Page 1: Team HK: Final Presentation

GUDC HONG KONG

STANFORD CAMPUS IN HONG KONG PROJECT (CHKP)

STANFORD UNIVERSITYLJUBLJANA UNIVERSITY

TEAM MEMBERSSam WrightAndy LiTheo LimJakob LozejDominik Košak MENTORSDerek OuyangSinan Mihelčič

Page 2: Team HK: Final Presentation

HONG KONG TEAM

STANFORD UNIVERSITY

UNIVERSITY OF LJUBLJANA

GUDCHONG KONG

Page 3: Team HK: Final Presentation

INTRODUCTION

WHAT? Stanford technological campus proposal WHERE? Search for the most suitable site in Hong Kong HOW? Via internet resources, online interaction, university professors and mentors WHY? To learn designing and making decisions for urban development,To use strategic thinking as a key for successful process in the project,To understand the decision-impact process based on gathered information

Page 4: Team HK: Final Presentation

MISSION STATEMENT

The Stanford Center in Hong Kong is a not-for-profit subsidiary of Stanford University headquartered in Hong Kong SAR, China, established in 2005 as an overseas office to facilitate Stanford University’s presence in the rapidly growing East Asia Region. Along with Stanford Centers in Beijing, China, and Kyoto, Japan, The Stanford Center in Hong Kong is concerned with supporting and cultivating academic and political relations with major East Asian institutions. In addition, the Stanford Center in Hong Kong has a particular focus on networking with local businesses and corporations, especially in the areas of engineering and technology. As part of its overall mission, The Stanford Center in Hong Kong is developing a new project, the Campus Hong Kong Project (CHKP), which has three main goals: TO ESTABLISH a physical campus in the city of Hong Kong which introduces undergraduate and graduate-level education in the technology sector, namely in sciences, engineering, and business; TO ENCOURAGE closer academic, social, business, and cultural ties between the University and the rapidly growing East Asia Region; TO ENGENDER a mutually beneficial interaction space for the people of Hong Kong and Stanford affliates around the world.

Page 5: Team HK: Final Presentation

ORDER OF PRESENTATION

1. Introduction 2. Context & Background 3. Site Selection 4. Site Analysis 5. Concepts 6. Financing 7. Public Relations & Outreach 8. Future Directions

Page 6: Team HK: Final Presentation

INTRODUCTION

HONG KONG

CHINA

HONG KONG

CHINA

Page 7: Team HK: Final Presentation

INTRODUCTION

HONG KONG

CHINA

Page 8: Team HK: Final Presentation

INTRODUCTION

LANTAU

NEW TERRITORIES

HONG KONG ISLAND

KOWLOON

MAINLAND CHINA

OUTLYING ISLANDS

Page 9: Team HK: Final Presentation

Official name: Hong Kong Special Administrative Region of the People's Republic of ChinaOfficial languages: Chinese, EnglishArea: land - 1,104 km² (426 sq mi), water - 50 km² (19 sq mi)Population: 7,061,200 (2010), 6,480 km² / 16,576/sq miTime zone: HKT (UTC+8)Currency: Hong Kong dollarHuman development index (HDI): 0.898 (very high)

GENERAL INFORMATION

Page 10: Team HK: Final Presentation

Current Hong Kong was first incorporated into China during the Qin Dynasty and largely remained under Chinese rule until 1841 during the Qing Dynasty. Hong Kong became a colony of the British Empire after the First Opium War (1839–42). Originally confined to Hong Kong Island, the colony's boundaries were extended in stages to the Kowloon Peninsula in 1860 and then the New Territories in 1898. It was occupied by Japan during the Pacific War, after which the British resumed control until 1997, when China resumed sovereignty.

Hong Kong in 1843 (English colonial area) seen from Kowloon peninsula.

BRIEF HISTORY

Page 11: Team HK: Final Presentation

HONG KONG ISLAND (Central, East Coast, South Coast)Hong Kong Island is the site of the original British settlement. Most of Hong Kong's highest skyscrapers and the financial centre can be found here, including its famous skyline along the northern coastline. Hong Kong's financial centre, shopping. Overall, Hong Kong Island is more modern and wealthy than the other areas of Hong Kong.

