Top Banner
Electrical Distribution System Startup and Operation Type CONTINUOUS Document No. ETF-25B-001 Rev/Mod A-6 Release Date 01/14/2019 Page 1 of 32 Tank Farm Plant Operating Procedure Effluent Treatment Facility USQ Not Required – ETF is a < Hazard Category 3 Radiological Facility CHANGE HISTORY ( LAST 5 REV-MODS ) Rev-Mod Release Date Justification: Summary of Changes A-6 01/14/2019 DOE-0359 Change Implementation Updated Safety section regarding preventative maintenance and applicable ERA to use. Removed special tools, equipment, and supplies section. Added ERA (Electrical Risk Assessment) acronym and applicable site form. Clarify location of applicable ERA per Safety Section. A-5 10/02/2018 Incorporation of eDARF changes Identified typo at Step 5.2.2. Correction to step for allowing of proper work. Signature updates to DP-1 and DP-3 Data Sheets. Corrected identifiers in MCC-3 and DP-2 Data Sheets. A-4 09/27/2018 Operations Request Added new step 4.3.6 “IF Hanford Fire Department configured the RAFR and/or FACU ENSURE Hanford Fire Department (phone 373-2845) has been notified that outage is complete.Added Sub Step “SOM RECORD MSA/FSM work package number:” Added new step 5.2.40 “REQUEST Fire Systems Maintenance restore RAFR and/or FACU per MSA work package provided in Step 4.2.6.1A-3 09/20/2018 Operations Request Added note ahead of Step 5.2.23 describing MDP positioning and updated breaker information in data sheets. A-2 05/02/2018 Address consistency for the ETFF and ETFS projects. Added admin procedure for Log Books to the performance documents. Modified Record section to be consistent with writers standard. For all Data Sheets, changed Special Instructions and references to be consistent with ETF requirements. Added new Section 5.1 for component lineup determination. Modified Data Sheets for consistency. Table of Contents Page 1.0 PURPOSE AND SCOPE ................................................................................................................ 3 1.1 Purpose................................................................................................................................ 3 1.2 Scope ................................................................................................................................... 3 2.0 INFORMATION............................................................................................................................. 3 2.1 Terms and Definitions......................................................................................................... 3 2.2 General Information ............................................................................................................ 3 3.0 PRECAUTIONS AND LIMITATIONS......................................................................................... 4 3.1 Personnel Safety.................................................................................................................. 4 3.2 Equipment Safety ................................................................................................................ 4 3.3 Radiation and Contamination Control ................................................................................ 5 3.4 Environmental Compliance ................................................................................................ 5 4.0 PREREQUISITES .......................................................................................................................... 6
32

Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Aug 14, 2019

Download

Documents

vomien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

1 of 32

Tank Farm Plant Operating Procedure Effluent Treatment Facility

USQ Not Required – ETF is a < Hazard Category 3 Radiological Facility

CHANGE HISTORY ( LAST 5 REV-MODS )

Rev-Mod Release Date Justification: Summary of Changes

A-6 01/14/2019 DOE-0359 Change

Implementation

Updated Safety section regarding preventative maintenance and

applicable ERA to use. Removed special tools, equipment, and

supplies section. Added ERA (Electrical Risk Assessment)

acronym and applicable site form. Clarify location of applicable

ERA per Safety Section.

A-5 10/02/2018 Incorporation of eDARF

changes

Identified typo at Step 5.2.2. Correction to step for allowing of

proper work. Signature updates to DP-1 and DP-3 Data Sheets.

Corrected identifiers in MCC-3 and DP-2 Data Sheets.

A-4 09/27/2018 Operations Request

Added new step 4.3.6 “IF Hanford Fire Department configured

the RAFR and/or FACU ENSURE Hanford Fire Department

(phone 373-2845) has been notified that outage is complete.“

Added Sub Step “SOM RECORD MSA/FSM work package

number:” Added new step 5.2.40 “REQUEST Fire Systems

Maintenance restore RAFR and/or FACU per MSA work

package provided in Step 4.2.6.1”

A-3 09/20/2018 Operations Request Added note ahead of Step 5.2.23 describing MDP positioning

and updated breaker information in data sheets.

