing shall be adopted for testing the shaft integrity of pile before uplift test.
When construction of uplift cast-in-place pile which is provided as a reference of
design shall be subject to pore forming quality testing, if pile with obvious hole
enlargement is found in middle or lower part of shaft shall not used as uplift test pile;
for prefabricated pile with joint, joint strength shall be calculated.
5.3.2 Low-speed maintenance load testing shall be applicable for vertical uplift static test of
8/18/2019 Technical Code for Testing of Building Foundation Piles
36/105
36
single pile. If necessary, multiple cycle load/unload testing method can also be adopted.
Load/unload classification of low-speed maintenance load testing method, test method
and stability standard shall be executed according to Clause 4.3.4 and 4.3.6 of this
Code, crack of shaft concrete shall be observed carefully.
5.3.3 In case of the following circumstances, loading can be terminated:
1. Under action of load at a certain level, uplift volume of pile top is bigger than uplift
volume under uplift load action of the previous level by 5 times.
2. If it is controlled according to uplift volume of pile top, when accumulated uplift
volume of pile top is more than 100mm.
3. If it is controlled according to reinforcement tensile strength, when uplift load of pile
top is up to 0.9 times of reinforcement strength standard value.
4. For job pile of acceptance sampling testing, when it is up to maximum uplift load value
required by design.
5.3.4 Testing data shall be recorded according to Format C.0.1 in Annex C of this Code .
5.3.5 Side uplift resistance of the testing pile or uplift displacement of pile end, measuring
and reading time of data shall meet regulations of Clause 4.3.6 of the Code.
5.4 Analysis and Determination of Testing Data
5.4.1 For clear up data, operator shall draw uplift load vs uplift volume ( δ −U )of pile top
relation curve and uplift volume of pile top-logarithm of time( t s lg− )relation curve.
5.4.2 Vertical anti-uplift limit bearing capacity of single pile can be determine according to
the following method:
8/18/2019 Technical Code for Testing of Building Foundation Piles
37/105
37
1. It is determined according to characteristics that uplift volume changes along with load:
For rapid-rise δ −U curve, load value corresponding to the starting/ending point for
rapid rise;
2. It is determined according to characteristics that uplift volume changes along with time:
operator shall take load value of previous level of obvious bend curve tail or obvious
rapid rise of slope of t s lg− curve.
3. When uplift reinforcement breaks under load at a certain level, operator shall take load
value of previous level.
5.4.3 Determinations of counting value of vertical uplift limit bearing capacity of single pile
shall comply with Clause 4.4.3 of the Code.
5.4.4 When testing pile used as acceptance sampling testing under maximum uplift load
action, if paragraph 3 listed in Clause 5.4.2 of this Code does not occur, the value can
be determined according to design.
5.4.5 Value of vertical uplift bearing capacity characteristic value of single pile of unit job
under same condition shall be taken according to one second (0.5 times) of counting
value of vertical uplift limit bearing capacity of single pile. Note: when job pile does not allow crack in job, load at the previous level of shaft crack as vertical uplift
bearing capacity characteristic value of single pile is taken. Compared with bearing capacity
characteristic value determined according to one second (0.5 times) of limit load value, smaller
value shall be taken.
5.4.6 The testing report shall include contents of Clause 3.5.5 of this Code and also include:
1. Geologic log corresponding to testing pile position;
2. Testing pile size cast-in-place pile shall indicate aperture curve and reinforcement
fixing situation;
3. Load/download method, load grading;
8/18/2019 Technical Code for Testing of Building Foundation Piles
38/105
38
4. Curve and relevant data form required to be drawn by Clause 5.4.1;
5. Reference for determining the bearing capacity;
6. When uplift friction resistance testing is carried out, sensor type, installation position,
axis calculation method, change curve of shaft axis under load of each level, uplift limit
friction resistance in each soil layer shall be available.
8/18/2019 Technical Code for Testing of Building Foundation Piles
39/105
39
6. Horizontal Static Load Test of Single Pile
6.1 Scope of Application
6.1.1 This method is applicable for Single pile horizontal static load test when pile top is
free; please refer to horizontal static load tests in other forms.
6.1.2 This method is applicable for testing horizontal bearing capacity of single pile, so as to
conclude proportion factor of foundation soil reaction coefficient.
