1 TEAC20 Thursday, March 4, 2004 Sheraton Hotel Springfield, Massachusetts REDACTED VERSION FOR POSTING
Jan 12, 2016
1
TEAC20
Thursday, March 4, 2004
Sheraton Hotel
Springfield, Massachusetts
REDACTED VERSION FOR POSTING
2
TEAC20 Agenda
• Welcoming Remarks• FDWG Update• Transmission Planning Study Updates
CT Area Issues ME-NH issues NB-NE Tie Performance
• Generator Clutch Technology• NEPOOL Project List Process
• ISO/RTO Planning Coordination Protocols• RTEP04 Planning Assumptions• RTEP04 Resource Adequacy Analysis
Assessment CasesPreliminary Case Results
3
Fuel Diversity Working Group
TEAC20 PresentationMarch 4, 2004
Mark Babula ISO-NEPower Supply & Reliability
4
Fuel Diversity Working Group
• In response to the events of January 2004, ISO-NE is proposing to reconstitute the FDWG with respect to changing:
– Name change to address specific gas & electric issues– Existing Mission Statement & Charter– Broaden the Scope– Requesting increased participation from:
• New England utility and environmental regulators• Natural gas industry• Interested stakeholders & market community
• The newly transformed Electric Gas Working Group (EGWG) will address both near and long term issues.
5
Electric Gas Working Group
• The newly transformed Electric Gas Working Group (GEWG) will address:
– The results and findings of ISO-NE’s Cold Snap report• Short-term issues – Resolve by Winter 2004/05• Long-term issues – TBD and coordination with RTEP
– Additional areas of investigation as suggested from stakeholders
– Liaison to regional and national committees on changing existing or developing new policy thru regulatory means• NERC GEITF (Gas/Electricity Interdependency Task
Force)• NAESB GECTF - North American Energy Standards Board
– (Gas Electric Coordination Task Force)
6
Electric Gas Working Group
• The Electric Gas Working Group (GEWG) should work to coordinate the education and understanding of both gas & electric systems through:
– Cross training of electric & gas system operators– Establishing emergency communications protocols
& procedures– Assess and address system restoration issues– Assess coordination of electric & gas system
maintenance requirements
– Address other common issues
7
Announcement
• FDWG next meeting Mass Electric Auditorium, Northborough, MA – March 19th - 9:30 a.m. to 4:00 p.m.
8
Transmission Planning Study Updates
Rich Kowalski
ISO-NE
System Planning
9
Eastern ConnecticutSystem Performance
Concerns
10
Area Characteristics
• Existing Area Load: 700 to 750 MW
• Basically three feeds into area:• Montville Substation – two 345-115kV
autotransformers and approximately 750 MW of generation
• Card Substation – one 345-115kV autotransformer
• 115kV tie to Rhode Island
• About 90 MW of local generation
11
Performance
• Several probable contingencies result in severe thermal overloads and unacceptable voltages (bordering on voltage collapse)
• SPS currently in place for loss of the Sherman Road to Lake Road 345kV line
• Issues surrounding the location ‘electrically’ of the Lake Road Plant
12
CIRCUIT DIAGRAM REDACTED
13
Alternatives Studied
• Various line taps, line reconductorings and 69 to 115kV conversions
• 345kV breaker additions
• Various 115kV line additions
• Various autotransformer additions – Brooklyn, Tracy and/or Lake Road
14
Preferred Plan
• Add 345-115kV autotransformer at Tracy
• Add 345kV circuit breaker at Card
• Benefits:– Relieves all thermal overloads– Acceptable voltages for all contingencies but
one borderline consideration– Quick fix without requiring line additions
15
Current Status
• Draft Thermal / Voltage report in Task Force review stage
• Transfer Analysis to be completed
16
Connecticut ImportReinforcement Study
17
Background
• Previous analyses have shown:– Interdependence of transfer capabilities for
SEMA/RI Export, East-West & CT Import Interfaces
– Transfers through these 3 interfaces contribute to heavy loadings on the same key transmission facilities
– The resource-rich area to the east of Connecticut is currently the best source for Connecticut.
18
System Performance
• RTEP03– With respect to CT Import Area Capacity,
“… Connecticut is at risk in 2003. Operating deficiencies could occur as a result of a higher than normal peak load. It also shows the likelihood of this deficiency occurring for more typical ‘reference’ load as early as 2006.”
19
RTEP03 Recommendation
• “Transmission planning studies should be completed to support the development and implementation of a 345kV line from Millbury to Card.”
20
GEOGRAPHICAL AREA:
Connecticut Import Reinforcement Project
CIRCUIT DIAGRAM REDACTED
21
Study Plan & Status
• ISO / TO Working Group established
• Scope of work / Schedule developed
• Various meetings and teleconferences held
• Comprehensive list of alternatives developed
• Target completion August 2004
22
Summary Of Alternatives
• Marine ties from Long Island, SEMA or RI through the Sound
• Ties from New York State – Pleasant Valley area
• Different over land routes from SEMA/RI (both AC and DC)
• Western Mass to CT
23
Maine – New HampshireTransmission System Studies
24
ME-NH Transmission Technical Issues List Heavy load growth in Maine and NH Seacoast
areas
Central and southern New Hampshire reliability assessment
Complex operating limits/dependencies for voltage and stability on Maine-New Hampshire Interfaces
Maine and NH reliability assessments for long-term autotransformer outages
25
ME-NH Transmission Technical Issues List Closing Y138 between Western Maine and
Central New Hampshire
Poor performance for several stuck breaker contingencies in Maine (Buxton and Surowiec)
Western Maine stability limit definition
Seabrook Uprate - reduction in generator reactive capability and new excitation system
26
Need to Coordinate the Studies of ME-NH Issues
• Interdependence of issues and solutions
• Comprehensive analysis of larger area
• Development of coordinated plans
27
Need to Coordinate the Studies of ME-NH Issues
• Broader range of ideas, solutions, and approaches
• Enhancements for future reliability for load and generation in this region
• Support effective use of transmission facilities across all Northern New England (NNE) interfaces
28
First Priority Studies• Maine Reliability Assessment – Schedule TBD
– Long-term autotransformer outages– Address seacoast area
• New Hampshire Reliability Assessment – Schedule TBD– Long-term autotransformer outages– Address seacoast and central/southern areas
• Additional transformation possibly at Deerfield, Newington, etc.
• Impact of Seabrook Up-rate
29
Second Priority Studies• Maine-New Hampshire Reliability Project–
In progress– Address complex operating
limits/dependencies for ME-NH– Address performance concerns associated
with ME stuck breakers • Currently three alternatives tested• Is being coordinated with the Closing Y-138
Project• Impact of Seabrook Up-rate
30
Second Priority Studies• Closing Y-138 Project– In progress
– Address central New Hampshire reliability– Should improve Western Maine stability/voltage
performance– Some increase in Maine-New Hampshire transfer
capability• Alternative development almost complete, reactive needs
outstanding• Is being coordinated with Maine-New Hampshire Reliability
project • Will be coordinated with Western Maine Stability assessment
31
Second Priority Studies
• Western Maine Stability Assessment– Schedule TBD– Assess the stability performance of the western Maine
transmission system• Will be coordinated with the Closing Y-138 Project.
32
NNE Transmission Corridor
• CIRCUIT DIAGRAM REDACTED
33
Maine-New Hampshire Reliability Project Report on 2003 Studies
Investigated three alternatives:
1. Add a dynamic voltage control system (SVD) at Deerfield S/S with a 500 – 600 MVAr capability.
2. Interconnect Section 391 at Deerfield S/S and add three breakers at Buxton for the re-termination of Section 386.
3. Add a dynamic voltage control system (SVD) at Deerfield S/S with a 500 – 600 MVAr capability and interconnect Section 391 at Deerfield S/S and add three breakers at Buxton for the re-termination of Section 386.