KOWLOONThis peninsula jutting south towards Hong Kong Island from the Asian continent is the most populous area in Hong Kong and at one time it was the most densely populated place in the world. Today, it offers a chaotic mix of malls, street markets and residential tenements.

NEW TERRITORIESNamed by British officials when leased from the Chinese government in 1898, the New Territories contain a curious mix of small farms, villages, industrial installations, mountainous country parks and towns that have populations the size of some cities.

LANTAUThe largest of the Outlying Islands, twice the size of Hong Kong Island and famous for its high peaks, wild landscapes, great beaches and the airport, which has a significant role in Hong Kong's economy.

OUTLYING ISLANDSWell-known weekend destinations for the locals, the Outlying Islands are most of the islands surrounding Hong Kong Island. They range from significant population centers to rocks poking out of the sea.

DISTRICTS

Page 12: Team HK: Final Presentation
Page 13: Team HK: Final Presentation

Average age is 41.7 years and life expectancy is 82.9 years.

EthnicityThe majority of Hong Kongers of Chinese descent trace their ancestry to various parts of Southern China: the Guangzhou area, Sze Yap, Chaoshan, Fujian and Shanghai.

SOCIAL REPORTPopulation by Age

0-14 15-24 25-34 35-44 45-54 55-64 65+

Percentage of Population

13.5% 13.1% 15.3% 18.1% 17.5% 10% 12.5%

Total Male Population

482,500 445,400 462,000 547,000 594,200 353,500 339,500

Total Female Population

452,100 459,300 592,000 698,400 613,400 337,400 464,800

Population by EthnicityChinese 95%Filipino 2.1%Indonesian 0.8%Westerners 0.7%Indian 0.3%Other 1.1%

Page 14: Team HK: Final Presentation

Labour Force Participation RateThe size of the total labor force in Hong Kong for 2010 was 3.65 million. This represented 59.7 per cent of the total population aged 15 and over. The distribution of the employed population in Hong Kong by occupation for 2010 was as follows:

Higher EducationMain higher education institutions in Hong Kong are The University of Hong Kong (21,500 students), The Hong Kong University of Science and Technology (8,000 students), Chinese University of Hong Kong (14,300 students), Hong Kong Polytechnic University (28,300 students).

Education Attainment 2005 2010No Schooling / Pre-Primary 6.4% 5.4%Primary 19.3% 17%Secondary 51.5% 52.3%Post-Secondary 22.8% 25.4%

Occupation Distribution 2005Managers and Administrators 9.7%Professionals 6.5%Associate Professionals 19.3%Clerks 16.1%Service Workers and Shop Sales Workers

16%

Craft and Related Workers 7.1%Plant and Machine Operators and Assemblers

5.8%

Elementary Occupations 19.4%

SOCIAL REPORT

Page 15: Team HK: Final Presentation

Reclaimed land in Hong Kong (yellow).

● 7,650 Skyscrapers● Lack of buildable area has created very dense construction● Many developed areas are on top of Reclaimed Land● Land Reclamation dates back to Han Dynasty (206 BCE – 9CE)● Many projects are in development on Hong Kong Island and West Kowloon● The closure of Kai Tak Airport has lifted height restrictions, allowing more high rises to be built in West Kowloon

CONSTRUCTION REPORT

Page 16: Team HK: Final Presentation

Salient Facts and Figures: ● Hong Kong has just over 1100 sq km of land controlled by a dedicated council● 40% of usable land is dedicated to conservation● 67% of land is still undeveloped● Permits to build are easier to obtain in the New Territories; harder to obtain in Kowloon; nearly impossible to obtain for HK island.● Most development is happening on new lands in the New Territories or reclaimed land in Kowloon.● Most new industries and universities are located in the New Territories. A spread-out American-style campus is possible in the New Territories.