6.1.3 Sensor for measuring shaft strain has been embedded, shaft stress under the
corresponding horizontal load action can be measured, and hence bending moment
of shaft shall be calculated.
6.1.4 Test pile provided as an reference for design shall be loaded until larger horizontal
displacement or shaft structure occurring in pile top; for sampling testing of
engineering pile, loading can be controlled according to horizontal displacement
allowable value required by design.
6.2 Instrumentation and Installation
6.2.1 Oil jack shall be used in loading device with horizontal thrust, loading capacity shall not
be less than 1.2 times of maximum test load.
6.2.2 Counterforce of horizontal thrust can be provided by neighboring pile; when
counterforce structure is designed exclusively, its bearing capacity and rigidity shall be
1.2 times of that of test pile.
8/18/2019 Technical Code for Testing of Building Foundation Piles
40/105
40
6.2.3 Technical requirements of load measurement and its instrumentations shall meet Clause
4.2.3 of this Code; horizontal force action point shall be consistent with actual
engineering elevation of bottom surface of pile cap of pile foundation; jack and test pile
contact surface shall be equipped with spherical bearing, acting force of jack shall pass
through shaft axes horizontally; contact surface between jack and test pile shall be
bolstered up.
6.2.4 Technical requirements for horizontal displacement measurement of pile and its
instrumentations shall meet Clause 4.2.4 of this Code. On both sides of test pile of
action plane of horizontal force shall be provided with two symmetrical displacement
meter installation; when measuring pile is needed to extrude outer corner, two
displacement meters shall also be installed symmetrically on both sides test pile, which
is 50cm above horizontal force action surface.
6.2.5 Datum mark of displacement measurement shall be set without any influence by test and
other factors, datum mark shall be set on the side of test pile which is opposite to
displacement direction and is vertical with acting force direction, clear distance between
datum mark and test pile shall not be less than of pile diameter by 1 time.
6.2.6 In case of measurement of shaft stress or strain, measurement sensor of each testing
section shall be arranged symmetrically, along stress direction, on tensioned and
pressed main reinforcement which is far away neutral axis; inclination between
longitudinal section of the embedded sensor and stress direction shall not more than 10
° . Test section of main underground stress part with 10 times of pile diameter pile
width shall be thickened, clearance between sections shall not more than pile diameter
by one time; if the clearance is more than this depth, clearance of test section can be
enlarged properly. Sensor shall be embedded in shaft according to Annex A of this
Code.
8/18/2019 Technical Code for Testing of Building Foundation Piles
41/105
41
6.3 On-the-Spot Inspection
6.3.1 Loading method shall be unilateral multi-cycle loading method or low-speed maintained
load method stipulated in Chapter Four of this Code according to actual stress
characteristics of engineering pile, other loading methods can also be adopted
according to design requirements. Test pile which needs measurement of shaft stress or
strain shall adopt maintenance load method.
6.3.2 Test load/unload mode and horizontal displacement measurement shall meet the
following regulations:
1. Grading load of unilateral multi-cycle loading method shall less than estimated 1/10 of
bearing capacity of horizontal limit or maximum test load. After applying load at every
level, operator shall measure and read horizontal displacement after executing dead load
for 4 minutes, and then unload to zero, stop for 2 minutes, measure and read remaining
horizontal displacement, thus a load/unload cycle can be completed, execute this cycle
for 5 times. Displacement observation of grade-I load shall be completed. Test shall not
be paused.
2. Load/unload grading, test method and stabilization standard of low-speed maintenance
load method shall be executed according to Clause 4.3.4 and 4.3.6 of this Code.
6.3.3 In case of one of the following circumstances, loading can be stopped:
1. Shaft breaks off;
2. Horizontal displacement is more than 30 40mm 40mm for soft soil ;
3. Horizontal displacement meets allowable value of horizontal displacement required by
design.
6.3.4 Measured Data shall be record as per format provided in enclosed form c.0.2 of Annex
8/18/2019 Technical Code for Testing of Building Foundation Piles
42/105
42
C of this Code.
6.3.5 In case of measurement of shaft stress or strain, measurement and reading of testing
data shall be synchronous with horizontal displacement measurement.
