Top Banner
Tech Report I Part I Elizabeth Kimble Lighting/Electrical Option Dr. Houser University Research Building Northeast United States October 14, 2013 Rendering courtesy of the S|L|A|M Collaborative
19

Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

Jul 15, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

Tech Report I Part I

Elizabeth Kimble

Lighting/Electrical Option

Dr. Houser

University Research Building

Northeast United States

October 14, 2013

Rendering courtesy of the S|L|A|M Collaborative

Page 2: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

2

Executive Summary

The University Research Building (URB) is being constructed to house three collaborative

research labs: the Extreme Materials Institute, the Individualized Health Initiative, and the Systems

Institute. Each of these research programs pulls expertise from multiple departments within the

university, and the URB will provide laboratory and office space to foster communication and

collaboration. The building will also be home to the university’s Computer Science department.

This report contains three main sections: electrical systems criteria and scope of work, an

overview of the electrical systems as currently designed, and an evaluation of the designed systems vs.

the initial criteria.

Page 3: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

3

Table of Contents Executive Summary ....................................................................................................................................... 2

Part I – Electrical Systems Criteria and Scope of Work ................................................................................. 5

Preliminary Electrical Load Calculation ................................................................................................. 5

Identify Power Company Serving Location ........................................................................................... 5

Preliminary Rate Schedule Selection .................................................................................................... 5

Voltages................................................................................................................................................. 5

Emergency Power Requirements – Based on IBC ................................................................................. 6

Special Occupancy Requirements ......................................................................................................... 6

Anticipated Special Equipment ............................................................................................................. 6

Priority Assessment ............................................................................................................................... 7

Optional Back-up Power ....................................................................................................................... 7

Communications Systems and Building Services .................................................................................. 7

Major Equipment Requiring Space ....................................................................................................... 7

Part II – Electrical Systems as Currently Designed ........................................................................................ 8

Actual Connected Building Loads .......................................................................................................... 8

Utility Rate Schedule ........................................................................................................................... 10

Voltage ................................................................................................................................................ 10

Emergency Loads ................................................................................................................................ 11

Special Occupancy Requirements ....................................................................................................... 11

Special Equipment............................................................................................................................... 11

Equipment Information ...................................................................................................................... 12

Optional Back-up Power ..................................................................................................................... 14

Special/Communications Systems ...................................................................................................... 14

Building Services ................................................................................................................................. 15

Dedicated Electrical and Communications Spaces ............................................................................. 15

Energy Saving/Energy Cost Saving Techniques ................................................................................... 15

Part III – Evaluate As-Designed Systems vs. Initial Criteria ......................................................................... 15

Estimated vs. Actual Loads .................................................................................................................. 15

Power Company Rate Schedule .......................................................................................................... 15

Building Utilization Voltage ................................................................................................................. 16

Emergency Power System ................................................................................................................... 16

Page 4: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

4

Equipment Specifications .................................................................................................................... 16

Optional Back-Up Power and UPS Systems ........................................................................................ 16

Reduced Cost of Ownership ................................................................................................................ 16

Systems Integration ............................................................................................................................ 17

Energy Cost Savings/Energy Reduction Techniques ........................................................................... 17

Page 5: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

5

Part I – Electrical Systems Criteria and Scope of Work

Preliminary Electrical Load Calculation

General Lighting Loads by Occupancy – NEC Table 220.12

Office Buildings: 3.5 VA/ft2 x 61858 ft2 = 216503 VA

Halls, Corridors, Closets, Stairways: 0.5 VA/ft2 x 8258 ft2 = 4129 VA

Storage Spaces: 0.25 VA/ ft2 x 168 ft2 = 42 VA

Total Anticipated Lighting Load = 220.7 kVA

Receptacle Outlets – NEC Article 220.14(K)

1 VA/ ft2 x 70284 ft2 = 70.3 kVA

HVAC Systems – R.S. Means Electrical Cost Data 2013 – Table D3020

15.6W/ft2 x 70384 ft2 = 1,100 KW

Identify Power Company Serving Location

Baltimore Gas and Electric (BGE)

Preliminary Rate Schedule Selection

The building is fed from a campus power distribution loop. The applicable rate schedule is likely

Schedule P – Primary, at a service voltage of 13.2 kV.

