Top Banner

of 169

Tariff Order WBSEDCL

Mar 02, 2016

Download

Documents

Sandip Sarkar

3
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • ORDER OF THE

    WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR 2011 2012 AND 2012 2013

    IN CASE NO: TP 53 / 12 13

    IN RE THE TARIFF APPLICATION OF THE WEST BENGAL

    STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED

    FOR THE YEARS 2011 2012, 2012 2013 AND 2013 2014

    UNDER SECTION 64(3)(a) READ WITH SECTION 62(1) AND

    SECTION 62(3) OF THE ELECTRICITY ACT, 2003

    Date : 01.12.2012

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    CHAPTER 1 INTRODUCTION

    West Bengal Electricity Regulatory Commission 2

    1.1 The West Bengal Electricity Regulatory Commission (hereinafter referred to as the

    Commission) was constituted by the Government of West Bengal in the year 1999 in

    terms of section 17 of the Electricity Regulatory Commissions Act, 1998, now

    repealed by section 185 of the Electricity Act, 2003 (hereinafter referred to as the

    Act) which came into force with effect from 10.06.2003. The first proviso to section

    82(1) of the Act has ensured continuity of all the State Electricity Regulatory

    Commissions, which were established by a State government under section 17 of

    the 1998 Act (and some other enactments) and functioning as such immediately

    before coming into force of the Act and shall be the State Commission for the

    purpose of the Act.

    1.2 The functions of a State Commission have been specified in Section 86 of the

    Electricity Act, 2003. One of the main functions of a State Commission relates to

    determination of tariff for generation, supply, transmission and wheeling of electricity,

    wholesale, bulk or retail, as the case may be, within a State. Further, Section 62(1)

    of the Act also requires the appropriate Commission to determine the tariff in

    accordance with the provisions of the Act, for supply of electricity by a generating

    company to a distribution Licensee, for transmission, for wheeling as also for retail

    sale of electricity.

    1.3 The Commission has, therefore, all the powers and authority under the Electricity

    Act, 2003 to determine the tariff, as laid down in the Act.

    1.4 WBSEDCL is deemed to be licensee under the Electricity Act, 2003 in terms of fifth

    proviso to Section 14 of the Act. The Commission determined the tariff of WBSEDCL

    for the first control period (2007 2008) and the second control period (2008 2009,

    2009 2010 and 2010 2011) under the then regulations related to tariff.

    1.5 West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff)

    Regulations, 2011 has come into effect with effect from 25th April, 2011. The said

    Tariff Regulations, 2011 was further amended by notifying the West Bengal

  • Tariff Order of WBSEDCL for the year 2011 2012 2012 2013

    West Bengal Electricity Regulatory Commission

    3

    Electricity Regulatory Commission (Terms and Conditions of Tariff) (Amendment)

    Regulations, 2012 in the extra ordinary edition of The Kolkata Gazette dated 27th

    August, 2012.

    1.6 A generating Company or a licensee, whose tariff is to be determined by the

    Commission as per the provisions of the Act, is now required to submit their

    application for determination of tariff for the ensuing years of the third control period

    under the multi-year tariff framework complying with the provisions of the West

    Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff)

    Regulations, 2011 (hereinafter to be referred as Tariff Regulations). Though as per

    the Tariff Regulations the last date for submission of the application to the

    Commission by a generating company or a licensee for determination of tariff for the

    third control period comprising three years from 2011 2012 to 2013 2014

    (hereinafter referred to as the third control period) was 28.5.2011, the Commission,

    after considering the prayers of WBSEDCL for extension of date for submission of

    the aforesaid application to the Commission, extended the date for the purpose upto

    28th July, 2011. Subsequently, WBSEDCL submitted application for extension of date

    time to time, latest on 31st October, 2011. WBSEDCL further prayed in their tariff

    application that on receiving the new tariff structure arising out of finalization of the

    plan for subsidization of certain category of the consumers by State Government and

    re-determination of tariff in pursuance to Appellate Tribunal of Electricitys order

    dated 4th April, 2011, and in view of the requirement to satisfy ERP (Enterprise

    Resource Planning) based billing system, WBSEDCL was required some time to

    finalize the tariff application for the third control period. They further prayed to be

    condoned for the delay in submission of tariff application.

    1.7 WBSEDCL, complying with the provisions of the Tariff Regulations, prepared the

    application for determination of its tariff for the third control period and submitted the

    same to the Commission on 5th April, 2012 which was considered by the Commission

    and numbered as TP-53/12-13.

  • Tariff Order of WBSEDCL for the year 2011 2012 2012 2013

    West Bengal Electricity Regulatory Commission

    4

    1.8 After admission of the application, WBSEDCL was directed to publish the gist of the

    tariff application, as approved by the Commission, in the newspapers and also in

    their website, as specified in the Tariff Regulations. The gist was, accordingly,

    published simultaneously on 10th April, 2012 in Pratidin, The Hindu Business Line,

    Ekdin and also in The Times of India. The gist along with the tariff application was

    also posted in the website of WBSEDCL. The publication invited the attention of all

    interested parties, stake holders and the members of the public to the application for

    determination of tariff of WBSEDCL for the third control period and requested for

    submission of suggestions, objections and comments, if any, on the tariff application

    to the Commission by 14th May, 2012 at the latest. Opportunities were also afforded

    to all to inspect the tariff application and take copies thereof.

    1.9 Objections to / comments on the aforementioned tariff petition of WBSEDCL for the

    third control period were received by the Commission from the following objectors

    within the stipulated time i.e., 14th May, 2012.

    1. Jayashree Textiles, A unit of Aditya Birla Nuvo Ltd.

    2. Hooghly Chamber of Commerce & Industry

    3. Eastern India Textile Mills Association

    4. The West Bengal Cold Storage Association

    5. Eastern Railway

    6. South Eastern Railway

    7. ABECA

    8. Balaji Paper and Newsprint Pvt. Ltd.

    9. Eastern India Textile Mills Association

    10. Hooghly Alloys & Steels Co. Pvt. Ltd.

    11. Chief Engineer, Kolkata Zone, MES

    12. ARVAC Forge Cast Ltd

    1.10 Objections and suggestions on the tariff application in question received by the

    Commission within the stipulated period i.e. 14th May, 2012 have been dealt with

    separately in Chapter 3.

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    CHAPTER 2 THE CASE OF WBSEDCL

    West Bengal Electricity Regulatory Commission 5

    2.1 West Bengal State Electricity Distribution Company Limited (WBSEDCL) in its tariff

    petition has claimed that the total distribution equity of WBSEDCL in terms of

    restructuring order of State Government was Rs.222300.00 lakh as on 01.04.2007.

    The equity added during the year 2008 - 2009 was Rs.8471.99 lakh being the assets

    of West Bengal Rural Energy Development Corporation Limited (in short

    WBREDCL) as handed over to WBSEDCL as per Government Order no. 100-

    PO/O/III/4M-12/2005 dated 20.03.2009 and during the year 2009 2010 was Rs.

    25068.01 lakh for restructuring of WBREDCL as per Government Order No. 108-

    PO/O/III/4M-12/2005 dated 31.03.2009. Considering the same, equity base

    considered by the petitioner at the beginning of the year 2010 - 2011 has been

    arrived at Rs.255840.00 lakh. No equity addition has been projected by the

    applicant during the years 2011 2012, 2012 2013 and 2013 2014. WBSEDCL

    has claimed permitted return on the average equity base for the years 2011 2012,

    2012 2013 and 2013 2014 in accordance with the provision of the Tariff

    Regulations as the entire equity.

    2.2 WBSEDCL has claimed to have taken the following measures to reduce the

    distribution loss (both technical and commercial):

    (a) Regular monitoring of revenue, collection and distribution loss,

    (b) Conduct of raids by Security and Loss Prevention Wing,

    (c) Introduction of High Voltage Distribution Supply (H.V.D.S.) primarily for power

    supply to irrigation consumers,

    (d) Installation of meters in the premises of un-metered irrigations, Kutir Jyoti /

    Lokdeep consumers and street light points,

    (e) To facilitate energy audit mapping and documentation of entire power

    network of WBSEDCL, Geographical Information System (GIS) has been

    stated to have been taken up and is under progress,

    (f) Spot billing facility for all categories of L & MV consumers under many

    customer care centres is stated to be already in place and such billing facility

    has been envisaged to be extended further,

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    6

    (g) Implementation of distribution transformer metering to locate loss prone

    areas,

    (h) Restructured Accelerated Power Development and Reform Programme (in

    short RAPDRP) (Part A) for 62 towns are under progress for installation of

    IT infrastructure for assessment and monitoring of loss on regular basis,

    (i) R-APDRP (Part B) for 45 towns are also to be taken up shortly for reducing

    AT&C loss of those towns.