6.4 Analysis and Determination of Measured Data
6.4.1 Measured data shall be cleared up according to the following requirements:
1. If unilateral multi-cycle loading method is adopted, horizontal force-time-action point
displacement )( 0Y t H −− relation curve and horizontal force-displacement gradient
)/( 0 H Y H ΔΔ− relation curve shall be drawn.
2. If low-speed maintenance load method is adopted, horizontal force, force action point
displacement 0Y H − relation curve, horizontal force vs displacement
gradient )/( 0 H Y H ΔΔ− relation curve, force action point displacement-time
logarithm )lg( 0 t Y − relation curve and horizontal force vs force action point
displacement double logarithmic )lg(lg 0Y H − relation curve.
3. Relation curve of proportion factor of horizontal reaction coefficients of horizontal force,
horizontal displacement of horizontal force action point vs foundation soil shall be
drawn )( 0 mY m H −− .
Pile top is free and action position of horizontal force is located on ground, m
value can be determined according to the following format:
8/18/2019 Technical Code for Testing of Building Foundation Piles
43/105
43
32
035
0
35
)(
).(
EI Y b
H vm y= 6.4.1-1
51
0
⎭⎬⎫
⎩⎨⎧=
EI mba 6.4.1-2
Where:
m ——Proportion factor of horizontal reaction coefficient on subgrade kN/m 4 ;
a ——Horizontal deformation coefficient m-1 of pile;
yν —— Horizontal displacement coefficient of pile top, α shall be calculated
according to formula 6.4.1-2 , when hα ≥ 4.0 h is buried depth of pile ,
yν =2.441;
H —— Horizontal force kN acting on the ground;
0Y ——horizontal displacement m of action point of horizontal force;
EI ——Bending rigidity kN · m2 of shaft; where, E is elastic modulus of shaft
material, I is moment of inertia of transformer section of shaft; 0b ——
calculation width of shaft m ; for annular pile: when pile diameter D ≤ 1m,
b=0.9 1.5 D+0.5 ; when pile diameter
D 1m, 0b = 0.9 D+1 . For rectangular pile: when margin B ≤ 1m, 0b =1.5 B+0.5;
when margin B 1m, 0b B+1.
6.4.2 The following curves shall be drawn for test embedded stress or strain measurement
sensor, and the corresponding data shall be listed in forms:1. Distribution graph of bending moment of shaft under action of horizontal force at each
level;
8/18/2019 Technical Code for Testing of Building Foundation Piles
44/105
44
2. Pulling/stress s H σ −
curve of horizontal force vs maximum bending moment section
reinforcement.
6.4.3 Horizontal critical load of single pile can be determined according to the following
methods:
1. Take the preceding level of the inflexion occurring on 0Y t H −− curve in case of
unilateral multi-cycle loading method or on 0Y H − curve in case of low-speed
maintenance load method.
2. Take horizontal load value corresponds to the first inflexion on
H Y H ΔΔ− /0 curve or 0lglg Y H − curve.
3. Take horizontal load value corresponds to the first inflexion on s H σ − curve.
6.4.4 Horizontal ultimate bearing capacity of single pile can be determined according to
the following methods:
1. Take horizontal load value corresponding to the preceding level of the inflexion
which drops sharply and obviously on 0Y t H −− curve in case of unilateral
multi-cycle loading method, or starting point which drops sharply and obviously on
0Y H − curve in case of low-speed maintenance load method.
2. Take horizontal load value of the preceding level of the place where obvious bend of
end of t Y lg0 − curve begins to occur in case of low-speed maintenance load
method.
3. Take horizontal load value, zontal load value corresponding to the second inflexion
on H Y H ΔΔ− /0 curve or 0lglg Y H − curve shall be taken.
4. Horizontal load value of previous level shall be taken when shaft breaks or tensioned
8/18/2019 Technical Code for Testing of Building Foundation Piles
45/105
45
reinforcement yields.
6.4.5 Horizontal ultimate bearing capacity and counting value of horizontal critical load of
single pile shall meet Clause 4.4.3 of this Code.
6.4.6 Determination of horizontal bearing capacity characteristic value of single pile in unit
job under same condition shall meet the following regulations:
1. When horizontal bearing capacity is controlled according to shaft strength, counting
value of horizontal critical load shall be taken as bearing capacity characteristic value
of single pile.
2. When pile receives long-term horizontal load action and is not allowed to be crack,
0.8 times of the counting value of horizontal critical load shall be taken as bearing
capacity characteristic value of single pile horizontal.
