Alcatel-Lucent GSM Merge G2 TC to 9125 TC BSC & TC Document Reconfiguration Method Release B10 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 1/32
Alcatel-Lucent GSM
Merge G2 TC to 9125 TC
BSC & TC Document
Reconfiguration Method
Release B10
3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 2/32
Status RELEASED
Short title MPI69 / MDR1
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel-Lucent.
BLANK PAGE BREAK
2 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 3/32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 4/32
Contents
4 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 5/32
Preface
Preface
Purpose This document describes how to merge G2 TC into 9125 TC.
It is applicable to BSS at technical release level B10.
What’s New In Edition 06
New section Declare the BSC at the 9125 TC Equipped with TC STM1-IP Subrack ( Section 2.3.3.1 ) is created.
In Edition 05
Update with the new equipment naming.
In Edition 04The following sections were updated:
Prerequisites (Section 1.2.1)
Site Specific Information (Section 1.2.2)
In Edition 03
Improvements were made in Restrictions (Section 1.1.3)
In Edition 02
Overall document quality was improved following an editorial review.Improvements were made in the following sections due to a system evolution:
Prerequisites (Section 1.2.1)
Site Specific Information (Section 1.2.2)
Overall document quality was improved following an editorial review.
First official release of the document for B10MR2.
In Edition 01
Overall document quality was improved following an editorial review.
First official release of the document for B10.
3BK 17430 0691 RJZZA Ed.06 5 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 6/32
Preface
Audience This document is intended for:
Field service technicians
Specialists
Project managers
Foremen.
6 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 7/32
Preface
Assumed Knowledge You must have a basic understanding of the following:
Planning:
Network architecture and reshuffling principles
Basic knowledge for scheduling.
Implementation:
Alcatel-Lucent operations and maintenance concepts for the BSS
9153 OMC-R operation
Equipment (BSC, BTS, MFS, TC) hardware configurations
Windows environment.
3BK 17430 0691 RJZZA Ed.06 7 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 8/32
Preface
8 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 9/32
1 Overview
1 Overview
This Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.
3BK 17430 0691 RJZZA Ed.06 9 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 10/32
1 Overview
1.1 Presentation
This scenario describes how to merge a G2 TC with an 9125 TC/ 9125 TCequipped with TC STM1–IP subrack.
After this procedure, the G2 TC must be dismantled at an appropriate time.
In case it is necessary to replace E1 links with STM1 or vice versa, see E1 to STM1 Configuration or STM1 to E1 Configuration , as needed.
This scenario does not cover the upgrade of an 9125 TC with TC STM1 board.If it is the case, first perform Upgrade 9125 TC with TC STM1 board .
1.1.1 Cases
The following cases apply:
C1: LCS activated on the BSS
C2: The BSS is multi GPU.
The scenario uses the configuration management rules specific to the 9153OMC-R.
1.1.2 Options
None.
1.1.3 Restrictions
This procedure does not handle BSC or TC extension.
10 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 11/32
1 Overview
1.1.4 Grouped Task Sequence
The following figure shows the grouped task sequence for this scenario.
Initial Checks
OMC−R TCMSC
Switch First Ater Mux Connection
Test Call Service
Test Call and GPRS Services
Change HR PRESENCE andTRAU LOUDNESS Parameters
Switch Other Ater Mux Connections
Final Checks
Figure 1: Merge G2 TC into 9125 TC
3BK 17430 0691 RJZZA Ed.06 11 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 12/32
1 Overview
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply:
The site is clean, tidy and easily reachable
The BSS is operational in release B10
If a new 9125 TC rack is needed, it must be installed and commissioned
before the operation. Note the TC rack number; it must be greater than
or equal to 5.
The generic transmission data settings for the 9125 TC are downloaded.
The newly inserted boards in an 9125 TC rack already in use are already
configured.
In the case of an X.25 connection routed through the Ater/A interface,
redundancy is mandatory.
12 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 13/32
1 Overview
1.2.2 Site Specific Information
You must have the following specific information to complete the scenario:
Site Preparation Specifications (SPS) with specific values for the Trau
Loudness parameter.
Site Preparation Specifications (SPS) with specific information on the
extraction point of X.25 connections, necessary for loading the right generic
transmission settings in the TC.
