ORDER OF THE
WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR 2011 2012 AND 2012 2013
IN CASE NO: TP 53 / 12 13
IN RE THE TARIFF APPLICATION OF THE WEST BENGAL
STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED
FOR THE YEARS 2011 2012, 2012 2013 AND 2013 2014
UNDER SECTION 64(3)(a) READ WITH SECTION 62(1) AND
SECTION 62(3) OF THE ELECTRICITY ACT, 2003
Date : 01.12.2012
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
CHAPTER 1 INTRODUCTION
West Bengal Electricity Regulatory Commission 2
1.1 The West Bengal Electricity Regulatory Commission (hereinafter referred to as the
Commission) was constituted by the Government of West Bengal in the year 1999 in
terms of section 17 of the Electricity Regulatory Commissions Act, 1998, now
repealed by section 185 of the Electricity Act, 2003 (hereinafter referred to as the
Act) which came into force with effect from 10.06.2003. The first proviso to section
82(1) of the Act has ensured continuity of all the State Electricity Regulatory
Commissions, which were established by a State government under section 17 of
the 1998 Act (and some other enactments) and functioning as such immediately
before coming into force of the Act and shall be the State Commission for the
purpose of the Act.
1.2 The functions of a State Commission have been specified in Section 86 of the
Electricity Act, 2003. One of the main functions of a State Commission relates to
determination of tariff for generation, supply, transmission and wheeling of electricity,
wholesale, bulk or retail, as the case may be, within a State. Further, Section 62(1)
of the Act also requires the appropriate Commission to determine the tariff in
accordance with the provisions of the Act, for supply of electricity by a generating
company to a distribution Licensee, for transmission, for wheeling as also for retail
sale of electricity.
1.3 The Commission has, therefore, all the powers and authority under the Electricity
Act, 2003 to determine the tariff, as laid down in the Act.
1.4 WBSEDCL is deemed to be licensee under the Electricity Act, 2003 in terms of fifth
proviso to Section 14 of the Act. The Commission determined the tariff of WBSEDCL
for the first control period (2007 2008) and the second control period (2008 2009,
2009 2010 and 2010 2011) under the then regulations related to tariff.
1.5 West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2011 has come into effect with effect from 25th April, 2011. The said
Tariff Regulations, 2011 was further amended by notifying the West Bengal
Tariff Order of WBSEDCL for the year 2011 2012 2012 2013
West Bengal Electricity Regulatory Commission
3
Electricity Regulatory Commission (Terms and Conditions of Tariff) (Amendment)
Regulations, 2012 in the extra ordinary edition of The Kolkata Gazette dated 27th
August, 2012.
1.6 A generating Company or a licensee, whose tariff is to be determined by the
Commission as per the provisions of the Act, is now required to submit their
application for determination of tariff for the ensuing years of the third control period
under the multi-year tariff framework complying with the provisions of the West
Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2011 (hereinafter to be referred as Tariff Regulations). Though as per
the Tariff Regulations the last date for submission of the application to the
Commission by a generating company or a licensee for determination of tariff for the
third control period comprising three years from 2011 2012 to 2013 2014
(hereinafter referred to as the third control period) was 28.5.2011, the Commission,
after considering the prayers of WBSEDCL for extension of date for submission of
the aforesaid application to the Commission, extended the date for the purpose upto
28th July, 2011. Subsequently, WBSEDCL submitted application for extension of date
time to time, latest on 31st October, 2011. WBSEDCL further prayed in their tariff
application that on receiving the new tariff structure arising out of finalization of the
plan for subsidization of certain category of the consumers by State Government and
re-determination of tariff in pursuance to Appellate Tribunal of Electricitys order
dated 4th April, 2011, and in view of the requirement to satisfy ERP (Enterprise
Resource Planning) based billing system, WBSEDCL was required some time to
finalize the tariff application for the third control period. They further prayed to be
condoned for the delay in submission of tariff application.
1.7 WBSEDCL, complying with the provisions of the Tariff Regulations, prepared the
application for determination of its tariff for the third control period and submitted the
same to the Commission on 5th April, 2012 which was considered by the Commission
and numbered as TP-53/12-13.
Tariff Order of WBSEDCL for the year 2011 2012 2012 2013
West Bengal Electricity Regulatory Commission
4
1.8 After admission of the application, WBSEDCL was directed to publish the gist of the
tariff application, as approved by the Commission, in the newspapers and also in
their website, as specified in the Tariff Regulations. The gist was, accordingly,
published simultaneously on 10th April, 2012 in Pratidin, The Hindu Business Line,
Ekdin and also in The Times of India. The gist along with the tariff application was
also posted in the website of WBSEDCL. The publication invited the attention of all
interested parties, stake holders and the members of the public to the application for
determination of tariff of WBSEDCL for the third control period and requested for
submission of suggestions, objections and comments, if any, on the tariff application
to the Commission by 14th May, 2012 at the latest. Opportunities were also afforded
to all to inspect the tariff application and take copies thereof.
1.9 Objections to / comments on the aforementioned tariff petition of WBSEDCL for the
third control period were received by the Commission from the following objectors
within the stipulated time i.e., 14th May, 2012.
1. Jayashree Textiles, A unit of Aditya Birla Nuvo Ltd.
2. Hooghly Chamber of Commerce & Industry
3. Eastern India Textile Mills Association
4. The West Bengal Cold Storage Association
5. Eastern Railway
6. South Eastern Railway
7. ABECA
8. Balaji Paper and Newsprint Pvt. Ltd.
9. Eastern India Textile Mills Association
10. Hooghly Alloys & Steels Co. Pvt. Ltd.
11. Chief Engineer, Kolkata Zone, MES
12. ARVAC Forge Cast Ltd
1.10 Objections and suggestions on the tariff application in question received by the
Commission within the stipulated period i.e. 14th May, 2012 have been dealt with
separately in Chapter 3.
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
CHAPTER 2 THE CASE OF WBSEDCL
West Bengal Electricity Regulatory Commission 5
2.1 West Bengal State Electricity Distribution Company Limited (WBSEDCL) in its tariff
petition has claimed that the total distribution equity of WBSEDCL in terms of
restructuring order of State Government was Rs.222300.00 lakh as on 01.04.2007.
The equity added during the year 2008 - 2009 was Rs.8471.99 lakh being the assets
of West Bengal Rural Energy Development Corporation Limited (in short
WBREDCL) as handed over to WBSEDCL as per Government Order no. 100-
PO/O/III/4M-12/2005 dated 20.03.2009 and during the year 2009 2010 was Rs.
25068.01 lakh for restructuring of WBREDCL as per Government Order No. 108-
PO/O/III/4M-12/2005 dated 31.03.2009. Considering the same, equity base
considered by the petitioner at the beginning of the year 2010 - 2011 has been
arrived at Rs.255840.00 lakh. No equity addition has been projected by the
applicant during the years 2011 2012, 2012 2013 and 2013 2014. WBSEDCL
has claimed permitted return on the average equity base for the years 2011 2012,
2012 2013 and 2013 2014 in accordance with the provision of the Tariff
Regulations as the entire equity.
2.2 WBSEDCL has claimed to have taken the following measures to reduce the
distribution loss (both technical and commercial):
(a) Regular monitoring of revenue, collection and distribution loss,
(b) Conduct of raids by Security and Loss Prevention Wing,
(c) Introduction of High Voltage Distribution Supply (H.V.D.S.) primarily for power
supply to irrigation consumers,
(d) Installation of meters in the premises of un-metered irrigations, Kutir Jyoti /
Lokdeep consumers and street light points,
(e) To facilitate energy audit mapping and documentation of entire power
network of WBSEDCL, Geographical Information System (GIS) has been
stated to have been taken up and is under progress,
(f) Spot billing facility for all categories of L & MV consumers under many
customer care centres is stated to be already in place and such billing facility
has been envisaged to be extended further,
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
6
(g) Implementation of distribution transformer metering to locate loss prone
areas,
(h) Restructured Accelerated Power Development and Reform Programme (in
short RAPDRP) (Part A) for 62 towns are under progress for installation of
IT infrastructure for assessment and monitoring of loss on regular basis,
(i) R-APDRP (Part B) for 45 towns are also to be taken up shortly for reducing
AT&C loss of those towns.