6.4.7 Besides Clause 6.4.6 of this Code, when horizontal bearing capacity is controlled
according to horizontal allowable displacement required by the design, horizontal load
corresponding to horizontal allowable displacement required by the design can be
taken as horizontal bearing capacity characteristic value of single pile, but the value
shall meet anti-crack design specified in relevant code.
6.4.8 The testing report shall include contents of Clause 3.5.5 in this Code, and shall also
include:
1 Geologic log of the testing pile;
2 Section size and reinforcement arrangement of the testing pile;
3 Load/unload method, load grading:
4 Curve and relevant data form required to be drawn by Clause 6.4.1;
5 Reference for determining the bearing capacity;
6 When reinforcement stress testing is carried out, and shaft bending moment is hence
calculated, sensor type, installation position, method for calculation of internal force,
8/18/2019 Technical Code for Testing of Building Foundation Piles
46/105
46
and curve and its relevant data form required to be drawn by Clause 6.4.2 shall be
available. .
8/18/2019 Technical Code for Testing of Building Foundation Piles
47/105
47
7. Core Drilling
7.1 Scope of Application
7.1.1 This method is applicable for testing the pile length, shaft concrete strength, dreg
thickness of pile toe and shaft integrity of concrete filling pile, for the purpose of
determination or identification of rock and soil character of end bearing layer of pile.
7. 2 Equipment
7.2.1 Drilling machine operated by hydraulic pressure shall be used for taking core sample.
Instrument parameters of drilling machine shall meet the following regulations:
1. Rated maximum rotating speed is not lower than 790 min/r .
2. Scope for adjustment of rotating speed is less than 4 tier.
3. Rated working pressure shall not less than 1.5MPa.
7.2.2 Driller shall be equipped with single-action dual-duct driller and relevant orifice pipe,
underreamer, snap spring, posing stabilizer and driller than can take soft and loose
dregs out. Drilling pole shall smooth and straight, diameter shall be 50mm.
7.2.3 Drilling bit shall be diamond with proper granularity, concentration and matrix hardness
according to concrete design strength grade, and outer diameter shall not be less than
100 mm. Matrix of the drilling bit shall not have visual cracks, wany edge, corner
8/18/2019 Technical Code for Testing of Building Foundation Piles
48/105
48
shortage, inclination and bell mouth deformation.
7.2.4 Water discharge of water pump shall be 50 160 min/ L , pump pressure shall be
1.0-2.0 a Mp .
7.2.5 Saw used for sawing and cutting core sample shall have device for cooling the system
and for tightening the core sample, the matched diamond circular saw blade shall have
enough rigidity.
7.2.6 Screeder and planishing machine used for end surface of core sample shall meet
requirement for making the core sample .
7.3 On-the-Spot Operation
7.3.1 Core-drilling bore counts and core drilling position of each piece of the testing pile shall
meet the following regulations:
1. Pile with a pile diameter of less than 1.2m shall be drilled one bore, pile with pile
diameter of 1.2-1.6m shall be drilled two bores, pile with pile diameter of more
than1.6m shall be drilled three bores.
2. In case of one core-drilling bore, the bore shall be opened in a position 10-15 cm away
from pile center; In case of two or above core-drilling bores, the bore shall be opened
uniformly and symmetrically in a position 0.15-0.25D cm away from pile center
0.15-0.25D.
3. For drilling of end bearing layer of pile, each piece of the testing pile shall not be less
than one bore, and drilling depth shall meet design requirement.
7.3.2 Drilling instrument shall be installed correctly and firmly, pedestal shall be horizontal.
8/18/2019 Technical Code for Testing of Building Foundation Piles
49/105
49
Vertical shaft center of driller, head sheave center point of tangency of front edge of
overhead crane and orifice center must be on same plumb line. Operator shall ensure
that no inclination, displacement of driller will occur in core-drilling process,
deviation of verticality of core-drilling bore shall not be more than 0.5%.
7.3.3 When distance between pile top surface and driller pedestal is bigger, orifice pipe shall
be installed vertically and firmly.
7.3.4 In drilling process, circulating water flow in drilling bore shall not be interrupted,
drilling velocity shall be adjusted according to sand content and color of return water.
