Target Services, ESMIG and ECMS François Maigre Senior Payment Expert SWIFT Thomas Redelberger Senior Manager Securities Initiatives SWIFT Operations Forum 2021
Target Services, ESMIG and ECMS
François Maigre
Senior Payment Expert
SWIFT
Thomas Redelberger
Senior Manager Securities Initiatives
SWIFT
Operations Forum 2021
TARGET Services - Main milestones and phases
2020 2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Migration
to ESMIG
contractual
framew ork
TIPS
T2S
T2
ECMS*
31/03
Functional Testing
NSP selection and contracts
preparation completed
30/06
NSP procurement
completed
T2 – 21 NovTIPS – 21 Nov T2S – 11 Jun ECMS – Nov
Functional Testing
User Connectivity Testing
NCB Connectivity Testing
Pre-Mig.PROD Connectivity Testing
Connectivity Testing
User Connectivity Testing
User Connectivity Testing Functional Testing
NCB and CSD Connectivity Testing
*To be confirmed
Functional Testing
Functional Testing
Functional Testing
PROD Connectivity Testing Pre.Mig.
TIPS customers successfully migrated to the ESMIG framework
TARGET Services - Main milestones and phases
2020 2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Migration
to ESMIG
contractual
framew ork
TIPS
T2S
T2
ECMS*
31/03
Functional Testing
NSP selection and contracts
preparation completed
30/06
NSP procurement
completed
T2 – 21 NovTIPS – 21 Nov T2S – 11 Jun ECMS – Nov
Functional Testing
User Connectivity Testing
NCB Connectivity Testing
Pre-Mig.PROD Connectivity Testing
Connectivity Testing
User Connectivity Testing
User Connectivity Testing Functional Testing
NCB and CSD Connectivity Testing
*To be confirmed
Functional Testing
Functional Testing
Functional Testing
PROD Connectivity Testing Pre.Mig.w
e a
re h
ere
TIPS customers successfully migrated to the ESMIG framework
TARGET Services - Main milestones and phases
2020 2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Migration
to ESMIG
contractual
framew ork
TIPS
T2S
T2
ECMS*
31/03
NSP selection and contracts
preparation completed
30/06
NSP procurement
completed
T2 – 21 NovTIPS – 21 Nov T2S – 11 Jun ECMS – Nov
Connectivity Testing
*To be confirmed
Functional Testing
we a
re h
ere
TIPS customers successfully migrated to the ESMIG framework
T2 – 21 NovT2S – 11 Jun ECMS – Nov Automated migration of existing TIPS customers to ESMIG is
completed (CERT + PROD environments)
TARGET Services - Main milestones and phases
2020 2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Migration
to ESMIG
contractual
framew ork
TIPS
T2S
T2
ECMS*
31/03
NSP selection and contracts
preparation completed
30/06
NSP procurement
completed
T2 – 21 NovTIPS – 21 Nov T2S – 11 Jun ECMS – Nov
Connectivity Testing
User Connectivity Testing
NCB and CSD Connectivity Testing
*To be confirmed
Functional Testing
Functional Testing
Functional Testing
we a
re h
ere
TIPS customers successfully migrated to the ESMIG framework
TIPS customers successfully migrated to the ESMIG framework
Automated migration of existing T2S
customers to ESMIG is completed (UTEST)
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Have you already analysed the technical
impacts of the migration of T2S to ESMIG ?
A: Yes
B: No
C: I am not a T2S user
Polling question
TARGET Services - Main milestones and phases
2020 2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Migration
to ESMIG
contractual
framew ork
TIPS
T2S
T2
ECMS*
31/03
Functional Testing
NSP selection and contracts
preparation completed
30/06
NSP procurement
completed
T2 – 21 NovTIPS – 21 Nov T2S – 11 Jun ECMS – Nov
Functional Testing
User Connectivity Testing
NCB Connectivity Testing
Pre-Mig.PROD Connectivity Testing
Connectivity Testing
User Connectivity Testing
NCB and CSD Connectivity Testing
*To be confirmed
Functional Testing
Functional Testing
Functional Testing
we a
re h
ere
TIPS customers successfully migrated to the ESMIG framework
Completion of User
Connectivity Testing
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Have you finalised your T2 connectivity tests?
A: Yes
B: No
C: I don’t know
Polling question
Some area of attention
• T2 registration form requested by the National Central Banks
Additional documentation published by SWIFT to clarify Technical Address for A2A and U2A Administrators to be used in the T2 registration form
• Setup U2A connectivity
Webinar to guide you through the key characteristics of the ESMIG U2A channel and how to successfully implement it recording available
Q&A
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
More help required ?1. SWIFT Customer Support teams are on hand 24/7 to answer specific queries if you do not find the
information resources you are looking for2. SWIFT engineers can guide you through the U2A implementation end-to-end, which can be requested
via your SWIFT account manager (until end of December 2021)
Eurosystem Collateral Management System (ECMS)
Functional aspects
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
How high is awareness of the ECMS in your
institution?
A: High
B: Fair
C: Low
Polling question
What is the "Eurosystem Collateral Management System" (ECMS)?
• The Eurosystem1) provides credit in central bank money only against "quality" collateral
(e.g. intra-day credit lines for T2, monetary policy operations).
• Today most Eurosystem NCBs have their own system to manage assets used as collateral
(19 different collateral management systems managed by European NCBs).
ECMS is a TARGET Service and will replace these 19 individual collateral management
systems
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Counterparty pool
Collateral Position
CreditPosition
Credit line
• ECMS will:
Keep track of the collateral value provided by the
counterparty bank, its usage (i.e. credit position) and the
available credit line
Interact with T2/CLM for the cash-related information (e.g.
credit line update)
Interact with T2S for the underlying securities settlement
(mobilization, de-mobilization)
1) the system of central banks of countries who adopted the Euro.
