Tech Report I Part I Elizabeth Kimble Lighting/Electrical Option Dr. Houser University Research Building Northeast United States October 14, 2013 Rendering courtesy of the S|L|A|M Collaborative
Tech Report I Part I
Elizabeth Kimble
Lighting/Electrical Option
Dr. Houser
University Research Building
Northeast United States
October 14, 2013
Rendering courtesy of the S|L|A|M Collaborative
2
Executive Summary
The University Research Building (URB) is being constructed to house three collaborative
research labs: the Extreme Materials Institute, the Individualized Health Initiative, and the Systems
Institute. Each of these research programs pulls expertise from multiple departments within the
university, and the URB will provide laboratory and office space to foster communication and
collaboration. The building will also be home to the university’s Computer Science department.
This report contains three main sections: electrical systems criteria and scope of work, an
overview of the electrical systems as currently designed, and an evaluation of the designed systems vs.
the initial criteria.
3
Table of Contents Executive Summary ....................................................................................................................................... 2
Part I – Electrical Systems Criteria and Scope of Work ................................................................................. 5
Preliminary Electrical Load Calculation ................................................................................................. 5
Identify Power Company Serving Location ........................................................................................... 5
Preliminary Rate Schedule Selection .................................................................................................... 5
Voltages................................................................................................................................................. 5
Emergency Power Requirements – Based on IBC ................................................................................. 6
Special Occupancy Requirements ......................................................................................................... 6
Anticipated Special Equipment ............................................................................................................. 6
Priority Assessment ............................................................................................................................... 7
Optional Back-up Power ....................................................................................................................... 7
Communications Systems and Building Services .................................................................................. 7
Major Equipment Requiring Space ....................................................................................................... 7
Part II – Electrical Systems as Currently Designed ........................................................................................ 8
Actual Connected Building Loads .......................................................................................................... 8
Utility Rate Schedule ........................................................................................................................... 10
Voltage ................................................................................................................................................ 10
Emergency Loads ................................................................................................................................ 11
Special Occupancy Requirements ....................................................................................................... 11
Special Equipment............................................................................................................................... 11
Equipment Information ...................................................................................................................... 12
Optional Back-up Power ..................................................................................................................... 14
Special/Communications Systems ...................................................................................................... 14
Building Services ................................................................................................................................. 15
Dedicated Electrical and Communications Spaces ............................................................................. 15
Energy Saving/Energy Cost Saving Techniques ................................................................................... 15
Part III – Evaluate As-Designed Systems vs. Initial Criteria ......................................................................... 15
Estimated vs. Actual Loads .................................................................................................................. 15
Power Company Rate Schedule .......................................................................................................... 15
Building Utilization Voltage ................................................................................................................. 16
Emergency Power System ................................................................................................................... 16
4
Equipment Specifications .................................................................................................................... 16
Optional Back-Up Power and UPS Systems ........................................................................................ 16
Reduced Cost of Ownership ................................................................................................................ 16
Systems Integration ............................................................................................................................ 17
Energy Cost Savings/Energy Reduction Techniques ........................................................................... 17
5
Part I – Electrical Systems Criteria and Scope of Work
Preliminary Electrical Load Calculation
General Lighting Loads by Occupancy – NEC Table 220.12
Office Buildings: 3.5 VA/ft2 x 61858 ft2 = 216503 VA
Halls, Corridors, Closets, Stairways: 0.5 VA/ft2 x 8258 ft2 = 4129 VA
Storage Spaces: 0.25 VA/ ft2 x 168 ft2 = 42 VA
Total Anticipated Lighting Load = 220.7 kVA
Receptacle Outlets – NEC Article 220.14(K)
1 VA/ ft2 x 70284 ft2 = 70.3 kVA
HVAC Systems – R.S. Means Electrical Cost Data 2013 – Table D3020
15.6W/ft2 x 70384 ft2 = 1,100 KW
Identify Power Company Serving Location
Baltimore Gas and Electric (BGE)
Preliminary Rate Schedule Selection
The building is fed from a campus power distribution loop. The applicable rate schedule is likely
Schedule P – Primary, at a service voltage of 13.2 kV.