    2.3 WBSEDCL has submitted that projection of the energy balance has been arrived

    based on the estimated consumption, loss in distribution system of WBSEDCL and

    loss in transmission system of WBSETCL at the normative level as per Tariff

    Regulations. They also submitted that the petitioner has to consider the loss in

    central and state grid, as applicable.

    2.4 WBSEDCL has claimed that with fast growing expanding distribution network,

    additional consumers are being added with WBSEDCLs system during last few

    years. WBSEDCL states that based on the trend of increase of consumers in last five

    years, consumer strength of WBSEDCL has been projected for the years 2011

    2012, 2012 2013 and 2013 2014.

    2.5 Accordingly, 10636.28 MU has been projected to be consumed by the consumers

    under L&MV category in the year 2011 2012. Under the same category in the year

    2012 2013 and 2013 2014 the petitioner has projected the consumption under

    the same category to be 11719.76 MU and 12926.69 MU respectively. Under the

    HV & EHV category consumption in the year 2011 2012 has been projected to be

    8425.50 MU while under the same category 9332.44 MU and 10340.24 MU

    respectively have been projected to be the consumption during the years 2012

    2013 and 2013 2014.

    2.6 Total sale of energy to own consumers of WBSEDCL has been projected as

    19061.78 MU in the year 2011 2012, 21052.20 MU in the year 2012 2013 and

    23266.93 MU in the year 2013 2014. T&D loss has been projected at a level of

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    7

    24.93% for the year 2011 2012 but considered on the normative basis at a level of

    17.75% and 17.50% respectively for the years 2012 2013 and 2013 2014.

    2.7 The petitioner has projected sale of total energy to other licensees like CESC, DPL

    and DPSCL at a level of 1270.00 MU, 2308.66 MU and 2875.92 MU respectively in

    the years 2011 2012, 2012 2013 and 2013 2014. The projection of sale of

    energy to licensees has been stated to have been made on the basis of present

    trend of drawal by CESC upto February, 2012, the present trend of drawal by DPL

    and as per projection given by DPSCL in the MYT application for third control period.

    2.8 In terms of an agreement signed between the Govt. of W.B and Govt. of Sikkim the

    petitioner has claimed that 40 MU of energy being 20% of the sent out generation

    from Rammam Hydel station Stage-II shall be supplied to Sikkim each year of the

    control period.

    2.9 Sale of incidental surplus energy to the persons other than consumers and licensee

    during 2011 2012, 2012 2013 and 2013 2014 has been estimated by the

    petitioner to be at a level of 657.00 MU, 3649.00 MU and 2005.00 MU respectively.

    WBSEDCL also considered 1283.00 MU of power in the year 2011 2012 only

    towards banking of power through swap arrangement without selling due to low

    market price or non-availability of buyer to purchase power through cash arising out

    of volatile market condition. The above considerations have been made taking into

    account surplus energy to be made available from the new projects / extension

    projects of WBPDCL / DPL after meeting the requirement of the own consumers, the

    licensees of the State & Government of Sikkim and considering the energy required

    in the pumping mode of PPSP.

    2.10 Sent out generation available from the hydel power stations of WBSEDCL has been

    projected to be 405.856 MU in 2011 2012, 442.433 MU in 2012 2013 and 442.53

    MU in 2013 2014. Out of the two main hydel station of WBSEDCL namely

    Rammam and Jaldhaka, Rammam is working at reasonably high PLF. The

    generation at Jaldhaka was suspended during 2009 2010 and 2010 2011 due to

    renovation and modernization work. However, according to WBSEDCL, the

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    8

    generation at Jaldhaka has started during the year 2011 2012. It is also submitted

    by WBSEDCL that the installation of a new unit of 9 MW capacity at stage-I of

    Jaldhaka Hydel Power Station is expected to be completed by July, 2012 thereby

    enhancing the capacity of Stage I to 36 MW from the existing capacity of 27 MW.

    The generation at TCF Hydel Power Station as stated by the petitioner, cannot be

    achieved by WBSEDCL at the designed value stated to be due to constraints

    towards release of 330 cusec of water as per DPR for non-completion of Dauk-nagar

    Main Canal by I & W Department and frequent shut down of Main Canal for long

    periods. Annual generation at PPSP at a level of 850.00 MU during the years 2012

    2013 and 2013 2014 has been estimated by the petitioner and has been said to be

    according to the system requirement during peak hours considering optimum

    utilization of the surplus energy mainly during off peak hours. However, for the year

    2011 2012, the same has been considered at 749.244 MU as per generation trend

    upto February, 2012. WBSEDCL is maintaining diesel generation plant only at

    Rudranagar in Sagar Island. Energy available from this diesel generating station has

    been estimated at a level of 0.88 MU, during all the ensuing years of third control

    period.

    2.11 Gross generation available from renewable and co-generation sources, as per

    WBSEDCL, has been estimated to be 116.03 MU, 150.30 MU and 150.30 MU during

    the years 2011 2012, 2012 2013 and 2013 2014, respectively.

    2.12 To discharge the function of a distribution licensee, WBSEDCL continues to

    purchase power in the same manner as was being followed by erstwhile WBSEB

    from different agencies namely West Bengal Power Development Corporation Ltd.

    (WBPDCL), The Durgapur Projects Ltd. (DPL), Dishergarh Power Supply

    Corporation Ltd. (DPSCL), Damodar Valley Corporation (DVC), National Thermal

    Power Corporation Ltd. (NTPC), National Hydel Power Corporation (NHPC) and

    Power Trading Corporation (PTC). It is also submitted by WBSEDCL that

    conventional power will also be purchased directly from the new units of WBPDCL,

    NTPC, NHPC, other generators and from electricity traders to meet the system

    demand of WBSEDCL during the ensuing years of the third control period.

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    9

    WBSEDCL will also purchase power from different renewable and co-generation

    sources of energy during the years of the third control period.

    2.13 The planning of power purchase has been claimed by WBSEDCL to have been done

    keeping in view the following aspects.

    (a) Estimated system demand for the ensuing years based on the projected load

    growth.

    (b) Maximum generation that may be available from the hydel power stations of

    WBSEDCL.

    (c) Commitment to meet the peak system demand.

    (d) Requirement of pumping energy for optimum utilization of PPSP to meet the

    system demand.

    2.14 WBSEDCL claimed that besides purchasing power through grid system, they will

    also purchase some quanta of power in radial mode from DVC at Asansol, Burdwan

    and other areas, from DPL (at 33 KV & 11 KV) in and around Durgapur area and

    from DPSC (at 11 KV) at Asansol area, Govt. of Sikkim (at 11 KV) at Rangpoo area

    and WBREADA (11 KV) at Frezerganj area for catering its own consumers during

    the years under third control period.

    2.15 It has been claimed by the petitioner that while computing the quantity of purchase of

    power from WBPDCL during the ensuing years under third control period, they have

    considered the net energy available to WBSEDCL from all the generating stations of

    WBPDCL based on the actual performance upto February, 2012, excepting BKTPS

    stage-II and STPS (Units V & VI). However, as stated by WBSEDCL, for BKTPS

    stage II and STPS (Units V & VI), the PAF is considered as per the norms due to

    the fact that the performance of these power stations during the year 2011 2012

    was nearer to the normative PAF.

    2.16 WBSEDCL has claimed that the energy charge and capacity charges for all the

    generating stations of WBPDCL are considered based on the following parameters:

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    10

    a) The capacity charges for all power stations of WBPDCL for the year 2012 2013

    and 2013 2014 have been estimated based on norms given in the Tariff

    Regulations.

    b) For the year 2011 2012, the capacity charge and energy charge including

    Monthly Fuel Cost Adjustment are considered as per actual upto February 2012

    and capacity charge rate and energy charge rate including MFCA for March 2012

    are considered from that of February 2012.

    c) For the year 2012 2013, the energy charge rate is considered as per energy

    charge rate including MFCA of February, 2012.

    d) Energy charge rate for the year 2013 2014 is considered with annual escalation

    rate of 6.66% as provided for indigenous coal supply in CERC notification no.

    Eco 1/2011-CERC dated 31.03.2011 over the energy charge rate of 2012

    2013.

    2.17 WBSEDCL has estimated own consumption at the offices and substations for 2011

    2012, 2012 2013 and 2013 2014 at 40 MU, 42 MU and 44 MU respectively.

    2.18 Considering the projected sent out generation from its own generating stations,

    power purchase from different agencies and the projected sales, energy

    consumption at own premises, WBSEDCL has projected the energy balance for the

    years 2011 2012, 2012 2013 and 2013 2014 also.