2.3 WBSEDCL has submitted that projection of the energy balance has been arrived
based on the estimated consumption, loss in distribution system of WBSEDCL and
loss in transmission system of WBSETCL at the normative level as per Tariff
Regulations. They also submitted that the petitioner has to consider the loss in
central and state grid, as applicable.
2.4 WBSEDCL has claimed that with fast growing expanding distribution network,
additional consumers are being added with WBSEDCLs system during last few
years. WBSEDCL states that based on the trend of increase of consumers in last five
years, consumer strength of WBSEDCL has been projected for the years 2011
2012, 2012 2013 and 2013 2014.
2.5 Accordingly, 10636.28 MU has been projected to be consumed by the consumers
under L&MV category in the year 2011 2012. Under the same category in the year
2012 2013 and 2013 2014 the petitioner has projected the consumption under
the same category to be 11719.76 MU and 12926.69 MU respectively. Under the
HV & EHV category consumption in the year 2011 2012 has been projected to be
8425.50 MU while under the same category 9332.44 MU and 10340.24 MU
respectively have been projected to be the consumption during the years 2012
2013 and 2013 2014.
2.6 Total sale of energy to own consumers of WBSEDCL has been projected as
19061.78 MU in the year 2011 2012, 21052.20 MU in the year 2012 2013 and
23266.93 MU in the year 2013 2014. T&D loss has been projected at a level of
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
7
24.93% for the year 2011 2012 but considered on the normative basis at a level of
17.75% and 17.50% respectively for the years 2012 2013 and 2013 2014.
2.7 The petitioner has projected sale of total energy to other licensees like CESC, DPL
and DPSCL at a level of 1270.00 MU, 2308.66 MU and 2875.92 MU respectively in
the years 2011 2012, 2012 2013 and 2013 2014. The projection of sale of
energy to licensees has been stated to have been made on the basis of present
trend of drawal by CESC upto February, 2012, the present trend of drawal by DPL
and as per projection given by DPSCL in the MYT application for third control period.
2.8 In terms of an agreement signed between the Govt. of W.B and Govt. of Sikkim the
petitioner has claimed that 40 MU of energy being 20% of the sent out generation
from Rammam Hydel station Stage-II shall be supplied to Sikkim each year of the
control period.
2.9 Sale of incidental surplus energy to the persons other than consumers and licensee
during 2011 2012, 2012 2013 and 2013 2014 has been estimated by the
petitioner to be at a level of 657.00 MU, 3649.00 MU and 2005.00 MU respectively.
WBSEDCL also considered 1283.00 MU of power in the year 2011 2012 only
towards banking of power through swap arrangement without selling due to low
market price or non-availability of buyer to purchase power through cash arising out
of volatile market condition. The above considerations have been made taking into
account surplus energy to be made available from the new projects / extension
projects of WBPDCL / DPL after meeting the requirement of the own consumers, the
licensees of the State & Government of Sikkim and considering the energy required
in the pumping mode of PPSP.
2.10 Sent out generation available from the hydel power stations of WBSEDCL has been
projected to be 405.856 MU in 2011 2012, 442.433 MU in 2012 2013 and 442.53
MU in 2013 2014. Out of the two main hydel station of WBSEDCL namely
Rammam and Jaldhaka, Rammam is working at reasonably high PLF. The
generation at Jaldhaka was suspended during 2009 2010 and 2010 2011 due to
renovation and modernization work. However, according to WBSEDCL, the
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
8
generation at Jaldhaka has started during the year 2011 2012. It is also submitted
by WBSEDCL that the installation of a new unit of 9 MW capacity at stage-I of
Jaldhaka Hydel Power Station is expected to be completed by July, 2012 thereby
enhancing the capacity of Stage I to 36 MW from the existing capacity of 27 MW.
The generation at TCF Hydel Power Station as stated by the petitioner, cannot be
achieved by WBSEDCL at the designed value stated to be due to constraints
towards release of 330 cusec of water as per DPR for non-completion of Dauk-nagar
Main Canal by I & W Department and frequent shut down of Main Canal for long
periods. Annual generation at PPSP at a level of 850.00 MU during the years 2012
2013 and 2013 2014 has been estimated by the petitioner and has been said to be
according to the system requirement during peak hours considering optimum
utilization of the surplus energy mainly during off peak hours. However, for the year
2011 2012, the same has been considered at 749.244 MU as per generation trend
upto February, 2012. WBSEDCL is maintaining diesel generation plant only at
Rudranagar in Sagar Island. Energy available from this diesel generating station has
been estimated at a level of 0.88 MU, during all the ensuing years of third control
period.
2.11 Gross generation available from renewable and co-generation sources, as per
WBSEDCL, has been estimated to be 116.03 MU, 150.30 MU and 150.30 MU during
the years 2011 2012, 2012 2013 and 2013 2014, respectively.
2.12 To discharge the function of a distribution licensee, WBSEDCL continues to
purchase power in the same manner as was being followed by erstwhile WBSEB
from different agencies namely West Bengal Power Development Corporation Ltd.
(WBPDCL), The Durgapur Projects Ltd. (DPL), Dishergarh Power Supply
Corporation Ltd. (DPSCL), Damodar Valley Corporation (DVC), National Thermal
Power Corporation Ltd. (NTPC), National Hydel Power Corporation (NHPC) and
Power Trading Corporation (PTC). It is also submitted by WBSEDCL that
conventional power will also be purchased directly from the new units of WBPDCL,
NTPC, NHPC, other generators and from electricity traders to meet the system
demand of WBSEDCL during the ensuing years of the third control period.
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
9
WBSEDCL will also purchase power from different renewable and co-generation
sources of energy during the years of the third control period.
2.13 The planning of power purchase has been claimed by WBSEDCL to have been done
keeping in view the following aspects.
(a) Estimated system demand for the ensuing years based on the projected load
growth.
(b) Maximum generation that may be available from the hydel power stations of
WBSEDCL.
(c) Commitment to meet the peak system demand.
(d) Requirement of pumping energy for optimum utilization of PPSP to meet the
system demand.
2.14 WBSEDCL claimed that besides purchasing power through grid system, they will
also purchase some quanta of power in radial mode from DVC at Asansol, Burdwan
and other areas, from DPL (at 33 KV & 11 KV) in and around Durgapur area and
from DPSC (at 11 KV) at Asansol area, Govt. of Sikkim (at 11 KV) at Rangpoo area
and WBREADA (11 KV) at Frezerganj area for catering its own consumers during
the years under third control period.
2.15 It has been claimed by the petitioner that while computing the quantity of purchase of
power from WBPDCL during the ensuing years under third control period, they have
considered the net energy available to WBSEDCL from all the generating stations of
WBPDCL based on the actual performance upto February, 2012, excepting BKTPS
stage-II and STPS (Units V & VI). However, as stated by WBSEDCL, for BKTPS
stage II and STPS (Units V & VI), the PAF is considered as per the norms due to
the fact that the performance of these power stations during the year 2011 2012
was nearer to the normative PAF.
2.16 WBSEDCL has claimed that the energy charge and capacity charges for all the
generating stations of WBPDCL are considered based on the following parameters:
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
10
a) The capacity charges for all power stations of WBPDCL for the year 2012 2013
and 2013 2014 have been estimated based on norms given in the Tariff
Regulations.
b) For the year 2011 2012, the capacity charge and energy charge including
Monthly Fuel Cost Adjustment are considered as per actual upto February 2012
and capacity charge rate and energy charge rate including MFCA for March 2012
are considered from that of February 2012.
c) For the year 2012 2013, the energy charge rate is considered as per energy
charge rate including MFCA of February, 2012.
d) Energy charge rate for the year 2013 2014 is considered with annual escalation
rate of 6.66% as provided for indigenous coal supply in CERC notification no.
Eco 1/2011-CERC dated 31.03.2011 over the energy charge rate of 2012
2013.
2.17 WBSEDCL has estimated own consumption at the offices and substations for 2011
2012, 2012 2013 and 2013 2014 at 40 MU, 42 MU and 44 MU respectively.
2.18 Considering the projected sent out generation from its own generating stations,
power purchase from different agencies and the projected sales, energy
consumption at own premises, WBSEDCL has projected the energy balance for the
years 2011 2012, 2012 2013 and 2013 2014 also.