Voltages
Lighting: primarily 277V, with some 120V for LED wall-grazing fixtures and undercabinet lighting
Receptacles: 120V
HVAC: 480V 3-phase
Servers: 120/208V Panels
6
Emergency Power Requirements – Based on IBC
Group B (Business) Occupancy
Emergency Power
- Exit Signs
- Means of Egress Illumination
Standby Power
- Smoke control systems
- Elevators
Fuel Source: Diesel
The sister building to the URB has a 250kW generator at 277/280V. The emergency and standby
load requirements will likely be similar for the URB, so a similar generator may be expected.
Special Occupancy Requirements
There are not any anticipated special occupancy requirements per Chapter 5 of the NEC. While it
is a university building, the URB does not feature any large lecture halls that would be
considered assembly spaces.
Anticipated Special Equipment
NEC – Chapter 6
605 – Office Furnishings
620 – Elevators
640 – Audio Systems
645 – Information Technology Equipment
647 – Sensitive Electronic Equipment
690 – Solar Photovoltaic (PV) Systems
7
Priority Assessment
Reliability – Medium
Power Quality – High
Redundancy – Medium
Low Initial Cost – Low
Long Term Ownership Cost – High
Flexibility – High
Optional Back-up Power
The server racks will most likely be the main equipment requiring optional back-up power. A
UPS is likely appropriate to serve these loads, though they may need additional long term back-
up power from a generator depending upon owner requirements.
Communications Systems and Building Services
Telephone/Data
Fire Alarm
- System shall annunciate at the fire alarm control unit and shall initiate
occupant notification upon activation
- Activated by: automatic fire detectors, automatic sprinkler system, manual
fire alarm boxes, and automatic fire-extinguishing systems.
Access Control
Security
Major Equipment Requiring Space
Mechanical equipment and motors, the generator, and panels will be the main equipment
requiring space. The building’s mechanical penthouse should provide adequate space for most
equipment, with some panels located in electrical closets on each floor.
8
Part II – Electrical Systems as Currently Designed
Actual Connected Building Loads
Lighting - ASHRAE 90.1 2010
Interior Lighting Power Allowance (Building Area Method)
Building Lighting Power Density Building Area Lighting Power Allowance
Type (W/ft2) (ft2) (W)
School/University 0.99 70284 69581.16
Total 69581.16
Interior Lighting Power Allowance (Space-by-Space Method)
Building Common/Specific Lighting Power Density Space Area Lighting Power Allowance
Type Space Type (W/ft2) (ft2) (W)
School/University Active Storage 0.63 358 225.54
School/University Classroom/Lecture/Training 1.24 7404 9180.96
School/University Conference/Meeting/Multipurpose 1.23 2910 3579.3
School/University Corridor/Transition 0.66 6372 4205.52
School/University Electrical/Mechanical 0.95 13895 13200.25
School/University Laboratory 1.81 11027 19958.87
School/University Lobby 0.90 1006 905.4
School/University Lounge/Recreation 0.73 3476 2537.48
School/University Office - Enclosed 1.11 15747 17479.17
School/University Office - Open Plan 0.98 5038 4937.24
School/University Restroom 0.98 1355 1327.9
School/University Stairs - Active 0.69 1696 1170.24
Total 78707.87
Based upon ASHRAE Standard 90.1 2010, a maximum of 78,707 W of lighting may be installed in the
URB.