    2.19 WBSEDCL submitted that considering the programme taken during the year 2011

    2012 (Upto February, 2012), they have projected 1190.00 MU and 834.55 MU to be

    received through power swap-in during the years 2011 2012 and 2012 2013

    respectively. WBSEDCL also projected the short term power purchase to the tune of

    990.00 MU, 364.55 MU and 1000.00 MU for the years 2011 2012, 2012 2013

    and 2013 2014 respectively mostly during the months March and April in order to

    bridge up the gap between supply of power and system demand which usually

    occurs during the months mentioned above.

    2.20 The petitioner has projected Rs.848522.00 lakh as total power purchase cost for the

    year 2011 2012 while for the years 2012 2013 and 2013 2014 the power

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    11

    purchase cost has been estimated to be Rs.1067741.00 lakh and Rs.1201642.00

    lakh respectively. This power purchase cost includes the cost of purchase of

    estimated quantum of infirm power from the units under stabilization.

    2.21 Transmission charges payable to WBSETCL for the energy required to be

    transmitted by the petitioner through WBSETCL system has been projected as Rs.

    98306.44 lakh for the year 2010 2011. Rs. 99654.57 lakh and Rs. 111121.04 lakh

    have been projected for the years 2012 2013 and 2013 2014 respectively.

    However, WBSEDCL has not claimed any amount for SLDC charges during the

    ensuing years under the third control period.

    2.22 An amount of Rs. 92001.70 lakh has been estimated as employees cost for the year

    2011 - 2012. For the years 2012 2013 and 2013 2014 employees cost have

    been projected as Rs. 93554.18 lakh and Rs. 99407.93 lakh respectively.

    2.23 The petitioner has considered a D.A hike @ 9% each year for the third control period

    i.e., 2011 2012, 2012 2013 and 2013 2014. Moreover, increase in pay in

    respect of employee cost has been considered @ 3% as per normal increment over

    basic and grade pay for the ensuing years 2011 2012, 2012 2013 and 2013

    2014. WBSEDCL further claimed that terminal benefits are reduced in the ensuing

    years 2011 2012, 2012 2013 and 2013 2014 as the service of newly recruited

    employees are not covered under the pension scheme of WBSEDCL. The

    capitalization rate of employee cost is considered 100% for RE works and 15% for all

    other Non-RE works.

    2.24 The petitioner has projected Repair & Maintenance (R&M) cost including

    consumables for the year 2011 2012 to be Rs.16911.80 lakh. WBSEDCL has

    claimed that distribution assets of WBSEDCL are increasing rapidly due to RGGVY

    programme and other work such as R-APDRP Part A, feeder segregation work etc.

    of WBSEDCL. WBSEDCL has added various distribution assets and generation

    assets for its generating stations in the year 2011 2012. In order to deliver power

    with reasonable quality parameters and to reduce instances of outages for the widely

    scattered large consumer base, the expenditure of R & M works of WBSEDCL has

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    12

    been increased in the year 2011 2012 mainly due to increase in expenditure for

    maintenance of line, cables and networks. For the years 2012 2013 and 2013

    2014 the petitioner has claimed to have estimated the R&M cost following the actual

    trend upto December, 2011 and has projected Rs.18617.32 lakh for the year 2012

    2013 and Rs.20498.58 lakh for the year 2013 2014.

    2.25 Rs. 8772.59 lakh has been estimated and claimed by the licensee as administration

    and general expenses for the year 2011 2012. The petitioner has further tried to

    justify this expenditure which is stated to be due to increase of distribution network

    and consumer strength and to fulfill the requirement of the large consumer strength,

    WBSEDCL has to introduce different services, besides existing facilities, following

    the guidelines given in the Regulations to match the requirement of large consumer

    base. Due to shortage of staff, WBSEDCL has claimed to have decided to outsource

    some of its services and the estimated expenditure of Rs. 16414.24 lakh has been

    considered for the year 2011 2012 to meet the cost of outsourcing. For the years

    2012 2013 and 2013 2014, Rs. 24554.88 lakh and Rs. 29565.45 lakh

    respectively has been estimated by the licensee as cost of outsourcing considering

    growth of those activities and actual upto December, 2011.

    2.26 The petitioner has claimed provision for bad debt to the tune of Rs. 85.80 lakh, Rs

    94.38 lakh and Rs. 103.82 lakh respectively for the years 2011 2012, 2012 2013

    and 2013 2014 on normative basis as per provisions of regulations of the Tariff

    Regulations.

    2.27 The petitioner has projected capitalization of expenses for employees cost,

    administrative and other expenditure and other finance charges under the

    construction activities following the existing policy of WBSEDCL for the years 2011

    2012, 2012 2013 and 2013 2014.

    2.28 WBSEDCL has also claimed an amount of Rs. 3025.00 lakh for 2011 2012, Rs.

    3675.00 lakh for 2012 2013 and Rs. 4008.00 lakh for 2013 2014 respectively for

    establishing and maintaining communication network set up for the complaint

    management mechanism as per West Bengal Electricity Regulatory Commission

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    13

    (Standard of Performance of Licensee Relating to Consumer Services) Regulations,

    2010.

    2.29 The capitalization of interest during the years 2011 2012, 2012 2013 and 2013

    2014 has been projected following the same policy.

    2.30 Cost of depreciation of assets of WBSEDCL which will be in service during the year

    2011 2012 has been stated to have been computed by the petitioner at Rs.

    33259.30 lakh on the basis of the methodology stipulated in the Schedule A of the

    Tariff Regulations of WBERC. The detail of the calculation of depreciation has been

    given in the prescribed format in Volume II of their petition. Depreciations for the

    years 2012 2013 and 2013 2014 have been projected as Rs. 36779.07 lakh and

    Rs. 40694.00 lakh respectively.

    2.31 WBSEDCL has projected Rs. 37295.88 lakh towards interest on borrowed capital,

    Rs. 13005.00 lakh towards interest on Bonds and Rs. 603.64 lakh towards other

    finance charges for the year 2011 2012. Similarly, for the years 2012 2013 and

    2013 2014, they have projected Rs. 38578.10 lakh and Rs. 38879.02 lakh as

    interest on borrowed capital, Rs. 13005.00 lakh and Rs. 13005.00 lakh towards

    interest on Bond and Rs. 625.46 lakh and Rs. 651.88 lakh towards other finance

    charges, respectively. The petitioner has provided the computations showing actual

    amounts of interest chargeable in revenue accounts in the Form-C to Annexure 1

    in Volume II of their petition.

    2.32 WBSEDCL claimed that while computing the interest on loan, they have considered

    a new loan of Rs. 106600.00 lakh to be taken in the ensuing years under the third

    control period for the purpose of procurement of meter and other materials for

    extending distribution service level network.

    2.33 WBSEDCL claimed that interest amount payable to consumers on the security

    deposit amount in the ensuing years 2011 2012, 2012 2013 and 2013 2014

    has been estimated as per existing procedure on the estimated security deposit of

    those years computed based on sale growth and tariff growth of respective year.

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    14

    WBSEDCL has projected Rs. 2870.44 lakh, Rs. 3315.31 lakh and Rs. 3829.19 lakh

    for the ensuing years of 2011 2012, 2012 2013 and 2013 2014 respectively.

    2.34 Regarding interest on working capital requirement, WBSEDCL has submitted that,

    based on the directive of the Commission vide paragraph 8.11 of its tariff order for

    2008 2009, they have not considered any working capital for the year 2011 2012

    but has considered Rs. 18579.00 lakh and Rs. 35470.70 lakh for the years 2012

    2013 and 2013 2014 respectively to meet up the gap between working capital

    requirement and security deposit amount lying with them. Accordingly, WBSEDCL

    has claimed interest on working capital to the tune of Rs. 2601.76 lakh and Rs.

    4965.77 lakh for the years 2012 2013 and 2013 2014 respectively.

    2.35 The petitioner has claimed Rs. 3011.09 lakh, Rs. 3512.56 lakh and Rs. 3721.09 lakh

    towards reserve for unforeseen exigencies on normative basis as per the Tariff

    Regulations for the years 2011 2012, 2012 2013 and 2013 2014 respectively.

    2.36 WBSEDCL has proposed to release a part of the regulatory asset created on the

    additional expenditure of WBSEDCL due to revision of pay and allowances as per

    ROPA, 2009, at Rs. 62500.00 lakh, Rs 1000.00 lakh and Rs. 8600.00 lakh during the

    year 2011 2012, 2012 2013 and 2013 2014 respectively.