A-2 05/02/2018 Address consistency for the

ETFF and ETFS projects.

Added admin procedure for Log Books to the performance

documents. Modified Record section to be consistent with

writer’s standard. For all Data Sheets, changed Special

Instructions and references to be consistent with ETF

requirements. Added new Section 5.1 for component lineup

determination. Modified Data Sheets for consistency.

Table of Contents Page

1.0 PURPOSE AND SCOPE ................................................................................................................ 3

1.1 Purpose ................................................................................................................................ 3

1.2 Scope ................................................................................................................................... 3

2.0 INFORMATION............................................................................................................................. 3

2.1 Terms and Definitions......................................................................................................... 3

2.2 General Information ............................................................................................................ 3

3.0 PRECAUTIONS AND LIMITATIONS......................................................................................... 4

3.1 Personnel Safety.................................................................................................................. 4

3.2 Equipment Safety ................................................................................................................ 4

3.3 Radiation and Contamination Control ................................................................................ 5

3.4 Environmental Compliance ................................................................................................ 5

4.0 PREREQUISITES .......................................................................................................................... 6

Page 2: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

2 of 32

4.1 Performance Documents ..................................................................................................... 6

4.2 Field Preparations ............................................................................................................... 6

5.0 PROCEDURE ................................................................................................................................. 7

5.1 Component Lineup Determination ..................................................................................... 7

5.2 Startup from Facility De-Energized, Electrical Distribution System Shutdown, Safety

Shutdown, or Loss of AC Electrical Power ........................................................................ 7

5.3 Records ............................................................................................................................. 11

Data Sheet 1 – Distribution Panel 1 (DP-1) Startup Alignment ............................................................... 12

Data Sheet 2 – Distribution Panel 3 (DP-3) Startup Alignment ............................................................... 14

Data Sheet 3 – Distribution Panel 4 (DP-4) Startup Alignment ............................................................... 16

Data Sheet 4 – Main Switchgear (MSWGR-1) Startup Alignment .......................................................... 18

Data Sheet 5 – Main Switchgear 2 (MSWGR-2) Startup Alignment ....................................................... 19

Data Sheet 6 – Motor Control Center 1 (MCC-1) Startup Alignment ...................................................... 20

Data Sheet 7 – Motor Control Center 2 (MCC-2) Startup Alignment ...................................................... 21

Data Sheet 8 - Motor Control Center 3 (MCC-3) Startup Alignment ...................................................... 23

Data Sheet 9 – Motor Control Center 4 (MCC-4) Startup Alignment ...................................................... 24

Data Sheet 10 – Main Distribution Panel 1 (MDP-1) Startup Alignment ................................................ 25

Data Sheet 11 – Main Distribution Panel 2 (MDP-2) Startup Alignment ................................................ 26

Data Sheet 12 – Main Distribution Panel 3 (MDP-3) Startup Alignment ................................................ 27

Data Sheet 13 – Distribution Panel 2 (DP-2) Startup Alignment ............................................................. 28

Data Sheet 14 – Distribution Panel 5 (DP-5) Startup Alignment ............................................................. 30

Data Sheet 15 – Distribution Panel 6 (DP-6) Startup Alignment – Rm. 104 ........................................... 31

Page 3: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

3 of 32

1.0 PURPOSE AND SCOPE

1.1 Purpose

This procedure provides instructions for safe, efficient startup and normal operation

of the 480V/277V and 208V/120V electrical distribution systems.

1.2 Scope

This procedure involves instructions for steps for the startup from facility

de-energized, recovery from safety shutdown, and recovery from loss of AC electrical

power.

2.0 INFORMATION

2.1 Terms and Definitions

EFR - Environmental Field Representative

MTT - Main Treatment Train.

2.2 General Information

2.2.1 This procedure shall only be performed under one of the following

circumstances:

Facility has been shut down per ETF-25B-002, Electrical Distribution

System Shutdown

Facility safety shutdown per ETF-AOP-85B-001, Response to ETF

Safety Shutdown

Facility has experienced a loss of power; respond per ETF-AOP-85B-

006, Response to Loss of AC Electrical Power.