7.3.5 When core sample is taken by pulling out way, drilling bit and underreamer shall be
screwed and unloaded, core shall not be unloaded by hammering.
7.3.6 R ound trip meterage shall be controlled within 1.5m; when drilling to pile toe, dreg
shall be drilled and taken by using suitable core-drilling method and technology, and
then dreg thickness shall be determined, rock and soil character of end bearing layer of
pile shall be identified by suitable method.
7.3.7 The drilled core sample shall be placed into core sample box according to round trip
sequence from up to down , core sample with round trip quantity, block number, total
block quantity of this round trip shall be clearly indicated on side surface, and the
drilling situation and drilling abnormal situation shall be recorded timely according to
format of Form D.0.1-1 of Annex D of this Code, preliminary description shall be
made on core sample quality.
7.3.8 During core-drilling process, concrete of core sample, dreg of pile toe and end-bearing
layer of pile shall be recorded in details as per format of Form D.0.1-2 of Annex D of
this Code.
7.3.9 After core-drilling operation is finished, photos of core sample and marking board
marked with engineering name, pile number, core-drilling bore number, sampling
8/18/2019 Technical Code for Testing of Building Foundation Piles
50/105
50
position for core sample, pile length, bore depth, testing unit name shall be shot.
7.3.10 when quality appraisal of single pile meets the design, 0.5 1.0 a Mp pressure shall
be adopted, re-inject grout upwards from core-drilling bore bottom and seal off it;
otherwise, shall core-drilling bore shall be sealed off for treatment.
7 .4 Sampling and Processing of Core Sample
7.4.1 Concrete compression resistance core sample shall be taken according to the following
regulations:
1. When pile length is 10-30m, 3 groups of core samples shall be taken; when pile length
is less than 10m, 2 groups can be taken, when pile length is more than30m, not less
than 4 groups.
2. Distance between the upper core sample position and the designed elevation of pile top
shall not be more than one time of pile diameter or 1m, distance between the lower
core sample position and pile toe shall not be more than one time of pile diameter or
1m, middle core sample shall be taken in equal clearance.
3. When samples can be taken in defect position, a group of core samples shall be taken
for concrete compression resistance test.
4. When core-drilling bore quantity of same foundation pile is more than one, in which, if
one bore has defect at a certain depth, core sample shall be taken at this depth of other
bores for the purpose of concrete compression resistance test.
7.4.2 When pile end-bearing layer is middle weak weathering terrane and core can be made
into a test piece, a group of rock core samples shall be taken from nearby pile toe;
8/18/2019 Technical Code for Testing of Building Foundation Piles
51/105
51
Samples shall be done at each layer in case of delamination lithology.
7.4.3 Three core samples for compression resistance shall be made in each group of core
sample . Core sample shall be processed and measured according to Annex E of this
Code.
7. 5 Compressive Strength Test of Core Sample Test Piece
7.5.1 Compressive strength test can be executed immediately after fabrication of core
sample is finished.
7.5.2 Compressive strength test of concrete core sample shall be executed according to
current national standard-------C ommon Concrete Mechanical Property Test Method
GB/T50081 — 2002.
7.5.3 After compressive strength test, if average diameter of core sample is founded to be
less than 2 times of maximum grain diameter of concrete coarse aggregate in the test
piece, and if strength value is abnormal, strength value of this test piece shall not
participate in counting the average value.
7.5.4 Compressive strength of concrete core sample shall be calculated according to the
following:
2
4d p
f cu π ξ •= 7.5.4
Where cu f —compressive strength a Mp of concrete core sample, within accuracy of
0.1 a Mp ;
p —failure load ( N) measured by core sample compression resistance test;
8/18/2019 Technical Code for Testing of Building Foundation Piles
52/105
52
d —average diameter mm of core sample;
ξ —compressive strength conversion coefficient of concrete core sample shall
consider effect of core sample size, influence caused by core-drilling
machine on core sample disturbance and concrete mould condition through
determination of test counting; when no test counting data is available, value
shall be 1 .0 .
7.5.5 Monaxial compressive strength test of drill core of pile toe can be executed according
to current national standard---Construction Subgrade Foundation Design Code
(GB50007 —2002 Annex J).