34
Conclusions of Maine – New Hampshire Reliability Project Alternative Assessments
Alternative #1 Insufficient benefit
for Maine and NH system reliability to
justify its high cost.
Alternative #3 Best method to
mitigate reliability issues but high cost.
Significant improvement in voltage, thermal, and stability transfer limits; mitigation of dependencies
Provides dynamic voltage support along NNE 345kV corridor.
Alternative #2 Increases transfer
limits as well for a much lower cost.
Elimination of stuck breaker contingencies is significant benefit to NNE reliability.
Looping Section 391 into Deerfield increases electrical performance of bulk power system.
35
Transfer Limits from Maine – New Hampshire
Reliability Project Analysis
2600 to 28002350 to 27002375 to 2725StabilityPlanningCriteria
Alt. 3Deerfield SVD
& 391 & Buxton Breakers
(MW)
Alt. 2Deerfield 391 & Buxton Breakers
(MW)
Alt. 1Deerfield SVC
(MW)
ExistingSystem(MW)
NNE Scobie plus 394 Interface Limits
>1800162517001550Stability
1550 to 16001525 to 15751375 to 14251375 to 1425Thermal
1600 to 17001350 to 14501225 to 13001100 to 1300VoltageOperatingCriteria
>1800162517001550Stability
1350 to 14751325 to 14251225 to 13251225 to 1300Thermal
1550 to 16501250 to 13001050 to 1175775 to 975VoltagePlanningCriteria
$34M$9M$25MCost
Alt. 3 -Deerfield SVD
& 391 & Buxton Breakers
(MW)
Alt. 2 -Deerfield 391 & Buxton Breakers
(MW)
Alt. 1 -Deerfield SVD
(MW)
ExistingSystem(MW)
ME-NH Interface Limits
2600 to 28002350 to 27002375 to 2725StabilityPlanningCriteria
Alt. 3Deerfield SVD
& 391 & Buxton Breakers
(MW)
Alt. 2Deerfield 391 & Buxton Breakers
(MW)
Alt. 1Deerfield SVC
(MW)
ExistingSystem(MW)
NNE Scobie plus 394 Interface Limits
>1800162517001550Stability
1550 to 16001525 to 15751375 to 14251375 to 1425Thermal
1600 to 17001350 to 14501225 to 13001100 to 1300VoltageOperatingCriteria
>1800162517001550Stability
1350 to 14751325 to 14251225 to 13251225 to 1300Thermal
1550 to 16501250 to 13001050 to 1175775 to 975VoltagePlanningCriteria
$34M$9M$25MCost
Alt. 3 -Deerfield SVD
& 391 & Buxton Breakers
(MW)
Alt. 2 -Deerfield 391 & Buxton Breakers
(MW)
Alt. 1 -Deerfield SVD
(MW)
ExistingSystem(MW)
ME-NH Interface Limits
36
Studies have concluded the following system upgrades are required for closing Y138:
Phase Shifter on B112 Re-tension Section 214 Beebe B112 Terminal Upgrades Add 2 breakers at Saco Valley Add 50 MVar at Kimball Road Add 22 MVar at White Lake (7 and 15 MVar)
Closing Y138 Report on 2003 Studies
37
Status of Y138 Closing Project
• Final design studies being conducted• Local area impacts on sub-transmission
networks being analyzed• Preparing to conduct 18.4 Level III Steady-state
and Stability Assessments • 18.4 approval estimated for 3rd quarter 2004
38
Example of Benefits to Coordinating Studies
In 2003, two studies were completed with different individual objectives.
Maine-New Hampshire Reliability Project• ME-NH transfer capability improvement• Eliminate complex operating guides for voltage and
stability
Closing Y138• Improve central New Hampshire reliability• Relieve congested Maine transmission interfaces
39
Combination of Projects from each Study Analyzed Together
Maine-New Hampshire Reliability Project Alternative #2 and Closing Y138 Study were analyzed together for voltage limits based on operating criteria. Preliminary increases to Maine-New Hampshire transfer are shown below:
ME-NH Voltage/Reactive Transfer Limit (MW)
Existing System 1100-1300
Alternative #2 ($9M) 1350-1450
Alternative #3 ($34M) 1600-1700
Alternative #2 with Y138 Closed ($19M)
1600-1800
40
Coordinated Solution
• Need to assess S. New Hampshire requirements• Assess impact of potential combined solutions• Develop a comprehensive plan
41
New Brunswick-New England/MEPCO Area
System Performance Concerns
42
Region Characteristics
• The Maritimes are synchronously connected to the Eastern Interconnection by only the 150 mile long, 345 kV Orrington to Keswick Line.
• There is a single 345 kV path from Orrington to Maine Yankee with a limited number of 115 kV parallel paths.
• This electrically weak corridor requires 8 SPS. (MY DCT, Maxcy’s Cross-trip, Bucksport Over-current, Bucksport Reverse Power, 396, GCX, Loss of Export on 396, KPR (if Chester SVC is OOS))
43
Region Characteristics
• New Brunswick–New England transfer capability is 700 MW.
• New England-New Brunswick transfer capability ranges from +/-250 MW. (Some conditions require a minimum import from NB)
• Orrington South transfer capability is approximately 1,050 MW.
44
CIRCUIT MAP REDACTED
45
New England System Concerns
• Consequences of large Maritime Provinces load loss (reason for Keswick GCX SPS)
• Keswick GCX SPS inadvertent operation• L/O 1200+ MW due to trips/inadvertent trips
of Keswick-Orrington 345 kV (NB-NE tie Section 396), Orrington-Maxcys 345 kV (Section 388), Maxcys-Maine Yankee 345 kV (Section 392)
• L/O 396 SPS (trips Maine Independence Station) (contributes to L/O 1200+ MW)
46
New England System Concerns
• Orrington-So. 1050 MW limit • MY DCT outage• CMP transient voltage response• NB-NE tie losses• Limited access of MPS/EMC to New England
resources (no direct ties to the New England transmission system)
47
New Brunswick System Concerns
• Consequences of large Maritime Provinces load loss (reason for Keswick GCX SPS)
• New Brunswick Power desires a more secure inter-Area interconnection with New England.
• New Brunswick Power desires a firm import capability from New England.
48
New Brunswick System Concerns
• NB-NE tie losses• New Brunswick Power is interested in
improved market access between NPCC/NEPOOL and the Maritime Control Area.
• The Maritimes are winter peaking while New England is summer peaking. Improved transfer capability would allow for better utilization of existing generation resources.
49
Alternatives Under Consideration(None individually address all concerns)
• Replace/Redesign GCX SPS [$?](Mar. Prov. l/o ld)
• Northeast Reliability Interconnect Project (2nd NB tie: LePreau-Orr. 345 kV) [$80M](MP l/o ld, GCX, 396 trip, 396-MIS SPS (?), CMP t.volt, NB-NE tie losses,
impr. MPS/EMEC access, NB benefits)
• Thyr.-Contr. Series Comp. (TCSC) in Keswick-Orrington 345 kV [~$25M](MP l/o ld, GCX (?), 396-388-392 trip, 396-MIS SPS (?), CMP t.volt (?))
