TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference
26

TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Jul 20, 2018

Download

Documents

dinhdiep
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

TDOT’s First CM/GC Design and Construction ProjectPresented at the

2016 Ohio Transportation Engineering Conference

Page 2: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Project Location

• Located on the South Loop in Downtown Nashville

Page 3: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Project History

• CM/GC Alternate Delivery Method – 1st TDOT Project• Design Consultant • CM/GC - Kiewit Infrastructure South Co. • Numerous Ongoing Maintenance Issues• 140,000+ ADT• Major Downtown Access Points

Page 4: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Options Studied as Part of the Project

• Deck Replacement with Full Depth Panels• Superstructure Replacement • Full Span Replacements • Eliminate Spans• Combination of Options

Page 5: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Option Evaluation Criteria

• Duration of Closures – Number of Weekends• Rough Order of Magnitude Costs• Life-Cycle Analysis• Railroad / Utility / ROW Impacts• Procurement of Materials• Constructability• Risk

Page 6: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 1 – Herman Street• Existing 345’ 4-Span Continuous Rolled Wide Flange Beams

• On-going Deck Maintenance• Over Herman St. & Nashville & Western Railroad

Page 7: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 1 – Herman Street• Replace Superstructure with Steel beam Superstructure Units

• Maintain Existing Beam Spacing• Existing Substructure in Good Condition• Modify Existing Abutment Endwall for New Cross-Slope & Expansion Joint• Spray Membrane Deck Seal & Asphalt Overlay

Page 8: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Herman Street

Page 9: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Herman Street

Page 10: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Herman Street

Page 11: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Herman Street

Herman EB Weekend Timelapse Video

Page 12: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 2 – Clinton – CSXT Crossing

• Existing 428’ 6-Span Continuous Rolled Wide Flange Beams• On-going Deck Maintenance• Over CSX Railroad and Clinton St.

Page 13: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 2 – Clinton – CSXT Crossing

• Superstructure Replacement of 2 Spans with 4 Spans Eliminated• Maintain Span 2 over CSXT and Span 5 over Clinton• Eliminate End Spans 1 & 6 and Interior Spans 3 & 4• Use Box Beams and Full Depth Deck Panels• Modify Existing Piers to act as Abutments• Spray Membrane Deck Seal & Asphalt Overlay

Page 14: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Clinton – CSXT Crossing

Page 15: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Clinton – CSXT Crossing

Page 16: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Clinton – CSXT Crossing

Clinton - CSX WB Weekend Timelapse Video

Page 17: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 3– Jo Johnston Avenue

• Existing 3-Span 178’ AASHTO I Beams• On-going Deck Maintenance• Over Jo Johnston Ave.

Page 18: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 3 – Jo Johnston Avenue

• Superstructure Replacement of 1 Span with 2 Spans Eliminated• Maintain Span 2 over Jo Johnston Avenue• Eliminate End Spans 1 & 3 • Use Box Beams and Full Depth Deck Panels• Use MSE walls to Contain New Roadway Fill• Modify Existing Piers to act as Abutments• Spray Membrane Deck Seal & Asphalt Overlay

Page 19: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Jo Johnston Avenue

Page 20: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Jo Johnston Avenue

Page 21: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 4 – Charlotte Avenue

• Existing 3-Span 196’ Continuous “K” Frame Wide Flange• Emergency Deck Repairs in 2013• Over Charlotte Ave.

Page 22: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Bridge Site 4 – Charlotte Avenue

• Structure Replacement with Single Span Steel Structure• Construct New Abutments Between “K-Frame” and Existing Abutment• Eliminate End Spans 1 & 3 • Use Steel Superstructure Units to Replace Existing Bridge• Use MSE walls to Contain New Roadway Fill• Spray Membrane Deck Seal & Asphalt Overlay

Page 23: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Charlotte Avenue

Page 24: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Charlotte Avenue

Page 25: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Conclusions

• Early Contractor Involvement with CM/GC Contract• Team Approach to Project (Owner-Contractor-Designer)• Personnel Continuity between Design and Construction Phases

• On-Site Bridge Farm or Fabrication Yard• Adapting Conventional Bridge Construction to fit ABC Needs

• Bridge Type and Material Selection Process• Ready-Mix Type Closure Pour Material• Debrief or Lessons Learned Meetings after each closure• Project Schedule – Incorporated all Phases and Disciplines

Page 26: TDOT’s First CM/GC Design and Construction Project ... · TDOT’s First CM/GC Design and Construction Project Presented at the 2016 Ohio Transportation Engineering Conference.

Questions