7. 6 Analysis and Determination of Measured Data
7.6.1 Representative value of compressive strength of concrete core sample shall be
determined according to average value of strength value of a group of three test
pieces. In case of representative values of compressive strength of two groups or
above of concrete core samples in same depth part of same testing pile, its average
value shall be taken to be representative value of compressive strength of concrete
core sample in this depth of this pile.
7.6.2 The minimum value of representative value of compressive strength of concrete core
sample in different depth position in the testing pile is representative value of
compressive strength of concrete core sample of pile.
7.6.3 For end bearing layer character of pile, rock and soil characteristics of pile end bearing
layer of pile shall be determined according to characteristics of core sample,
8/18/2019 Technical Code for Testing of Building Foundation Piles
53/105
53
monoaxial compressive strength test of rock core sample, dynamic sound logging or
standard penetration test results , .
7.6.4 Shaft integrity type shall be determined according to core-drilling bore counts,
characteristics of concrete core sample on site, monoaxial compressive strength test
results of core sample, according to characteristics specified in Form 3.5.1 and Form
7.6.4 of this Code.
7.6.5 Appraisal of piling quality shall be executed according to single pile. In case of the
following circumstances, operator shall determine whether the following testing piles
are not meet design requirement:
1. Pile with type- Ⅳ shaft integrity.
2. Representative value of compressive strength of concrete core sample of the testing
pile shall be less than pile of concrete design strength grade.
3. Pile whose pile length and dreg thickness of pile toe do not meet design or this Code.
4. Pile whose soil character strength or thickness of end bearing layer of pile does not
meet design or this Code.
8/18/2019 Technical Code for Testing of Building Foundation Piles
54/105
54
Form 7.6.4 Determination of Shaft Integrity
Type Characteristics
Concrete core sample is continue, complete, smooth in surface, in good cementation, uniform
in aggregate distribution, in long column shape, anastomosing fracture, a small quantity of air
vents can be seen on side of core sample.
Concrete core sample is continue, complete, in good cementation, uniform in aggregate
distribution, in long column shape, approximately anastomosing fracture, honeycomb and
pockmarked face can be seen on partial of core sample side.
Ⅲ
A majority of concrete core sample is in good cementation, no loosening, or layered situation,
but one of the following situations can be seen:
Partial of core sample is broken and broken length is not more than 10cm
Not uniform in aggregate distribution of core sample;
Shortprismatic or massiveness situations of core sample;
Honeycomb and pockmarked face on side of core sample, grooves are connected together
Ⅳ
Difficult for drilling in;
Core sample breaks at random, slurry or layered stratum can be seen;
Partial core sample breaks and length of the broken part is more than 10cm
7.6.6 If core-drilling bore deviates pile, appraisal shall be only made on part which is used
for drilling the core sample.
7.6.7 Testing report shall include contents of Clause 3.5.5 of this Code, and shall include:
1. Core-drilling instrument;
2. Testing pile quantity, quantity of drilled bore, overhead, concrete core footage,
footage of drill core, total footage, group count of concrete test piece, group count of
rock test piece, dynamic sound logging or standard penetration test results ;
3. Histogram of each hole shall be drawn according to format in From D.0.1-3 of Annex
8/18/2019 Technical Code for Testing of Building Foundation Piles
55/105
55
D of this Code;
4. Monoaxial compressive strength test results of core sample;
5. Color pictures of core sample;
6. Statement of abnormal situation.
8/18/2019 Technical Code for Testing of Building Foundation Piles
56/105
56
8. Low Strain Integrity Testing
8.1 Scope of Application
8.1.1 This method is applicable for testing the shaft integrity of concrete pile so as to
determine degree and position of shaft defect.
8.1.2 Effective testing pile length scope of this method shall be determined by on-the-spot
test.
8.2 Instrumentations
8.2.1 Main technical performance index of the testing instrumentations shall meet the
current industrial standard Dynamic Testing Instruments of Foundation Pile (JG/T3055)
and shall have functions of signal display, storage, treatment and analysis.
8.2.2 Transient state excitation instrument shall include hammer and pallet that can excite
broad pulse and spike pulse ; hammer can load force sensor; transient state excitation
instrument shall include electromagnetic steady state excitation with swept frequency
range of 10 2000 Hz and adjustable excitation force.