• Orrington-Maxcys 345 kV fixed series compensation* [$13.5M](Or-S 1050MW)
• Reconductor Bucksport-Highland 115 kV Line, western Maine capacitors [$5M](Or-S 1050MW)
50
Alternatives Under Consideration(None individually address all concerns)
• Split MY DCT [~$12M](MY DCT outage)
• MY DCT SPS to trip NB generation* [~$0.5M](MY DCT outage)
• MEPCO SPS redesign [$0.5M-$5M](CMP t.volt)
• Northern Maine Interconnection Project – 115 kV [$13.6M](MPS access)
*Part of 2nd NB tie project
51
Potential Additional Benefits of Northeast Reliability Interconnect Project
(2nd NB tie: LePreau-Orrington 345 kV)• Strengthens a section of a very weak 345 kV
path• Reduces contingencies that separate Maritimes
Provinces from Eastern Interconnection• Increases NB to Orrington capability from 700
MW to 1000MW• Increase in resource capacity available to New
England (Orrington; S. ME with Orrington-Maxcys series comp.)
52
Potential Additional Benefits of Northeast Reliability Interconnect Project
(2nd NB tie: LePreau-Orrington 345 kV)
• Increase in energy available to New England (Orrington; S. ME with Orrington-Maxcys series comp.)
• Increased New England-New Brunswick transfer capability could provide opportunities for locked-in generation in Maine.
• Future potential for increased sharing of ancillary services with New Brunswick.
53
Potential Alternative Configurations of theNortheast Reliability Interconnect Project
• 2nd NB tie: LePreau-Orrington 345 kV [$80M on US side, $40M on Can. Side]
• Up-rate existing Orrington to Keswick 345 kV[$?]] – Also requires Orrington-South & MY DCT reinforcements– Would increase magnitude of L/O source contingencies– If feasible, would likely require substantial combinations of
fixed/dynamic series/shunt reactive compensation
• Convert existing Orrington to Keswick 345 kV Line to HVDC. [~$200M] – Also requires Orrington-South & MY DCT reinforcements.– Would increase magnitude of L/O source contingencies– Would create a small Maritime Province asynchronous system; L/O
source and load contingencies would be very problematic
54
Potential Alternative Configurations of theNortheast Reliability Interconnect Project
• LePreau-Orrington 500 kV [$?]– Also requires Orrington-South & MY DCT reinforcements.– Might eliminate need for one of the project SPSs and series
compensation– Canadian side permitted for 345 kV construction
• LePreau-Maxcys (further south?) 500 kV [$?]– Also requires MY DCT reinforcements– Might eliminate need for one of the project SPSs and series
compensation– Might eliminate trip issues– Canadian side permitted for 345 kV construction
55
Summary of Possible Solutions Alternative
Prob./Issue
NRIP 345 kV: Orrington-Lepreau 345 kV
388 Series Comp* 86 Recond. & ME caps.
MY Dct SPS*
Split MY Dct
TCSC No. ME IP 115 kV
LePreau - ? 500 kV
MP Ld loss (GCX redesign)
Tech. solution Tech. sol. demo Need detailed analysis
Probably
396 trip Tech. solution Tech. sol. demo Need detailed analysis
Probably
388/392 trip Tech. sol. demo Need detailed analysis
Possibly (Past Orr.)
MIS L/O 396 SPS
Tech. sol. demo Need detailed analysis
Tech. sol. demo Need detailed analysis
Probably
Orr-So.150 MW increase
Tech. sol. Study Reliability
& Economic benefit
Tech. sol. demo Need detailed analysis
Study Reliability & Economic benefit
Possibly (Past Orr.)
MY DCT outage Tech. sol. Tech. sol. Possibly (Past ME Ynk)
CMP trans. volt Tech. solution Tech. sol. demo Need detailed analysis
Probably
NB-NE loss savings
Quantify Quantify
NB-NE 300 MW & Orr-So. 150 MW increase
Tech. solution Study Reliability & Economic benefit
Same as 345 kV
MPS benefit Tech. sol. demo Need detailed analysis
Study benefit
Tech. sol. Same as 345 kV
EMEC benefit Tech. sol. demo Need detailed analysis
Study benefit
Same as 345 kV
* Required with NRIP 345 kV
56
Summary of Remaining Analyses• Orrington-South 150 MW limit increase
– Reliability & Economic analysis
• NRIP 345 kV - 2nd NB tie: LePreau-Orrington 345 kV – Study supplemental TCSC to address 388 & 392
trip– Verify that MIS-L/O 396 SPS can be eliminated– Evaluate loss reduction– Reliability & Economic analysis (w/Orrington-South
150 MW increase)
• TCSC– Study with “detailed” models
57
Summary of Remaining Analyses• CMP/MEPCO SPS redesign
– Finish design review and analysis
• EMEC Interconnection• NE-NB Transfer Capability
– Evaluate “Firm” NE export capability
• NB Benefits
58
Operating Large Generators as Synchronous Condensers
Presented byDave Bertagnolli – ISO-New England
TEAC20March 4, 2004
59
Synchronous Generator Idea
Disconnect the turbine from the generator
Accelerate the generator to synchronous speed
Connect it as synchronous condenser
System impact study required
(contributes to short circuit current)
60
BenefitsGet all the voltage/stability benefits without the
energy
Could re-connect turbine when MW’s are needed
Short implementation time (6 months)
Supports Fuel Diversity
61
Capital Costs
Low cost compared to alternatives:
$2 million for Clutch & misc. equipmentVs.
$20+ million for Statcomm
62
ProgressPresented to TTF/TWG September 2002
Visited several plants in New England:WF Wyman, Newington Steam, Schiller, Middletown,
Millstone
Other candidate units:Mystic, Bridgeport
All generating stations are “open” to the idea
63
Significant issues
Who benefits?
Who pays?
Under NEPOOL discussion
64
RTEP03 - April ‘04 Update
Issue Date: April, 2004
65
Introduction & Background
It is our objective in 2004 to formalize interim planning activity in order to improve the communication of ‘Plan’ progress, provide a process for interim approvals (should this be necessary), and maintain visibility of system needs.
We will be pursuing an improvement to the quality of update information, enhancing the management of change associated with the Plan, and publishing updated information as a service to our stakeholders.
To facilitate the internal and external review of our April ‘04 update, we have highlighted changes to the Project Listing, provided an analysis of changes since the RTEP03 approval, and included progress summaries on high-profile projects.
66
Introduction & Background (cont’d)
We will update and publish the system plan and associated project listing on a periodic basis in 2004 (shown below). This document represents our April ‘04 update.
J
2004
F M A M J J A S O N D
RTEP-031st ‘04 Update
Apr ‘04
RTEP-032nd ’04 Update
Jul ‘04
RTEP-041st Update
Oct ‘04
RTEP-04ApprovalPeriod
RTEP-04‘Board Draft’
RTEP-04TEAC ‘Draft’
2005
RTEP-041st ’05 Update
Apr ‘05
SeptemberPublic Mtg
67
The Interim Update Process
TOs UpdateProjectListing
ISO-NE Inte-grates Informa-tion & AnalyzesChanges
ISO-NE Conducts Follow-up
ISO-NE PreparesDraft UpdateReport
TEAC & RC Forward anyMajor Issues toISO-NE prior to meeting
ISO-NE PreparesResponses
ISO-NERevises theUpdate as Necessary
IntroduceProcessTo TOs
UpdateRequest &Guidelineto TOs
01/13/04 01/16/04
‘Draft’Providedto TEAC/RC
02/23/04
TEAC & RCReview ‘Draft’Update Report 02/26/04
Responsesto TEAC& RC
Presentat RC &TEAC Mtgs
Prior to meeting
03/02/04 &03/04/04
SubmitApril ‘04
Joint TO/ISO-NE Update
TEAC & RC Review
System OperatorApproval
68
Requested Review Actions
TOs: Verify project information previously provided to ISO-NE staff.
TEAC & RC: Review this interim plan. Recognize system needs, and where applicable, identify market responses and/ortransmission alternatives.
System Operator: Approve and publish the interim plan.