Receptacles – Loads referenced from Panel Schedules
Panel PA
Connected Load: 25.6 kVA
Demand Load: 17.9 kVA
Panel PB
Connected Load: 24.1 kVA
Demand Load: 18.1 kVA
Panel PC
Connected Load: 18 kVA
Demand Load: 14 kVA
Panel P1A
Connected Load: 16.9 kVA
Demand Load: 14.2 kVA
Panel P1B
Connected Load: 24.5 kVA
Demand Load: 17.2 kVA
9
Panel P1C
Connected Load: 9.5 kVA
Demand Load: 9.1 kVA
Panel P2A
Connected Load: 13.3 kVA
Demand Load: 11.8 kVA
Panel P2B
Connected Load: 27 kVA
Demand Load: 18.5 kVA
Panel P2C
Connected Load: 14.8 kVA
Demand Load: 13.3 kVA
Panel P3A
Connected Load: 14.4 kVA
Demand Load: 12.5 kVA
Panel P3B
Connected Load: 29.2 kVA
Demand Load: 19.6 kVA
Panel P3C
Connected Load: 15.9 kVA
Demand Load: 13.8 kVA
Total Receptacle Connected Load = 233.2 kVA
Total Receptacle Demand Load = 180 kVA
Mechanical – Loads Referenced from Panel Schedules
Panel M
Connected Load: 208 kVA
Demand Load: 167 kVA
Panel MP
Connected Load: 28.1 kVA
Demand Load: 23 kVA
Panel M4A
Connected Load: 125.8 kVA
Demand Load: 100.6 kVA
Panel M4B
Connected Load: 114.9 kVA
Demand Load: 92.6 kVA
Panel MP4
Connected Load: 6.5 kVA
Demand Load: 5.9 kVA
Total Mechanical Connected Load = 483.3 kVA
Total Mechanical Demand Load = 389.1 kVA
Servers – Loads Referenced from Panel Schedules
10
Panel CPA
Connected Load: 57.6 kVA
Demand Load: 33.8 kVA
Panel CPB
Connected Load: 38.4 kVA
Demand Load: 24.2 kVA
Total Server Connected Load = 96 kVA
Total Server Demand Load = 58 kVA
Specialized Equipment – Loads Referenced from Panel Schedules e.g. specialty lab equipment, elevator pit lighting, smoke dampers
Panel SP
Connected Load: 6.7 kVA
Demand Load: 6.7 kVA
Total Building Potential Connected Load = 898 kVA
Utility Rate Schedule
The campus is a customer of BGE – 13.2 kV is delivered to the campus delivery system, so the
campus is likely on the “P – Primary” rate schedule. However, because the URB is part of a
campus power distribution system, building power will not be metered individually by the
power company.
Voltage
Power is delivered to the building by the campus distribution loop at 13.2 kV. The building
transformer then drops the voltage down to 480Y/277.
Lighting – The existing lighting design primarily consists of 277V fixtures, however four fixture
types do require 120V power.
Receptacles – 120V
Mechanical – 277/480 3-phase power
Special Equipment – The special equipment is fed from a panel at 120/208V.
11
Emergency Loads
Panel E – Emergency Power: 4.7 kVA
Panel E feeds panel EP and emergency lighting loads. Panel EP powers elevator cab
lighting, the fire alarm control panel, and an air-compressor pre-action.
Panel S – Standby: 6.7 kVA
Panel S feeds panel SP, which in turn provides standby power to receptacles with
standby loads (in Biology lab and refrigerator loads), elevator pit lights, smoke dampers,
and a sump pump.
There appears to be an existing generator and generator panel “EDP” located beneath a parking
garage underneath the adjacent quad and a nearby building. The generator runs on diesel fuel.
Special Occupancy Requirements
No occupancy requirements were found, as the building does not contain a large lecture hall
which would count as an “assembly” occupancy.
Special Equipment
The URB features a raised floor system, and with this system it will utilize floor boxes in
many areas of the building. In many areas, these floor boxes will provide power into the office
furniture. These floor boxes and the furniture systems are both shown on the drawings and
listed in the specifications.
The building features one elevator, which is located on the North end of the building.
The elevator is shown on the drawings, and more information about the elevator systems can
be found in the building specifications.
Ceiling-mounted intercom speakers are located throughout the building, and can be
found on the AV drawings.
Telecommunications plans detail the locations of IT equipment and connections
throughout the University Research Building.
As the URB is home to the computer science department and several labs, there is likely
to be sensitive electronic equipment. At the time bid drawings were issued, it was known that
the bio lab would have sensitive equipment requiring standby power to receptacles. More
detailed information about other sensitive equipment was not available.