1.2.3 External Tasks
None.
3BK 17430 0691 RJZZA Ed.06 13 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 14/32
1 Overview
1.3 Scheduling
Time based on technical constraintsThe number of resources shown in the following table does not take intoaccount individual customer or safety requirements.
Grouped Task MSC BSC Impacted TC OMC-R Time/Task
Initial Checks - - - 1 ope.
(15 min.)
15 min.
Change TRAULOUDNESS Parameter
- - - 1 ope.
(1-7 min.)
1-7 min.
Switch First Ater Mux
Connection
1 ope.
(5 min.)
- 1 com.
(16 min.)
1 ope.
(54 min.)
64 min.
Test Call Service - - - 1 ope.
(10 min.)
10 min.
Switch Other Ater MuxConnections
1 ope.
(5 min./AterMux)
- 1 com.
(15 min.)
1 ope.
45 min. + 2min./NSVC (forGboFR) or 2min./SGSN
_IP_
ENDPOINT(for GboIP) +4 min./Ater Mux+ 3 min. 30sec./board
(60 min. + 2min./NSVC (forGboFR) or 2min./SGSN _IP_ ENDPOINT (forGboIP) + 4min./Ater Mux
+ 3 min. 30sec./board)
Test Call and GPRSServices
- - - 1 ope.
(10 min.)
10 min.
Final Checks - - - 1 ope.
(20 min.)
20 min.
TOTAL TIME 1 h 58 min. + 19 min./ Ater Mux + 2 min./GSL + 4 min./board + 2 min. /NS-VC(for GboFR) or 2 min./SGSN_IP_ENDPOINT (for GboIP)
ope. : OMC-R, TC or MSC operator
com. : Commissioning Team
14 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 15/32
1 Overview
1.4 Telecom/Supervision Outage and Operating Impact
The following table describes the traffic outage and loss of supervision causedby each grouped task.
Out.Ref. Grouped Task
Tel. /GPRS/ LCSOut
Tel. / GPRSRed Sup.Out
Oper.Impact Impacts...
- Initial Checks - - - - None.
- Change TRAULOUDNESS Parameter
- - - - None.
1, 2 Switch First Ater MuxConnection
- (1) 30 min. / (2) 33 min.
- - (1) CS Reduction
(2) GPRS Reduction
- Test Call Service - - - - None.
1, 2 or4, 3
Switch Other Ater MuxConnections
- / (4) 40min./ (3) 41min.
(1) 30min./AterMux / (2) 33min./Ater Mux
- - (1) CS Reduction
(2) GPRS Reduction
(3) LCS Outage, if lastGSL on BSS
(4) GPRS Outage, iflast GSL on BSS
- Test Call and GPRSServices
- - - - None.
- Final Checks - - - - None.
TOTAL TIME (4) 40 min.
(3) 41 min.
(1) 30min./AterMux
(2)33min./AterMux
-
3BK 17430 0691 RJZZA Ed.06 15 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 16/32
1 Overview
1.5 Resources
1.5.1 Tools
The following tables describe the necessary hardware tools, software tools,
and forms.
1.5.1.1 Hardware Tools
Item Part Number Use at ...
PC with CD-ROM reader and associated cables. - TC
Installation tools. - TC
Anti-static wrist strap. - TC
1.5.1.2 Software Tools
Item Part Number Use at ...
9125 TC Terminal. - TC
Customer documentation CD with the version associated with the currentdocument edition. Remember that the document you are reading cannot beused as a paper version. It is online documentation using hypertext linkswhich take you to other parts of a document on the same CD-ROM. All wordsin italics are hypertext links.
- TC,OMC-R
1.5.1.3 Forms
None.
1.5.2 Supplies
The following table describes the necessary supplies for moving a BSS from aTC to another.
Item Part Number Contents Use at ...
Site Documentation. - - TC, OMC-R
16 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 17/32
1 Overview
1.5.3 Applicable Documents
You must have the following documents or have electronic access to thefollowing documents:
B10 BSS Methods Handbook
BSS Configuration Handbook
BSS Surveillance Handbook
Network Reconfiguration Recommendations
9125 TC User Guide
Site Preparation Specifications (SPS)
3BK 17430 0691 RJZZA Ed.06 17 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 18/32
1 Overview
18 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 19/32
2 Scenario
2 Scenario
This Scenario presents all checks needed before beginning the scenario, andall detailed tasks to be performed on each site.