A spread-out American-style campus is possible in the New Territories cf. China University of HK near Fo Tan, below

ZONING AND PARKS

Page 17: Team HK: Final Presentation

PROPOSED SITES MAP1) KAI TAK AIRPORT, KOWLOON2) WEST KOWLOON, KOWLOON3) AUSTIN, KOWLOON

4) FO TAN, NEW TERRITORIES5) TUEN MUN, NEW TERRITORIES

Page 18: Team HK: Final Presentation

1) KAI TAK AIRPORT, KOWLOON

Page 19: Team HK: Final Presentation

2) WEST KOWLOON, KOWLOON

Page 20: Team HK: Final Presentation

3) AUSTIN, KOWLOON

Page 21: Team HK: Final Presentation

4) FO TAN, NEW TERRITORIES

Page 22: Team HK: Final Presentation

5) TUEN MUN, NEW TERRITORIES

Page 23: Team HK: Final Presentation

1) DECISION MATRIX CRITERIA

Decision Matrix Explanation: - Each criteria and sub-criteria is evaluated in 1-5 tier system (1 - worst, 5 - best)- Each sub-criteria is differently weighted, based on the importance of the subject- All provided data is objective and was found on the Internet or other authentic sources- Decision matrix also includes subjective data, provided by the locals

Economic - 20% Transportation - 20% Construction - 15% Parks and Zoning - 10% Sustainability and Environment - 15% Political and Neighborhood Feasibility - 20%

Page 24: Team HK: Final Presentation

ECONOMIC DECISION MATRIX

Site / Subject Construction Costs

Land prices

Financial feasibility

Weighted total

Kai Tak Airport 3 2 5 3.3

Austin 3 2 5 3.3

West Kowloon 3 2 5 3.3

Fo Tan 4 4 4 4

Tuen Mun 4 4 4 4

Economic - 20 % 1. Construction Cost - 33.3% 2. Land Prices - 33.3% 3. Financial Feasibility - 33.3%

Page 25: Team HK: Final Presentation

TRANSPORTATION DECISION MATRIX

Travel

Time to Airport

Travel Time to Downtown

Travel Time to Mainland

China

Distance to Closest MTR

Station

Frequency of MTR Transit

Number of MTR Lines

near the Site

Weighted Total

Rounded Weighted

Total

Kai Tak Airport 1 3 4 2 5 3 2.95 3

West Kowloon 3 5 5 5 3 5 4.6 4.6

Austin 2 3 5 4 3 5 4.1 4.1

Fo Tan 1 2 3 5 5 3 3.65 3.7Tuen Mun 1 1 1 2 4 2 2.05 2

Transportation - 20% 1. Travel Time to Airport - 5% 2. Travel Time to Downtown HK - 15% 3. Travel Time to China Mainland Travel Hub - 5% 4. Distance to Closest MTR station - 30% 5. Frequency of MTR Trains - 15% 6. Number of MTR Lines near the Site - 30%

Page 26: Team HK: Final Presentation

CONSTRUCTION DECISION MATRIX

Existing

Infrastructure (Water)

Existing Infrastructure

(Roads)

Existing Infrastructure (Electricity)

Land Quality

Typhoon Flooding Danger

Landslide Danger

Casting Shadow

s

Traffic Noise

Weighted Total

Rounded Weighted

Total

Kai Tak Airport 3 3 5 5 3 5 5 4 4.25 4.3

West Kowloon 3 3 4 5 1 5 4 3 3.7 3.7

Austin 0 0 5 5 2 5 4 2 3.15 3.2

Fo Tan 0 0 2 3 5 3 5 5 3 3

Tuen Mun 0 0 1 3 5 4 5 5 3 3

Construction - 15 % 1. Existing Infrastructure (water 33.3%, electricity 33.3%, roads 33.3%) - 30 % 2. Land Quality - 25 % 3. Typhoon Flooding Danger - 10 % 4. Landslide Danger - 10 % 5. Casting Shadows - 10 % 6. Traffic Noise - 15 %