12
While conduit provisions were made for future photovoltaic installations on the flat roof
above the curved curtain wall of the building, there are not PV arrays in the current project as it
is being built.
Equipment Information
Main Service and Distribution Equipment
Medium Voltage Switchgear
Specification Section 26 1300
Equal to Square D Type HVL/CC metal-enclosed load-interrupter switchgear
System Voltage: 13.2 kV, 3-phase, 3-wire
Operating Frequency: 60 Hz
Max. Design Voltage: 17.5 kV
Switchboard SB
Specification Section 26 2413
Voltage: 277/480V
Main Service Transformer
Medium-Voltage Transformer
Specification Section 26 1200
15-kV substation transformer, indoor.
Owned by University. Liquid type.
13.2 kV delta primary with 2.5 percent full capacity taps above and below normal to
480Y/277 V secondary.
Distribution Step Down Transformers
Low-Voltage Transformers
Specification Section 26 2200
Designed in accordance with NEMA ST 20: Dry-type transformers for general
applications
13
Panelboards
Panelboards
Specification Section 26 2416
Some panelboards are MCB type, while others are MLO type. Type is specified for each
panel on the panel schedule within the drawings.
Bolt-on type circuit breakers. Copper.
Main Risers and Feeders
Modular Wiring System
Specification Section 26 0537
The modular wiring system specified will interface with various power applications
throughout the URB, including raised floor boxes, service poles, surface raceways,
wireways, and convenience outlets.
Conductors
Wires and Cables
Specification Section 26 0519
Conductors will be copper, with 98% conductivity
Conduit
Conduit
Specification Section 26 0533
Types:
Galvanized Steel Conduit
Steel Conduit
Electrical Metallic Tubing
Flexible Metal Conduit – Used to connect floor boxes to wire distribution bus
beneath raised floor.
Liquidtight Flexible Metal Conduit
14
Receptacles
Wiring Devices
Specification Section 26 2726
Receptacles provided shall be specification grade.
Switch and Receptacle Faceplates
Device Plates
Device plates shall be stainless steel, aluminum, brass, smooth plastic, or smooth nylon,
as selected by the Architect.
Device plates for receptacles controlled by an automatic control device shall be custom
engraved metal or pad printed plastic, and shall identify the device with the words
“Switched Receptacle”.
Motor Starters
Enclosed Motor Controllers
Specification Sections 26 2914 and 26 2923
Both manual motor starters and variable speed drives are specified on this project.
UPS
There are no UPS types specified on the project.
Optional Back-up Power
Receptacles in the biology lab, as well as receptacles serving refrigerator loads, are
connected to optional back-up power. They are provided with this back-up power by the
standby panel, panel “SP”. In total, these optional back-up loads have a load of 0.4 kVA and they
are 120V receptacles.
Special/Communications Systems
Telephone/data – there are telephone and data connections throughout the URB.
Fire Alarm – fire alarm equipment is located throughout the building to alert occupants in the
event of an emergency.
Access control and security cameras will help to prevent unauthorized individuals from entering
the labs contained within the building.
15
Building Services
Cables will be installed to provide for both voice and data connections throughout the building.
Dedicated Electrical and Communications Spaces
Including the server room, there is 2,026 ft2 of dedicated electrical and communications space
within the building. This represents 2.89% of the total building S.F.
Energy Saving/Energy Cost Saving Techniques
There are not currently photovoltaic arrays included in the scope of the building project,
although conduit provisions were included to provide for future installations. The building uses daylight
harvesting with daylight sensors and dimmable light fixtures. The URB is pursuing LEED Gold
certification.
Part III – Evaluate As-Designed Systems vs. Initial Criteria
Estimated vs. Actual Loads
The estimated building load was about 1391 kVA, while the building as designed has a
connected load of about 898 kVA. One reason for the significant decrease is that the lighting loads
allowed by ASHRAE Standard 90.1 2010 (which has been adopted in Maryland) are much lower than the
W/ft2 listed in the NEC. While the actual receptacle connected loads were much higher than the
estimate based on NEC for an office building, there are significantly more receptacles in the lab areas of
the URB. Finally, the mechanical system as designed is much more efficient than the estimate made
based on R.S. Means Electrical cost data, as the mechanical system was designed to contribute to the
building’s LEED Gold rating.