2.19 WBSEDCL submitted that considering the programme taken during the year 2011
2012 (Upto February, 2012), they have projected 1190.00 MU and 834.55 MU to be
received through power swap-in during the years 2011 2012 and 2012 2013
respectively. WBSEDCL also projected the short term power purchase to the tune of
990.00 MU, 364.55 MU and 1000.00 MU for the years 2011 2012, 2012 2013
and 2013 2014 respectively mostly during the months March and April in order to
bridge up the gap between supply of power and system demand which usually
occurs during the months mentioned above.
2.20 The petitioner has projected Rs.848522.00 lakh as total power purchase cost for the
year 2011 2012 while for the years 2012 2013 and 2013 2014 the power
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
11
purchase cost has been estimated to be Rs.1067741.00 lakh and Rs.1201642.00
lakh respectively. This power purchase cost includes the cost of purchase of
estimated quantum of infirm power from the units under stabilization.
2.21 Transmission charges payable to WBSETCL for the energy required to be
transmitted by the petitioner through WBSETCL system has been projected as Rs.
98306.44 lakh for the year 2010 2011. Rs. 99654.57 lakh and Rs. 111121.04 lakh
have been projected for the years 2012 2013 and 2013 2014 respectively.
However, WBSEDCL has not claimed any amount for SLDC charges during the
ensuing years under the third control period.
2.22 An amount of Rs. 92001.70 lakh has been estimated as employees cost for the year
2011 - 2012. For the years 2012 2013 and 2013 2014 employees cost have
been projected as Rs. 93554.18 lakh and Rs. 99407.93 lakh respectively.
2.23 The petitioner has considered a D.A hike @ 9% each year for the third control period
i.e., 2011 2012, 2012 2013 and 2013 2014. Moreover, increase in pay in
respect of employee cost has been considered @ 3% as per normal increment over
basic and grade pay for the ensuing years 2011 2012, 2012 2013 and 2013
2014. WBSEDCL further claimed that terminal benefits are reduced in the ensuing
years 2011 2012, 2012 2013 and 2013 2014 as the service of newly recruited
employees are not covered under the pension scheme of WBSEDCL. The
capitalization rate of employee cost is considered 100% for RE works and 15% for all
other Non-RE works.
2.24 The petitioner has projected Repair & Maintenance (R&M) cost including
consumables for the year 2011 2012 to be Rs.16911.80 lakh. WBSEDCL has
claimed that distribution assets of WBSEDCL are increasing rapidly due to RGGVY
programme and other work such as R-APDRP Part A, feeder segregation work etc.
of WBSEDCL. WBSEDCL has added various distribution assets and generation
assets for its generating stations in the year 2011 2012. In order to deliver power
with reasonable quality parameters and to reduce instances of outages for the widely
scattered large consumer base, the expenditure of R & M works of WBSEDCL has
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
12
been increased in the year 2011 2012 mainly due to increase in expenditure for
maintenance of line, cables and networks. For the years 2012 2013 and 2013
2014 the petitioner has claimed to have estimated the R&M cost following the actual
trend upto December, 2011 and has projected Rs.18617.32 lakh for the year 2012
2013 and Rs.20498.58 lakh for the year 2013 2014.
2.25 Rs. 8772.59 lakh has been estimated and claimed by the licensee as administration
and general expenses for the year 2011 2012. The petitioner has further tried to
justify this expenditure which is stated to be due to increase of distribution network
and consumer strength and to fulfill the requirement of the large consumer strength,
WBSEDCL has to introduce different services, besides existing facilities, following
the guidelines given in the Regulations to match the requirement of large consumer
base. Due to shortage of staff, WBSEDCL has claimed to have decided to outsource
some of its services and the estimated expenditure of Rs. 16414.24 lakh has been
considered for the year 2011 2012 to meet the cost of outsourcing. For the years
2012 2013 and 2013 2014, Rs. 24554.88 lakh and Rs. 29565.45 lakh
respectively has been estimated by the licensee as cost of outsourcing considering
growth of those activities and actual upto December, 2011.
2.26 The petitioner has claimed provision for bad debt to the tune of Rs. 85.80 lakh, Rs
94.38 lakh and Rs. 103.82 lakh respectively for the years 2011 2012, 2012 2013
and 2013 2014 on normative basis as per provisions of regulations of the Tariff
Regulations.
2.27 The petitioner has projected capitalization of expenses for employees cost,
administrative and other expenditure and other finance charges under the
construction activities following the existing policy of WBSEDCL for the years 2011
2012, 2012 2013 and 2013 2014.
2.28 WBSEDCL has also claimed an amount of Rs. 3025.00 lakh for 2011 2012, Rs.
3675.00 lakh for 2012 2013 and Rs. 4008.00 lakh for 2013 2014 respectively for
establishing and maintaining communication network set up for the complaint
management mechanism as per West Bengal Electricity Regulatory Commission
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
13
(Standard of Performance of Licensee Relating to Consumer Services) Regulations,
2010.
2.29 The capitalization of interest during the years 2011 2012, 2012 2013 and 2013
2014 has been projected following the same policy.
2.30 Cost of depreciation of assets of WBSEDCL which will be in service during the year
2011 2012 has been stated to have been computed by the petitioner at Rs.
33259.30 lakh on the basis of the methodology stipulated in the Schedule A of the
Tariff Regulations of WBERC. The detail of the calculation of depreciation has been
given in the prescribed format in Volume II of their petition. Depreciations for the
years 2012 2013 and 2013 2014 have been projected as Rs. 36779.07 lakh and
Rs. 40694.00 lakh respectively.
2.31 WBSEDCL has projected Rs. 37295.88 lakh towards interest on borrowed capital,
Rs. 13005.00 lakh towards interest on Bonds and Rs. 603.64 lakh towards other
finance charges for the year 2011 2012. Similarly, for the years 2012 2013 and
2013 2014, they have projected Rs. 38578.10 lakh and Rs. 38879.02 lakh as
interest on borrowed capital, Rs. 13005.00 lakh and Rs. 13005.00 lakh towards
interest on Bond and Rs. 625.46 lakh and Rs. 651.88 lakh towards other finance
charges, respectively. The petitioner has provided the computations showing actual
amounts of interest chargeable in revenue accounts in the Form-C to Annexure 1
in Volume II of their petition.
2.32 WBSEDCL claimed that while computing the interest on loan, they have considered
a new loan of Rs. 106600.00 lakh to be taken in the ensuing years under the third
control period for the purpose of procurement of meter and other materials for
extending distribution service level network.
2.33 WBSEDCL claimed that interest amount payable to consumers on the security
deposit amount in the ensuing years 2011 2012, 2012 2013 and 2013 2014
has been estimated as per existing procedure on the estimated security deposit of
those years computed based on sale growth and tariff growth of respective year.
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
14
WBSEDCL has projected Rs. 2870.44 lakh, Rs. 3315.31 lakh and Rs. 3829.19 lakh
for the ensuing years of 2011 2012, 2012 2013 and 2013 2014 respectively.
2.34 Regarding interest on working capital requirement, WBSEDCL has submitted that,
based on the directive of the Commission vide paragraph 8.11 of its tariff order for
2008 2009, they have not considered any working capital for the year 2011 2012
but has considered Rs. 18579.00 lakh and Rs. 35470.70 lakh for the years 2012
2013 and 2013 2014 respectively to meet up the gap between working capital
requirement and security deposit amount lying with them. Accordingly, WBSEDCL
has claimed interest on working capital to the tune of Rs. 2601.76 lakh and Rs.
4965.77 lakh for the years 2012 2013 and 2013 2014 respectively.
2.35 The petitioner has claimed Rs. 3011.09 lakh, Rs. 3512.56 lakh and Rs. 3721.09 lakh
towards reserve for unforeseen exigencies on normative basis as per the Tariff
Regulations for the years 2011 2012, 2012 2013 and 2013 2014 respectively.
2.36 WBSEDCL has proposed to release a part of the regulatory asset created on the
additional expenditure of WBSEDCL due to revision of pay and allowances as per
ROPA, 2009, at Rs. 62500.00 lakh, Rs 1000.00 lakh and Rs. 8600.00 lakh during the
year 2011 2012, 2012 2013 and 2013 2014 respectively.
2.37 WBSEDCL has also proposed to consider the impact of APR of WBSEDCL for 2009
2010 and the impact of instalments payment claimed by WBPDCL against the
revision of tariff of their new units in the ARR for the years under the third control
period.
