1 Mechanical Design of Collimators and Manufacturing Strategy Review of the Cryogenic By-pass for the LHC DS Collimators 26.05.2011 Alessandro Bertarelli (EN-MME) on behalf of the EN-MME Collimation Team with inputs from many colleagues in EN, TE and BE departments
Mechanical Design of Collimators and Manufacturing Strategy Review of the Cryogenic By-pass for the LHC DS Collimators 26.05.2011 Alessandro Bertarelli (EN-MME) on behalf of the EN-MME Collimation Team with inputs from many colleagues in EN, TE and BE departments. TCLD Mechanical Design. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1
Mechanical Design of Collimators and Manufacturing Strategy
Review of the Cryogenic By-pass for the LHC DS Collimators26.05.2011
Alessandro Bertarelli (EN-MME)on behalf of the EN-MME Collimation Team with inputs from many colleagues in EN, TE and BE departments
A. Bertarelli EN/MME 26.05.2011 2
TCLD MECHANICAL DESIGN
A. Bertarelli EN/MME 26.05.2011 3
COLLIMATOR MODULE (TCLD) LAYOUT
Ion Pump(30 L/s)
Ion Pump(30 L/s)
Pirani Gauge
Penning Gauge
Angle valve
Collimator Support Assembly (HTC_)
Warm Module (VMGDA)
Key Features• TCLD fully independent
from QTC• Specific support and
jacks for TCLD.• Horizontal Orientation• Hydraulic and
electrical manual connections
Vacuum Equipment
Mechanical Equipment
Collimator Jack
Collimator Module(TCLD)
A. Bertarelli EN/MME 26.05.2011 4
TCLD
Actuation system
Vacuum tank
Vacuum tankand jaws
TCLD PRODUCT BREAKDOWN
A. Bertarelli EN/MME 26.05.2011 5
Key Features• Total length: 1200 mm
(including 100m tapering)• Active length: 1000 mm (5
1. DS Collimators for IR3 (LTC) – 5 units• Engineering & Design• Manufacturing and assembly of 5 units (QTC+TCLD)
2. Phase 1 collimators for IR3 (Phase 1+) – 7 units. • Design update.• Manufacturing of 1 Primary Collimator (TCP)• Procurement of raw material and strategic components.
3. TCTP (Tertiary Collimators with BPMs) – 18 units.• Engineering & Design • Manufacturing of 1 prototype. • Procurement of raw material and strategic components.
Manufacturing & Cold Test of QTC 1 (1st Prototype)
June 2011
Manufacturing & Cold Test of QTC 2 and QTC 3
Manufacturing & Cold Test of QTC 4 and QTC 5
MANUFACTURING TIMELINE
May 2012
Col
limat
ion
Rev
iew
(ins
tall.
rele
ase)
Dec.2012
July 2013
Kept as spare Two Assembly Teams (Staff + Ind. Supp.)
A. Bertarelli EN/MME 26.05.2011 16
• Many interactions with several parties during assembly and testing phases.
• Use of subcontracted resources for QTC manufacturing requiring training and close follow-up.
• Risks of manufacturing conflict with other priority projects (Linac4, Shut-down preparation, other collimators) in case of delays.
• LTC production to end by late spring 2013. Conflicts in manpower allocation with Splice Consolidation cannot be ruled out.
CHALLENGES
A. Bertarelli EN/MME 26.05.2011 17
Thank you for your attention!
A. Bertarelli EN/MME 26.05.2011 18
BPM CABLES CONFIGURATION
Cable rooting
4 feadthrough connections on tank cables
Brazed Jaw
Tungsten support
Cooling circuit
Back stiffener
A. Bertarelli EN/MME 26.05.2011 20
Screwed from behind after brasing
5 Tungsten blocks (20 x 30 x 200)
Tungsten block assembly
A. Bertarelli EN/MME 26.05.2011 21
Seen from the inside15o slopes
1.6mm gap
50mm (maximum opening)
A. Bertarelli EN/MME 26.05.2011 22
RF CONFIGURATION FOR TCLD COLLIMATOR – extra illustrations
RF screen/tank contactRF screen contacts
RF extremity fingersHorizontal fixed contactVertical mobile contact
4 Temperature probes (1at each jaw extremity)
TEMP. PROBE CONFIGURATION
A. Bertarelli EN/MME 26.05.2011 24
Step Motor Bearing
Roller screw SpringMechanical Stops
Stroke adjustment
ACTUATION SYSTEM
A. Bertarelli EN/MME 26.05.2011 25
W-GLIDCOP THERMAL CONTACT
hc P( ) 1.55ks a
Rq
2 PE' a
0.94
Glidcop to WPressure 15 barhc = ~5000 kW/m2.K
0 5 105 1 106 1.5 106 2 1060
2 103
4 103
6 103
8 103
hc P( )
P
26
27
A. Bertarelli EN/MME 26.05.2011 28
ID Task Name
2 LTC (DS Collimator Assy) In-house production3 Engineering9 QTC (By-pass Cryomodule)10 Design and drafting29 Drawings released30 Material Procurement35 Manufacturing36 Production Release Review37 Preparation38 Bus-bars39 Bus-bars Avai lable40 End covers (x12)41 Flat End Assy (Welded & T ested)42 Conical shells integrated with End Covers43 Machined components (Bottom tray, ancil laries …)44 Cold Vacuum components (Beam screens, plug-ins, …)45 Vacuum Vessel SubAssemblies (Cradle, Seagull Plate, Flat Covers)46 MLI Manufacturing47 Tools Manufacturing48 Components cleaning49 Leak tests of subcontracted subassies50 QTC 1111 QTC 1 ex-works (ready for SM18)112 SM18 electrical/cold tests113 Preparation for Instal lation (stripping)114 QTC 1 ready for installation transport115 QTC 2176 QTC 2 ex-works (ready for SM18)177 SM18 electrical/cold tests178 Preparation for intal lation (stripping)179 QTC 2 Ready for intallation transport180 QTC 3241 QTC 3 ex-works (ready for SM18)242 SM18 electrical/cold tests243 Preparation for intal lation (stripping)244 QTC 3 Ready for intallation transport245 QTC 4306 QTC 4 ex-works (ready for SM18)307 SM18 electrical/cold tests308 Preparation for intal lation (stripping)309 QTC 4 Ready for intallation transport310 QTC 5371 QTC 5 ex-works (ready for SM18)372 SM18 electrical/cold tests373 Preparation for intal lation (stripping)374 QTC 5 Ready for intallation transport
26/05
16/06
28/09METSO
NortemecanicaNortemecanica
NortemecanicaTE-VSC
NortemecanicaJehier
TE-VSCTE-VSC
25/04TE-MSC
30/05
19/11TE-MSC
10/01
03/12TE-MSC
24/01
04/06TE-MSC
09/07
18/06TE-MSC
23/07
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepQtr 2, 2011 Qtr 3, 2011 Qtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013 Qtr 3, 2013
5 LTC ex-works. The budget includes work provided by SU and VSC as embedded "service". Components provided by MSC, BI, VSC for the as-delivered product are not included. It does not include components added at a later stage, e.g. Vacuum valves and gauges, motorization, electronics etc.
Scope
Grand Total(To Be Provisioned)
Phase 1+
Updated design
1 TCP + Plan B (backup production in case industry fails). Material procurement for Plan A and for equipment added after delivery (supports, plugins, cabling, support stands, cradles etc. ) is not included in this budget even if done by MME.