Page 4: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

4 of 32

3.0 PRECAUTIONS AND LIMITATIONS

3.1 Personnel Safety

3.1.1 All work will be performed in accordance with DOE-0359, Hanford Site

Electrical Safety Program.

3.1.2 Operation of Circuit Breakers, Electrical disconnect Switches, and Similar

Switching Equipment shall be performed by a qualified person.

3.1.3 Component operation requires completion of an Electrical Risk Assessment

(ERA).

3.1.4 Stored-energy devices (springs) operate power circuit breakers with

tremendous force. Use extreme caution when opening or closing breakers.

3.1.5 When the clean and inspects are current on the electrical equipment (breaker,

switchgear, disconnects, motor starters, etc.), the ERA for normal operating

condition is applicable, for those workers interacting with electrical

equipment.

3.1.5.1 Use safety glasses and leather gloves when manipulating

electrical components per the normal ERA.

3.1.6 When the clean and inspects are delinquent, the ERA for non-normal

operating condition is applicable, for those workers interacting with electrical

equipment.

3.2 Equipment Safety

3.2.1 Circuit breakers in panels and switchgear shall be operated one at a time to

avoid possible equipment damage.

3.2.2 Opening breaker LP-1 at MDP-1 de-energizes facility lighting, monitoring

and control system, and communication systems, and activates the UPS.

De-energizing breaker LP-1 (or any other breaker) is performed when

directed to do so by procedure or by the SOM.

Page 5: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

5 of 32

3.3 Radiation and Contamination Control

3.3.1 When this procedure is worked in radiological areas, an approved

radiological work permit (RWP) is required. If radiological conditions or

work performed falls outside the scope of the RWP, all work activities must

be discontinued until a new or revised RWP has been issued in accordance

with TFC-ESHQ-RP_RWP-C-03.

3.4 Environmental Compliance

3.4.1 In the event of a spill/leak/release, notify the SOM/FWS and respond per

ETF-ERP-85B-003, Emergency Spill or Release at ETF.

Page 6: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

6 of 32

4.0 PREREQUISITES

4.1 Performance Documents

The following documents may be needed to perform this procedure:

DOE-0359, Hanford Site Electrical Safety Program

ETF-25B-003, UPS Operation

ETF-55-001, Monitor and Control System Operations

TFC-OPS-OPER-C-17, Operating Logbooks

A-6007-595, Hanford Site Electrical Risk Assessment.

4.2 Field Preparations

4.2.1 ENSURE facility is ready for startup.

4.2.2 CHECK 13.8KV/480V transformers are energized.

4.2.3 ENSURE all distribution circuits are free of ground straps and/or personnel

grounds.

4.2.4 ENSURE communication is established between CRO and operators

performing task.

4.2.5 OBTAIN SOM permission prior to operating breakers.

4.2.6 IF Hanford Fire Department configured the RAFR and/or FACU ENSURE

Hanford Fire Department (phone 373-2845) has been notified that outage is

complete.

4.2.6.1 SOM RECORD MSA/FSM

work package number: _____________.

4.2.7 ENSURE proper PPE is available and consistent with the ERA described in

Section 3.1.

Page 7: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

7 of 32

5.0 PROCEDURE

Special Instructions

SOM or electrical engineer will direct which step the procedure may be started at depending on

how or why the plant was shut down.

All trips and resetting of protective devices must be recorded in ETF Control Room Logbook.

5.1 Component Lineup Determination

5.1.1 (SOM) DETERMINE which component lineup Checklists/Data sheets need

to be performed.

5.1.2 (SOM) IF components are known to be in the required position and do not

require verification, INITIAL/DATE AND DOCUMENT reason in the

comments section of the Checklist/Data Sheet.