    2.37 WBSEDCL has also proposed to consider the impact of APR of WBSEDCL for 2009

    2010 and the impact of instalments payment claimed by WBPDCL against the

    revision of tariff of their new units in the ARR for the years under the third control

    period.

    2.38 WBSEDCL has also proposed to allow special appropriation on account of the

    followings:

    a) Additional amount of capacity charge claimed by NTPC Limited for the period

    2004 2005 to 2010 2011 arising out of additional capitalization of assets as

    per order of Honble Appellate Tribunal for Electricity.

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    15

    b) Additional charges to be borne by WBSEDCL on account of increased tariff of

    NTPC power stations for the period from 2009 -2010 to 2010 2011 in addition

    to the normal power purchase cost for the year 2011 2012.

    c) Additional claim of DVC for supply of ;power from Mejia Power Station for the

    period 2007 2008 to 2010 2011 and also for radial power supply for the

    period from 2009 2010 to 2010 2011 due to the tariff order passed for Units V

    & VI of Mejia TPS by CERC.

    2.39 Total expenditure of Rs.1338659.51 lakh has been computed by the petitioner and

    after excluding the revenue earned from other income, from bulk supply and supply

    to Sikkim, expenses attributable to export and taking into account the benefits

    passed on to the consumers, interest credit on depreciation and U.I earning of

    previous year the annual revenue required from sale of energy to its consumers has

    been estimated by the petitioner as Rs. 1117029.82 lakh for 2011 - 2012. Similarly,

    for the years 2012 2013 and 2013 2014 total expenditure of Rs. 1530998.93 lakh

    and Rs. 1712422.17 lakh respectively have been projected by the petitioner and after

    aforesaid deductions estimated for those years, the ARR from sale of energy to its

    own consumers have been projected as Rs. 1235858.35.00 lakh and Rs.

    1419318.98 lakh respectively.

    2.40 With projected revenue requirement of Rs. 1117029.82 lakh proposed by the

    petitioner from sale of 19061.77 MU of energy to its own consumers, the average

    cost of supply per unit has been computed by the petitioner to be 586.01 paise / kWh

    for the year 2011 2012. Similarly, the average cost of supply for the years 2012

    2013 and 2013 2014 have been projected at Rs. 587.04 paise / kWh and 610.01

    paise / kWh respectively.

    2.41 WBSEDCL has also requested to accommodate increase in power purchase cost

    arising out of any new tariff order or APR order or FPPCA order on WBPDCL, DPL,

    DPSCL, DVC, NTPC or NHPC power stations, etc., which are in addition to what is

    mentioned in paragraph 2.40 above.

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    16

    2.42 Changes proposed by WBSEDCL in their tariff for 2011 2012, 2012 2013 and

    2013 2014 are as follows.

    (a) The existing B-ID tariff categories are segregated into two L&MV tariff

    categories such as B-ID (Industrial) for L&MV industrial consumers and B-ID

    (Commercial) for L&MV Commercial consumers who have contract demand

    in between 50 KVA and 125 KVA.

    (b) One new L&MV tariff category as Rate C-ID for other L&MV consumers who

    have contract demand in between 50 KVA and 125 KVA has been proposed.

    (c) The demand charge, fixed charge and energy charge for different categories

    of supply have been proposed to be revised.

    (d) Voltage wise graded load factor rebate and surcharge have been proposed

    for EHV and HV industrial consumers and also for industrial consumers under

    Rate B-ID (Industrial) category for 2011 2012, 2012 2013 and 2013

    2014 separately.

    (e) WBSEDCL has also proposed separate rate for P.F. rebate and surcharge for

    the years 2011 2012, 2012 2013 and 2013 2014 for those categories of

    consumers to whom those are applicable at present.

    (f) WBSEDCL has also proposed revised rates for meter rentals, meter testing

    charges, fuse call charges, etc.

    (g) Rebate on energy charge for industrial consumers taking supply at 33 KV and

    66 KV has been proposed by the petitioner to be 1% of the energy charge

    and the same has been proposed for 132 KV at 2%.

    (h) Additional rebate of 30 paise per kWh on energy charge has been proposed

    for consumers taking supply at 33 KV or above whose contract demand is

    1.50 MVA or above and whose load factor is not less than 75% in the billing

    period and whose recorded maximum demand during the billing period is not

    less than 80% of the contract demand subject to payment of bill within due

  • Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission

    17

    date. However, for the consumer supply at above 33 KV, the contracted load

    will be 10 MV and above.

    (i) Rebate for timely payment for the year 2011 2012 has been proposed to be

    1% of the billing amount excluding meter rent, taxes, duties, levies and

    arrears for those consumers who are already getting such rebate in the year

    2011 2012 as well as for Street Light category.

    (j) To encourage one time payment for three months bill and to minimize

    transaction, a special rebate of 10 paise / unit on energy charge has been

    proposed for domestic and commercial consumers under L&MV category

    who are covered under quarterly billing system under normal or normal-TOD

    tariff scheme provided the payment is made for the quarter at a time within

    the due date stipulated for the first month of the quarter.

    (k) 1% rebate in addition to the timely payment rebate is proposed to be given to

    the consumers who will pay energy bills through e-payment facility within due

    date on introduction of it by the petitioner.

    (l) Hatchery has been proposed to be included in Rate A (Cm-III) and Cinema

    hall are proposed to be considered as commercial consumers.

  • Tariff Order of WBSEDCL for the yeas 2011 2012 and 2012 2013

    CHAPTER - 3 OBJECTIONS AND SUGGESTIONS

    West Bengal Electricity Regulatory Commission 18

    3.1 Twelve objectors have provided their objections and suggestions within due date of

    14.05.2012 in response to invitation of objections and suggestions on the MYT

    application of WBSEDCL for 3rd control period. The documents submitted within due

    date of receiving of such objections and suggestions have been considered in this

    tariff order only. The suggestions and objections submitted by the objectors which

    are relevant to the submitted MYT application of WBSEDCL for 3rd control period,

    are discussed below:

    3.2 On generation aspect to WBSEDCL, HCCI has objected to showing the conservative

    generation plan by WBSEDCL from their own generating station allegedly without

    any reason and thus HCCI preferred to consider design energy. In such a context

    the Commission has following observations. The conventional hydro system

    generation, being must run generation if available for operation, depends on the

    availability of water which is fully dependent on the climatic condition of each year

    and thus no normative parameter has been considered in this aspect. However if

    climatic condition is satisfactory in terms of design parameter but the availability of

    machine is less than the normative parameter then such deviation is accounted for

    in Annual Performance Review (APR). For Purulia Pumped Storage Project (PPSP)

    the generation depends on number of factors such as system demand, its pattern,

    availability of cheaper peak power and also on the overall conduciveness of the

    system to operate PPSP. Thus in tariff order the trend of the past years has been

    considered for future projection. However, while projecting sent-out/ generation from

    any sources in case any year is already past or partially past, actual generation

    figure for the year is preferred if the year has fully past and the generation/ sent-out

    figures are estimated after taking into effect the actual portion for a partially past

    year. Accordingly energy availability is calculated. Thus, while considering energy

    balance for 2011-12, the energy amount on actual basis has been considered to the

    extent possible as the year has already passed over. For 2012-13 and 2013-14 the

    generation/ sent-out has been estimated based on latest trend as explained in

    Chapter - 4. But where specific deviation has been made that has also been

    mentioned in the relevant paragraph of this order.

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 19

    3.3 On O&M expenses of generating station, HCCI has requested that such O&M

    expenses should be allowed strictly in accordance with the norms prescribed in the

    MYT regulations. Commission dealt the matter along same line in chapter 5.

    3.4 On Power purchase cost the submissions by the objectors along with the views of

    the Commission are as follows.

    3.4.1 Regarding power purchase expenses Jayashree Textiles has stated that

    Commission should exercise strict prudence check while allowing such expenses.

    Commission noted the point.

    3.4.2 ABECAs submissions are as follows.

    i. The power purchase cost should be done on the basis of present tariff rate

    and not on the basis of future tariff.

    ii. The cost of coal per MT allowed by the Commission to the licensee is much

    more than listed coal prices of Coal India Ltd.

    iii. According to ABECA by having 100% capacity utilization of DPL & WBPDCL

    the demand can be met without sourcing power from other sources.

    iv. To minimize cost of power of WBPDCL and DPL by increasing their PLF and

    lowering T&D loss, by reducing their Return on equity and by disallowing the

    unforeseen exigencies and Bad Debt.

    On the above issues Commissions views are as follow:

    The contention of ABECA in (i) above has been considered in view of the availability of mechanism of power purchase cost recovery through MVCA in

    case there is any increase in power purchase price.