Voltages

Lighting: primarily 277V, with some 120V for LED wall-grazing fixtures and undercabinet lighting

Receptacles: 120V

HVAC: 480V 3-phase

Servers: 120/208V Panels

Page 6: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

6

Emergency Power Requirements – Based on IBC

Group B (Business) Occupancy

Emergency Power

- Exit Signs

- Means of Egress Illumination

Standby Power

- Smoke control systems

- Elevators

Fuel Source: Diesel

The sister building to the URB has a 250kW generator at 277/280V. The emergency and standby

load requirements will likely be similar for the URB, so a similar generator may be expected.

Special Occupancy Requirements

There are not any anticipated special occupancy requirements per Chapter 5 of the NEC. While it

is a university building, the URB does not feature any large lecture halls that would be

considered assembly spaces.

Anticipated Special Equipment

NEC – Chapter 6

605 – Office Furnishings

620 – Elevators

640 – Audio Systems

645 – Information Technology Equipment

647 – Sensitive Electronic Equipment

690 – Solar Photovoltaic (PV) Systems

Page 7: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

7

Priority Assessment

Reliability – Medium

Power Quality – High

Redundancy – Medium

Low Initial Cost – Low

Long Term Ownership Cost – High

Flexibility – High

Optional Back-up Power

The server racks will most likely be the main equipment requiring optional back-up power. A

UPS is likely appropriate to serve these loads, though they may need additional long term back-

up power from a generator depending upon owner requirements.

Communications Systems and Building Services

Telephone/Data

Fire Alarm

- System shall annunciate at the fire alarm control unit and shall initiate

occupant notification upon activation

- Activated by: automatic fire detectors, automatic sprinkler system, manual

fire alarm boxes, and automatic fire-extinguishing systems.

Access Control

Security

Major Equipment Requiring Space

Mechanical equipment and motors, the generator, and panels will be the main equipment

requiring space. The building’s mechanical penthouse should provide adequate space for most

equipment, with some panels located in electrical closets on each floor.

Page 8: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

8

Part II – Electrical Systems as Currently Designed

Actual Connected Building Loads

Lighting - ASHRAE 90.1 2010

Interior Lighting Power Allowance (Building Area Method)

Building Lighting Power Density Building Area Lighting Power Allowance

Type (W/ft2) (ft2) (W)

School/University 0.99 70284 69581.16

Total 69581.16

Interior Lighting Power Allowance (Space-by-Space Method)

Building Common/Specific Lighting Power Density Space Area Lighting Power Allowance

Type Space Type (W/ft2) (ft2) (W)

School/University Active Storage 0.63 358 225.54

School/University Classroom/Lecture/Training 1.24 7404 9180.96

School/University Conference/Meeting/Multipurpose 1.23 2910 3579.3

School/University Corridor/Transition 0.66 6372 4205.52

School/University Electrical/Mechanical 0.95 13895 13200.25

School/University Laboratory 1.81 11027 19958.87

School/University Lobby 0.90 1006 905.4

School/University Lounge/Recreation 0.73 3476 2537.48

School/University Office - Enclosed 1.11 15747 17479.17

School/University Office - Open Plan 0.98 5038 4937.24

School/University Restroom 0.98 1355 1327.9

School/University Stairs - Active 0.69 1696 1170.24

Total 78707.87

Based upon ASHRAE Standard 90.1 2010, a maximum of 78,707 W of lighting may be installed in the

URB.

