Page 1: Tech Talk: Master Planning - Microsoft Dynamics
Page 2: Tech Talk: Master Planning - Microsoft Dynamics
Page 3: Tech Talk: Master Planning - Microsoft Dynamics

Tech Talk: Master Planning

Page 4: Tech Talk: Master Planning - Microsoft Dynamics

2. Planning Considerations and Setup 3. Coverage Groups4. Coverage Settings5. Demo

Tech Talk: Master Planning

Page 5: Tech Talk: Master Planning - Microsoft Dynamics

-50

-40

-30

-20

-10

0

1 2 3 4

Net requirement, calculated from known issues

Planning to fit the net-requirement

Master planning

◼ sales orders

◼ production lines

IssuesReceipts

◼ purchase orders

◼ productions

Gross requirementBasic setup

Page 6: Tech Talk: Master Planning - Microsoft Dynamics

Master

Planning

Organization

Administration

Accounts

payable

Accounts

receivable

Product

information

management

Production

control

Inventory and

warehouse

management

Sales and

marketing

Page 7: Tech Talk: Master Planning - Microsoft Dynamics
Page 8: Tech Talk: Master Planning - Microsoft Dynamics

Regenerative

• Creates or adjusts the plan

• Considers or reconsiders each dependency between resources

• Includes the bills of materials (BOMs)

• Items on all levels

Net Change

• Obtains a picture of the affect of current changes

• Only immediate changes are considered

• Less time to process than running a regenerative plan

Page 9: Tech Talk: Master Planning - Microsoft Dynamics

Static Plan

• The static plan does not change until master scheduling is run

• This plan frequently serves as an operating plan for company personnel

Dynamic Plan

• The dynamic plan updates every time that the master data changes

• Updates can occur, for example, when a new sales order is created

Page 10: Tech Talk: Master Planning - Microsoft Dynamics

1. Master Planning Overview2. Planning Considerations and Setup 3. Coverage Groups4. Coverage Settings5. Demo

Tech Talk: Master Planning

Page 11: Tech Talk: Master Planning - Microsoft Dynamics

• Overview of Plan Input and Output

• Preliminary Considerations

• Understanding the Overall Setup Process

• Master Planning Parameters Form

• Master Plans Form

• Operations and Job Scheduling

Page 12: Tech Talk: Master Planning - Microsoft Dynamics
Page 13: Tech Talk: Master Planning - Microsoft Dynamics

Use of forecast scheduling

• Should you use it?

• When will you run it?

Inventory levels

• What are appropriate inventory levels?

• What settings are important?

One or two master plan strategies

• Do we use one or two master plans?

Page 14: Tech Talk: Master Planning - Microsoft Dynamics
Page 15: Tech Talk: Master Planning - Microsoft Dynamics
Page 16: Tech Talk: Master Planning - Microsoft Dynamics
Page 17: Tech Talk: Master Planning - Microsoft Dynamics

Operations Scheduling

Job Scheduling

Page 18: Tech Talk: Master Planning - Microsoft Dynamics

1. Master Planning Overview2. Planning Considerations and Setup 3. Coverage Groups4. Coverage Settings5. Demo

Tech Talk: Master Planning

Page 19: Tech Talk: Master Planning - Microsoft Dynamics

• Different delivery times that apply to different items

• The importance of the item to the production process

• The monetary value of the item

• Whether requirements for bill of materials (BOMs) and route versions

are enabled

• Whether actions and calculated delays are desired

• How planned production orders are managed

Page 20: Tech Talk: Master Planning - Microsoft Dynamics
Page 21: Tech Talk: Master Planning - Microsoft Dynamics
Page 22: Tech Talk: Master Planning - Microsoft Dynamics
Page 23: Tech Talk: Master Planning - Microsoft Dynamics
Page 24: Tech Talk: Master Planning - Microsoft Dynamics

Coverage

Explosion

Capacity

Action

message

Future

messages

Freeze

FirmingAutomatic firming of planned orders (production and purchase)

Existing planned orders within this time fence are not changed when new scheduling is run

Time fence within Delays are created to warn the user if orders will not be ready at the scheduled date

Time fence within messages are created that suggest actions for existing receipts (e.g. Advance, postpone) and therefore optimize stock

Capacity and Job scheduling of routes

Explosion of BOMs (concerning material and capacity)

Period where coverage shall be planned and calculated

Page 25: Tech Talk: Master Planning - Microsoft Dynamics

Date

9.1.8.1.7.1.6.1.5.1.4.1.3.1.1.1. 2.1.

purchase

P2

New purchase 6.1. no action6.1.

Purchase P1 postpone6.1.

Purchase P2 advance9.1.

Purchase P1

Purchase P2

postpone

cancel

6.1.

9.1

Pos. / Neg. Planned coveragePeriod ActionOn hand date

0 1 212

Negativedays

Positivedays 34 3

2 / 2 4.1. - 8.1.

2 / 3 4.1. - 9.1.

4 / 2 2.1. - 8.1.

4 / 3 2.1. - 9.1.

purchase

P1

sales

Page 26: Tech Talk: Master Planning - Microsoft Dynamics

days20 2515105

Salesorder

Itemarrival

Receipt

“net requ.”

Issue

Create purchase

Reorder Lead time

Purchase order

issue = 5 receipt = 5reorder = 5

Safety margins

purchase = 5

Lead time

Item on hand

Item ready to be sent

Page 27: Tech Talk: Master Planning - Microsoft Dynamics
Page 28: Tech Talk: Master Planning - Microsoft Dynamics

• Realize delays and plan a possible delivery date

• “Backward planning” and “Forward planning”

time

Sales

A1

Planned production time(to cover A1) - 4 days

Necessary date to

start production

Possible delivery date

time

Necessary

order date

Planned purchase time(Raw mat.) - 3 days

Planned production time(to cover A1) - 4 days

Planned purchase time(Raw mat.) - 3 days

delay

Possible

order date

Possible date to

start production

delay

Sales

A1

Page 29: Tech Talk: Master Planning - Microsoft Dynamics
Page 30: Tech Talk: Master Planning - Microsoft Dynamics

1. Master Planning Overview2. Planning Considerations and Setup 3. Coverage Groups4. Coverage Settings5. Demo

Tech Talk: Master Planning

Page 31: Tech Talk: Master Planning - Microsoft Dynamics

• Coverage Settings Order of Precedence

• Item Coverage

• Minimum/Maximum Keys

• Item Coverage Setup

• Safety Stock Journal

Page 32: Tech Talk: Master Planning - Microsoft Dynamics

Item Coverage

Form

Released

Products Form

Maser Planning

Parameters

Page 33: Tech Talk: Master Planning - Microsoft Dynamics
Page 34: Tech Talk: Master Planning - Microsoft Dynamics
Page 35: Tech Talk: Master Planning - Microsoft Dynamics
Page 36: Tech Talk: Master Planning - Microsoft Dynamics
Page 37: Tech Talk: Master Planning - Microsoft Dynamics

Master Planning Home Page

Planning Optimization Preview – Getting Started

Page 38: Tech Talk: Master Planning - Microsoft Dynamics