Power Company Rate Schedule
There are not really any other options available for the university in terms of a utility rate
schedule, as they are already operating a university-owned campus distribution loop. As such, the
campus could consider participating in a Load Response Program, for which there is a rider, but this
would likely have to be approached on a campus-wide basis, as the URB is not individually metered.
16
Building Utilization Voltage
I would not suggest any changes to the building utilization voltage. The only change I might
suggest for the power distribution throughout the building would be to switch from the current
underfloor distribution system to a system like Snake Tray’s Snake Bus, which could provide increased
flexibility and cost-savings, especially through installation time and costs.
Emergency Power System
The URB appears to have all of the emergency power systems as required by code. I would not
suggest any changes to the generator system, as it is existing equipment that has already been designed
to power the surrounding buildings and the URB.
Equipment Specifications
The only changes I might suggest regarding the electrical equipment specified would be to
consider a Snake Tray bus system as mentioned above, and to provide UPS systems for some loads that
may benefit from increased power reliability.
Optional Back-Up Power and UPS Systems
I might suggest increased back-up power for some of the sensitive lab equipment and servers in
the building. There is still space available on the standby panel “SP”, and the exact loads and locations
may not have been specified in the bid drawings because the exact equipment and requirements may
not have been known at that time. I think a UPS system would be helpful to provide reliability to the
building’s server racks.
Reduced Cost of Ownership
The current design for the URB already specifies very high quality equipment, as it is on the
campus of a prestigious university. The equipment is also efficient, as the building is pursuing LEED Gold
certification.
17
Systems Integration
As ASHRAE Standard 90.1 already requires advances lighting controls in most of the spaces
throughout the building, one could consider integrating the building’s occupancy sensors with the
building’s mechanical system, to allow for more precise HVAC operation and increased energy savings.
The advantages of such an integrated system would be reduced HVAC costs, and lower equipment costs,
as you would not need to purchase separate occupancy sensors for both the lighting and mechanical
systems. However, this systems integration would likely have a high initial cost, and would require very
advanced coordination between the two systems. Furthermore, it could limit the lighting and
mechanical controls equipment that could be specified, as only some of the control systems are able to
effectively interface with each other.
Energy Cost Savings/Energy Reduction Techniques
The building design could consider the potential electric generation capabilities of actually
installing the PV arrays that the conduit has been provided for.
GROUND FLOOR
PANEL CP2 SECTION120/208V
CBCB
XFMR TCP
FUSE
D S
WIT
CH
TRAN
SITI
ON
SWIT
CH
SWIT
CH
TRAN
SITI
ON
TRAN
SITI
ON
MAI
N
DIS
TRIB
UTI
ON
MEDIUM-VOLTAGE
TRANSFORMER
FIRST FLOOR
SECOND FLOOR
THIRD FLOOR
PENTHOUSE
DIST. PANEL DP277/480V
DIST. PANEL PP120/208V
PANEL P3 SECTION120/208V
PANEL L277/480V
XFMR TPP
MECHANICALROOM G25
SERVER ROOMG29
SPD
SPD
SPD
ELECTRICAL ROOM 204
ELECTRICAL ROOM 304
ELECTRICAL ROOM 104
4" EMPTY CONDUIT WITH PULL ROPEFOR FUTURE USE
PANEL MP4120/208V
XFMR TMP4
INCOMINGPRIMARYFEEDERS
MEDIUM-VOLTAGESWITCHGEAR
ELECTRICAL ROOMSG04 & G13
SWITCHBOARD SB277/480V
MANHOLE MH-37B
PANEL P13 SECTION120/208V
PANEL L2277/480V
PANEL P33 SECTION120/208V
SPACE FORPHOTOVOLTAIC(SOLAR)EQUIPMENT
1
2
DIST. PANEL M4277/480V
SURGE PROTECTIVEDEVICE (TYPICAL)
MMM
MMM
SPD SPD
11(TYPICAL OF 6)
PANEL M277/480V
PANEL P23 SECTION120/208V
PANEL MP120/208V
XFMR TMP
1
SPECIFIC NOTES:
ENCLOSED CIRCUIT BREAKER 3P-400A-600V, NEMA 1 ENCLOSURE.