2.38 WBSEDCL has also proposed to allow special appropriation on account of the
followings:
a) Additional amount of capacity charge claimed by NTPC Limited for the period
2004 2005 to 2010 2011 arising out of additional capitalization of assets as
per order of Honble Appellate Tribunal for Electricity.
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
15
b) Additional charges to be borne by WBSEDCL on account of increased tariff of
NTPC power stations for the period from 2009 -2010 to 2010 2011 in addition
to the normal power purchase cost for the year 2011 2012.
c) Additional claim of DVC for supply of ;power from Mejia Power Station for the
period 2007 2008 to 2010 2011 and also for radial power supply for the
period from 2009 2010 to 2010 2011 due to the tariff order passed for Units V
& VI of Mejia TPS by CERC.
2.39 Total expenditure of Rs.1338659.51 lakh has been computed by the petitioner and
after excluding the revenue earned from other income, from bulk supply and supply
to Sikkim, expenses attributable to export and taking into account the benefits
passed on to the consumers, interest credit on depreciation and U.I earning of
previous year the annual revenue required from sale of energy to its consumers has
been estimated by the petitioner as Rs. 1117029.82 lakh for 2011 - 2012. Similarly,
for the years 2012 2013 and 2013 2014 total expenditure of Rs. 1530998.93 lakh
and Rs. 1712422.17 lakh respectively have been projected by the petitioner and after
aforesaid deductions estimated for those years, the ARR from sale of energy to its
own consumers have been projected as Rs. 1235858.35.00 lakh and Rs.
1419318.98 lakh respectively.
2.40 With projected revenue requirement of Rs. 1117029.82 lakh proposed by the
petitioner from sale of 19061.77 MU of energy to its own consumers, the average
cost of supply per unit has been computed by the petitioner to be 586.01 paise / kWh
for the year 2011 2012. Similarly, the average cost of supply for the years 2012
2013 and 2013 2014 have been projected at Rs. 587.04 paise / kWh and 610.01
paise / kWh respectively.
2.41 WBSEDCL has also requested to accommodate increase in power purchase cost
arising out of any new tariff order or APR order or FPPCA order on WBPDCL, DPL,
DPSCL, DVC, NTPC or NHPC power stations, etc., which are in addition to what is
mentioned in paragraph 2.40 above.
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
16
2.42 Changes proposed by WBSEDCL in their tariff for 2011 2012, 2012 2013 and
2013 2014 are as follows.
(a) The existing B-ID tariff categories are segregated into two L&MV tariff
categories such as B-ID (Industrial) for L&MV industrial consumers and B-ID
(Commercial) for L&MV Commercial consumers who have contract demand
in between 50 KVA and 125 KVA.
(b) One new L&MV tariff category as Rate C-ID for other L&MV consumers who
have contract demand in between 50 KVA and 125 KVA has been proposed.
(c) The demand charge, fixed charge and energy charge for different categories
of supply have been proposed to be revised.
(d) Voltage wise graded load factor rebate and surcharge have been proposed
for EHV and HV industrial consumers and also for industrial consumers under
Rate B-ID (Industrial) category for 2011 2012, 2012 2013 and 2013
2014 separately.
(e) WBSEDCL has also proposed separate rate for P.F. rebate and surcharge for
the years 2011 2012, 2012 2013 and 2013 2014 for those categories of
consumers to whom those are applicable at present.
(f) WBSEDCL has also proposed revised rates for meter rentals, meter testing
charges, fuse call charges, etc.
(g) Rebate on energy charge for industrial consumers taking supply at 33 KV and
66 KV has been proposed by the petitioner to be 1% of the energy charge
and the same has been proposed for 132 KV at 2%.
(h) Additional rebate of 30 paise per kWh on energy charge has been proposed
for consumers taking supply at 33 KV or above whose contract demand is
1.50 MVA or above and whose load factor is not less than 75% in the billing
period and whose recorded maximum demand during the billing period is not
less than 80% of the contract demand subject to payment of bill within due
Tariff Order of WBSEDCL for the year 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission
17
date. However, for the consumer supply at above 33 KV, the contracted load
will be 10 MV and above.
(i) Rebate for timely payment for the year 2011 2012 has been proposed to be
1% of the billing amount excluding meter rent, taxes, duties, levies and
arrears for those consumers who are already getting such rebate in the year
2011 2012 as well as for Street Light category.
(j) To encourage one time payment for three months bill and to minimize
transaction, a special rebate of 10 paise / unit on energy charge has been
proposed for domestic and commercial consumers under L&MV category
who are covered under quarterly billing system under normal or normal-TOD
tariff scheme provided the payment is made for the quarter at a time within
the due date stipulated for the first month of the quarter.
(k) 1% rebate in addition to the timely payment rebate is proposed to be given to
the consumers who will pay energy bills through e-payment facility within due
date on introduction of it by the petitioner.
(l) Hatchery has been proposed to be included in Rate A (Cm-III) and Cinema
hall are proposed to be considered as commercial consumers.
Tariff Order of WBSEDCL for the yeas 2011 2012 and 2012 2013
CHAPTER - 3 OBJECTIONS AND SUGGESTIONS
West Bengal Electricity Regulatory Commission 18
3.1 Twelve objectors have provided their objections and suggestions within due date of
14.05.2012 in response to invitation of objections and suggestions on the MYT
application of WBSEDCL for 3rd control period. The documents submitted within due
date of receiving of such objections and suggestions have been considered in this
tariff order only. The suggestions and objections submitted by the objectors which
are relevant to the submitted MYT application of WBSEDCL for 3rd control period,
are discussed below:
3.2 On generation aspect to WBSEDCL, HCCI has objected to showing the conservative
generation plan by WBSEDCL from their own generating station allegedly without
any reason and thus HCCI preferred to consider design energy. In such a context
the Commission has following observations. The conventional hydro system
generation, being must run generation if available for operation, depends on the
availability of water which is fully dependent on the climatic condition of each year
and thus no normative parameter has been considered in this aspect. However if
climatic condition is satisfactory in terms of design parameter but the availability of
machine is less than the normative parameter then such deviation is accounted for
in Annual Performance Review (APR). For Purulia Pumped Storage Project (PPSP)
the generation depends on number of factors such as system demand, its pattern,
availability of cheaper peak power and also on the overall conduciveness of the
system to operate PPSP. Thus in tariff order the trend of the past years has been
considered for future projection. However, while projecting sent-out/ generation from
any sources in case any year is already past or partially past, actual generation
figure for the year is preferred if the year has fully past and the generation/ sent-out
figures are estimated after taking into effect the actual portion for a partially past
year. Accordingly energy availability is calculated. Thus, while considering energy
balance for 2011-12, the energy amount on actual basis has been considered to the
extent possible as the year has already passed over. For 2012-13 and 2013-14 the
generation/ sent-out has been estimated based on latest trend as explained in
Chapter - 4. But where specific deviation has been made that has also been
mentioned in the relevant paragraph of this order.
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 19
3.3 On O&M expenses of generating station, HCCI has requested that such O&M
expenses should be allowed strictly in accordance with the norms prescribed in the
MYT regulations. Commission dealt the matter along same line in chapter 5.
3.4 On Power purchase cost the submissions by the objectors along with the views of
the Commission are as follows.
3.4.1 Regarding power purchase expenses Jayashree Textiles has stated that
Commission should exercise strict prudence check while allowing such expenses.
Commission noted the point.
3.4.2 ABECAs submissions are as follows.
i. The power purchase cost should be done on the basis of present tariff rate
and not on the basis of future tariff.
ii. The cost of coal per MT allowed by the Commission to the licensee is much
more than listed coal prices of Coal India Ltd.
iii. According to ABECA by having 100% capacity utilization of DPL & WBPDCL
the demand can be met without sourcing power from other sources.
iv. To minimize cost of power of WBPDCL and DPL by increasing their PLF and
lowering T&D loss, by reducing their Return on equity and by disallowing the
unforeseen exigencies and Bad Debt.
On the above issues Commissions views are as follow:
The contention of ABECA in (i) above has been considered in view of the availability of mechanism of power purchase cost recovery through MVCA in
case there is any increase in power purchase price.
In the submitted application of the instant licensee there is no scope of allowing higher coal price and thus the point (ii) is not relevant.