3BK 17430 0691 RJZZA Ed.06 19 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 20/32
2 Scenario
2.1 Before Going Onsite
Before going onsite, you must check that the following information and suppliesare available:
All Prerequisites (Section 1.2.1) are met
The customer is informed of the:
Date and time
Site name and address
Purpose of operation.
Personnel are available (refer to Scheduling (Section 1.3))
Site Specific Information (Section 1.2.2) is available
Tools (Section 1.5.1) are available and ready for operation
Supplies (Section 1.5.2) are available and ready for operationApplicable Documents (Section 1.5.3) are available.
Ensure that the technical release level of the delivered board is in accordancewith the BSS hardware technical release document.
Ensure that the method used at the BSS site is at the same level as at theOMC-R.
20 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 21/32
2 Scenario
2.2 Before You Start
2.2.1 Checks
Perform the following operations:
Check that all Prerequisites (Section 1.2.1) are met
Check the availability of all necessary Tools (Section 1.5.1) and Supplies
( Section 1.5.2)
Inform the operator.
Among the cases described in Cases (Section 1.1.1) and the options describedin Options (Section 1.1.2), identify which cases and options apply to you.
2.2.2 Required KnowledgeYou must be familiar with the following:
Safety Rules and Precautions
Telecom/Supervision Outage and Operating Impact (Section 1.4)
Reverse Procedure
Grouped Task Sequence (Section 1.1.4)
Operating Hints
How to document Faults and Anomalies .
3BK 17430 0691 RJZZA Ed.06 21 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 22/32
2 Scenario
2.3 Scenario Description
This section describes how to merge a G2 TC into an 9125 TC.
2.3.1 Initial Checks
Note Task Description Site To do Outage
CHECK Perform an Audit Alarm State on the BSS. OMC-R 5 min. None.
CHECK View Status of Managed Objects and Alarms (TC) and print them.
OMC-R 10 min. None.
2.3.2 Change TRAU LOUDNESS Parameter
The following operations must be repeated for each BSC or TC G2 rack.
You must adjust the ’TRAU Loudness’ (up and down) parameter according tothe site requirements.
Note Task Description Site To do Outage
OMC-R 1 min. NoneINPUT Modify Ater TRAU Loudness to set theright value.
Note:Modifying the TRAU LOUDNESS parameterautomatically launches a programming
transmission, but you can immediately start thenext task.
22 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 23/32
2 Scenario
2.3.3 Switch First Ater Mux Connection
You must take into account the following information before starting the tasksin this section:
Disconnect the first Ater Mux and the related A interfaces from the terminal
blocks of the G2 TC and then reconnect to the terminal blocks of the 9125TC on the BSC side and on the MSC side at the same time. The old SM
Adapt from the TC site (ASMC board) related to this Ater Mux is unplugged.
During this time, the MSC operator is advised to lock the CICs in order to
avoid alarms.
It is advisable to ensure GSL resource redundancy. If GSL/GPU redundancy
is not ensured, the Ater Mux carrying the GSL must belong to the second
part of the moved Ater Mux.
There is CS traffic outage when there are no more available N7s; otherwisethere is CS traffic reduction.There is GPRS outage when there are no more available GSL orNS-VC/SGSN_IP_ENDPOINT; otherwise there is GPRS reduction.
The following actions must be synchronized with the MSC in order to updatethe addresses of the reconnected Ater Mux and A Interfaces.
2.3.3.1 Declare the BSC at the 9125 TC Equipped with TC STM1-IP Subrack
This task refers to the 9125 TC equipped with TC STM1-IP subrack andbefore the merging procedure starts, it is necessary to declare the associatedBSCs in the TC-NEM.
Note Task Description Site To do Outage
- Declare the BSC associated to the 9125TC equipped with TC STM1-IP subrackin the TC NEM.
TC 6 min. None
2.3.3.2 Declare the 9125 TC at the OMC-R (if needed)
Note: This task refers to the 9125 TC equipped with TC STM1-IP subrack, and it hasto be performed if the 9125 TC was not previously declared at the OMC-R.