Page 27: Team HK: Final Presentation

PARKS AND ZONING MATRIX

Site / subject measurement

% Park Space1 mile radius

% Park Space5 mile radius

Official Land Utilization

Distance to Edge of City

(m)

Distance to shore

Kai Tak airport

0

2.1

Residential

2500 m

0m

West Kowloon

4.8

5.1

Commercial

6500 m

200 m

Austin

4.9

4.8

Vacant

7000 m

250 m

Fo Tan

18.2%

16.0%

Open Space

500 m

8500 m

Tuen Mun

15.3%

14.9%

Commercial

500 m

6700 m

% of Total 20% 30% N/A 30% 20%

Parks and Zoning - 10%

Page 28: Team HK: Final Presentation

SUSTAINABILITY AND ENVIRONMENT MATRIX

Site / subject measurement

H2O2/HNO3 (Ave. 2007)

O3 Concentration (Ave. 2007)

Kai Tak Airport 22.4 330 micrograms/cubic meter

West Kowloon 19.5 290

Austin 27.4 320

Fo Tan 8.8 200

Tuen Mun 16.2 250

% of Total 60% 40%

Sustainability and Environment - 15%

Page 29: Team HK: Final Presentation

POLITICAL AND NEIGHBORHOOD FEASIBILITY MATRIX

Political and Neighborhood Feasibility - 20%

Page 30: Team HK: Final Presentation

FINAL DECISION MATRIX

Current Weighting:

Economic 20%

Transportation 20%

Construction 15%

Parks & Zoning 10%

Environment & Sustainability 15%

Politics & Neighborhood Feasibility 20%

Economic Transportation Construction Parks & Zoning

Environment & Sustainability

Political & Neighborhood

FeasibilityTotal

Kai Tak Airport 3.3 3 4.3 2 2.5 3.3 3.1

West Kowloon 3.3 4.6 3.7 2.3 2 3.8 3.4

Austin 3.3 4.1 3.1 2.2 1 4.1 3.1

Fo Tan 4 3.7 3 3 5 2.3 3.5

Tuen Mun 4 2.1 3 4 4.1 2.3 3.1

Page 31: Team HK: Final Presentation

SELECTED SITEWEST KOWLOON, KOWLOON

Page 32: Team HK: Final Presentation

SELECTED SITEWEST KOWLOON, KOWLOON- Highly Urbanised Area- Waterfront Proximity- Well-integrated in the City

Page 33: Team HK: Final Presentation

SITE ANALYSIS - built / void

Page 34: Team HK: Final Presentation

SITE ANALYSIS - tissue

Page 35: Team HK: Final Presentation

SITE ANALYSIS - typologies

Page 36: Team HK: Final Presentation

SITE ANALYSIS – structure size

Page 37: Team HK: Final Presentation

SITE ANALYSIS - height dominants

Page 38: Team HK: Final Presentation

SITE ANALYSIS - traffic

Page 39: Team HK: Final Presentation

SITE ANALYSIS – geometry and characteristics of space

Page 40: Team HK: Final Presentation

SITE ANALYSIS – construction

- coastal land reclamation consists of two layers: highly permeable layer consisting of crushed rock fragments underneath a less permeable layer (sand)- land reclamation increases water level- deep foundations have a profound impact on underground water flow● building on reclaimed land demands ground improvement and

constant maintenance (drainages) – Source: Preliminary assessment of the impacts of deep foundations and land reclamation on groundwater flow in a coastal area in Hong Kong, China