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 20
The WBSEDCLs peak demand is of the order of 4900 MW for its own command area and another 550 MW to 750 MW is required to supply to CESC. Whereas
the availability from WBPDCL at 100% capacity utilization is 3493 MW. Similarly
the maximum possible surplus from DPL considering its 100% capacity utilization
of installed capacity is 310 MW. Moreover 100% capacity utilization of installed
capacity in longer perspective is mere theoretical from technological aspects.
Thus ABECAs contention as per (iii) above does not seem to have merits.
On issue (iv) above the cost reduction issue of power from WBPDCL and DPL is related to the tariff applications of WBPDCL and DPL. Thus Commission does
not intend to deal such matter in this order.
3.4.3 On quantum of procurement of power by WBSEDCL from WBPDCL, HCCI has the
following observations:
i) Projected purchase of power from WBPDCL is in lesser quantity than the
normative generation of WBPDCL which has resulted in procurement
proposal for short-term power from traders/exchange at high cost.
ii) The normative generation level of WBPDCL should be considered for
purchase of power from them by WBSEDCL.
iii) In case past performance is considered instead of normative generation for
WBPDCL and lower than benchmark (normative) generation level are
considered for WBPDCL generation, then the capacity charges should be
reduced pro-rata on account of lower plant availability factor.
iv) According to HCCI though WBSEDCL considers the past trend to be the sole
reason for assumption of conservative generation from WBPDCL generation
plant for ensuing years of 3rd control period, in certain years of the past the
energy received by WBSEDCL are much higher than the conservative
projections made by it for the 3rd control period.
On the above issue the Commission is of the view that WBSEDCLs projection on
the basis of past trend may not be inappropriate since real time situation in the past
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 21
shows that WBPDCL has failed to provide normative generation for some of its
plants. This has resulted into distorted energy balancing scenario which is reflected
by wide variation in projection vis--vis actual energy sold to persons other than
licensee and consumers in tariff order and APR respectively as is being detailed out
in paragraph 5.27 of this order. As a consequential impact the consumers are likely
to be burdened with increased tariff through FPPCA/APR in future as well as there is
likely to be shortage of cash flow in real time operation. On the other hand
WBPDCLs norms cannot be resolved as it will tantamount to rewarding the
inefficiency of WBPDCL. Accordingly, WBSEDCLs projection of energy on the basis
of past trend of different sources has been considered by the Commission. Thus
Commission has preferred to consider the actual sent out energy of WBPDCL from
each power station of WBPDCL for recently fully/ partially passed years to capture
the current trend of performance after due consideration of the outliers. In fact the
lower level of performance as shown in table under the paragraph 4.4(i) of this order
by Sagardighi Thermal Power Station (SgTPS) in first six months compared to same
period of 2011-12 shows the necessity to depend upon average performance of a
longer period specially from points of view of energy balancing of a licensee or power
purchase planning. The matter is being detailed in Chapter 4 of this order where due
explanation is provided wherever necessary. For capacity charge recovery the
suggestion of HCCI has been well taken and accordingly the capacity charge
payable to WBPDCL has been considered in this order.
3.4.4 Regarding power purchase from DPL, HCCI has mentioned that WBSEDCL has not
substantiated the load growth of DPL. The Commission feels that the essential issue
being the availability of power to WBSEDCL from DPL. In that context the
Commission observes that WBSEDCL has already shown the decreasing trend in
sale of surplus power by DPL to WBSEDCL in the last few years. As there is no new
unit to be commissioned by DPL during 3rd control period and there will be at least
normal growth in DPL command area, supply from DPL to WBSEDCL is not likely to
improve any further.
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 22
3.4.5 HCCIs view on conservative estimates of energy received from Bhutan without
substantiated reasons has been noted by the Commission. Commission on scrutiny
of Annexure-5 of Appendix-A of the MYT application of WBSEDCL for 3rd control
period found that Govt. of Bhutan has already intimated the beneficiaries of the
power stations of Bhutan through Eastern Regional Power Committee (ERPC) on
reduction in quantum of energy for each year. Accordingly, the reduction in quantum
of sent out power as projected is accepted by the Commission.
3.4.6 On capacity charges of NTPC Power Stations HCCIs view is that WBSEDCL has
estimated capacity charges at higher proportion than the proportion of energy it has
considered from the Farakka STPS (FSTPS) and Talcher TPS (TTPS). In this
context Commission likes to draw the attention to the fact that capacity charge does
not reflects always the delivered energy. Such capacity charge may also include
back-down periods due to low demand. Thus capacity charge recoverable during a
period may not be necessarily proportional to the actual delivered energy in
comparison to normative generation. Thus, the HCCIs objection on grounds of non-
commensurable capacity charge in respect to energy delivered cannot be accepted.
The same trend of the demand pattern and back-down level can be considered to
remain more or less same during the 3rd control period. Accordingly the recovery of
capacity charge from 2011-12 to 2013-14 is appropriately dealt with in Chapter 5.
3.4.7 The objectors view that the purchase of energy from Maithon Right Bank of only
508 MU in FY 2012-13 instead of 1016 MU as proposed for FY 2013-14 without
substantial reason has been noted by the Commission. Maithon Right Bank Project
Unit-2 has started supply of power commercially from 24th July, 2012 as reported by
WBSEDCL in response to Commissions letter vide no. WBERC/TP-53/11-12/0995
dated 01.10.2012, which was raised in accordance to the Tariff Regulations.
Accordingly the energy from such source for 2012-13 is being modified to 857 MU.
3.4.8 The HCCI has objected to the purchase of power in short-term mode as according to
them such purchase is consequent to the non-achievement of distribution loss
norms, which means that short-term power is always required to meet the shortage
arising out of non-achievement of distribution loss norms. In many instances it is
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 23
required to meet the actual shortage in supply also. Moreover for 2012-13 and 2013-
14 WBSEDCL has made the energy balance on the basis of normative loss only. It is
also found that the proposed volume of short term power purchase is only a small
part as shown below:
Particulars 2011-12 2012-13 2013-14 Short-term power purchase (MU) 990.00 364.55 1000.00Total power purchase (MU) 29862.00 32221.05 34006.00Percentage of short-term power purchase (MU) 3.32 % 1.13% 2.94%
Moreover, the distribution loss takes place over the time period under consideration
more or less equally whereas short-term power is procured for a very small part of
that period only. In such circumstances it cannot be said that the procured power
under short-term mechanism is also supplementing the power for excess distribution
loss due to non-achievement of distribution loss in those part of the period under
reference when there is no supply from short-term sources.
Thus, the contention of HCCI that the short-term power is consequent to non-
achievement of distribution loss norms cannot be accepted.
On the issue of price of such short-term power Commission would deal with the
matter in Chapter-4.
3.5 On distribution loss the submission of the objectors along with the view of the
Commission are as follows:
3.5.1 ARCVAC Forge Cast Pvt. Limited has suggested for following merit order dispatch
principle for disallowing cost of excess distribution loss. In this context, the
Commission feels that this is not logical as this will be tantamount to say that only
high cost energy contributes towards distribution loss. In fact, the power purchase at
different rates are sourced at different instant of time throughout the year and more
or less distributed over the year according to demand pattern and loss occurs at
each and every instant of time under the same law of physics. Thus, it cannot be
said that power procured at higher cost will be considered for disallowed portion due
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 24
to high distribution loss. According to the Commission weighted average price of
pooled power purchase is to be considered as a rational approach for disallowance
of excess power purchase cost for excess distribution loss over the normative loss.
3.5.2 Regarding distribution loss, the West Bengal Cold Storage Association (WBCSA)
has mentioned that the distribution loss for the year 2011-12 may be fixed at 17.49%
for the purpose of computation of revenue requirement though the distribution loss
as stated by WBSEDCL in their application is 24.93% for the year 2011-12. In this
context it needs to be mentioned that for determination of revenue requirement by
WBSEDCL the distribution loss has been considered only at the normative level for
the concerned year so that the excess loss is not allowed to pass through to the
consumers.
3.5.3 Regarding distribution loss ABECA has proposed that it should not be allowed more
than 9% and opposes the claim in excess of 9% distribution loss. ABECA has not
provided any details in establishing their claim. As normative parameters on such
issue has already been fixed in the Tariff Regulations after inviting objection &
suggestions, only such norms of distribution loss will be considered in this order.