69
Contact Information
TEAC members should forward any major issues to the following address by March 11th:
Please check and review the latest Project Listing at:
www.iso-ne.com/committees/Transmission_Expansion_Advisory_Committee/protected/
70
Glenbrook STATCOM 3.6(3 projects)
Boston Import 7.6(12 projects)
Monadnock 44.9(14 projects)
Canton-N.Bloomfield Term. 6.9
Scobie Station Rebuild 3.0
Other (aggregate) 0.4(7 projects)
Make-up of the aggregate cost estimate change between the RTEP03 November publication and the February, 2004 progress update:
April ‘04 Change Highlights (cont’d)
+ $66.4 Million
Project $ Change (millions)
71
New Brentwood 115 kV Substation Reliability need – provide(Southwest New Hampshire) capacity to supply load
Upgrade Garvins 115 kV Substation Reliability need to meet (Southeast New Hampshire) compliance requirements
New Colburn St. 115/13.8 kV Substation Reliability need – provide (Boston) capacity to supply load
Second 115/13.8 kV Dover Substation Reliability need – provide (Boston) capacity to supply load
Pequonnock 115 kV Substation Bus Upgrade Substation Equipment Bracing & Ground Grid Upgrade to Higher Short Circuit Capability(Southwest Connecticut)
Five (5) new Projects and Corresponding Needs (*):
April ‘04 Change Highlights (cont’d)
Project Need
(*) Projects may have some non-PTF components
72
Draft Northeastern ISO/RTO Planning
Coordination Protocol
Mike HendersonISO-New EnglandSystem Planning
73
• Coordinates system planning activities• Establishes
– Inter-Area Planning Stakeholder Advisory Committee
– Joint ISO/RTO Planning Committee
• Data and information exchange• Coordinates Tariff studies• Northeastern coordinated system plan• Dispute resolution
Draft Northeastern ISO/RTOPlanning Coordination Protocol
74
• ISO/RTO draft protocol developed– Full participation by PJM, NYISO, and ISO-NE– Limited participation by the IMO, TransEnergie Quebec, and New Brunswick
• Stakeholder review of draft protocols– New England– Jointly, if required
• Cost responsibility for planning activities– Studies
• Tariff studies – customer• Northeastern coordinated plan – each party
– Administrative• Load ratio• Stakeholder meetings• Web site
• Cost responsibility for network upgrades– Process to be developed consistent with the provisions of each area’s Tariff
Next Steps . . .
75
Draft Northeastern ISO/RTO Planning Coordination Protocol
ITEM PAST RECENT
IMPROVEMENTS DRAFT PROTOCOL COMMENTS Coordination of System Plans
NPCC review of individual area assessments for inter-area impacts
Better informal coordination with NY
Joint studies to ensure individual area plans are well coordinated
Identification of improvements required for reliability.
Study process similar to NE’s including stakeholder group
Coordination of data, timelines, scopes of work, etc. will greatly improve inter-area planning
Approvals are subject to each region’s planning procedures.
Tariff Studies NPCC review of individual area assessments for inter-area impacts
Better informal coordination with NY
Recognizes different interconnection requirements
Early notification of inter-area impacts
Payment for full scope of work that considers inter-area issues
Web site listing queue of projects with potential inter-area impacts
Network upgrades identified as part of the SIS under terms and conditions of potentially impacted system consistent with FERC and regulatory policy
Customers understand inter-area impacts at earliest possible date.
Customers to address remote area upgrades as a requirement of interconnection.
Many issues to be addressed by JIPC with input from stakeholders.
Cost Allocation for Projects with Inter-Area Impact
Consistent with each area’s Tariff, including negotiated agreements. FERC is the ultimate arbitrator.
Earlier identification of issues achieved through informal coordination
Cost of elements of the Northeastern Coordinated System Plan (NCSP) and Tariff studies will be addressed consistent with provisions of each area’s Tariff.
Allows for smooth transition to RTO-NE.
No obligation for remote system to make NCSP improvements for neighbor. Will require further evolution.
2/23/04 4
76
• Current Process– ISO-NE comments on interconnection plan will be
conveyed to NYISO prior to NY stakeholder review. These will include a scope of work for testing the NEPOOL system.
– Impacts on NEPOOL system considered at New York Stakeholder meetings?
– Impacts on NEPOOL system considered at New York State licensing process?
– Impacts on NEPOOL system considered at NPCC? (While NPCC decisions are non-binding, NPCC is an important forum.)
– Impacts considered by FERC?
Example: Interconnection Project in NY
77
• Draft Protocol– NYISO advises ISO-NE of the interconnection application.– ISO-NE provides NYISO with scope of work and estimated
cost of studies of the New England system. ISO-NE can participate in studies.
– Under the NYISO agreement with the interconnection customer, any impacts on the New England system will be addressed in the NYISO interconnection studies.
• Impacts on the New England system to be determined in accordance with ISO-NE procedures and criteria. Needed network upgrades on the New England system to be identified in the NYISO system impact study.
Example: Interconnection Project in New York (cont.)
78
Planning Protocol Input
• Please provide comments on draft planning protocol by March 12th.
• Comments received to date:– NEPOOL Information Policy Compliance– NPCC Role
79
RTEP04 Planning Assumptions
• Load Forecast • Issues Raised at TEAC19• Information updated
• Fuel Prices
• Emission Allowances
• Control Area Imports/Exports
80
NSTAR Provided Updated Forecast Growth Rates for BECO and Commonwealth Electric:
•Increased Boston Sub-area Summer Peak by 40 MW and SEMA by 30 MW in 2013
•Decreased CMA/NEMA Summer Peak by 25 MW and W-MA by 30 MW in 2013
81
Summer Peak Impacts of NSTAR Peak Growth Rate Changes on 2004 Forecast of RTEP Sub-areas
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
BOSTONRevised 5185 5310 5440 5505 5570 5630 5695 5765 5855 5920 5980Original 5195 5320 5445 5500 5555 5610 5665 5730 5820 5885 5940DIFFER -10 -10 -5 5 15 20 30 35 35 35 40
CMA/NEMARevised 1660 1700 1735 1750 1765 1780 1795 1815 1845 1865 1885Original 1660 1700 1740 1760 1775 1790 1810 1835 1865 1890 1910DIFFER 0 0 -5 -10 -10 -10 -15 -20 -20 -25 -25
W-MARevised 1945 1980 2020 2030 2040 2050 2065 2080 2100 2115 2125Original 1945 1980 2025 2040 2055 2070 2085 2100 2125 2140 2155DIFFER 0 0 -5 -10 -15 -20 -20 -20 -25 -25 -30
SEMARevised 2550 2620 2685 2715 2745 2780 2810 2855 2910 2950 2990Original 2540 2610 2670 2705 2735 2765 2800 2840 2890 2925 2960DIFFER 10 10 15 10 10 15 10 15 20 25 30
RIRevised 2295 2345 2400 2430 2460 2490 2520 2555 2595 2630 2655Original 2295 2345 2405 2430 2465 2495 2530 2565 2600 2640 2665DIFFER 0 0 -5 0 -5 -5 -10 -10 -5 -10 -10
82
Reviewed Own and Coincident Summer Peak Relationship for the New England States, 2000-2003
For Most States Own Peak the Same or Only Marginally Higher
Own and Coincident Peaks Tend to Converge Under Extreme Weather Conditions
83
Effects of Non-Coincidence Are Negligible
Percent Difference Between Own and Coincident Summer Peak Loads by State 2000-2003
Extreme Weather Impact2000 2001 2002 2003Average on Peak Forecast
CT 0.6 0.0 1.0 0.1 0.4 6.4ME 3.6 1.8 0.9 0.3 1.6 4.2MA 0.0 0.0 0.0 0.0 0.0 6.0NH 0.7 0.0 0.0 2.1 0.7 7.9RI 3.5 0.0 0.0 0.0 0.9 6.2VT 3.6 2.3 1.3 4.2 2.8 5.3
84
Fuel Price Assumptions
• Fuel Price Forecast Based on Energy Information Administration’s forecast
• January 2004 Short Term Energy Outlook (STEO) for 2004, 2005– “Reference Case” forecast was used
• Dec 2003 Annual Energy Outlook (AEO) for 2006 through 2013
85
RTEP 04 AssumptionsRelative Fuel Price Forecast
2004Annual Energy Outlook Blended With Short-Term Outlook (Jan. 2004)
0.001.002.003.004.005.006.007.008.00
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Fu
el P
ric
e (
$/M
Btu
)
Distillate Fuel (FO2) Residual Fuel (FO6)
Natural Gas Steam Coal
86
RTEP 03 AssumptionsRelative Fuel Price Forecast
2003Annual Energy Outlook Blended With Short-Term Outlook
0.001.002.003.004.005.006.007.008.00
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020F
ue
l Pri
ce
($
/MB
tu)
Distillate Fuel (FO2) Residual Fuel (FO6) Natural Gas Steam Coal
87
Comparison of Fuel Price Assumptions
Fuel Price ComparisonRTEP04 Forecast - RTEP03 Forecast
-1.50
-1.00
-0.50
0.00
0.50
1.00
1.50
2.00
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Years
Pri
ce D
iffe
ren
ce (
$/
MM
Btu
)
Distillate Fuel (FO2) Residual Fuel (FO6)
Natural Gas Steam Coal
88
RTEP04 Fuel Price Assumptions
• Earlier RTEP efforts considered the commodity cost of fuel
• Seeking TEAC input on including fuel transportation costs– Residual Oil– Natural Gas– Coal
89
Emission Allowances
• Past RTEP economic studies did not account for emission allowances as a component of fossil unit production cost.