Receptacles – Loads referenced from Panel Schedules

Panel PA

Connected Load: 25.6 kVA

Demand Load: 17.9 kVA

Panel PB

Connected Load: 24.1 kVA

Demand Load: 18.1 kVA

Panel PC

Connected Load: 18 kVA

Demand Load: 14 kVA

Panel P1A

Connected Load: 16.9 kVA

Demand Load: 14.2 kVA

Panel P1B

Connected Load: 24.5 kVA

Demand Load: 17.2 kVA

Page 9: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

9

Panel P1C

Connected Load: 9.5 kVA

Demand Load: 9.1 kVA

Panel P2A

Connected Load: 13.3 kVA

Demand Load: 11.8 kVA

Panel P2B

Connected Load: 27 kVA

Demand Load: 18.5 kVA

Panel P2C

Connected Load: 14.8 kVA

Demand Load: 13.3 kVA

Panel P3A

Connected Load: 14.4 kVA

Demand Load: 12.5 kVA

Panel P3B

Connected Load: 29.2 kVA

Demand Load: 19.6 kVA

Panel P3C

Connected Load: 15.9 kVA

Demand Load: 13.8 kVA

Total Receptacle Connected Load = 233.2 kVA

Total Receptacle Demand Load = 180 kVA

Mechanical – Loads Referenced from Panel Schedules

Panel M

Connected Load: 208 kVA

Demand Load: 167 kVA

Panel MP

Connected Load: 28.1 kVA

Demand Load: 23 kVA

Panel M4A

Connected Load: 125.8 kVA

Demand Load: 100.6 kVA

Panel M4B

Connected Load: 114.9 kVA

Demand Load: 92.6 kVA

Panel MP4

Connected Load: 6.5 kVA

Demand Load: 5.9 kVA

Total Mechanical Connected Load = 483.3 kVA

Total Mechanical Demand Load = 389.1 kVA

Servers – Loads Referenced from Panel Schedules

Page 10: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

10

Panel CPA

Connected Load: 57.6 kVA

Demand Load: 33.8 kVA

Panel CPB

Connected Load: 38.4 kVA

Demand Load: 24.2 kVA

Total Server Connected Load = 96 kVA

Total Server Demand Load = 58 kVA

Specialized Equipment – Loads Referenced from Panel Schedules e.g. specialty lab equipment, elevator pit lighting, smoke dampers

Panel SP

Connected Load: 6.7 kVA

Demand Load: 6.7 kVA

Total Building Potential Connected Load = 898 kVA

Utility Rate Schedule

The campus is a customer of BGE – 13.2 kV is delivered to the campus delivery system, so the

campus is likely on the “P – Primary” rate schedule. However, because the URB is part of a

campus power distribution system, building power will not be metered individually by the

power company.

Voltage

Power is delivered to the building by the campus distribution loop at 13.2 kV. The building

transformer then drops the voltage down to 480Y/277.

Lighting – The existing lighting design primarily consists of 277V fixtures, however four fixture

types do require 120V power.

Receptacles – 120V

Mechanical – 277/480 3-phase power

Special Equipment – The special equipment is fed from a panel at 120/208V.

Page 11: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

11

Emergency Loads

Panel E – Emergency Power: 4.7 kVA

Panel E feeds panel EP and emergency lighting loads. Panel EP powers elevator cab

lighting, the fire alarm control panel, and an air-compressor pre-action.

Panel S – Standby: 6.7 kVA

Panel S feeds panel SP, which in turn provides standby power to receptacles with

standby loads (in Biology lab and refrigerator loads), elevator pit lights, smoke dampers,

and a sump pump.

There appears to be an existing generator and generator panel “EDP” located beneath a parking

garage underneath the adjacent quad and a nearby building. The generator runs on diesel fuel.

Special Occupancy Requirements

No occupancy requirements were found, as the building does not contain a large lecture hall

which would count as an “assembly” occupancy.

Special Equipment

The URB features a raised floor system, and with this system it will utilize floor boxes in

many areas of the building. In many areas, these floor boxes will provide power into the office

furniture. These floor boxes and the furniture systems are both shown on the drawings and

listed in the specifications.

The building features one elevator, which is located on the North end of the building.

The elevator is shown on the drawings, and more information about the elevator systems can

be found in the building specifications.

Ceiling-mounted intercom speakers are located throughout the building, and can be

found on the AV drawings.

Telecommunications plans detail the locations of IT equipment and connections

throughout the University Research Building.