    In the submitted application of the instant licensee there is no scope of allowing higher coal price and thus the point (ii) is not relevant.

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 20

    The WBSEDCLs peak demand is of the order of 4900 MW for its own command area and another 550 MW to 750 MW is required to supply to CESC. Whereas

    the availability from WBPDCL at 100% capacity utilization is 3493 MW. Similarly

    the maximum possible surplus from DPL considering its 100% capacity utilization

    of installed capacity is 310 MW. Moreover 100% capacity utilization of installed

    capacity in longer perspective is mere theoretical from technological aspects.

    Thus ABECAs contention as per (iii) above does not seem to have merits.

    On issue (iv) above the cost reduction issue of power from WBPDCL and DPL is related to the tariff applications of WBPDCL and DPL. Thus Commission does

    not intend to deal such matter in this order.

    3.4.3 On quantum of procurement of power by WBSEDCL from WBPDCL, HCCI has the

    following observations:

    i) Projected purchase of power from WBPDCL is in lesser quantity than the

    normative generation of WBPDCL which has resulted in procurement

    proposal for short-term power from traders/exchange at high cost.

    ii) The normative generation level of WBPDCL should be considered for

    purchase of power from them by WBSEDCL.

    iii) In case past performance is considered instead of normative generation for

    WBPDCL and lower than benchmark (normative) generation level are

    considered for WBPDCL generation, then the capacity charges should be

    reduced pro-rata on account of lower plant availability factor.

    iv) According to HCCI though WBSEDCL considers the past trend to be the sole

    reason for assumption of conservative generation from WBPDCL generation

    plant for ensuing years of 3rd control period, in certain years of the past the

    energy received by WBSEDCL are much higher than the conservative

    projections made by it for the 3rd control period.

    On the above issue the Commission is of the view that WBSEDCLs projection on

    the basis of past trend may not be inappropriate since real time situation in the past

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 21

    shows that WBPDCL has failed to provide normative generation for some of its

    plants. This has resulted into distorted energy balancing scenario which is reflected

    by wide variation in projection vis--vis actual energy sold to persons other than

    licensee and consumers in tariff order and APR respectively as is being detailed out

    in paragraph 5.27 of this order. As a consequential impact the consumers are likely

    to be burdened with increased tariff through FPPCA/APR in future as well as there is

    likely to be shortage of cash flow in real time operation. On the other hand

    WBPDCLs norms cannot be resolved as it will tantamount to rewarding the

    inefficiency of WBPDCL. Accordingly, WBSEDCLs projection of energy on the basis

    of past trend of different sources has been considered by the Commission. Thus

    Commission has preferred to consider the actual sent out energy of WBPDCL from

    each power station of WBPDCL for recently fully/ partially passed years to capture

    the current trend of performance after due consideration of the outliers. In fact the

    lower level of performance as shown in table under the paragraph 4.4(i) of this order

    by Sagardighi Thermal Power Station (SgTPS) in first six months compared to same

    period of 2011-12 shows the necessity to depend upon average performance of a

    longer period specially from points of view of energy balancing of a licensee or power

    purchase planning. The matter is being detailed in Chapter 4 of this order where due

    explanation is provided wherever necessary. For capacity charge recovery the

    suggestion of HCCI has been well taken and accordingly the capacity charge

    payable to WBPDCL has been considered in this order.

    3.4.4 Regarding power purchase from DPL, HCCI has mentioned that WBSEDCL has not

    substantiated the load growth of DPL. The Commission feels that the essential issue

    being the availability of power to WBSEDCL from DPL. In that context the

    Commission observes that WBSEDCL has already shown the decreasing trend in

    sale of surplus power by DPL to WBSEDCL in the last few years. As there is no new

    unit to be commissioned by DPL during 3rd control period and there will be at least

    normal growth in DPL command area, supply from DPL to WBSEDCL is not likely to

    improve any further.

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 22

    3.4.5 HCCIs view on conservative estimates of energy received from Bhutan without

    substantiated reasons has been noted by the Commission. Commission on scrutiny

    of Annexure-5 of Appendix-A of the MYT application of WBSEDCL for 3rd control

    period found that Govt. of Bhutan has already intimated the beneficiaries of the

    power stations of Bhutan through Eastern Regional Power Committee (ERPC) on

    reduction in quantum of energy for each year. Accordingly, the reduction in quantum

    of sent out power as projected is accepted by the Commission.

    3.4.6 On capacity charges of NTPC Power Stations HCCIs view is that WBSEDCL has

    estimated capacity charges at higher proportion than the proportion of energy it has

    considered from the Farakka STPS (FSTPS) and Talcher TPS (TTPS). In this

    context Commission likes to draw the attention to the fact that capacity charge does

    not reflects always the delivered energy. Such capacity charge may also include

    back-down periods due to low demand. Thus capacity charge recoverable during a

    period may not be necessarily proportional to the actual delivered energy in

    comparison to normative generation. Thus, the HCCIs objection on grounds of non-

    commensurable capacity charge in respect to energy delivered cannot be accepted.

    The same trend of the demand pattern and back-down level can be considered to

    remain more or less same during the 3rd control period. Accordingly the recovery of

    capacity charge from 2011-12 to 2013-14 is appropriately dealt with in Chapter 5.

    3.4.7 The objectors view that the purchase of energy from Maithon Right Bank of only

    508 MU in FY 2012-13 instead of 1016 MU as proposed for FY 2013-14 without

    substantial reason has been noted by the Commission. Maithon Right Bank Project

    Unit-2 has started supply of power commercially from 24th July, 2012 as reported by

    WBSEDCL in response to Commissions letter vide no. WBERC/TP-53/11-12/0995

    dated 01.10.2012, which was raised in accordance to the Tariff Regulations.

    Accordingly the energy from such source for 2012-13 is being modified to 857 MU.

    3.4.8 The HCCI has objected to the purchase of power in short-term mode as according to

    them such purchase is consequent to the non-achievement of distribution loss

    norms, which means that short-term power is always required to meet the shortage

    arising out of non-achievement of distribution loss norms. In many instances it is

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 23

    required to meet the actual shortage in supply also. Moreover for 2012-13 and 2013-

    14 WBSEDCL has made the energy balance on the basis of normative loss only. It is

    also found that the proposed volume of short term power purchase is only a small

    part as shown below:

    Particulars 2011-12 2012-13 2013-14 Short-term power purchase (MU) 990.00 364.55 1000.00Total power purchase (MU) 29862.00 32221.05 34006.00Percentage of short-term power purchase (MU) 3.32 % 1.13% 2.94%

    Moreover, the distribution loss takes place over the time period under consideration

    more or less equally whereas short-term power is procured for a very small part of

    that period only. In such circumstances it cannot be said that the procured power

    under short-term mechanism is also supplementing the power for excess distribution

    loss due to non-achievement of distribution loss in those part of the period under

    reference when there is no supply from short-term sources.

    Thus, the contention of HCCI that the short-term power is consequent to non-

    achievement of distribution loss norms cannot be accepted.

    On the issue of price of such short-term power Commission would deal with the

    matter in Chapter-4.

    3.5 On distribution loss the submission of the objectors along with the view of the

    Commission are as follows:

    3.5.1 ARCVAC Forge Cast Pvt. Limited has suggested for following merit order dispatch

    principle for disallowing cost of excess distribution loss. In this context, the

    Commission feels that this is not logical as this will be tantamount to say that only

    high cost energy contributes towards distribution loss. In fact, the power purchase at

    different rates are sourced at different instant of time throughout the year and more

    or less distributed over the year according to demand pattern and loss occurs at

    each and every instant of time under the same law of physics. Thus, it cannot be

    said that power procured at higher cost will be considered for disallowed portion due

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 24

    to high distribution loss. According to the Commission weighted average price of

    pooled power purchase is to be considered as a rational approach for disallowance

    of excess power purchase cost for excess distribution loss over the normative loss.

    3.5.2 Regarding distribution loss, the West Bengal Cold Storage Association (WBCSA)

    has mentioned that the distribution loss for the year 2011-12 may be fixed at 17.49%

    for the purpose of computation of revenue requirement though the distribution loss

    as stated by WBSEDCL in their application is 24.93% for the year 2011-12. In this

    context it needs to be mentioned that for determination of revenue requirement by

    WBSEDCL the distribution loss has been considered only at the normative level for

    the concerned year so that the excess loss is not allowed to pass through to the

    consumers.

    3.5.3 Regarding distribution loss ABECA has proposed that it should not be allowed more

    than 9% and opposes the claim in excess of 9% distribution loss. ABECA has not

    provided any details in establishing their claim. As normative parameters on such

    issue has already been fixed in the Tariff Regulations after inviting objection &

    suggestions, only such norms of distribution loss will be considered in this order.