• Further consideration along with the changing dynamics of the allowance markets suggest these generator costs could have an impact on future study results.
90
NOx Allowances
• 1994 MOU established the Ozone Transport Commission
• 11 NE States and DC
• Cap on NOx emissions from major sources (May – September)
• Operated through 2003
91
NOx Allowances
• On May 1, 2003, compliance under the expanded NOx SIP Call market program began, to be implemented in phases
92
NOx Allowance Amounts
93
NOx Allowances Costs
• Driven by;– Continued ratcheting down of allowances to
meet ambient ozone standard.– High natural gas costs– Buying allowances as a stop-gap measure to
reduce capital expenditures– EPA estimates of $2000 to $2500 per ton for
average incremental control costs for the region.
94
NOx Allowance Costs
Dec. 31,2003 SIP NOx Prices
0100020003000400050006000700080009000
2003 2004 2005 2006 2007
Do
llars
pe
r T
on
Forward Prices (12/31/03) Spot Price (12/31/03)
95
NOx Allowances
• Consider that a coal-fired generator, with a 10,500 BTU/KWh heat rate and a 0.45 lbs.-NOx/MMBtu emission rate will incur an added production cost of more than $10.00 per MWh to account for the NOx allowances consumed at a $5,000 price.
• The impact of NOx allowance costs becomes even more important during a period of high gas costs.
96
SO2 Allowances
• Historically SO2 Allowances are lower than NOx Allowances– $200 vs. $ 2500 per ton– Less volatile than NOx Allowances
• Driven by much lower compliance costs
97
SO2 Allowance Cost
98
RTEP04 Assumption
• Include Allowance costs as an additional production cost
• Updated emission database to capture expected regulatory changes
• SO2 Allowances at $ 200 / ton• NOx Allowances (per ton)
• 2004 - $5000• 2005 - $5000• 2006 - $3500• 2007 - $2700• Beyond 2007 – $ 2200 EPA estimated
mitigation cost
99
Control Area Imports/Exports• Reviewed historic control area transfers
– Seasonal variations– On Peak vs. Off peak– Trends– Developments
100
Weekly Interchange Profile by Season
Historical Interchange Weekly Profile(Jan. 2002- Nov. 2003)(Negative Flow means Imports to NEPOOL)_Winter
-1400
-400
600
1 25 49 73 97 121 145
Hours
Inte
rch
ang
e F
low
(M
W)
AvgOfNEW YORK AvgOfNEW BRUNS
AvgOfPHASE I/II AvgOfHIGHGATE
Historical Interchange Weekly Profile(Jan. 2002- Nov. 2003)(Negative Flow means Imports to NEPOOL)_Summer
-1500
-1000
-500
0
500
1 25 49 73 97 121 145
Hours
Inte
rch
ang
e F
low
(M
W)
AvgOfNEW YORK AvgOfNEW BRUNS AvgOfPHASE I/II AvgOfHIGHGATE
101
Historical Interchange at Time of Daily Peak
H isto rica l In te rch an g e an d N E P OOL D aily P eak L o ad _2002
-1 50 0
-1 00 0
-50 0
0
50 0
1 00 0
1 50 0
2 00 0
1 31 6 1 91 12 1 1 5 1 1 81 21 1 2 4 1 2 71 30 1 3 31 3 61
D ay
Inte
rch
an
ge
(MW
)
0
5 00 0
1 00 00
1 50 00
2 00 00
2 50 00
3 00 00
NE
PO
OL
Da
ily
Pe
ak
Lo
ad
(M
W)
Ne wYo rk New Brun swick HQ Pha se II/I HQ Hig hg a te NE_ L O AD
Historical Interchange and NEPOOL Daily Peak Load_2003
-2000
-1000
0
1000
2000
1 31 61 91 121 151 181 211 241 271 301 331 361
Da y
Inte
rch
an
ge
(MW
)
050001000015000200002500030000
NE
PO
OL
Da
ily
Pe
ak
Lo
ad
(MW
)
NewYork New Brunswick HQ Phase II/I HQ Highgate NE_LOAD
102
Correlation between NE Daily Peak Load and Historical Interchange
Correlation between NEPOOL Daily Peak Load and Interchange_2002
-1500
-1000
-500
0
500
1000
1500
2000
11000 13000 15000 17000 19000 21000 23000 25000
Sorted NEPOOL Daily Peak Load
Inte
rch
an
ge
(M
W)
NewYork
New Brunswick
HQ Phase II/I
HQ Highgate
Corre lation be twee n NEPOO L Daily Peak Load and Interchange _2003
-2000
-1500
-1000
-500
0
500
1000
1500
2000
11000 13000 15000 17000 19000 21000 23000 25000
Sorte d NEP OOL Da ily P e a k Loa d
Inte
rch
an
ge
(M
W)
NewYork
New B runswick
HQ Phase II/I
HQ Highgate
103
RTEP04 Modeling Assumptions
• Seeking TEAC Input– NY
• 85 MW Import - NYPA Contract– NB
• 200 MW Fixed Import • 500 MW Import modeled as a gas fired combined cycle
unit– HQ
• 300 MW fixed Import• 500 MW Import modeled as a gas fired combined cycle
unit• 500 MW Import modeled as a gas fired steam unit• 200 MW Import modeled as a distillate GT
104
RTEP04 Resource Adequacy Analysis
TEAC20 PresentationMarch 4, 2004
Peter Wong ISO-NEPower Supply & Reliability
105
2004 Resource Adequacy Analysis
• Westinghouse/ABB Capacity Model Program used to determine single area NEPOOL LOLE covering 2004 through 2013
• Why run Westinghouse single area model”?– Determine NEPOOL Objective Capability/Installed Capacity
Requirements according to the current OC methodology– Provide signals to the market regarding future OC/ICAP
needs
Note: Weather related load forecast uncertainty is modeled.