As the URB is home to the computer science department and several labs, there is likely

to be sensitive electronic equipment. At the time bid drawings were issued, it was known that

the bio lab would have sensitive equipment requiring standby power to receptacles. More

detailed information about other sensitive equipment was not available.

Page 12: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

12

While conduit provisions were made for future photovoltaic installations on the flat roof

above the curved curtain wall of the building, there are not PV arrays in the current project as it

is being built.

Equipment Information

Main Service and Distribution Equipment

Medium Voltage Switchgear

Specification Section 26 1300

Equal to Square D Type HVL/CC metal-enclosed load-interrupter switchgear

System Voltage: 13.2 kV, 3-phase, 3-wire

Operating Frequency: 60 Hz

Max. Design Voltage: 17.5 kV

Switchboard SB

Specification Section 26 2413

Voltage: 277/480V

Main Service Transformer

Medium-Voltage Transformer

Specification Section 26 1200

15-kV substation transformer, indoor.

Owned by University. Liquid type.

13.2 kV delta primary with 2.5 percent full capacity taps above and below normal to

480Y/277 V secondary.

Distribution Step Down Transformers

Low-Voltage Transformers

Specification Section 26 2200

Designed in accordance with NEMA ST 20: Dry-type transformers for general

applications

Page 13: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

13

Panelboards

Panelboards

Specification Section 26 2416

Some panelboards are MCB type, while others are MLO type. Type is specified for each

panel on the panel schedule within the drawings.

Bolt-on type circuit breakers. Copper.

Main Risers and Feeders

Modular Wiring System

Specification Section 26 0537

The modular wiring system specified will interface with various power applications

throughout the URB, including raised floor boxes, service poles, surface raceways,

wireways, and convenience outlets.

Conductors

Wires and Cables

Specification Section 26 0519

Conductors will be copper, with 98% conductivity

Conduit

Conduit

Specification Section 26 0533

Types:

Galvanized Steel Conduit

Steel Conduit

Electrical Metallic Tubing

Flexible Metal Conduit – Used to connect floor boxes to wire distribution bus

beneath raised floor.

Liquidtight Flexible Metal Conduit

Page 14: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

14

Receptacles

Wiring Devices

Specification Section 26 2726

Receptacles provided shall be specification grade.

Switch and Receptacle Faceplates

Device Plates

Device plates shall be stainless steel, aluminum, brass, smooth plastic, or smooth nylon,

as selected by the Architect.

Device plates for receptacles controlled by an automatic control device shall be custom

engraved metal or pad printed plastic, and shall identify the device with the words

“Switched Receptacle”.

Motor Starters

Enclosed Motor Controllers

Specification Sections 26 2914 and 26 2923

Both manual motor starters and variable speed drives are specified on this project.

UPS

There are no UPS types specified on the project.

Optional Back-up Power

Receptacles in the biology lab, as well as receptacles serving refrigerator loads, are

connected to optional back-up power. They are provided with this back-up power by the

standby panel, panel “SP”. In total, these optional back-up loads have a load of 0.4 kVA and they

are 120V receptacles.

Special/Communications Systems

Telephone/data – there are telephone and data connections throughout the URB.

Fire Alarm – fire alarm equipment is located throughout the building to alert occupants in the

event of an emergency.

Access control and security cameras will help to prevent unauthorized individuals from entering

the labs contained within the building.

Page 15: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

15

Building Services

Cables will be installed to provide for both voice and data connections throughout the building.

Dedicated Electrical and Communications Spaces

Including the server room, there is 2,026 ft2 of dedicated electrical and communications space

within the building. This represents 2.89% of the total building S.F.

Energy Saving/Energy Cost Saving Techniques

There are not currently photovoltaic arrays included in the scope of the building project,

although conduit provisions were included to provide for future installations. The building uses daylight

harvesting with daylight sensors and dimmable light fixtures. The URB is pursuing LEED Gold

certification.