2 ENCLOSED CIRCUIT BREAKER 3P-150A-600V, NEMA 1 ENCLOSURE.
3 ENCLOSED CIRCUIT BREAKER 3P-125A-600V, NEMA 1 ENCLOSURE.
4 ENCLOSED CIRCUIT BREAKER 3P-70A-600V, NEMA 1 ENCLOSURE.
5 CONNECT TO GROUNDING BUSBAR IN MAIN SWITCHBOARD.
6 PROVIDE ELECTRICAL SERVICE BUSBAR/INTERSYSTEM BONDINGTERMINATION GROUNDING BUSBAR (IBGB). REFER TO DETAILS1/E502 AND 2/E502 FOR ADDITIONAL INFORMATION.
7 PROVIDE TELECOMMUNICATIONS BONDING BACKBONE (TBB), #3/0INSULATED COPPER GROUNDING CONDUCTOR, IN 1-1/4" EMT CONDUIT.PROVIDE 0.1 OHM BOND BETWEEN 1-1/4" EMT CONDUIT AND CONDUITFITTINGS. UTILIZE GROUNDING JUMPERS AS NEEDED.
8 PROVIDE #6 PIGTAIL CONNECTION (IRREVERSIBLE COMPRESSIONFITTING OR EXOTHERMIC WELD) OR IRREVERSIBLE BONDING CLAMPFOR CONDUIT.
9 PROVIDE #6 INSULATED COPPER GROUNDING CONDUCTOR FROMTELECOMMUNICATIONS GROUNDING BUSBAR TO METAL PARTS OFACCESS FLOORS WITHIN SERVER AND TEL/DATA ROOMS, METAL PARTSOF ACCESS FLOORS OUTSIDE OF SERVER AND TEL/DATA ROOMS,COMPUTER EQUIPMENT ENCLOSURES (DATA CABINETS AND DATARACKS), CABLE TRAYS, AND/OR ALL EQUIPMENT ENCLOSURES IN ROOMWHERE BUSBAR IS LOCATED. MAKE ALL GROUNDING CONNECTIONSWITH BOLTED CONNECTORS.
10 PROVIDE #6 INSULATED COPPER GROUNDING CONDUCTOR FROMTELECOMMUNICATIONS GROUNDING BUSBAR TO BUILDING STEEL ANDNEAREST COLD WATER PIPE. MAKE ALL GROUNDING CONNCTIONS TOBUILDING STEEL WITH EXOTHERMIC WELD OR IRREVERSIBLECOMPRESSION FITTING.
11 PROVIDE POWER MONITORS AS INDICATED TO MONITOR THEFOLLOWING EQUIPMENT:
1. 15-KV MEDIUM-VOLTAGE SWITCHGEAR FOR PRIMARY METERING.2. DISTRIBUTION PANEL DP FOR LIGHTING LOADS.3. DISTRIBUTION PANEL PP FOR RECEPTACLE AND PLUG LOADS.4. DISTRIBUTION PANEL MD4 FOR MECHANICAL LOADS IN PENTHOUSE.5. PANEL MP FOR MECHANICAL LOADS ON THE GROUND FLOOR.6. PANEL CP FOR SERVER ROOM G29.
PROVIDE WIRING IN CONDUIT FROM POWER MONITORS TO MONITOREDEQUIPMENT. PROVIDE CURRENT TRANSFORMERS, POTENTIALTRANSFORMERS, AND MAKE CONNECTIONS NECESSARY FOR COMPLETEINSTALLATION.
GENERAL NOTES:
A.
B.