106
2004 Resource Adequacy Analysis
• GE MARS used to determine sub-area LOLE covering the same time frame
• Why run the GE MARS model?– Determine the impact of transmission
constraints on NEPOOL generation resource adequacy. However, it does not capture transmission adequacy issues
– Provide signals to the market regarding future LICAP needs
Note: Weather related load forecast uncertainty is modeled.
107
Resource Adequacy Analysis Assumptions
• Loads – Based on 2004 CELT Data– Includes weather related load uncertainty
• Capacity Data– “CELT like” data – Difference in monthly SCC report reference
for winter rating– Capacity Additions – Based on 18.4 approval and under
construction (CELT includes all approved 18.4 Applications)– Capacity Attrition – Based on 18.4 approved retirements (CELT
does not include all approved 18.4 retirements/deactivations)– SWCT RFP– Known ICAP Contracts
• Any required expansion units needed to meet the NEPOOL criterion of 0.1 days/year LOLE have summer and winter ratings of 172.5 MW, 5 weeks of maintenance, and an equivalent forced outage rate (EFOR) of 10%
108
Resource Adequacy Analysis Assumptions
• Generating Unit Availability – 5 year historical performance (1999 – 2003)– New CC units break-in period represented
• Tie Reliability Benefits– 600 MW from NY year round– 200 MW from NB year round
• HQICC (when assumed)– As filed with FERC on December 31, 2003
• OP-4 Load Relief (327 MW* + 1.42% of load)– *Reflects 58 MW of Price Response Program Resources
• Load Response Program Assets– Values as of October 31, 2003
• Load Shift in CT and NEMA/BOSTON will be modeled
109
Capacity Addition Assumptions
Summer Rating (MW)
Milford Units 1 + 2 (SWCT) 490 Millstone 2 Uprate (CT) 31
Total 521
SWCT RFP (NOR & SWCT) 200
All assumed in service by June 1, 2004
110
Generating Unit Retirements
Summer Rating (MW)
Mason 4 – 6 98
Total 98
Assumed to be retired by June 1, 2004
111
Generating Unit Retirements
• To-be-Retired Units currently under RMR– Devon 7 and 8– New Boston– Salem Harbor 1 – 4 (RMR under negotiation)
• Units applied for 18.4 Deactivation (but denied)– Wallingford 2-5
112
Transmission Interface Transfer Limit
Assumptions (Static Limits Used for Modeling)
InterfacesInterface Limit Assumptions
(MW)
Basic Information for Interface Limits
ExplanationRelevant Study or
Descriptive Information
Availability
NB-NE700
2007 : 1000Stability NB-NE Tie Study
Public – Contact ISO-NE
HQ-NE (Highgate)
210HVDC Design
Limit and Voltage
N/A N/A
NY – NE (w/o Cross Sound
Cable)
Summer – 1,225
Winter – 1,475Thermal
NYISO S 2002 Operating Study NYISO 2001-02 Operating Study
Public – NYISO website
Cross Sound Cable
300 (NY to NE)
330 (NE to NY)
HVDC Equipment
Design LimitN/A N/A
HQ-NE (Phase II)
1500External Voltage
Constraints (PJM & NY)
Historical operating limit
N/A
113
Transmission Interface Transfer Limit
Assumptions (Static Limits Used for Modeling)
InterfacesInterface Limit Assumptions
(MW)
Basic Information for Interface Limits
ExplanationRelevant Study or
Descriptive Information
Availability
Maine – New Hampshire
1,400 Stability
2000 Maine Operating Study
NB – NE Tie Study
Confidential – Strategic
Information
Orrington South Export
2004: 1,050
2007: 1,200
Thermal (Summer) Bucksport System
Impact Study
Public – Contact Central
Maine Power
Surowiec South
1,150 Stability2000 Maine
Operating Study
Confidential – Strategic
Information
North - South
2,700Thermal
(Summer)Typical Operating
Study Results
Confidential – Strategic
Information
114
Transmission Interface Transfer Limit
Assumptions (Static Limits Used for Modeling)
Interfaces
Interface Limit
Assumptions (MW)
Basic Information for Interface Limits
ExplanationRelevant Study or Descriptive
InformationAvailability
Boston Import2004 : 3,600
2006 : 4,500 Thermal
(Summer)
Boston Import 2004 – 2008
Reliability Review
Public – ISO-NE website –
RC documents Section
SE Mass Export No limit Stability ISO-NE StudiesTo be
determined
(A)SE Mass/RI Export
(B)East – West
(C)Connecticut Import
(A)3,000
(B)2,400
(C)2,200
Simultaneous Stability / Thermal Voltage
ISO-NE StudiesTo be
determined
115
Transmission Interface Transfer Limit
Assumptions (Static Limits Used for Modeling)
Interfaces
Interface Limit
Assumptions (MW)
Basic Information for Interface Limits
ExplanationRelevant Study or Descriptive
InformationAvailability
Connecticut Export
2,030Thermal
(Summer)
Export Limit – NU Haddam Neck
SIS
Confidential – Strategic
Information
Southwest Connecticut
Import
2004: 2,000
2006: 2,550
2008: 3,400
Voltage
Thermal
Thermal
ISO-NE Studies
ISO-NE Studies
ISO-NE Studies
To be determined
To be determined
To be determined
Norwalk – Stamford
2004: 1,100
2006: 1,300
2008: 1,650
Thermal (Summer)
Typical Operating Study Result
ISO-NE Studies
Confidential – Strategic
Information
116
RTEP04 Resource Adequacy Cases
Case ID Single Area Simulation (SAS) Case Description
Case SAS1SAS using assumptions presented in TEAC19&20 at Reference Load Growth.
Case SAS2SAS using assumptions presented in TEAC19&20 at High Economic Load Growth.
Case SAS3SAS using assumptions presented in TEAC19&20 at Reference Load Growth and HQ Phase II assumed zero starting in 2005/06.
Case SAS4SAS using assumptions presented in TEAC19&20 at High Economic Load Growth and HQ Phase II assumed zero starting in 2005/06.
Case SAS5 - ???