Part III – Evaluate As-Designed Systems vs. Initial Criteria

Estimated vs. Actual Loads

The estimated building load was about 1391 kVA, while the building as designed has a

connected load of about 898 kVA. One reason for the significant decrease is that the lighting loads

allowed by ASHRAE Standard 90.1 2010 (which has been adopted in Maryland) are much lower than the

W/ft2 listed in the NEC. While the actual receptacle connected loads were much higher than the

estimate based on NEC for an office building, there are significantly more receptacles in the lab areas of

the URB. Finally, the mechanical system as designed is much more efficient than the estimate made

based on R.S. Means Electrical cost data, as the mechanical system was designed to contribute to the

building’s LEED Gold rating.

Power Company Rate Schedule

There are not really any other options available for the university in terms of a utility rate

schedule, as they are already operating a university-owned campus distribution loop. As such, the

campus could consider participating in a Load Response Program, for which there is a rider, but this

would likely have to be approached on a campus-wide basis, as the URB is not individually metered.

Page 16: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

16

Building Utilization Voltage

I would not suggest any changes to the building utilization voltage. The only change I might

suggest for the power distribution throughout the building would be to switch from the current

underfloor distribution system to a system like Snake Tray’s Snake Bus, which could provide increased

flexibility and cost-savings, especially through installation time and costs.

Emergency Power System

The URB appears to have all of the emergency power systems as required by code. I would not

suggest any changes to the generator system, as it is existing equipment that has already been designed

to power the surrounding buildings and the URB.

Equipment Specifications

The only changes I might suggest regarding the electrical equipment specified would be to

consider a Snake Tray bus system as mentioned above, and to provide UPS systems for some loads that

may benefit from increased power reliability.

Optional Back-Up Power and UPS Systems

I might suggest increased back-up power for some of the sensitive lab equipment and servers in

the building. There is still space available on the standby panel “SP”, and the exact loads and locations

may not have been specified in the bid drawings because the exact equipment and requirements may

not have been known at that time. I think a UPS system would be helpful to provide reliability to the

building’s server racks.

Reduced Cost of Ownership

The current design for the URB already specifies very high quality equipment, as it is on the

campus of a prestigious university. The equipment is also efficient, as the building is pursuing LEED Gold

certification.

Page 17: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

17

Systems Integration

As ASHRAE Standard 90.1 already requires advances lighting controls in most of the spaces

throughout the building, one could consider integrating the building’s occupancy sensors with the

building’s mechanical system, to allow for more precise HVAC operation and increased energy savings.

The advantages of such an integrated system would be reduced HVAC costs, and lower equipment costs,

as you would not need to purchase separate occupancy sensors for both the lighting and mechanical

systems. However, this systems integration would likely have a high initial cost, and would require very

advanced coordination between the two systems. Furthermore, it could limit the lighting and

mechanical controls equipment that could be specified, as only some of the control systems are able to

effectively interface with each other.

Energy Cost Savings/Energy Reduction Techniques

The building design could consider the potential electric generation capabilities of actually

installing the PV arrays that the conduit has been provided for.

Page 18: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel
emk5189
Text Box
Page 19: Tech Report I Part I - Pennsylvania State University · lighting, the fire alarm control panel, and an air-compressor pre-action. Panel S – Standby: 6.7 kVA Panel S feeds panel

GROUND FLOOR

PANEL CP2 SECTION120/208V

CBCB

XFMR TCP

FUSE

D S

WIT

CH

TRAN

SITI

ON

SWIT

CH

SWIT

CH

TRAN

SITI

ON

TRAN

SITI

ON

MAI

N

DIS

TRIB

UTI

ON

MEDIUM-VOLTAGE

TRANSFORMER

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

PENTHOUSE

DIST. PANEL DP277/480V

DIST. PANEL PP120/208V

PANEL P3 SECTION120/208V

PANEL L277/480V

XFMR TPP

MECHANICALROOM G25

SERVER ROOMG29

SPD

SPD

SPD

ELECTRICAL ROOM 204

ELECTRICAL ROOM 304

ELECTRICAL ROOM 104

4" EMPTY CONDUIT WITH PULL ROPEFOR FUTURE USE

PANEL MP4120/208V

XFMR TMP4

INCOMINGPRIMARYFEEDERS

MEDIUM-VOLTAGESWITCHGEAR

ELECTRICAL ROOMSG04 & G13

SWITCHBOARD SB277/480V

MANHOLE MH-37B

PANEL P13 SECTION120/208V

PANEL L2277/480V

PANEL P33 SECTION120/208V

SPACE FORPHOTOVOLTAIC(SOLAR)EQUIPMENT

1

2

DIST. PANEL M4277/480V

SURGE PROTECTIVEDEVICE (TYPICAL)