After go-live, the ECMS will replace the individual collateral management systems currently in use by NCBs.
Remark: Some NCBs will continue to make use of their national systems for
the management of some or all of their credit claims.
Source: ECB Business Description Document for the ECMS
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
ECMS Interactions
ECMS
Counterparty pool
T2S
T2/CLM
Counterparty*
CSD
TPA
Settlement Inx
Payments
Credit Line
updates
Marketable
asset Inx,
Position details
Corporate
Actions
Triparty Inx
ES
MIG
*Counterparties = banks that are Eurosystem NCB customers and are eligible to participate in monetary policy operations
Nota bene: The existing legal relationships between the NCBs and their communities,
i.e. counterparties and external actors, remain unchanged
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Internal to
Eurosystem
ISO 20022 messages used for ECMS
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Securities Settlement
Sese
Mobilisation / demobilisation
Collateral & Ref.Data
colr & reda
Margin calls, pool positions, tri-party
messages
Payment C&S & Cash Management
pacs & camt
Securities Management
Semt
Statement of holdings &
transactions
FI CT, DD, status reports
Securities Events
seev
Corporate Actions notification,
instructions, confirmationNEW
SWIFT Professional Services staff can help you analyse the
impact on your processes and systems
ECMS User Connectivity Options
• A counterparty / bank that wants to continue to do monetary operations or get T2
intra day credit line has to connect to ECMS:
Either using A2A and U2A, or U2A only
Banking groups need to check which legal entities shall use ECMS and register with the respective
National Central Bank (NCB) and the Network Service Provider (NSP) for ESMIG access
• For the securities leg a Counterparty/bank has the following options:
Connect directly to T2S (DCP)
Connect indirectly via a CSD (ICP)
Use an account operator - i.e. another bank - which manages the securities account(s) (at a CSD),
using power of attorney
• TPAs and CSDs have to implement the A2A channel (U2A only channel is not
possible for these players)
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Operational aspects
ECMS approach for SWIFT customers
• Access to ECMS if achieved via the Eurosystem Market Infrastructure Gateway (ESMIG)
ESMIG covers T2, T2S, TIPS and ECMS (so called "Target Services")
Access rights to Target Services are granted by a national central bank (for T2, ECMS, TIPS) or a central securities depository (for T2S)
• If a SWIFT customer has concluded an ESMIG contract with SWIFT - for example to
access the new T2 - then ECMS is covered by this contract as well
However, the ESMIG contract is per legal entity, hence customers need to check whether ECMS - which is often used by treasury departments - is done by the same legal entity or another legal entity in a group
• The technical SWIFT infrastructure for ESMIG can be re-used for ECMS as well
SWIFT software is multi-tenant. Adding another legal entity is only a matter of adding a software license and suitable configuration (unless running the software has been out-sourced)
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Customer Infrastructure
User to
Application
A customer can connect to all of
the Target Services via SWIFT ESMIG
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Application to
Application
Eurosystem
T2S
T2
TIPS
ECMS
Customer's
SWIFT
infrastructure
ISO 20022
How to Order SWIFT ESMIG Connectivity for ECMS
Same procedure as the other TARGET
Services:
1) General Contract (Service Levels, Cost) Subscribe to SWIFT's Solution for ESMIG for one or
more legal entities
2) To access the messaging channels for
the TARGET Services (just operational
orders) The ESMIG ECMS configuration form will be
available in time for connectivity testing, which starts 20 Feb. 2023
See also SWIFT document esmig_subscription_and_service_configuration_steps.pdf, July 2021Note: For existing TIPS and T2S customers, this step is not required if no changes are needed in the current configuration.
Subscribe to
SWIFT’s Solution for
ESMIG
(T2 EAC*) T2 UTEST
STEP 1
Select SWIFT as NSP
STEP 2
Configure the access to TARGET service
(T2S EAC*) T2S UTEST
TIPS CERT TIPS PROD
ECMS
UTEST
ECMS
PROD
T2 PROD
T2 PROD
(TIPS
EAC*)
(ECMS
EAC*)
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Source: https://www.ecb.europa.eu/paym/target/ecms/profuse/shared/pdf/ecb.targetecms210111_17_milestones_and_readiness.en.pdf
TARGET Services, ESMIG and ECMS - SOF 1st December 2021
Source: https://www.ecb.europa.eu/paym/target/ecms/profuse/shared/pdf/ecb.targetecms210111_17_milestones_and_readiness.en.pdf
TARGET Services - Eurosystem's Main Connectivity Milestones and Phases
2020 2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Migration
to ESMIG
contractual
framew ork
TIPS
T2S
T2
ECMS*)
31/03
Functional Testing
NSP selection and contracts
preparation completed
30/06
NSP procurement
completed
T2 – 21 Nov.TIPS – 21 Nov. T2S – 11 Jun. ECMS – 20 Nov.
Functional Testing
User Connectivity Testing
NCB Connectivity Testing
Pre-Mig.PROD Connectivity Testing
Connectivity Testing
User Connectivity Testing
User Connectivity Testing Functional Testing
NCB and CSD Connectivity Testing
*) Source: https://www.ecb.europa.eu/paym/target/ecms/profuse/shared/pdf/ecb.targetecms210111_17_milestones_and_readiness.en.pdf
Functional Testing
Functional Testing
Functional Testing
PROD Connectivity Testing Pre.Mig.
TARGET Services, ESMIG and ECMS - SOF 1st December 2021