Additional cases under development to cover possible unit retirements or additions
117
SAS Reference Load Growth (SAS1)
ICAP Resources included all New England claimed capacity (including units classified as Settlement Only), ICAP capable Load Response Resources, and Hydro Quebec Interconnection Credits
0.04330.043332,44133,71028,8802013-14
0.03000.030032,05933,71028,5502012-13
0.01910.019131,60833,71028,1702011-12
0.01090.010931,10433,71027,7402010-11
0.00670.006730,70233,71027,3902009-10
0.00420.004233,71027,0582008-09
0.00270.002733,71026,8152007-08
0.00170.001729,72133,71026,5702006-07
0.00100.001029,36633,71026,3052005-06
0.00050.000528,91533,71025,7352004-05
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP Resources
Summer (MW)
Peak Load(MW)
Power Year
0.04330.043332,44133,71028,8802013-14
0.03000.030032,05933,71028,5502012-13
0.01910.019131,60833,71028,1702011-12
0.01090.010931,10433,71027,7402010-11
0.00670.006730,70233,71027,3902009-10
0.00420.004233,71027,0582008-09
0.00270.002733,71026,8152007-08
0.00170.001729,72133,71026,5702006-07
0.00100.001029,36633,71026,3052005-06
0.00050.000528,91533,71025,7352004-05
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP Resources
Summer (MW)
Peak Load(MW)
Power Year
118
SAS Reference Load Growth (SAS1)
Total ICAP requirement reflect the accounting of the HQICC
2013-14
2012-13
2011-12
2010-11
2009-10
2008-09
2007-08
2006-07
2005-06
2004-05
Power Year
3,561
3,509
3,438
3,364
3,312
3,289
3,217
3,151
3,061
3,180
MW
Required Reserves
12.316.74,830
12.318.15,160
12.219.75,540
12.121.55,970
12.123.16,320
12.224.66,652
12.025.76,895
11.926.97,140
11.628.27,405
12.431.07,975
%%MW
Installed Reserves
2013-14
2012-13
2011-12
2010-11
2009-10
2008-09
2007-08
2006-07
2005-06
2004-05
Power Year
3,561
3,509
3,438
3,364
3,312
3,289
3,217
3,151
3,061
3,180
MW
Required Reserves
12.316.74,830
12.318.15,160
12.219.75,540
12.121.55,970
12.123.16,320
12.224.66,652
12.025.76,895
11.926.97,140
11.628.27,405
12.431.07,975
%%MW
Installed Reserves
119
SAS High Economic Load Growth (SAS2)
* 2 Proxy units added** 4 Proxy units added (total of 6 proxy units added)
ICAP Resources included all New England claimed capacity (including units classified as Settlement Only), ICAP capable Load Response Resources, and Hydro Quebec Interconnection Credits
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP ResourcesSummer
(MW)
Peak Load(MW)
Power Year
0.15170.091734,37134,745**30,4802013-14
0.12420.096033,73934,055*29,9652012-13
0.07260.072633,04933,71029,3902011-12
0.03800.038032,30333,71028,7652010-11
0.02010.020131,66233,71028,2152009-10
0.01070.010731,09533,71027,7302008-09
0.00560.005630,56933,71027,2802007-08
0.00270.002730,03633,71026,8452006-07
0.00120.001229,48833,71026,4152005-06
0.00050.000528,97833,71025,7902004-05
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP ResourcesSummer
(MW)
Peak Load(MW)
Power Year
0.15170.091734,37134,745**30,4802013-14
0.12420.096033,73934,055*29,9652012-13
0.07260.072633,04933,71029,3902011-12
0.03800.038032,30333,71028,7652010-11
0.02010.020131,66233,71028,2152009-10
0.01070.010731,09533,71027,7302008-09
0.00560.005630,56933,71027,2802007-08
0.00270.002730,03633,71026,8452006-07
0.00120.001229,48833,71026,4152005-06
0.00050.000528,97833,71025,7902004-05
120
SAS High Economic Load Growth (SAS2)
* 2 Proxy units added** 4 Proxy units added (total of 6 proxy units added)Total ICAP Requirement calculation reflect the accounting of the HQICC
2013-14
2012-13
2011-12
2010-11
2009-10
2008-09
2007-08
2006-07
2005-06
2004-05
Power Year
3,891
3,774
3,659
3,538
3,447
3,365
3,289
3,191
3,073
3,188
MW
Required Reserves
12.814.04,265**
12.613.64,090*
12.414.74,320
12.317.24,945
12.219.55,495
12.121.65,980
12.123.66,430
11.925.66,865
11.627.67,295
12.430.77,920
%%MW
Installed Reserves
2013-14
2012-13
2011-12
2010-11
2009-10
2008-09
2007-08
2006-07
2005-06
2004-05
Power Year
3,891
3,774
3,659
3,538
3,447
3,365
3,289
3,191
3,073
3,188
MW
Required Reserves
12.814.04,265**
12.613.64,090*
12.414.74,320
12.317.24,945
12.219.55,495
12.121.65,980
12.123.66,430
11.925.66,865
11.627.67,295
12.430.77,920
%%MW
Installed Reserves
121
SAS -Reference Load Growth (SAS3)
• 2 Proxy units added in 2013-14• HQICC included in ICAP Resources Total in 04/05 and assumed to be zero starting in
2005/06
0.12160.093032,49632,855*28,8802013-14
0.08890.088932,10032,51028,5502012-13
0.06050.060531,62332,51028,1702011-12
0.03780.037831,09832,51027,7402010-11
0.02500.025030,67532,51027,3902009-10
0.01700.017030,29832,51027,0582008-09
0.01180.011829,97432,51026,8152007-08
0.00800.008029,64732,51026,5702006-07
0.00490.004929,27032,51026,3052005-06
0.00050.000528,91533,71025,7352004-05
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP Resources
Summer (MW)
Peak Load(MW)
Power Year
0.12160.093032,49632,855*28,8802013-14
0.08890.088932,10032,51028,5502012-13
0.06050.060531,62332,51028,1702011-12
0.03780.037831,09832,51027,7402010-11
0.02500.025030,67532,51027,3902009-10
0.01700.017030,29832,51027,0582008-09
0.01180.011829,97432,51026,8152007-08
0.00800.008029,64732,51026,5702006-07
0.00490.004929,27032,51026,3052005-06
0.00050.000528,91533,71025,7352004-05
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP Resources
Summer (MW)
Peak Load(MW)
Power Year
122
SAS- Reference Load Growth (SAS3)
•2 Proxy units added in 2013-14•HQICC not included in Installed Capacity Total in 04/05 and assumed zero starting in 2005/06
2013-14
2012-13
2011-12
2010-11
2009-10
2008-09
2007-08
2006-07
2005-06
2004-05
Power Year
3,616
3,550
3,453
3,358
3,285
3,240
3,159
3,077
2,965
3,180
MW
Required Reserves
12.513.83,975
12.413.93,960
12.315.44,340
12.117.24,770
12.018.75,120
12.020.15,452
11.821.25,695
11.622.45,940
11.323.66,205
12.426.36,775
%%MW
Installed Reserves
2013-14
2012-13
2011-12
2010-11
2009-10
2008-09
2007-08
2006-07
2005-06
2004-05
Power Year
3,616
3,550
3,453
3,358
3,285
3,240
3,159
3,077
2,965
3,180
MW
Required Reserves
12.513.83,975
12.413.93,960
12.315.44,340
12.117.24,770
12.018.75,120
12.020.15,452
11.821.25,695
11.622.45,940
11.323.66,205
12.426.36,775
%%MW
Installed Reserves
123
SAS - High Economic Load Growth (SAS4)
• 1 Proxy unit added in 2010-11• 5 Proxy units added in 2011-12• 4 Proxy units added in 2012-13• 3 Proxy units added (total of 13 proxy units added) in 2013-14• HQICC included in ICAP Total in 04/05 but assumed to be zero starting in 2005-06
0.36500.096634,44534,753****30,4802013-14