5.1.3 (SOM) IF components are not in the required position because of an existing

process (i.e., LOTO, Caution Tag, Work Package, Administrative Lock,

Facility Tag or Status Seals), MARK N/A on the Checklist/Data Sheet AND

INITIAL/DATE AND DOCUMENT reason in the comments section of the

Checklist/Data Sheet.

5.2 Startup from Facility De-Energized, Electrical Distribution System

Shutdown, Safety Shutdown, or Loss of AC Electrical Power

NOTE - Steps 5.2.1 through 5.2.3 supplies power to the ETF lighting and energizes

receptacles.

5.2.1 CLOSE MAIN breaker for MSWGR-2.

5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2.

5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1.

NOTE - Steps 5.2.4 through 5.2.11 are for UPS, MCS, and communications system.

5.2.4 ENSURE UPS startup per ETF-25B-003.

5.2.5 ENSURE DP-1 startup alignment per Data Sheet 1 – Distribution Panel 1

(DP-1) Startup Alignment.

5.2.6 INITIAL Data Sheet 1 as verification of DP-1 breaker alignment.

Page 8: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

8 of 32

5.2 Startup from Facility De-Energized, Electrical Distribution System

Shutdown, Safety Shutdown, or Loss of AC Electrical Power (Cont.)

5.2.7 ENSURE DP-3 startup alignment per Data Sheet 2 – Distribution Panel 3

(DP-3) Startup Alignment.

5.2.8 INITIAL Data Sheet 2 as verification of DP-3 breaker alignment.

5.2.9 ENSURE DP-4 startup alignment per Data Sheet 3 – Distribution Panel 4

(DP-4) Startup Alignment.

5.2.10 INITIAL Data Sheet 3 as verification of DP-4 breaker alignment.

5.2.11 INITIATE start of the MCS per ETF-55-001.

NOTE - All systems must be in shutdown mode before proceeding.

5.2.12 WAIT, DO NOT PROCEED until directed by SOM.

NOTE - Steps 5.2.13 through 5.2.20 are performed by CRO.

5.2.13 ON graphic MTT, INITIATE AND CONFIRM MTT is shut down.

5.2.14 ON graphic EVAP, INITIATE AND CONFIRM evaporator is shut down.

5.2.15 ON graphic SWRT, INITIATE AND CONFIRM the following SWRTs are

shut down:

SWRT-A

SWRT-B.

5.2.16 ON graphic CONC, INITIATE AND CONFIRM the following are shut

down:

CT-A

CT-B.

5.2.17 ON graphic Dryer, INITIATE AND CONFIRM Thin Film Dryer is

shut down.

5.2.18 ON graphic Utility, INITIATE AND CONFIRM utility systems are all

shut down.

5.2.19 ON graphic EVAP, CONFIRM boiler has stopped.

5.2.20 IF boiler is in OPERATION, NOTIFY SOE to shut down boiler.

Page 9: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

9 of 32

5.2 Startup from Facility De-Energized, Electrical Distribution System

Shutdown, Safety Shutdown, or Loss of AC Electrical Power (Cont.)

NOTE - Steps 5.2.21 through 5.2.42 energize remaining electrical distribution system

circuits.

5.2.21 ENSURE MSWGR-1 startup alignment per Data Sheet 4 – Main Switchgear

(MSWGR-1) Startup Alignment.

5.2.22 INITIAL Data Sheet 4 as verification of MSWGR-1 breaker alignment.

NOTE - MSWGR-2, Main was placed to BREAKER CLOSED in step 5.2.1.

- MDP was placed to CLOSED position in Step 5.2.2.

5.2.23 ENSURE MSWGR-2 startup alignment per Data Sheet 5 – Main Switchgear

2 (MSWGR-2) Startup Alignment.

5.2.24 INITIAL Data Sheet 5 as verification of MSWGR-2 breaker alignment.

NOTE - MCC-1 through MCC-4 alignments may be performed concurrently.

5.2.25 ENSURE MCC-1 startup alignment per Data Sheet 6 – Motor Control Center

1 (MCC-1) Startup Alignment.

5.2.26 INITIAL Data Sheet 6 as verification of MCC-1 breaker alignment.

5.2.27 ENSURE MCC-2 startup alignment per Data Sheet 7 – Motor Control Center

2 (MCC-2) Startup Alignment.