3.6 On transmission charges the submission of the objectors along with the views of the
Commission are as follows:
3.6.1 On STU charges the objection by HCCI is primarily on the following points:
i. The STU charges payable by WBSEDCL shall be based on ARR determined
for WBSETCL by the Commission for the year 2011-12, 2012-13 and 2013-
14 which is also a suggestion from ABECA.
ii. The charges for intra-state transmission line that are being recovered through
POC charges of Inter-state transmission charges shall not be recovered
through STU charges
3.6.2 The claim of enhanced CTU charges payable by WBSEDCL as per point of
connection (POC) method has been kept pending due to legal issues at the time of
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 25
submission of tariff application. ABECA have suggested to furnish the court order of
legal dispute by WBSEDCL and after that the Commission may consider the merit of
the claim of WBSEDCL regarding CTU charges.
3.6.3 The view in 3.6.1(i) has been considered by the Commission and the matter related
to 3.6.1(ii) is in the scope of tariff order of WBSETCL and thus is not being dealt
here. On the issue of 3.6.2 Commission asked the status of the legal cases from
WBSEDCL vide letter no. WBERC/TP-53/11-12/0995 dt. 01.10.2012 and
WBERC/TP-53/11-12/1078 dated 19.10.2012 which were issued in accordance to
the Tariff Regulations. In response it reveals that though legal case is pending the
payment of POC charges has been implemented. The matter has been further dealt
with in Chapter 5.
3.7 On Employee Cost the submission of objectors along with the views of the
Commission are as follows:
3.7.1 On Employee Cost, both HCCI and Jayashree Textiles have mentioned that
employee cost increase is 35% in 2011-12 over 2010-11. According to them
regarding the employees cost, the actual employees cost in FY 2010-11 of
WBSEDCL was 855.45 crore which constitutes of an abnormal expense amounting
to Rs.171.81 crore towards provision for terminal benefit on account of revision in the
ceiling of gratuity amount which means normal employees cost during FY 2010-11 is
Rs.683.64 crore (Rs.855.45 less 171.81 crore). Thus, according to the objector, the
projected employee cost of Rs. 920.02 crore for FY 2011-12 which is 34% higher
than the normal employee cost for 2010-11, is abnormal by any standard.
3.7.2 ABECA have opposed the increased pay and allowances of the employees since the
revised pay and allowances of WBSEDCL is effective from 01.04.2008 and the Tariff
Order for 2008-09, 2009-10 and 2010-11 was passed on the basis of revised pay
effective from 01.04.2008. So there is no reason for revision of Tariff on the ground
of revised pay and allowance. ABECA have also suggested that WBSEDCL should
furnish detailed list of staff grade wise pay fixation as per revision of pay and
allowances and arrear of pay allowed to the staff individually along with specific order
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 26
of the licensee in this regard. They have also requested to consider the difference
that arises after tariff order in the APR on the basis of actual and audited report.
3.7.3 The objectors sought to reason out against the proposed employee cost by
WBSEDCL is not properly justified due to following reasons.
i. The way of normalization of employee cost is being done by HCCI/
Jayashree Textile through reducing the employee cost in 2010-11 by an
amount of the terminal benefit is not justifiable as such component will also
be an eligible amount for each year including in the year 2011-12 which has
the terminal benefit amount in the employee cost for 2011-12.
ii. The employee cost of WBSEDCL in 2010-11 as per the annual accounts of
WBSEDCL stands at Rs 856.00 crore.
iii. The pay structure of the employee is governed under the rules framed under
Revision of Pay and Allowance (ROPA), 2009 of WBSEDCL and thus is to be
taken into consideration as wage revision does not imply that increase in cost
for such wage revision is for one time only and such cost will have no future
increase with the inflationary trend.
iv. Objectors view of not allowing increased employee cost at this point of tariff
determination stage with an ultimate intention to consider such increased cost
on actually incurred basis at later stage, i.e., APR stage cannot be
considered by the Commission as this will affect the cash flow of the licensee,
the consequence of which will be the requirement of extra financing cost.
Such extra cost would imply extra tariff at a later stage.
3.8 The objector HCCI in its objection on O&M costs has referred to different regulations
and model regulations without however mentioning the purpose of such referencing.
HCCI has claimed that WBSEDCL claim O&M expenses under various
nomenclatures. HCCI also provides a comparative study on O&M expenses for per
unit of sales in different States.
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 27
On the above observation, the objectors view on different elements of O&M cost
has been taken into consideration by the Commission in accordance with the Tariff
Regulations and the elements which are not considered as elements of O&M cost
under Tariff Regulations are considered separately in a manner as has been dealt
with in the Tariff Regulations.
3.9 On the issues of Administrative and General Expenses the submission of the
objectors along with the views of the Commission are as follows:
3.9.1 Regarding Administrative and General Expenditure ABECA have suggested that the
claim on the basis of actual cost incurred by WBSEDCL at the time of furnishing the
proposal is to be considered. The point is noted and has been dealt with in Chapter
5.
3.9.2 On Other Administrative and General (A&G) expenses HCCI stated that WBSEDCL
has considered a year on year escalation of 17% in the MYT period. According to
HCCI such high escalation in A&G expenses should not be allowed to WBSEDCL
and marginal increase linked with inflation indices may only be permitted. HCCI has
also drawn the attention that there is no specific reference in the tariff application of
capitalization. On the issue of capitalization Commission finds that in paragraph 5.9
of Volume-1 in the MYT application WBSEDCL deals with the capitalization issue.
The annual accounts of 2011-12 have also shown the capitalization. On the other
issue Commission noted the point and dealt with the issue in Chapter 5 of this order.
3.9.3 On individual components of Administrative & General Expenses for distribution such
as Rent, Legal charges and Auditor fees, HCCI has objected that the expenses have
been considered with a high growth rate. HCCI is also of the opinion that such cost
can be considered during APR only on actual basis. As rent, Auditors fee and legal
charges are parts of controllable item of Administrative and General expenses,
overall excess cost, if any, with respect to above heads may not be allowed during
APR due to the ceiling in Administrative and General Expenses on account of being
a controllable item. Thus the suggestion of HCCI for considering such cost on actual
basis in APR in general cannot be accepted. Moreover, there are issues like
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 28
financing cost for any cash gap and tariff impact. Considering all the above aspects
and other information available in the application submitted by WBSEDCL and
annual accounts, the Commission decides the amount to be admitted in Chapter-5.
3.10 ABECA have also opposed the proposal of increase in R&M cost due to increase in
consumer base.
On repair and maintenance expenses, HCCI has stated that increase in the
expenses shall be reflective of the inflationary index.
On this account Commission is of the opinion that increase in consumer base along
with matching distribution network shall also be reflective parameters while deciding
the repair & maintenance cost. Improving the service quality is also a major relevant
parameter.
3.11 On the point of cost of outsourcing HCCIs views are as follows:
i) The cost of outsourcing should not be allowed to WBSEDCL as there is very
little rationale with regard to its nature, cost and effectiveness and having no
results demonstrated by WBSEDCL for the cost supposedly incurred.
ii) Certain jobs and services can be performed effectively through outsourcing
but to consider that around 15,000- 20,000 contracted employees would be
required by WBSEDCL is implausible and unconvincing.
iii) Jobs like substation and line maintenance were previously being done by the
own staff of WBSEDCL.
iv) Measures such as Online billing, spot billing, etc are novel ways of billing but
it does not entail that some new jobs are now being taken up by WBSEDCL.
The expenses on spot billing should be demonstrated by a reduction in the
A&G expenses of WBSEDCL as it is only an alternate way of bill distribution.
On the above issues the Commission is of the view that
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 29
i) WBSEDCL has raised claim in accordance with the provisions in the Tariff
Regulations.
ii) On the issue of number of contracted employee and rationality of it, from
HCCIs submission it cannot be found that why such numbers are implausible
and what are the reasons on which it can be said unconvincing. On scrutiny,
Commission finds in the annual accounts of WBSEDCL for 2011-12 the
consumer strength has already increased to 106.73199 lakh from 85.65 lakh
in 2010-11 which shows an increase of 24.61% by a single year.
Simultaneously Commission also observes that the employee in regular
establishment has been reduced significantly in the last control period
whereas consumer strength is increasing rapidly as shown in the following
table.