    3.6 On transmission charges the submission of the objectors along with the views of the

    Commission are as follows:

    3.6.1 On STU charges the objection by HCCI is primarily on the following points:

    i. The STU charges payable by WBSEDCL shall be based on ARR determined

    for WBSETCL by the Commission for the year 2011-12, 2012-13 and 2013-

    14 which is also a suggestion from ABECA.

    ii. The charges for intra-state transmission line that are being recovered through

    POC charges of Inter-state transmission charges shall not be recovered

    through STU charges

    3.6.2 The claim of enhanced CTU charges payable by WBSEDCL as per point of

    connection (POC) method has been kept pending due to legal issues at the time of

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 25

    submission of tariff application. ABECA have suggested to furnish the court order of

    legal dispute by WBSEDCL and after that the Commission may consider the merit of

    the claim of WBSEDCL regarding CTU charges.

    3.6.3 The view in 3.6.1(i) has been considered by the Commission and the matter related

    to 3.6.1(ii) is in the scope of tariff order of WBSETCL and thus is not being dealt

    here. On the issue of 3.6.2 Commission asked the status of the legal cases from

    WBSEDCL vide letter no. WBERC/TP-53/11-12/0995 dt. 01.10.2012 and

    WBERC/TP-53/11-12/1078 dated 19.10.2012 which were issued in accordance to

    the Tariff Regulations. In response it reveals that though legal case is pending the

    payment of POC charges has been implemented. The matter has been further dealt

    with in Chapter 5.

    3.7 On Employee Cost the submission of objectors along with the views of the

    Commission are as follows:

    3.7.1 On Employee Cost, both HCCI and Jayashree Textiles have mentioned that

    employee cost increase is 35% in 2011-12 over 2010-11. According to them

    regarding the employees cost, the actual employees cost in FY 2010-11 of

    WBSEDCL was 855.45 crore which constitutes of an abnormal expense amounting

    to Rs.171.81 crore towards provision for terminal benefit on account of revision in the

    ceiling of gratuity amount which means normal employees cost during FY 2010-11 is

    Rs.683.64 crore (Rs.855.45 less 171.81 crore). Thus, according to the objector, the

    projected employee cost of Rs. 920.02 crore for FY 2011-12 which is 34% higher

    than the normal employee cost for 2010-11, is abnormal by any standard.

    3.7.2 ABECA have opposed the increased pay and allowances of the employees since the

    revised pay and allowances of WBSEDCL is effective from 01.04.2008 and the Tariff

    Order for 2008-09, 2009-10 and 2010-11 was passed on the basis of revised pay

    effective from 01.04.2008. So there is no reason for revision of Tariff on the ground

    of revised pay and allowance. ABECA have also suggested that WBSEDCL should

    furnish detailed list of staff grade wise pay fixation as per revision of pay and

    allowances and arrear of pay allowed to the staff individually along with specific order

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 26

    of the licensee in this regard. They have also requested to consider the difference

    that arises after tariff order in the APR on the basis of actual and audited report.

    3.7.3 The objectors sought to reason out against the proposed employee cost by

    WBSEDCL is not properly justified due to following reasons.

    i. The way of normalization of employee cost is being done by HCCI/

    Jayashree Textile through reducing the employee cost in 2010-11 by an

    amount of the terminal benefit is not justifiable as such component will also

    be an eligible amount for each year including in the year 2011-12 which has

    the terminal benefit amount in the employee cost for 2011-12.

    ii. The employee cost of WBSEDCL in 2010-11 as per the annual accounts of

    WBSEDCL stands at Rs 856.00 crore.

    iii. The pay structure of the employee is governed under the rules framed under

    Revision of Pay and Allowance (ROPA), 2009 of WBSEDCL and thus is to be

    taken into consideration as wage revision does not imply that increase in cost

    for such wage revision is for one time only and such cost will have no future

    increase with the inflationary trend.

    iv. Objectors view of not allowing increased employee cost at this point of tariff

    determination stage with an ultimate intention to consider such increased cost

    on actually incurred basis at later stage, i.e., APR stage cannot be

    considered by the Commission as this will affect the cash flow of the licensee,

    the consequence of which will be the requirement of extra financing cost.

    Such extra cost would imply extra tariff at a later stage.

    3.8 The objector HCCI in its objection on O&M costs has referred to different regulations

    and model regulations without however mentioning the purpose of such referencing.

    HCCI has claimed that WBSEDCL claim O&M expenses under various

    nomenclatures. HCCI also provides a comparative study on O&M expenses for per

    unit of sales in different States.

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 27

    On the above observation, the objectors view on different elements of O&M cost

    has been taken into consideration by the Commission in accordance with the Tariff

    Regulations and the elements which are not considered as elements of O&M cost

    under Tariff Regulations are considered separately in a manner as has been dealt

    with in the Tariff Regulations.

    3.9 On the issues of Administrative and General Expenses the submission of the

    objectors along with the views of the Commission are as follows:

    3.9.1 Regarding Administrative and General Expenditure ABECA have suggested that the

    claim on the basis of actual cost incurred by WBSEDCL at the time of furnishing the

    proposal is to be considered. The point is noted and has been dealt with in Chapter

    5.

    3.9.2 On Other Administrative and General (A&G) expenses HCCI stated that WBSEDCL

    has considered a year on year escalation of 17% in the MYT period. According to

    HCCI such high escalation in A&G expenses should not be allowed to WBSEDCL

    and marginal increase linked with inflation indices may only be permitted. HCCI has

    also drawn the attention that there is no specific reference in the tariff application of

    capitalization. On the issue of capitalization Commission finds that in paragraph 5.9

    of Volume-1 in the MYT application WBSEDCL deals with the capitalization issue.

    The annual accounts of 2011-12 have also shown the capitalization. On the other

    issue Commission noted the point and dealt with the issue in Chapter 5 of this order.

    3.9.3 On individual components of Administrative & General Expenses for distribution such

    as Rent, Legal charges and Auditor fees, HCCI has objected that the expenses have

    been considered with a high growth rate. HCCI is also of the opinion that such cost

    can be considered during APR only on actual basis. As rent, Auditors fee and legal

    charges are parts of controllable item of Administrative and General expenses,

    overall excess cost, if any, with respect to above heads may not be allowed during

    APR due to the ceiling in Administrative and General Expenses on account of being

    a controllable item. Thus the suggestion of HCCI for considering such cost on actual

    basis in APR in general cannot be accepted. Moreover, there are issues like

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 28

    financing cost for any cash gap and tariff impact. Considering all the above aspects

    and other information available in the application submitted by WBSEDCL and

    annual accounts, the Commission decides the amount to be admitted in Chapter-5.

    3.10 ABECA have also opposed the proposal of increase in R&M cost due to increase in

    consumer base.

    On repair and maintenance expenses, HCCI has stated that increase in the

    expenses shall be reflective of the inflationary index.

    On this account Commission is of the opinion that increase in consumer base along

    with matching distribution network shall also be reflective parameters while deciding

    the repair & maintenance cost. Improving the service quality is also a major relevant

    parameter.

    3.11 On the point of cost of outsourcing HCCIs views are as follows:

    i) The cost of outsourcing should not be allowed to WBSEDCL as there is very

    little rationale with regard to its nature, cost and effectiveness and having no

    results demonstrated by WBSEDCL for the cost supposedly incurred.

    ii) Certain jobs and services can be performed effectively through outsourcing

    but to consider that around 15,000- 20,000 contracted employees would be

    required by WBSEDCL is implausible and unconvincing.

    iii) Jobs like substation and line maintenance were previously being done by the

    own staff of WBSEDCL.

    iv) Measures such as Online billing, spot billing, etc are novel ways of billing but

    it does not entail that some new jobs are now being taken up by WBSEDCL.

    The expenses on spot billing should be demonstrated by a reduction in the

    A&G expenses of WBSEDCL as it is only an alternate way of bill distribution.

    On the above issues the Commission is of the view that

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 29

    i) WBSEDCL has raised claim in accordance with the provisions in the Tariff

    Regulations.

    ii) On the issue of number of contracted employee and rationality of it, from

    HCCIs submission it cannot be found that why such numbers are implausible

    and what are the reasons on which it can be said unconvincing. On scrutiny,

    Commission finds in the annual accounts of WBSEDCL for 2011-12 the

    consumer strength has already increased to 106.73199 lakh from 85.65 lakh

    in 2010-11 which shows an increase of 24.61% by a single year.

    Simultaneously Commission also observes that the employee in regular

    establishment has been reduced significantly in the last control period

    whereas consumer strength is increasing rapidly as shown in the following

    table.