8/18/2019 Technical Code for Testing of Building Foundation Piles
57/105
57
8.3 On-the-Spot Inspection
8.3.1 The testing pile shall meet the following regulations:
1. Shaft strength shall meet paragraph of Clause 3 .2.6 of this Code.
2. For material of pile head, strength, section size shall be approximately same with
shaft.
3. Pile top surface shall flat, smooth, dense, and shall be approximately vertical with pile
axes.
8.3.2 Setting of testing parameters shall meet the following regulations:
1. Time quantum length recorded by time domain signal shall not be less than 5 ms after
2 c L / ; upper limit of frequency scope analyzed by amplitude frequency signal shall
not be less than 2000 Hz .
2. The preset pile length shall be length from survey point of pile top to construction pile
of pile toe, the preset shaft section area shall be construction section area.
3. Shaft wave velocity can be set preliminarily according to testing value of same type
of pile in local region.
4. The sampling time interval or sampling frequency shall be set according to pile length,
shaft wave velocity and frequency domain resolution shall be chosen reasonably;
sampling point of time domain signal shall not be less than 1024 points.
5. Preset value of sensor shall be set according to results of metrological verification .
8.3.3 Installation of measurement sensor and excitation operation shall meet the following
regulations:
1. Installation of sensor shall be vertical with pile top surface; and the sensor shall have
enough binding strength if sensor is bound by using couplant.
8/18/2019 Technical Code for Testing of Building Foundation Piles
58/105
58
2. Excitation point position of solid pile shall be chosen at pile center, measurement
sensor installation position shall be 2/3 of radius of pile center; excitation point of
hollow pile and installation position of measuring sensor shall be on same horizontal
surface, inclination between this surface and the connecting line of pile center shall be
90° , excitation point and installation position of the measuring sensor shall be 1/2 of
thickness of pile wall.
3. Excitation point and installation position of the measuring sensor shall be free of
influence of main reinforcement of reinforcement cage.
4. Excitation direction shall be pile axes direction.
5. Transient state excitation shall be subject to on-the-spot tap test, operator shall choose
excitation hammer and pallet with proper weight, and shall obtain pile toe or defect
echo signal at lower part of shaft by using broad pulse, and shall obtain defect echo
signal at higher part of shaft by using spike pulse.
6. For excitation of steady state, operator shall obtain stable response signal under each
preset frequency, and shall adjust excitation force according to pile diameter, pile
length and pile soil restrain.
8.3.4 Collection and screening of signal shall meet the following regulations:
1. According to pile diameter, 2-4 testing points shall be arranged at pile center
symmetrically; valid signal counts recorded by each testing point shall not be less than
3.
2. Check and judge whether the actually-measured signals have reflected shaft integrity
characteristics.
3. Consistency between different testing points and time domain signal measured after
many times is poorer, operator shall analyze reason and increase testing point quantity.
4. Distortion and null shift of signal shall be avoided, signal value shall not be more than
8/18/2019 Technical Code for Testing of Building Foundation Piles
59/105
59
range of measurement system.
8.4 Analysis and Determination of Measured Data
8.4.1 Determination of average value of wave velocity of shaft shall meet the following
regulations:
1. When pile length has been known and echo signal of pile toe is explicated, in
foundation pile with same geographical conditions, design pile type and piling
technology, operator shall choose shaft wave velocity value of type-I pile of not less
than 5 pieces, its average value shall be calculated according to the following formula:
n
iim cn
c1
1
=∑= c 8.4.1-1
T L
c i Δ= 200 8.4.1-2
f Lc i Δ•= 2 8.4.1-3
Where mc ——average value m/s of shaft wave velocity ;
ic ——shaft wave velocity value m/s of No. i piece of the testing pile, and
mmi ccc /− ≤ 5%
L —— pile length m under survey point;
T Δ ——Time difference ms between the first peak of velocity wave and echo
wave peak of pile toe;
f Δ —— frequency difference Hz between neighboring resonance peaks of pile
8/18/2019 Technical Code for Testing of Building Foundation Piles
60/105
60
toe on amplitude frequency curve ;
n ——foundation pile quantity n ≥ 5 participate in calculation of average
value of wave velocity.
2. When the value cannot be determined according to the aforesaid clause, average value
of wave velocity can be determined according to actually-measured value of same pile
type and piling technology in local region in other pile foundation works with the
same pile type and piling technology in local region, and according to aggregate
variety and strength grade of shaft concrete.