MMM

MMM

SPD SPD

11(TYPICAL OF 6)

PANEL M277/480V

PANEL P23 SECTION120/208V

PANEL MP120/208V

XFMR TMP

1

SPECIFIC NOTES:

ENCLOSED CIRCUIT BREAKER 3P-400A-600V, NEMA 1 ENCLOSURE.

2 ENCLOSED CIRCUIT BREAKER 3P-150A-600V, NEMA 1 ENCLOSURE.

3 ENCLOSED CIRCUIT BREAKER 3P-125A-600V, NEMA 1 ENCLOSURE.

4 ENCLOSED CIRCUIT BREAKER 3P-70A-600V, NEMA 1 ENCLOSURE.

5 CONNECT TO GROUNDING BUSBAR IN MAIN SWITCHBOARD.

6 PROVIDE ELECTRICAL SERVICE BUSBAR/INTERSYSTEM BONDINGTERMINATION GROUNDING BUSBAR (IBGB). REFER TO DETAILS1/E502 AND 2/E502 FOR ADDITIONAL INFORMATION.

7 PROVIDE TELECOMMUNICATIONS BONDING BACKBONE (TBB), #3/0INSULATED COPPER GROUNDING CONDUCTOR, IN 1-1/4" EMT CONDUIT.PROVIDE 0.1 OHM BOND BETWEEN 1-1/4" EMT CONDUIT AND CONDUITFITTINGS. UTILIZE GROUNDING JUMPERS AS NEEDED.

8 PROVIDE #6 PIGTAIL CONNECTION (IRREVERSIBLE COMPRESSIONFITTING OR EXOTHERMIC WELD) OR IRREVERSIBLE BONDING CLAMPFOR CONDUIT.

9 PROVIDE #6 INSULATED COPPER GROUNDING CONDUCTOR FROMTELECOMMUNICATIONS GROUNDING BUSBAR TO METAL PARTS OFACCESS FLOORS WITHIN SERVER AND TEL/DATA ROOMS, METAL PARTSOF ACCESS FLOORS OUTSIDE OF SERVER AND TEL/DATA ROOMS,COMPUTER EQUIPMENT ENCLOSURES (DATA CABINETS AND DATARACKS), CABLE TRAYS, AND/OR ALL EQUIPMENT ENCLOSURES IN ROOMWHERE BUSBAR IS LOCATED. MAKE ALL GROUNDING CONNECTIONSWITH BOLTED CONNECTORS.

10 PROVIDE #6 INSULATED COPPER GROUNDING CONDUCTOR FROMTELECOMMUNICATIONS GROUNDING BUSBAR TO BUILDING STEEL ANDNEAREST COLD WATER PIPE. MAKE ALL GROUNDING CONNCTIONS TOBUILDING STEEL WITH EXOTHERMIC WELD OR IRREVERSIBLECOMPRESSION FITTING.

11 PROVIDE POWER MONITORS AS INDICATED TO MONITOR THEFOLLOWING EQUIPMENT:

1. 15-KV MEDIUM-VOLTAGE SWITCHGEAR FOR PRIMARY METERING.2. DISTRIBUTION PANEL DP FOR LIGHTING LOADS.3. DISTRIBUTION PANEL PP FOR RECEPTACLE AND PLUG LOADS.4. DISTRIBUTION PANEL MD4 FOR MECHANICAL LOADS IN PENTHOUSE.5. PANEL MP FOR MECHANICAL LOADS ON THE GROUND FLOOR.6. PANEL CP FOR SERVER ROOM G29.

PROVIDE WIRING IN CONDUIT FROM POWER MONITORS TO MONITOREDEQUIPMENT. PROVIDE CURRENT TRANSFORMERS, POTENTIALTRANSFORMERS, AND MAKE CONNECTIONS NECESSARY FOR COMPLETEINSTALLATION.