ASCERTAINMENTS:● LESS CONTACT AREA WITH GROUND = LOWER COSTS FOR

CONSTRUCTION AND MAINTAINING● BUILDING ON RECLAIMED LAND DEMANDS AT LEAST 20 % MORE

INVESTMENT THAN BUILDING ON ORDINARY LAND

Page 41: Team HK: Final Presentation

SITE VIEWS – union square

Page 42: Team HK: Final Presentation

SITE ANALYSIS – harbour city

Page 43: Team HK: Final Presentation

SITE ANALYSIS – harbour city

Page 44: Team HK: Final Presentation

SITE ANALYSIS – WK waterfront promenade

Page 45: Team HK: Final Presentation

CAMPUS PROGRAMMATIC SCHEME

Common Facilities

Student Housing

Technical Facilities

Laboratories Building

Technical Incubator Building

Business School Building

Engineering School Building

168,000 ft2

30,000 ft2

20,000 ft2

10,000 ft2

15,000 ft2

12,500 ft2

12,500 ft2

Page 46: Team HK: Final Presentation

CAMPUS VOLUMETRIC PROGRAM

Common Facilities

Student Housing

Technical Facilities

Laboratories Building

Technical Incubator Building

Business School Building

Engineering School Building13F

10F

50F

7F9F9F 11F

Page 47: Team HK: Final Presentation

CAMPUS PROGRAMMATIC SCHEME

ENGINEERING SCHOOL + LABORATORY BUILDING – specialized in construction techniques and innovative approaches to construction and materials which will contribute to local developement TECHNOLOGICAL INCUBATOR – making collaborative environment with local companies and young enterprises which will boost approaching to the market BUSINESS SCHOOL – exploring new ways of fostering an entrepreneurship community STUDENT HOUSING – providing residential space for 800 students COMMON FACILITIES – providing comfortable and healthy environment for staff, students and locals OPEN SPACES – use of existing green space on the western side (peninsula)

Page 48: Team HK: Final Presentation

CAMPUS CONCEPT 1

Page 49: Team HK: Final Presentation

CAMPUS CONCEPT 1

Page 50: Team HK: Final Presentation

CAMPUS CONCEPT 1

Page 51: Team HK: Final Presentation

CAMPUS CONCEPT 1

Page 52: Team HK: Final Presentation

CAMPUS CONCEPT 2

Page 53: Team HK: Final Presentation

CAMPUS CONCEPT 2

Page 54: Team HK: Final Presentation

FINAL CONCEPT DETAILS - Concept 1

Page 55: Team HK: Final Presentation

FINAL CONCEPT DETAILS - Concept 1 (Phase 2)

Page 56: Team HK: Final Presentation

FINAL CONCEPT DETAILS - Concept 2

Page 57: Team HK: Final Presentation

CONCEPT DECISION FACTORS

Concept 1 Concept 2

Construction Better

Views Better

Access Better

Building Heights Better

Potential for Growth Better

Distance to Green Spaces Better

Plot Size-Cost Better

Feng Shui Better

Overall Better

Page 58: Team HK: Final Presentation

FINANCE

Minimize Risks

Mitigate Costs

1. Buy the land

2. Partner with a local developer

3. Make a pre-emption agreement with the city of Hong Kong

Principal sources of data used in the cost estimation model :

- Hong Kong's Rating and Valuation Department

- Hong Kong's land sales in 2009-2011

- Hong Kong Census and Statistics

Page 59: Team HK: Final Presentation

Phasing Plan & Timeline Schedule

FINANCE

Page 60: Team HK: Final Presentation

Laboratories building

15,000 sq ft $17.5 mil.

Engineering building

30,000 sq ft $26 mil.

FINANCE

Page 61: Team HK: Final Presentation

Student Housing

170,000 sq ft $115.5 mil.

Common Facilities

12,500 sq ft $8.25 mil.

FINANCE

Page 62: Team HK: Final Presentation

Best-case scenario

Worst-case scenario

Phase 1 scenarios:

-Signed pre-emption agreement-Differences in cultures won‘t represent a bigger obstacle-Equivalent sponsor funding to Stanford CA-Popularity among students

-Unavailability of land for growth-Local disapproval-Cultural barrier-Lack of sponsor funding-Unpopularity among students

Predicted risks

Selling all the facilities with profit.

Continue the project to phase 2 as planned.

Rent the facilities until it is possible to buy aditional land.