0.30730.088833,81434,234***29,9652012-13
0.19100.087933,11433,545**29,3902011-12
0.10870.095132,35732,683*28,7652010-11
0.06330.063331,68532,51028,2152009-10
0.03730.037331,08832,51027,7302008-09
0.02170.021730,53632,51027,2802007-08
0.01180.011829,97732,51026,8452006-07
0.00580.005829,39532,51026,4152005-06
0.00050.000528,97833,71025,7902004-05
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP Resources
Summer MW
Peak Load(MW)
Power Year
0.36500.096634,44534,753****30,4802013-14
0.30730.088833,81434,234***29,9652012-13
0.19100.087933,11433,545**29,3902011-12
0.10870.095132,35732,683*28,7652010-11
0.06330.063331,68532,51028,2152009-10
0.03730.037331,08832,51027,7302008-09
0.02170.021730,53632,51027,2802007-08
0.01180.011829,97732,51026,8452006-07
0.00580.005829,39532,51026,4152005-06
0.00050.000528,97833,71025,7902004-05
LOLE w/o Expansion
UnitsLOLE
Summer Requirement
(MW)
ICAP Resources
Summer MW
Peak Load(MW)
Power Year
124
SAS- High Economic Load Growth (SAS4)
* 1 Proxy unit added** 5 Proxy units added*** 4 Proxy units added**** 3 Proxy units added (total of 13 proxy units added)HQICC included in ICap Total in 04/05 but assumed to be zero starting in 2005-06
2 0 1 3 -1 4
2 0 1 2 -1 3
2 0 1 1 -1 2
2 0 1 0 -1 1
2 0 0 9 -1 0
2 0 0 8 -0 9
2 0 0 7 -0 8
2 0 0 6 -0 7
2 0 0 5 -0 6
2 0 0 4 -0 5
P o w e r Y e a r
3 ,9 6 5
3 ,8 4 9
3 ,7 2 4
3 ,5 9 2
3 ,4 7 0
3 ,3 5 8
3 ,2 5 6
3 ,1 3 2
2 ,9 8 0
3 ,1 8 8
M W
R e q u ire d R e s e rv e s
1 3 .01 4 .04 ,2 7 3 * * * *
1 2 .81 4 .24 ,2 6 9 * * *
1 2 .71 4 .14 ,1 5 5 * *
1 2 .51 3 .63 ,9 1 8 *
1 2 .31 5 .24 ,2 9 5
1 2 .11 7 .24 ,7 8 0
1 1 .91 9 .25 ,2 3 0
1 1 .72 1 .15 ,6 6 5
1 1 .32 3 .16 ,0 9 5
1 2 .42 6 .16 ,7 2 0
%%M W
In s ta lle d R e s e r v e s
2 0 1 3 -1 4
2 0 1 2 -1 3
2 0 1 1 -1 2
2 0 1 0 -1 1
2 0 0 9 -1 0
2 0 0 8 -0 9
2 0 0 7 -0 8
2 0 0 6 -0 7
2 0 0 5 -0 6
2 0 0 4 -0 5
P o w e r Y e a r
3 ,9 6 5
3 ,8 4 9
3 ,7 2 4
3 ,5 9 2
3 ,4 7 0
3 ,3 5 8
3 ,2 5 6
3 ,1 3 2
2 ,9 8 0
3 ,1 8 8
M W
R e q u ire d R e s e rv e s
1 3 .01 4 .04 ,2 7 3 * * * *
1 2 .81 4 .24 ,2 6 9 * * *
1 2 .71 4 .14 ,1 5 5 * *
1 2 .51 3 .63 ,9 1 8 *
1 2 .31 5 .24 ,2 9 5
1 2 .11 7 .24 ,7 8 0
1 1 .91 9 .25 ,2 3 0
1 1 .72 1 .15 ,6 6 5
1 1 .32 3 .16 ,0 9 5
1 2 .42 6 .16 ,7 2 0
%%M W
In s ta lle d R e s e r v e s
125
Resource Adequacy MARS Cases
The following are some of the MARS multi-area cases for RTEP04. We seek your input for additional cases or modification of these proposed cases, including possible assumptions associated with these cases.
126
RTEP04 Resource Adequacy Cases
Case ID MARS Multi-Area Simulation Description
Case 1Existing transmission capabilities using assumptions presented in TEAC19&20.
Case 2 Case 1 w/o SWCT RFP 200 MW of resources
Case 3
Case 1 plus likely new generation & deactivations based on 18.4 approvals, retirement requests and future environmental regulations. Seeking TEAC Input
Case 4The SWCT Phase I & II as per current expected schedule.
127
RTEP04 Resource Adequacy Cases
Case ID MARS Multi-Area Simulation Description
Case 5 Additional resources estimated by examining the New England State Renewable Portfolio Standards
Case 6
Load reductions and additional resources forecast by the DR Market Penetration Study. Examine impacts assuming 100 % of potential is achieved over time.
128
RTEP04 Resource Adequacy Cases
Case ID MARS Multi-Area Simulation Description
Case 7 Improvements of the Boston import 345 kV cable project.
Case 7A Case 7 plus assumed likely retirements in the Boston Import Area
Case 7B
Boston Import Alternative – Additional quick start resources in the Boston Import area that will result in reliability similar to Case 7
129
RTEP04 Resource Adequacy Cases
Case ID MARS Multi-Area Simulation Description
Case 8 Impacts on CT Import (SEMA/RI export) Improvement Project.
Case 8A Case 8 with assumed CT area retirements
Case 8B
CT Import Alternative – Additional quick start resources in the CT Import area that will result in reliability similar to Case 8.
130
RTEP04 Resource Adequacy Cases
Case ID MARS Multi-Area Simulation Description
Case 9 Impacts of 2nd NB Tie.
Case 10 Impacts of CSC Export
Case11 Impacts of CSC Import
Cases 12a-x
Cases with fuel restrictions as provided by the FDWG.
131
GE MARS – NE System LOLE
Year
(Jan – Dec)
Case 1
With 200 MW RFP
Case 2
w/o 200 MW RFP
Case 4
With 200 MW RFP* and SWCT Phase I
and II
2004 0.003 0.016 0.003
2005 0.004 0.020 0.004
2006 0.007 0.027 0.011
2007 0.011 0.035 0.014
2008 0.015 0.047 0.020
2009 0.020 0.061 0.024
2010 0.031 0.097 0.035
2011 0.050 0.137 0.059
2012 0.080 0.215 0.082
2013 0.099 0.290 0.110
*The 200 MW RFP is assumed retired when SWCT Phase I is in service.
132
GE MARS Results CT Sub-Area LOLE
Year
(Jan – Dec)
Case 1
With 200 MW RFP
Case 2
w/o 200 MW RFP
Case 4
With 200 MW RFP* and SWCT Phase I
and II
2004 0.001 0.001 0.001
2005 0.001 0.002 0.001
2006 0.002 0.003 0.003
2007 0.002 0.003 0.003
2008 0.004 0.006 0.006
2009 0.005 0.006 0.007
2010 0.005 0.006 0.007
2011 0.009 0.012 0.012
2012 0.011 0.014 0.016
2013 0.013 0.017 0.018*The 200 MW RFP is assumed retired when SWCT Phase I is in service.
133
GE MARS Results
SWCT Sub-Area LOLEYear
(Jan – Dec)
Case 1
With 200 MW RFP
Case 2
w/o 200 MW RFP
Case 4
With 200 MW RFP* and SWCT Phase I
and II
2004 0.002 0.009 0.002
2005 0.003 0.013 0.003
2006 0.004 0.017 0.008
2007 0.005 0.021 0.009
2008 0.009 0.027 0.014
2009 0.012 0.037 0.016
2010 0.018 0.062 0.023
2011 0.028 0.084 0.040
2012 0.045 0.129 0.054
2013 0.059 0.170 0.078* The 200 MW RFP is assumed retired when SWCT Phase I is in service.
134
GE MARS Results NOR Sub-Area LOLE
Year
(Jan – Dec)
Case 1
With 200 MW RFP
Case 2
w/o 200 MW RFP
Case 4
With 200 MW RFP* and SWCT Phase I
and II
2004 0.002 0.012 0.002
2005 0.002 0.016 0.002
2006 0.004 0.021 0.009
2007 0.005 0.026 0.009
2008 0.008 0.028 0.014
2009 0.011 0.047 0.017
2010 0.016 0.078 0.024
2011 0.027 0.112 0.041
2012 0.044 0.179 0.055
2013 0.065 0.259 0.079* The 200 MW RFP is assumed retired when SWCT Phase I is in service.
135
GE MARS Results
Boston Sub-Area LOLEYear
(Jan – Dec)
Case 1
With 200 MW RFP
Case 2
w/o 200 MW RFP
Case 4
With 200 MW RFP* and SWCT Phase I
and II
2004 0.001 0.001 0.001
2005 0.001 0.001 0.001
2006 0.002 0.002 0.002
2007 0.005 0.005 0.005
2008 0.006 0.006 0.006
2009 0.007 0.008 0.007
2010 0.011 0.011 0.011
2011 0.019 0.018 0.019
2012 0.029 0.029 0.028
2013 0.033 0.034 0.034*The 200 MW RFP is assumed retired when SWCT Phase I is in service.