GENERAL NOTES:

A.

B.

INFORMATION SHOWN ON THIS DRAWING PERTAINING TO EXISTING CONDITIONSHAS BEEN OBTAINED FROM AVAILABLE BUILDING DRAWINGS OR GENERAL FIELDOBSERVATIONS AND MAY NOT INDICATE ACTUAL EXISTING CONDITIONS IN DETAILOR DIMENSIONS. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING THEACTUAL EXISTING CONDITIONS PRIOR TO FABRICATION OR PERFORMANCE OF ANYWORK. SHOULD CONDITIONS BE DISCOVERED THAT PREVENT EXCETUION OF THENEW WORK AS INDICATED, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THEARCHITECT IN WRITING AND AWAIT DIRECTION BEFORE PROCEEDING WITH THEWORK.

CAMPUS MEDIUM VOLTAGE DISTRIBUTION SYSTEM OPERATES AT 13,200 VOLTS.

GROUND FLOOR

MAI

N

DIS

TRIB

UTI

ON

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

PENTHOUSE

ELECTRICAL ROOM 204

ELECTRICAL ROOM 304

ELECTRICAL ROOM 104

ELECTRICAL ROOMSG04 & G10

SWITCHBOARD SB277/480V

CB CB

NORTH ENTRY 101

GENERATORREMOTEANNUNCIATOR

ATS-1LIFE SAFETY4P, 125A

ATS-2OPTIONALSTANDBY4P, 125A

PANEL E277/480V

PANEL S277/480V

PANEL SP120/208V

PANEL EP120/208V

GENERATOR MONITORAND CONTROL WIRINGFROM GENERATORCONTROL PANEL

TO EXISTING 3P-150ACIRCUIT BREAKER INEXISTING PANEL EDP(GENERATOR PANEL).PROVIDE 4 #1/0 + #6GROUND IN 2" CONDUIT.

XFMR TEP

XFMR TSP

34

GROUND FLOOR

MAI

N

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

PENTHOUSE

TEL/DATAROOM 302

SWITCHBOARD SB

BB BB

BB

BB

BB

TEL/DATAROOM 202

TEL/DATAROOM 102

TEL/DATAROOM G02

5

8

6

6 6

6

7

7

7

7

109

88

10

98

8

10

9

8

8

10

9

8

8

TGB

TGB

TGB

TELECOMMUNICATIONSGROUNDING BUSBAR (TGB)

ELECTRICALROOM G10

SERVERROOM G29

BB

7

109

88

TELECOMMUNICATIONS MAINGROUNDING BUSBAR (TMGB)

7

7

INTERSYSTEM BONDINGTERMINATION GROUNDINGBUSBAR (IBGB)

MICROSCOPYROOM G38

BB

7

88

TGB

ArchitecturePlanningInteriors

EngineeringLandscape Architecture

Construction ServicesTechnology

C 20

1 1 T

he S

/L/A

/M C

ollab

o rat

ive, In

c.

Somerset Square80 Glastonbury Boulevard

GlastonburyConnecticut 06033-4415

Telephone 860 657-8077Fax 860 657-3141

S L A M

T h e

C o l l a b o r a t i v e

Drawn

Checked

Date

Scale

Proj. Number

Drawing Number

KEYPLAN

54321

A

B

C

D

E

Proj. No. 6000-11

As indicated

C:\U

ser s

\pm

arqu

ez\D

ocum

ents

\ME

P_6

000-

11_J

HU

Mal

one

Hal

l_pm

arq

uez.

rvt

9/14

/201

2 12

:07:

38 P

M

E60109/14/12

11037.00

MALONE HALL

RISER DIAGRAMS

PMM

PJM

SCALE: NTSE601NORMAL POWER RISER DIAGRAM1

SCALE: NTSE601GENERATOR POWER RISER DIAGRAM2

SCALE: NTSE601SUPPLEMENTAL GROUNDING RISER DIAGRAM3

Number M/D/Y Issued For