Predicted scenarios in year 2021

FINANCE

Business as Usual

Page 63: Team HK: Final Presentation

Technological incubator

10,000 sq ft $9 mil.

Business school building

20,000 sq ft $17.25 mil.

FINANCE

Page 64: Team HK: Final Presentation

FINANCE

Technical Facilities

15,000 sq ft $10 mil.

Land Purchase

32,300 sq ft $9.5 mil.

Page 65: Team HK: Final Presentation

Phase 2 scenarios:

Best-case scenario

Worst-case scenario

-Stanford University is a key element of HK‘s education system- Differences in cultures won‘t rapresent a bigger obstacle-Equivalent sponsor funding to Stanford CA-Popularity among students

- Non-acceptance from local companies-Local disapproval-Cultural barrier-Lack of sponsor funding

Predicted risks

In case of unpredictable events facilities will be sold with loss.

The project is a enormous success. Revenues and donations are higher than predicted.

School activities will pursue normally. Stanford will need to foster relationship with surrounding companies.

Predicted scenarios in year 2028

FINANCE

Business as Usual

Page 66: Team HK: Final Presentation

All Facilities and Invested Capital (IC) Engineering building 30,000 sq ft $26 mil.

Laboratories building 15,000 sq ft $17.5 mil.

Student housing 170,000 sq ft $115.5 mil.

Common facilities 12,500 sq ft $8.25 mil.

Business school 20,000 sq ft $17.25 mil.

Tech incubator 10,000 sq ft $9 mil.

Technical facilities 15,000 sq ft $10 mil.

Surrounding land 32,300 sq ft $9.5 mil.

Total IC $213 mil.

FINANCE

Page 67: Team HK: Final Presentation

How to justify the higher investment compared to other sites in Hong Kong? Is it justifiable at all?

Justification:- proximity of corporations and companies- prestigious location- closeness to all needed infrastructure- facilitation of the exit strategy

FINANCE

Page 68: Team HK: Final Presentation

DEVELOPER LIAISON

Terms of Agreement: 1. Stanford is the owner of the land, SHKP is the main developer. 2. SHKP develops campus and other properties together with Stanford as a main stakeholder. 3. SHKP will take full profit from any non university-related residential, retail, and office tower units. 4. SHKP and Stanford will jointly manage architectural design and character of the entire development. The two areas of the project should be integrated to a certain extent, but the Stanford area should have more of the feel of a campus. 5. SHKP will profit from proximity and prestige to leverage higher profits on their development units. 6. Stanford and SHKP will agree upon further terms regarding compensation through annuities or other means.

Sun Hung Kai Properties (SHKP)

Page 69: Team HK: Final Presentation

PUBLIC OUTREACH AND INVOLVEMENT

Inform and Engage the Public Public Information Meetings -Union Square-Docks and Harbor Development-HKU, other universities-West Kowloon Local contribution to project -Public art -Architecture Competition-Information Booths in Local Malls, MTR Stations

Information Media Channels -Twitter (@StanfordinHK)-Facebook (StanfordinHK)-Newspaper and TV ads

Page 70: Team HK: Final Presentation

POLITICS, PERMITTING AND PROCESS

We will consult with SHKP to guide us through the permitting process. We will need to gain permits from the following authorities: HK Planning and Development BoardHK Department of EducationHK Buildings DepartmentHK Environmental Protection DepartmentWest Kowloon District CouncilUnion City District Council In addition, we will collaborate with the following groups to ensure social and cultural integration of our project: Society for Community Organization (SoCO)HK Heritage Studies and Promotion OrganizationMonte Jade Science Technology AssociationHong Kong Electronics and Technology Association (HKETA)and others

Page 71: Team HK: Final Presentation

FUTURE DIRECTIONS

1. Develop Institutional and Developer Relations 2. Obtain Stanford-side Approvals and Final Program Requirements 3. Detailed Architectural and Schematic Design 4. Carry Out PR and Outreach Plan 5. Environmental Review Process

Page 72: Team HK: Final Presentation

CONCLUSION