2009 2010 2011 2012 No of Employee in thousands 24072 19236 18851 17932No of Consumer in lakh 7246759 7622178 8565374 10673202N.B: a) No. of consumers available from Annual Reports and Accounts of WBSEDCL b) No. of employee for 2009 available from APR application and c) No. of employees for 2010, 2011 and 2012 from MYT tariff application for the year
2011-12, 2012-13 and 2013-14.
It is also to be noted that due to reduction in employee in regular
establishment its impact on employee cost has been duly considered by the
Commission while admitting employee cost. Under such circumstances
commission feels that with the increasing consumer strength and decreasing
trend of own employee the outsourcing has merit for discharging of statutory
obligations. Thus Commission proceeds to determine the outsourcing cost
that is required to be admitted for the ensuing years of 3rd control period.
iii) The expenses claimed for new Sub-station and lines are for operating
personnel which are new.
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 30
iv) The expenses of spot billing are basically replacement of the existing job.
Thus this expenditure, being totally outsourced job, shall be passed as a part
of outsourcing cost and not under the Administrative and General Expenses.
On scrutiny it is found from the application of WBSEDCL that WBSEDCL has
claimed outsourcing cost on number of items which are being dealt with in
Chapter 5 of this order.
3.12 In the point of interest on loan HCCI has stated that interest on loans may be
allowed only after considering our objections in respect of capital investment,
programme proposed by WBSEDCL. As no details, justification of capex schemes
has been provided and no investment approvals furnished, the capital investment
plan proposed by WBSEDCL is liable to be rejected. Consequently the interest on
long term loans has to be recomputed considering no eligible drawals of loan. In
addition HCCIs observation is that interest expense claimed by WBSEDCL does not
commensurate with the capitalization sought by WBSEDCL in the MYT period.
HCCI says that interest on R-APDRP loan should not be allowed in tariff as such
loan will be converted into grant. HCCI also raised question about inadequacy of
detailing on certain loan such as REC Limited Package, loans from Bank/RECL
and for different schemes under plan and Non-plan other than securitization of CPS
outstanding.
The capital expenditure programme under R-APDRP Part A and R-APDRP Part
B scheme has already been approved by the Commission in case no. WBERC/OA-
68/2009-10 and WBERC/OA-118/10-11 vide order dated 23.04.2010 and
01.09.2011 respectively. Thus as long as the loan of R-APDRP Part A or R-
APDRP Part B is not being converted into grant partly or fully its interest will be
eligible to be admitted by the Commission if such interest is payable in the
concerned year. Other schemes such as RGGVY, APDRP do not require any
investment approval as those schemes were introduced by the Government of India
at a period when such investment approval was not required by the licensee in
accordance with the then regulation of the Commission applicable at that time.
However, such schemes, being approved by the concerned nodal department/
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 31
agency of Government of India, the due diligence has been done by different
concerned authority and thus do not require any fresh investment approval at this
stage of the projects which has already attained finality and thus will be considered
for interest calculation purpose.
Regarding inadequacy of data for certain loans such as REC Limited Package,
loans from Bank/RECL and for different schemes under plan and Non-plan other
than securitization of CPS outstanding, the details have been gone through by the
Commission from the Annual Accounts of 2011-12 and accordingly dealt with in
Chapter 5.
3.13 On interest on Consumer Security Deposit the HCCI has apprehension that the
amount claimed by WBSEDCL is not adjusted in bills paid to the consumers in toto.
The Commission cannot act merely on the basis of apprehension of any person
unless there is at least some prima facie instances of any anomaly on the related
issue. Moreover in case of non-receiving of interest on security deposit consumer
has appropriate remedial measures under the law. However the issue is dealt with in
Chapter 5.
3.14 On the issue of bad debt the submission of different objectors along with the view of
the Commission are as follows:
3.14.1 ABECA have suggested that WBSEDCL should furnish the detailed chart of
defaulting consumers and unrealized amount from them and steps taken to realize
the amount. Before furnishing such data no amount should be allowed to WBSEDCL
on this account.
3.14.2 HCCI has referred to regulation 5.10 of the Tariff Regulation.
3.14.3 The comments of objector at 3.14.1 and 3.14.2 have been noted and is duly dealt
with in chapter 5 in accordance with the Tariff Regulations for due consideration.
3.15 On the issue of Minimum Alternate Tax HCCI refers regulation 5.13.1 and rely on the
point that it is allowable and to be recovered as pass through element. Commission
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 32
is of the opinion that the regulation has to be looked into with the following points
also.
a) The regulation does not say that such pass through cannot be done at tariff
determination stage.
b) Where Minimum Alternate Tax is mandatory for payment at certain frequency
within the period under consideration then just after the payment has been
made, it cannot be recovered normally at such frequent interval through
revision of tariff as it is under fixed cost head.
c) MAT as deposited can be allowed by the Commission without the
assessment order.
In view of the above fact the licensee is required to pay the tax in a quarterly
frequency. Thus to ensure proper cash flow the projected amount of MAT is required
to be passed through the tariff order subject to truing up in the APR as in the mid
way of a year separate order on this small amount cannot be brought out as it is not
rational.
3.16 On the issue of unforeseen exigencies the submission of the objectors and the view
of the Commission are as follows:
3.16.1 According to ABECA unforeseen exigencies is not a cost at all and as per the Act
this cannot be included in the ARR and thus they suggest to refund the accumulated
fund with income derived out of such fund to the consumers through reduction of the
said accumulated amount from the ARR for the year 2011-12, 2012-13, 2013-14 and
no fund is to be allowed further.
3.16.2 On the other hand HCCI feels that Reserve for unforeseen exigencies may be
allowed by the Honble Commission only after strict prudent check duly verifying that
such reserves are invested in interest paying securities and the interest income
earned on such reserve are ploughed back / netted-off while claiming the reserve for
unforeseen exigencies of subsequent years.
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 33
3.16.3 Commission is of the opinion that the expenditure for unforeseen exigencies is
statutorily approved cost and has been maintained to serve the purpose for which it
is created. Commission noted the points in 3.16.1 and 3.16.2 and duly dealt with in
Chapter 5.
3.17 On the issue of interest on Working Capital the objectors submission along with the
Commissions view are given below:
3.17.1 On interest on Working Capital the objection of HCCI is with respect to the
provisional amount of security deposit which according to HCCI shall be static over
the MYT period. On the contrary, WBSEDCL has claimed interest on security deposit
in an increasing trend at Rs 28.70 crore, Rs 33.15 crore and Rs 38.29 crore in 2011-
12, 2012-13 and 2013-14 respectively thereby implying that it has considered a
yearly increase in security deposits from consumers. According to HCCI, WBSEDCL
has ignored to take this increase into account while computing the interest on
working capital. HCCI has submitted that the Commission should take this anomaly
into account and suitably adjust the computations in respect of interest of working
capital.
3.17.2 Regarding interest on Working Capital ABECA have opposed the same stating the
reason that as the Commission directed WBSEDCL to invest the Security Deposit
received from the consumers as Working Capital there would be no need to claim
any amount as interest on Working Capital. Secondly they opposed the rate of
Interest on Working Capital @ 14% whereas the rate of interest payable on Security
Deposit is 6%. According to them interest on Working Capital shall be 6%. They
have also suggested to direct WBSEDCL to furnish details of the security deposit
held by WBSEDCL till date and to submit the status report regarding quantum of
Security Deposit, utilization of such deposit and rate of interest paid by them to the
consumers before entertaining the claim of WBSEDCL on interest on Working
Capital.
3.17.3 Commission noted the point in 3.17.1 and dealt with this accordingly in Chapter 5.
Regarding the issue of 3.17.2 Commission cannot ignore the need of additional
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 34
working capital requirement within normative level as provided in the Tariff
Regulations if the security deposit of consumer is not sufficient to cover the
normative working capital requirement. Moreover as such working capital
requirement beyond the amount collected from security deposit of consumer is
required to be mobilized in the form of loan from financial institutions or market, thus
the interest on such loan is bound to be at market driven rate. Thus commission is
bound by the regulation to provide the interest as specified in the regulation.