Note Task Description Site To do Outage
- If the 9125 TC was not previously declaredat the OMC-R, perform the task Declare an 9125 TC with TC-STM1 Boards to OMC-R..
OMC-R 6 min. None
3BK 17430 0691 RJZZA Ed.06 23 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 24/32
2 Scenario
2.3.3.3 Stop Traffic on First Ater Mux
Note Task Description Site To do Outage
- If this Ater Mux carries a GSL, Lock GSL. OMC-R 1 min. START2
OMC-R 5 min. + 2min. /AterMux
START1
Reduction2
- Shut Down Traffic on Ater Mux (WTC=4min.) on first Ater Mux.
Note: If the ATR carries a GSL, a warningmessage appears. Confirm the message tocontinue with the operation.
EXCH Inform the TC site that cabling can begin. OMC-R 1 min. Reduction1
Reduction2
2.3.3.4 Cable First Ater Mux
Note: In case it is necessary to replace E1 links with STM1 see E1 to STM1Configuration . In order to avoid outage, modify in the configuration file onlythe links that are moved at this step.
Note Task Description Site To do Outage
TC 15 min. Reduction1
Reduction2
- For the first Ater Mux link: disconnectthe following from the G2 TC andreconnect them to the 9125 TC:
Four A interface PCMs between theTC and the MSC
One Ater Mux PCM between the TC
and the BSC (MFS).
Note: Disconnection and reconnection areperformed simultaneously on the Ater Mux andA interface sides by both commissioners tominimize traffic reduction.
- Unplug the concerned ASMC board fromthe G2 TC.
TC 30 sec. Reduction1
Reduction2
EXCH Inform the OMC-R site when cabling isfinished.
TC 1 min. Reduction1
Reduction2
2.3.3.5 Set Traffic on First Ater Mux
Note Task Description Site To do Outage
- Unlock Traffic on Ater Mux (first AterMux).
OMC-R 1 min. + 2min./ Ater Mux
END1
Reduction2
- Lock Board (the concerned ASMC board),using Display Related TC Boards .
OMC-R 30 sec. / board
Reduction2
24 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 25/32
2 Scenario
Note Task Description Site To do Outage
OMC-R 3 min. / board START1
END1
Reduction2
- Unlock Board (the concerned ASMCboard), using Display Related TC Boards .
Note:This operation is necessary to force thedownload of the new transmission settings.
- If the GSL was locked, Unlock GSL on theAter Mux.
OMC-R 1 min. END2
Automaticactions
30 min. None.- Wait for the TC auto-identification, ahardware audit triggered after 15 minutesand transmission programming.
Note:At the end of this step, in the ’BSSUSM’window of the OMC-R, the new MT120 board(related to the first Ater Mux) is visible.
When the Abis/Ater view is not up to date!
It will be reloaded message appears, click on[ OK ].
2.3.4 Test Call Service
If tests are unsuccessful, apply the Reverse Procedure (Section 2.4).
Note Task Description Site Time/Task Outage
OMC-R 10 min. None.CHECK Display USD Detailed DTC Information to checkin the DTC report if CS calls are made on movedAter Mux and print the report. The Reverse Procedure (Section 2.4) can
be performed from this point onwards.
2.3.5 Switch Other Ater Mux Connections
Repeat the following operations for each Ater Mux.
Disconnect the Ater Muxes from the terminal blocks of the G2 TC and thenreconnect them to the terminal blocks of the 9125 TC on the BSC side and
on the MSC side at the same time.During this time, the MSC operator is advised to lock the CICs in order toavoid alarms.
The following actions must be synchronized with the MSC in order to updatethe addresses of the reconnected Ater Mux and A Interfaces.
3BK 17430 0691 RJZZA Ed.06 25 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 26/32
2 Scenario
2.3.5.1 Stop Traffic on Other Ater Mux
Note Task Description Site To do Outage
- If the Ater Mux supports the lastoperational GSL on the BSS, Lock GPRS
Traffic on BSS .
OMC-R 1 min. START4
C2 If the Ater Mux supports the last GSL onthe GPU in the case of multi-GPU, Lock GPRS on cells from NSEI for all cellsmapped on this GPU.