    2009 2010 2011 2012 No of Employee in thousands 24072 19236 18851 17932No of Consumer in lakh 7246759 7622178 8565374 10673202N.B: a) No. of consumers available from Annual Reports and Accounts of WBSEDCL b) No. of employee for 2009 available from APR application and c) No. of employees for 2010, 2011 and 2012 from MYT tariff application for the year

    2011-12, 2012-13 and 2013-14.

    It is also to be noted that due to reduction in employee in regular

    establishment its impact on employee cost has been duly considered by the

    Commission while admitting employee cost. Under such circumstances

    commission feels that with the increasing consumer strength and decreasing

    trend of own employee the outsourcing has merit for discharging of statutory

    obligations. Thus Commission proceeds to determine the outsourcing cost

    that is required to be admitted for the ensuing years of 3rd control period.

    iii) The expenses claimed for new Sub-station and lines are for operating

    personnel which are new.

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 30

    iv) The expenses of spot billing are basically replacement of the existing job.

    Thus this expenditure, being totally outsourced job, shall be passed as a part

    of outsourcing cost and not under the Administrative and General Expenses.

    On scrutiny it is found from the application of WBSEDCL that WBSEDCL has

    claimed outsourcing cost on number of items which are being dealt with in

    Chapter 5 of this order.

    3.12 In the point of interest on loan HCCI has stated that interest on loans may be

    allowed only after considering our objections in respect of capital investment,

    programme proposed by WBSEDCL. As no details, justification of capex schemes

    has been provided and no investment approvals furnished, the capital investment

    plan proposed by WBSEDCL is liable to be rejected. Consequently the interest on

    long term loans has to be recomputed considering no eligible drawals of loan. In

    addition HCCIs observation is that interest expense claimed by WBSEDCL does not

    commensurate with the capitalization sought by WBSEDCL in the MYT period.

    HCCI says that interest on R-APDRP loan should not be allowed in tariff as such

    loan will be converted into grant. HCCI also raised question about inadequacy of

    detailing on certain loan such as REC Limited Package, loans from Bank/RECL

    and for different schemes under plan and Non-plan other than securitization of CPS

    outstanding.

    The capital expenditure programme under R-APDRP Part A and R-APDRP Part

    B scheme has already been approved by the Commission in case no. WBERC/OA-

    68/2009-10 and WBERC/OA-118/10-11 vide order dated 23.04.2010 and

    01.09.2011 respectively. Thus as long as the loan of R-APDRP Part A or R-

    APDRP Part B is not being converted into grant partly or fully its interest will be

    eligible to be admitted by the Commission if such interest is payable in the

    concerned year. Other schemes such as RGGVY, APDRP do not require any

    investment approval as those schemes were introduced by the Government of India

    at a period when such investment approval was not required by the licensee in

    accordance with the then regulation of the Commission applicable at that time.

    However, such schemes, being approved by the concerned nodal department/

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 31

    agency of Government of India, the due diligence has been done by different

    concerned authority and thus do not require any fresh investment approval at this

    stage of the projects which has already attained finality and thus will be considered

    for interest calculation purpose.

    Regarding inadequacy of data for certain loans such as REC Limited Package,

    loans from Bank/RECL and for different schemes under plan and Non-plan other

    than securitization of CPS outstanding, the details have been gone through by the

    Commission from the Annual Accounts of 2011-12 and accordingly dealt with in

    Chapter 5.

    3.13 On interest on Consumer Security Deposit the HCCI has apprehension that the

    amount claimed by WBSEDCL is not adjusted in bills paid to the consumers in toto.

    The Commission cannot act merely on the basis of apprehension of any person

    unless there is at least some prima facie instances of any anomaly on the related

    issue. Moreover in case of non-receiving of interest on security deposit consumer

    has appropriate remedial measures under the law. However the issue is dealt with in

    Chapter 5.

    3.14 On the issue of bad debt the submission of different objectors along with the view of

    the Commission are as follows:

    3.14.1 ABECA have suggested that WBSEDCL should furnish the detailed chart of

    defaulting consumers and unrealized amount from them and steps taken to realize

    the amount. Before furnishing such data no amount should be allowed to WBSEDCL

    on this account.

    3.14.2 HCCI has referred to regulation 5.10 of the Tariff Regulation.

    3.14.3 The comments of objector at 3.14.1 and 3.14.2 have been noted and is duly dealt

    with in chapter 5 in accordance with the Tariff Regulations for due consideration.

    3.15 On the issue of Minimum Alternate Tax HCCI refers regulation 5.13.1 and rely on the

    point that it is allowable and to be recovered as pass through element. Commission

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 32

    is of the opinion that the regulation has to be looked into with the following points

    also.

    a) The regulation does not say that such pass through cannot be done at tariff

    determination stage.

    b) Where Minimum Alternate Tax is mandatory for payment at certain frequency

    within the period under consideration then just after the payment has been

    made, it cannot be recovered normally at such frequent interval through

    revision of tariff as it is under fixed cost head.

    c) MAT as deposited can be allowed by the Commission without the

    assessment order.

    In view of the above fact the licensee is required to pay the tax in a quarterly

    frequency. Thus to ensure proper cash flow the projected amount of MAT is required

    to be passed through the tariff order subject to truing up in the APR as in the mid

    way of a year separate order on this small amount cannot be brought out as it is not

    rational.

    3.16 On the issue of unforeseen exigencies the submission of the objectors and the view

    of the Commission are as follows:

    3.16.1 According to ABECA unforeseen exigencies is not a cost at all and as per the Act

    this cannot be included in the ARR and thus they suggest to refund the accumulated

    fund with income derived out of such fund to the consumers through reduction of the

    said accumulated amount from the ARR for the year 2011-12, 2012-13, 2013-14 and

    no fund is to be allowed further.

    3.16.2 On the other hand HCCI feels that Reserve for unforeseen exigencies may be

    allowed by the Honble Commission only after strict prudent check duly verifying that

    such reserves are invested in interest paying securities and the interest income

    earned on such reserve are ploughed back / netted-off while claiming the reserve for

    unforeseen exigencies of subsequent years.

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 33

    3.16.3 Commission is of the opinion that the expenditure for unforeseen exigencies is

    statutorily approved cost and has been maintained to serve the purpose for which it

    is created. Commission noted the points in 3.16.1 and 3.16.2 and duly dealt with in

    Chapter 5.

    3.17 On the issue of interest on Working Capital the objectors submission along with the

    Commissions view are given below:

    3.17.1 On interest on Working Capital the objection of HCCI is with respect to the

    provisional amount of security deposit which according to HCCI shall be static over

    the MYT period. On the contrary, WBSEDCL has claimed interest on security deposit

    in an increasing trend at Rs 28.70 crore, Rs 33.15 crore and Rs 38.29 crore in 2011-

    12, 2012-13 and 2013-14 respectively thereby implying that it has considered a

    yearly increase in security deposits from consumers. According to HCCI, WBSEDCL

    has ignored to take this increase into account while computing the interest on

    working capital. HCCI has submitted that the Commission should take this anomaly

    into account and suitably adjust the computations in respect of interest of working

    capital.

    3.17.2 Regarding interest on Working Capital ABECA have opposed the same stating the

    reason that as the Commission directed WBSEDCL to invest the Security Deposit

    received from the consumers as Working Capital there would be no need to claim

    any amount as interest on Working Capital. Secondly they opposed the rate of

    Interest on Working Capital @ 14% whereas the rate of interest payable on Security

    Deposit is 6%. According to them interest on Working Capital shall be 6%. They

    have also suggested to direct WBSEDCL to furnish details of the security deposit

    held by WBSEDCL till date and to submit the status report regarding quantum of

    Security Deposit, utilization of such deposit and rate of interest paid by them to the

    consumers before entertaining the claim of WBSEDCL on interest on Working

    Capital.

    3.17.3 Commission noted the point in 3.17.1 and dealt with this accordingly in Chapter 5.

    Regarding the issue of 3.17.2 Commission cannot ignore the need of additional

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 34

    working capital requirement within normative level as provided in the Tariff

    Regulations if the security deposit of consumer is not sufficient to cover the

    normative working capital requirement. Moreover as such working capital

    requirement beyond the amount collected from security deposit of consumer is

    required to be mobilized in the form of loan from financial institutions or market, thus

    the interest on such loan is bound to be at market driven rate. Thus commission is

    bound by the regulation to provide the interest as specified in the regulation.