3.18 On capital investment issue objections put forwarded by HCCI are as follows:
1. The detailed break-up of the capital investment with respect to schemes,
justifications etc. have not been provided by the Petitioner. Further the additional
capitalization may not be allowed by the Honble Commission as the filing made
do not strictly adhere with the requirements of Regulation 5.1 and 5.2 of the
MYT Regulations and the status of investment approvals mandated under
Regulation 2.8.2.3 is neither known nor available with the Petition. In such case,
the capital investment plan should be out rightly rejected by the Honble
Commission.
2. Without prejudice to the above, the capitalization towards assets created
pursuant to RGGVY and R-APDRP scheme and through consumer
contributions and other grants, etc. should be segregated from the other capex
schemes. Depreciation on assets created under RGGVY, R-APDRP scheme
and through consumer contributions and other grants etc. should not be allowed
in the ARR.
3. The depreciation which has already been claimed on assets created under
RGGVY, R-APDRP scheme and through consumer contributions and other
grants etc. should be clawed back and given effect in the MYT order.
In addition to the above objection, HCCI raised the question that whether WBSEDCL
is entitled to recover
i) Capital created out of consumers contribution or grant.
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 35
ii) Depreciation of asset formed through consumers contribution or grant.
iii) While finding out equity on normative basis, whether the asset created out of
consumers contribution or grant will be considered.
In fact, the question of recovery of capital created out of consumers contribution
or grant is not very clear. However the values of such asset are not considered
as equity base. In case of normative equity calculation the mater is dealt with in
Chapter 5 of this order. However, depreciation on the assets formed through
consumers contribution or grant is recoverable as such amount is required for
future replacement of such assets on expiry of their life.
Regarding the issue raised on capital expenditure programme or investment
proposal in relation to depreciation and normative equity the points raised by
HCCI have been noted and accordingly dealt with in chapter 5 while arriving at
the depreciation and equity base and appropriate direction has been given in
chapter-10 to WBSEDCL to provide details so that during APR the truing up can
be done on the basis of such details.
3.19 Regarding depreciation ABECA have proposed to furnish detailed item wise
depreciation amount with life span of each item and repayment of loan out of such
depreciation. Balaji Paper & Newsprint Pvt. Ltd. has referred statutory auditors para
in relation to fixed asset registers. This issue of fixed asset registers was reported in
annual accounts of 2009-10 for not following CARO, 2003. The same annual
accounts show that figures of fixed assets with depreciation and value of
depreciated assets are available accounting unit wise and accounting code wise.
Such report also reveals that the job of identification and verification of fixed assets
has already undertaken by the company and has been completed for assets
capitalized upto 31.03.2008 and the balance work was in progress. Subsequently
such issues are not reported in the annual accounts of 2010-11 and 2011-12. Thus it
implies that such fixed asset now is being maintained more comprehensively.
Moreover, Commission observes that WBSEDCL has furnished the information
related to depreciation and repayment of loan in a manner as specified in the Tariff
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 36
Regulations. However, direction has been provided in relation to this issue as
already explained in paragraph 3.18.
3.20 Regarding return on equity ABECA have suggested that the rate of return should not
be allowed at more than the RBI rate of interest as WBSEDCL is being a
government company and before the enactment of the Electricity Act 2003,
WBSEDCL would have earned 3%.surplus. In this context commission will follow the
Tariff Regulations which has gone through previous publications.
3.21 On the issue of distribution loss level vis-a-vis lease rentals HCCIs view is that if the
expenses of R-APDRP is allowed then the loss trajectories prescribed in the MYT
regulations need to be revised. In this context the Commissions view is that the cost
of such R- APDRP Part A is limited only to 62 towns in the State covering about 15
lakh consumers only (as provided in the details of the scheme of R-APDRP Part-A
during investment approval). For R-APDRP Part-A there is no conditionality of any
targeted AT&C loss. Such target has been provided only for R-APDRP Part-B
scheme which is under implementation phase and as per programme those projects
will be completed beyond the period of 3rd Control Period. Thus the benefit of loss
reduction of such project is not expected within this 3rd Control Period. Moreover,
merely on the basis of a small part of the area of supply of the licensee the norms of
the distribution loss for the whole area of supply cannot be changed as such type of
improvement programme is a natural process undertaken by any licensee while they
are being offered with the normative target. Furthermore on the point of expenses on
MPLS-VPN connectivity the matter shall be looked into in the light of need of
discharging regulatory obligation of the licensee under SOP Regulation as
mentioned by WBSEDCL in addition to other purpose for which such network is
being used.
3.22 On other Incomes HCCI has objected to the conservative estimates of WBSEDCL in
respect of income from investments and bank balances which roughly translates to a
paltry return of 4% according to them and asked for detailed investigation by the
Commission. HCCI also mentioned that a normative rate of interest of 8% on FDR
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 37
balance for allowing the income from investment and bank balances including FDR
income.
Commission has observed that Investment amount of Rs. 577.12 crore for the year
2010-11 is reflected in the Annual Accounts for the year 2010-11 under Schedule-10
which is shown as cash and bank balance. This head indicates that such balance is
temporary in nature and is for the closing date of the Accounts. This implies that
such amount is not expected to be continued throughout the year at the same level.
Thus the accrued interest as shown in the audited accounts of Rs 39.79 crore in the
Note no. 24 of Annual Account of 2011-12 is being admitted by the Commission and
accordingly dealt with in Chapter 5 of this order.
3.23 The submission of the objector in relation to sale to other licensee along with the
view of the Commission are as follows:
3.23.1 On the question of sale of energy to other licensee, HCCIs submissions are:
i. Increase in power purchase cost and cost of supply of WBSEDCL is around
14.23% and 16.50% respectively, the increase in sale price to other licensee
considered in MYT projections is only 4.17%.
ii. The basis of arriving at the sale price projected for sale to other licensee has
not been explained in the MYT Petition.
iii. It is unclear why WBSEDCL would supply power to other licensee at lower
than its cost of supply.
iv. Price for sale to other licensee shall be at the cost of supply of that respective
year or at a price which factors in the year on year increase in power
purchase cost and cost of supply in FY 2011-12 over FY 2010-11.
3.23.2 ABECA have pointed out that sale of power to CESC Ltd is at a rate less than the
rate of power purchase from Central Generating Company and Bhutan. ABECA have
also mentioned that WBSEDCL purchases power from CESC Ltd. and CESC Ltd.
also purchases power from WBSEDCL and both are pleading the tariff hike of each
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 38
other. ABECA suggested the drawal of power of CESC Ltd. from WBSEDCL should
be adjusted with the power drawal of WBSEDCL from CESC Ltd.
3.23.3 In this context Commissions view is that the purchase price of power by one
licensee from another licensee is being regulated keeping in view of the interest of
the consumers of both the licensees. Moreover, the market price trend and long term
power purchase cost from new Power Stations are also looked into before deciding
such price. Otherwise any reduction in load demand of any seller licensee due to
replacement of such demand by other new sources may affect the consumers of the
referred selling licensee severely as they may require to bear the liability of
compensation of such business loss. Moreover, the demand pattern of the purchaser
licensee and any other conditions under which purchase are taking place are also
required to be looked into. Moreover, there is wide disparity in retail tariff among the
licensees due to such type of inter-licensee selling prices which are also required to
bring under control to a reasonable extent gradually. Further, the proposal for selling
power by WBSEDCL to other licensee at a rate not less than the costlier sources
does not have any merit as the demand of such licensees is historically met from
long past and the costlier power procurement decisions are taken at different time to
meet the increasing demand of both own consumer and other licensee. In fact,
Commission is required to strike a balance on different aspects for such purchase of
power. On the basis of such factors the purchase price for power by different
licensees is required to be set in their Tariff Order.
3.24 On share of benefit passed on to consumers the objection of HCCI is primarily on the
two aspects:
The projected selling rate considered for sale of power to persons other than consumers and licensees and for the notional sale of power against swap
out, and
While computing the presumptive gains, due consideration has not been provided to the fact that lower sales were reported to persons other than
Tariff Order of WBSEDCL for the years 2011 2012 and 2012 2013
West Bengal Electricity Regulatory Commission 39
consumers and licensee as there was a significant under-achievement of
distribution losses.
The licensees are penalized by disallowance of expenditure arising out of under
achievements of distribution losses and thus the Commission is of the view that they
cannot be penalized for second time on the basis of notional gain on account of
notional sale as claimed by the objector.
The other point has been only noted by the Commission but not accepted the logic
as the expenses due to swap out is also considered for reducing the ARR to be
borne by the consumers and license