OMC-R 1 min. START2
- If the operation to lock the GPRS on theBSS or on cells was already performed
for GboFR, Lock NS-VC for related
NS-VC
for GboIP, Lock SGSN_IP_ENDPOINT
for related SGSN_IP_ENDPOINT.
OMC-R 1 min./NS-VC(for GboFR) or1 min./SGSN_ IP_ ENDPOINT
(for GboIP)
Outage4 orReduction2
C1 If the Ater Mux supports the lastoperational GSL on BSS, ’Disable LCSon BSS’.
OMC-R 1 min. Outage4 orReduction2
START3
- If this Ater Mux carries a GSL Lock GSL. OMC-R 1 min. START2
OMC-R 5 min. + 2min./Ater Mux
START1
Reduction2
- Shut Down Traffic on Ater Mux (WTC=4min.) on each Ater Mux to bemoved.
Note:If the Ater Mux supports the last activeX.25 connection or the last active N7, the AterMux cannot be locked. Traffic is cut when thecabling is disconnected.
If the ATR carries a GSL, a warning messageappears. Confirm the message to continue withthe operation.
EXCH Inform the TC site that cabling can begin. OMC-R 1 min. Reduction1
Reduction2
26 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 27/32
2 Scenario
2.3.5.2 Cable Other Ater Mux
Note: In case it is necessary to replace E1 links with STM1 see E1 to STM1Configuration . Modify in the configuration file the rest of the links that remainedto be moved at this step.
Note Task Description Site To do Outage
TC 15 min. Reduction1
Reduction2
- For each Ater Mux link to be recabled:disconnect the following from the G2 TCand reconnect them to the 9125 TC:
Four A Interface PCMs between the
TC and the MSC
One Ater Mux PCM between the TC
and the BSC (MFS).
Note:Disconnection and reconnection areperformed simultaneously on the Ater Mux andA interface sides by both commissioners tominimize traffic reduction.
EXCH Inform the OMC-R site when cabling is
finished.
TC 1 min. Reduction1
Reduction2
2.3.5.3 Set Traffic on Other Ater Mux
Note Task Description Site To do Outage
- Unlock Traffic on Ater Mux . OMC-R 1 min. + 2min./Ater Mux
END1
Reduction2
- Lock Board (the concerned ASMC board),using Display Related TC Boards .
OMC-R 30 sec./board Reduction2
OMC-R 3 min./board START1
END1
Reduction2
- Unlock Board (the concerned ASMCboard) using Display Related TC Boards .
Note:This operation is necessary to force thedownload of the new transmission settings.
- If GPRS was already locked on the BSS,Unlock GPRS Traffic on BSS .
OMC-R 1 min. END2
C2 If GPRS was already locked on cells,Unlock GPRS on Cells from NSEI .
OMC-R 1 min. END2
- In the case of
GboFR, Unlock NS-VC for the related
Ater Mux
GboIP, Unlock SGSN_IP_ENDPOINT
for the related Ater Mux
OMC-R 1 min./NSVC(for GboFR) or1 min./SGSN
_IP_ ENDPOINT(for GboIP)
Reduction2
- If the GSL was already locked, Unlock
GSL on the Ater Mux.
OMC-R 1 min. END2
3BK 17430 0691 RJZZA Ed.06 27 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 28/32
2 Scenario
Note Task Description Site To do Outage
C1 If the Ater Mux supports the lastoperational GSL on the BSS, ’Enable LCSon BSS’.
OMC-R 1 min. END3
Automaticactions
30 min. None.- Wait for TC auto-identification, a hardwareaudit triggered after 15 minutes andtransmission programming.
Note: At the end of this step, in the ’BSSUSM ’window of the OMC-R, the new MT120 board(related to all Ater Mux) is visible.
When the Abis/Ater view is not up to
date! It will be reloaded messageappears, click on [ OK ].
2.3.6 Test Call and GPRS Services
If tests are unsuccessful, apply the Reverse Procedure (Section 2.4).
Note Task Description Site Time/Task Outage
OMC-R 10 min. None.CHECK Perform CS and GPRS calls to test theAter Mux.
Display USD Detailed DTC Information tocheck in the DTC report if CS and GPRScalls are made on each moved Ater Mux
and print the report.