8.4.2 Shaft defect position shall be calculated according to the following formula:
ct x x •Δ•= 20001
8.4.2-1
/21
f c
x Δ•= 8.4.2-2
Where x ——distance m) between shaft defect and sensor installation point;
. xt Δ —— time difference m between the first peak of velocity wave and defect echo
wave peak;
c ——shaft wave velocity m/s) of the testing pile can be substituted by c value if the
value cannot be determined.
/ f Δ ——frequency difference Hz between neighboring defect resonance peaks on
amplitude frequency on signal curve.
8.4.3 For shaft integrity type, attenuation characteristic of signal, designed pile type, piling
technology, geographical conditions, construction circumstance shall be tested
according to depth of defect, and shall be analyzed and determined according to
actually measured time domain or amplitude frequency signal characteristics
stipulated in Clause 3.5.1 and Form 8.4.3 of this Code.
8/18/2019 Technical Code for Testing of Building Foundation Piles
61/105
61
Form 8.4.3 Determination of Shaft Integrity
Type Signal characteristics of time domain Amplitude frequency signal
characteristics
Before the time of 2 c L / , there is no defect echo wave, pile toe
echo wave is available.
Clearance of joint array of column
base, its neighboring frequency
difference Lc f 2/≈Δ Before the time of 2 c L / , slight defect echo wave occurs, and pile
toe echo wave is available.
Clearance of resonance peak array of
pile toe is approximately equal, its
neighboring frequency difference is as
follows: Lc f 2/≈Δ , frequencydifference between resonance peak
arising from slight defect and resonance
peak of pile toe is as follows:
Lc f 2// fΔ Ⅲ With obvious defect echo wave, other characteristics are between type Ⅱ and Ⅳ .
Ⅳ Before 2 c L / serious defect echo wave or cycle echo wave
occur, there is no pile toe echo wave;
or serious defect of shallow part of column makes wave shape
show low frequency large-amplitude damped vibration, there is no
pile toe echo wave.
Clearance of defect resonance peak
array is approximately equal,
neighboring frequency difference
shall be as
follows Lc f 2// fΔ ,there is no piletoe resonance peak; .
or serious defect at shallow part of
column is that only single resonance
peak occurs, there is no pile toe
resonance peak.
Note: For foundation pile with same site, similar geographical conditions, pile type and piling technology, when no pile toe
echo wave occurs in actually measured signal due to impedance of shaft and impedance of bearing stratum of pile end, shaft
integrity type with pile toe echo wave can be determined according to other piles with actually-measured signals under same
conditions of this site.
8/18/2019 Technical Code for Testing of Building Foundation Piles
62/105
62
8.4.4 For concrete filling pile, when time domain signal is used for analysis, after shaft
section change gradually, it restores to primary echo at sudden change position of
impedance of the original pile diameter, or secondary echo at sudden change position
of diameter expansion, determine integrity type of the testing pile according to
analysis piling technology and geographical conditions. If necessary,
actually-measured curve can be adopted for legal assistance in determination of shaft
integrity or in virtue of admittance value, relative high-low assistant determine shaft
integrity of dynamic rigidity.
8.4.5 For rock-socketed pile, when time domain echo signal of pile toe is single echo wave
and has same direction with hammering impulse signal, other methods shall be
adopted for verification of rock-socketed situation of pile end.
8.4.6 In case of the following circumstances, shaft integrity shall be determined according
to other testing method:
1 Actually measured signals are complicated and has no rule, so exact appraisal on it
cannot be available..
2 Concrete filling pile with gradual or frequent large changes of shaft section.
8.4.7 Low strain testing report shall provide actually measured signal curve of shaft
integrity testing.
8.4.8 The testing report shall include Clause 3.5.5 of this Code and shall also include the
following:
1 Value of shaft wave velocity;
2 Shaft integrity description, defect position and shaft integrity type;
3 Measuring scale of shaft length, index or linear amplification scope and multiple
in time domain signal period; or frequency scope for analysis of amplitudefrequency signal curve, pile toe or frequency difference among neighboring
resonance peaks corresponding to shaft defect.
8/18/2019 Technical Code for Testing of Building Foundation Piles
63/105
63
9. High Strain Dynamic Testing
9.1 Scope of Application
9.1.1 The method is applicable to measurement of vertical bearing capacity of the foundation