INFORMATION SHOWN ON THIS DRAWING PERTAINING TO EXISTING CONDITIONSHAS BEEN OBTAINED FROM AVAILABLE BUILDING DRAWINGS OR GENERAL FIELDOBSERVATIONS AND MAY NOT INDICATE ACTUAL EXISTING CONDITIONS IN DETAILOR DIMENSIONS. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING THEACTUAL EXISTING CONDITIONS PRIOR TO FABRICATION OR PERFORMANCE OF ANYWORK. SHOULD CONDITIONS BE DISCOVERED THAT PREVENT EXCETUION OF THENEW WORK AS INDICATED, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THEARCHITECT IN WRITING AND AWAIT DIRECTION BEFORE PROCEEDING WITH THEWORK.
CAMPUS MEDIUM VOLTAGE DISTRIBUTION SYSTEM OPERATES AT 13,200 VOLTS.
GROUND FLOOR
MAI
N
DIS
TRIB
UTI
ON
FIRST FLOOR
SECOND FLOOR
THIRD FLOOR
PENTHOUSE
ELECTRICAL ROOM 204
ELECTRICAL ROOM 304
ELECTRICAL ROOM 104
ELECTRICAL ROOMSG04 & G10
SWITCHBOARD SB277/480V
CB CB
NORTH ENTRY 101
GENERATORREMOTEANNUNCIATOR
ATS-1LIFE SAFETY4P, 125A
ATS-2OPTIONALSTANDBY4P, 125A
PANEL E277/480V
PANEL S277/480V
PANEL SP120/208V
PANEL EP120/208V
GENERATOR MONITORAND CONTROL WIRINGFROM GENERATORCONTROL PANEL
TO EXISTING 3P-150ACIRCUIT BREAKER INEXISTING PANEL EDP(GENERATOR PANEL).PROVIDE 4 #1/0 + #6GROUND IN 2" CONDUIT.
XFMR TEP
XFMR TSP
34
GROUND FLOOR
MAI
N
FIRST FLOOR
SECOND FLOOR
THIRD FLOOR
PENTHOUSE
TEL/DATAROOM 302
SWITCHBOARD SB
BB BB
BB
BB
BB
TEL/DATAROOM 202
TEL/DATAROOM 102
TEL/DATAROOM G02
5
8
6
6 6
6
7
7
7
7
109
88
10
98
8
10
9
8
8
10
9
8
8
TGB
TGB
TGB
TELECOMMUNICATIONSGROUNDING BUSBAR (TGB)
ELECTRICALROOM G10
SERVERROOM G29
BB
7
109
88
TELECOMMUNICATIONS MAINGROUNDING BUSBAR (TMGB)
7
7
INTERSYSTEM BONDINGTERMINATION GROUNDINGBUSBAR (IBGB)
MICROSCOPYROOM G38
BB
7
88
TGB
ArchitecturePlanningInteriors
EngineeringLandscape Architecture
Construction ServicesTechnology
C 20
1 1 T
he S
/L/A
/M C
ollab
o rat
ive, In
c.
Somerset Square80 Glastonbury Boulevard
GlastonburyConnecticut 06033-4415
Telephone 860 657-8077Fax 860 657-3141
S L A M
T h e
C o l l a b o r a t i v e
Drawn
Checked
Date
Scale
Proj. Number
Drawing Number
KEYPLAN
54321
A
B
C
D
E
Proj. No. 6000-11
As indicated
C:\U
ser s
\pm
arqu
ez\D
ocum
ents
\ME
P_6
000-
11_J
HU
Mal
one
Hal
l_pm
arq
uez.
rvt
9/14
/201
2 12
:07:
38 P
M
E60109/14/12
11037.00
MALONE HALL
RISER DIAGRAMS
PMM
PJM
SCALE: NTSE601NORMAL POWER RISER DIAGRAM1
SCALE: NTSE601GENERATOR POWER RISER DIAGRAM2
SCALE: NTSE601SUPPLEMENTAL GROUNDING RISER DIAGRAM3
Number M/D/Y Issued For