    3.18 On capital investment issue objections put forwarded by HCCI are as follows:

    1. The detailed break-up of the capital investment with respect to schemes,

    justifications etc. have not been provided by the Petitioner. Further the additional

    capitalization may not be allowed by the Honble Commission as the filing made

    do not strictly adhere with the requirements of Regulation 5.1 and 5.2 of the

    MYT Regulations and the status of investment approvals mandated under

    Regulation 2.8.2.3 is neither known nor available with the Petition. In such case,

    the capital investment plan should be out rightly rejected by the Honble

    Commission.

    2. Without prejudice to the above, the capitalization towards assets created

    pursuant to RGGVY and R-APDRP scheme and through consumer

    contributions and other grants, etc. should be segregated from the other capex

    schemes. Depreciation on assets created under RGGVY, R-APDRP scheme

    and through consumer contributions and other grants etc. should not be allowed

    in the ARR.

    3. The depreciation which has already been claimed on assets created under

    RGGVY, R-APDRP scheme and through consumer contributions and other

    grants etc. should be clawed back and given effect in the MYT order.

    In addition to the above objection, HCCI raised the question that whether WBSEDCL

    is entitled to recover

    i) Capital created out of consumers contribution or grant.

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 35

    ii) Depreciation of asset formed through consumers contribution or grant.

    iii) While finding out equity on normative basis, whether the asset created out of

    consumers contribution or grant will be considered.

    In fact, the question of recovery of capital created out of consumers contribution

    or grant is not very clear. However the values of such asset are not considered

    as equity base. In case of normative equity calculation the mater is dealt with in

    Chapter 5 of this order. However, depreciation on the assets formed through

    consumers contribution or grant is recoverable as such amount is required for

    future replacement of such assets on expiry of their life.

    Regarding the issue raised on capital expenditure programme or investment

    proposal in relation to depreciation and normative equity the points raised by

    HCCI have been noted and accordingly dealt with in chapter 5 while arriving at

    the depreciation and equity base and appropriate direction has been given in

    chapter-10 to WBSEDCL to provide details so that during APR the truing up can

    be done on the basis of such details.

    3.19 Regarding depreciation ABECA have proposed to furnish detailed item wise

    depreciation amount with life span of each item and repayment of loan out of such

    depreciation. Balaji Paper & Newsprint Pvt. Ltd. has referred statutory auditors para

    in relation to fixed asset registers. This issue of fixed asset registers was reported in

    annual accounts of 2009-10 for not following CARO, 2003. The same annual

    accounts show that figures of fixed assets with depreciation and value of

    depreciated assets are available accounting unit wise and accounting code wise.

    Such report also reveals that the job of identification and verification of fixed assets

    has already undertaken by the company and has been completed for assets

    capitalized upto 31.03.2008 and the balance work was in progress. Subsequently

    such issues are not reported in the annual accounts of 2010-11 and 2011-12. Thus it

    implies that such fixed asset now is being maintained more comprehensively.

    Moreover, Commission observes that WBSEDCL has furnished the information

    related to depreciation and repayment of loan in a manner as specified in the Tariff

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 36

    Regulations. However, direction has been provided in relation to this issue as

    already explained in paragraph 3.18.

    3.20 Regarding return on equity ABECA have suggested that the rate of return should not

    be allowed at more than the RBI rate of interest as WBSEDCL is being a

    government company and before the enactment of the Electricity Act 2003,

    WBSEDCL would have earned 3%.surplus. In this context commission will follow the

    Tariff Regulations which has gone through previous publications.

    3.21 On the issue of distribution loss level vis-a-vis lease rentals HCCIs view is that if the

    expenses of R-APDRP is allowed then the loss trajectories prescribed in the MYT

    regulations need to be revised. In this context the Commissions view is that the cost

    of such R- APDRP Part A is limited only to 62 towns in the State covering about 15

    lakh consumers only (as provided in the details of the scheme of R-APDRP Part-A

    during investment approval). For R-APDRP Part-A there is no conditionality of any

    targeted AT&C loss. Such target has been provided only for R-APDRP Part-B

    scheme which is under implementation phase and as per programme those projects

    will be completed beyond the period of 3rd Control Period. Thus the benefit of loss

    reduction of such project is not expected within this 3rd Control Period. Moreover,

    merely on the basis of a small part of the area of supply of the licensee the norms of

    the distribution loss for the whole area of supply cannot be changed as such type of

    improvement programme is a natural process undertaken by any licensee while they

    are being offered with the normative target. Furthermore on the point of expenses on

    MPLS-VPN connectivity the matter shall be looked into in the light of need of

    discharging regulatory obligation of the licensee under SOP Regulation as

    mentioned by WBSEDCL in addition to other purpose for which such network is

    being used.

    3.22 On other Incomes HCCI has objected to the conservative estimates of WBSEDCL in

    respect of income from investments and bank balances which roughly translates to a

    paltry return of 4% according to them and asked for detailed investigation by the

    Commission. HCCI also mentioned that a normative rate of interest of 8% on FDR

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 37

    balance for allowing the income from investment and bank balances including FDR

    income.

    Commission has observed that Investment amount of Rs. 577.12 crore for the year

    2010-11 is reflected in the Annual Accounts for the year 2010-11 under Schedule-10

    which is shown as cash and bank balance. This head indicates that such balance is

    temporary in nature and is for the closing date of the Accounts. This implies that

    such amount is not expected to be continued throughout the year at the same level.

    Thus the accrued interest as shown in the audited accounts of Rs 39.79 crore in the

    Note no. 24 of Annual Account of 2011-12 is being admitted by the Commission and

    accordingly dealt with in Chapter 5 of this order.

    3.23 The submission of the objector in relation to sale to other licensee along with the

    view of the Commission are as follows:

    3.23.1 On the question of sale of energy to other licensee, HCCIs submissions are:

    i. Increase in power purchase cost and cost of supply of WBSEDCL is around

    14.23% and 16.50% respectively, the increase in sale price to other licensee

    considered in MYT projections is only 4.17%.

    ii. The basis of arriving at the sale price projected for sale to other licensee has

    not been explained in the MYT Petition.

    iii. It is unclear why WBSEDCL would supply power to other licensee at lower

    than its cost of supply.

    iv. Price for sale to other licensee shall be at the cost of supply of that respective

    year or at a price which factors in the year on year increase in power

    purchase cost and cost of supply in FY 2011-12 over FY 2010-11.

    3.23.2 ABECA have pointed out that sale of power to CESC Ltd is at a rate less than the

    rate of power purchase from Central Generating Company and Bhutan. ABECA have

    also mentioned that WBSEDCL purchases power from CESC Ltd. and CESC Ltd.

    also purchases power from WBSEDCL and both are pleading the tariff hike of each

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 38

    other. ABECA suggested the drawal of power of CESC Ltd. from WBSEDCL should

    be adjusted with the power drawal of WBSEDCL from CESC Ltd.

    3.23.3 In this context Commissions view is that the purchase price of power by one

    licensee from another licensee is being regulated keeping in view of the interest of

    the consumers of both the licensees. Moreover, the market price trend and long term

    power purchase cost from new Power Stations are also looked into before deciding

    such price. Otherwise any reduction in load demand of any seller licensee due to

    replacement of such demand by other new sources may affect the consumers of the

    referred selling licensee severely as they may require to bear the liability of

    compensation of such business loss. Moreover, the demand pattern of the purchaser

    licensee and any other conditions under which purchase are taking place are also

    required to be looked into. Moreover, there is wide disparity in retail tariff among the

    licensees due to such type of inter-licensee selling prices which are also required to

    bring under control to a reasonable extent gradually. Further, the proposal for selling

    power by WBSEDCL to other licensee at a rate not less than the costlier sources

    does not have any merit as the demand of such licensees is historically met from

    long past and the costlier power procurement decisions are taken at different time to

    meet the increasing demand of both own consumer and other licensee. In fact,

    Commission is required to strike a balance on different aspects for such purchase of

    power. On the basis of such factors the purchase price for power by different

    licensees is required to be set in their Tariff Order.

    3.24 On share of benefit passed on to consumers the objection of HCCI is primarily on the

    two aspects:

    The projected selling rate considered for sale of power to persons other than consumers and licensees and for the notional sale of power against swap

    out, and

    While computing the presumptive gains, due consideration has not been provided to the fact that lower sales were reported to persons other than

  • Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013

    West Bengal Electricity Regulatory Commission 39

    consumers and licensee as there was a significant under-achievement of

    distribution losses.

    The licensees are penalized by disallowance of expenditure arising out of under

    achievements of distribution losses and thus the Commission is of the view that they

    cannot be penalized for second time on the basis of notional gain on account of

    notional sale as claimed by the objector.

    The other point has been only noted by the Commission but not accepted the logic

    as the expenses due to swap out is also considered for reducing the ARR to be

    borne by the consumers and license