The Reverse Procedure (Section 2.4) can beperformed from this point onwards.
2.3.7 Final Checks
Note Task Description Site To do Outage
CHECK Perform an Audit Alarm State on the BSSand compare alarms and states withthose generated during the Initial Checks ( Section 2.3.1).
OMC-R 10 min. None.
CHECK View Status of Managed Objects and Alarms (TC) and compare with printedvalues from Initial Checks (Section 2.3.1).
OMC-R 10 min. None.
28 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 29/32
2 Scenario
2.4 Reverse Procedure
Repeat the following operations for every BSC rack.
2.4.1 Stop Traffic on Ater Mux
Note Task Description Site To do Outage
OMC-R 1 min. + 2min./Ater Mux
-- Lock Traffic on Ater Mux (on all Ater Muxlinks to be recabled).
Note:If the Ater Mux supports the last activeX.25 connection or the last active N7, the AterMux cannot be locked. Traffic is cut when thecabling is disconnected.
If the ATR carries a GSL, a warning messageappears. Confirm the message to continue withthe operation.
2.4.2 Cable Moved Ater Mux
Disconnect all the Ater Mux links and related A interfaces to be recabledfrom the terminal blocks of the 9125 TC and then reconnect them to theterminal blocks of the G2 TC. Reconnect the BSC side and the MSC side atthe same time.
Note: In case it is necessary to replace STM1 links with E1 see STM1 to E1Configuration .
Note Task Description Site To do Outage
- Plug the ASMC board that was unpluggedduring the scenario into the G2 TC rack.
TC 30 sec. -
- For all Ater Mux links to be recabled:Disconnect the following from the 9125 TCand reconnect them to the G2 TC:
Four A Interface PCMs between the TCand the MSC
One Ater Mux PCM between the TC
and the BSC (MFS).
TC 15 min. -
3BK 17430 0691 RJZZA Ed.06 29 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 30/32
2 Scenario
2.4.3 Set Traffic on Ater Mux
Note Task Description Site To do Outage
- Unlock Traffic on Ater Mux (on each
recabled Ater Mux).
OMC-R 1 min. + 2
min./Ater Mux
-
- Lock Board (all MT120 boards related tothe recabled Ater Muxs) using Display Related Boards TC .
OMC-R 30 sec./board -
- Unlock Board (all MT120 boards related tothe recabled Ater Mux links) using Display Related TC Boards .
OMC-R 3 min./board -
Automaticactions
30 min. -- Wait for TC auto-identification, a thehardware audit triggered after 15 minutesof tempo and transmission programming.
Note:At the end of this step, in the ’BSSUSM’window of the OMC-R, the ASMC and ATBXboards (related to all Ater Mux) are visible.
When the Abis/Ater view is not up to
date! It will be reloaded messageappears, click on [ OK ].
- Lock TC-Adapt (four related ATBX boardsfor each recabled Ater Mux), using Lock Board .
OMC-R 30 sec./board -
- Unlock TC-Adapt (four related ATBX
boards for each recabled Ater Mux), usingUnlock Board .
OMC-R 2 min./board -
2.4.4 Test Call and GPRS Services
Note Task Description Site To do Outage
OMC-R 10 min. -CHECK Perform CS and GPRS calls to test themodified Ater Mux.
Display USD Detailed DTC Information tocheck in the DTC report if CS and GPRS callsare made on each recabled Ater Mux andprint the report.
Note:Several packets must be transferred.Resource allocation is not performed at mobileconnection but at data transfer.
30 / 32 3BK 17430 0691 RJZZA Ed.06
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 31/32
2 Scenario
2.4.5 Final Checks
Note Task Description Site To do Outage
CHECK Perform an Audit Alarm State on the BSS
and compare alarms and states withthose generated during the Initial Checks ( Section 2.3.1).
OMC-R 10 min. -
CHECK View Status of Managed Objects and Alarms (TC) and compare with printedvalues from the Initial Checks (Section 2.3.1).
OMC-R 10 min. -
3BK 17430 0691 RJZZA Ed.06 31 / 32
8/12/2019 TC Document
http://slidepdf.com/reader/full/tc-document 32/32
2 Scenario
BLANK PAGE BREAK