5.2.28 INITIAL Data Sheet 7 as verification of MCC-2 breaker alignment.

5.2.29 ENSURE MCC-3 startup alignment per Data Sheet 8 - Motor Control Center

3 (MCC-3) Startup Alignment.

5.2.30 INITIAL Data Sheet 8 as verification of MCC-3 breaker alignment.

5.2.31 ENSURE MCC-4 startup alignment per Data Sheet 9 – Motor Control Center

4 (MCC-4) Startup Alignment.

5.2.32 INITIAL Data Sheet 9 as verification of MCC-4 breaker alignment.

NOTE - MDP-1 through MDP-3 alignments may be performed concurrently.

- Circuit breaker MDP-1, LP-1 was placed to ON in step 5.2.1.

5.2.33 ENSURE MDP-1 startup alignment per Data Sheet 10 – Main Distribution

Panel 1 (MDP-1) Startup Alignment.

Page 10: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

10 of 32

5.2 Startup from Facility De-Energized, Electrical Distribution System

Shutdown, Safety Shutdown, or Loss of AC Electrical Power (Cont.)

5.2.34 INITIAL Data Sheet 10 as verification of MDP-1 breaker alignment.

5.2.35 ENSURE MDP-2 startup alignment per Data Sheet 11 – Main Distribution

Panel 2 (MDP-2) Startup Alignment.

5.2.36 INITIAL Data Sheet 11 as verification of MDP-2 breaker alignment.

5.2.37 ENSURE MDP-3 startup alignment per Data Sheet 12 – Main Distribution

Panel 3 (MDP-3) Startup Alignment.

5.2.38 INITIAL Data Sheet 12 as verification of MDP-3 breaker alignment.

5.2.39 REQUEST Fire Systems Maintenance restore RAFR and/or FACU per MSA

work package provided in Step 4.2.6.1.

5.2.40 ENSURE DP-2 startup alignment per Data Sheet 13 – Distribution Panel 2

(DP-2) Startup Alignment.

5.2.41 INITIAL Data Sheet 13 as verification of DP-2 breaker alignment.

5.2.42 ENSURE DP-5 startup alignment per Data Sheet 14 – Distribution Panel 5

(DP-5) Startup Alignment.

5.2.43 INITIAL Data Sheet 14 as verification of DP-5 breaker alignment.

5.2.44 ENSURE DP-6 startup alignment per Data Sheet 15 – Distribution Panel 6

(DP-6) Startup Alignment – Rm. 104.

5.2.45 INITIAL Data Sheet 15 as verification of DP-6 breaker alignment.

Page 11: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

11 of 32

5.3 Records

5.3.1 PERFORM the following for records identified within this procedure:

5.3.1.1 RECORD the number of times the record was generated in

applicable column

OR

PLACE a check mark () in the N/A column.

5.3.1.2 SUBMIT the package for verification of completed records.

Records Submittal Checklist

Number of

times

completed

N/A

()

Data Sheets

Data Sheet 1 – Distribution Panel 1 (DP-1) Startup Alignment

Data Sheet 2 – Distribution Panel 3 (DP-3) Startup Alignment

Data Sheet 3 – Distribution Panel 4 (DP-4) Startup Alignment

Data Sheet 4 – Main Switchgear (MSWGR-1) Startup Alignment

Data Sheet 5 – Main Switchgear 2 (MSWGR-2) Startup Alignment

Data Sheet 6 – Motor Control Center 1 (MCC-1) Startup Alignment

Data Sheet 7 – Motor Control Center 2 (MCC-2) Startup Alignment

Data Sheet 8 - Motor Control Center 3 (MCC-3) Startup Alignment

Data Sheet 9 – Motor Control Center 4 (MCC-4) Startup Alignment

Data Sheet 10 – Main Distribution Panel 1 (MDP-1) Startup Alignment

Data Sheet 11 – Main Distribution Panel 2 (MDP-2) Startup Alignment

Data Sheet 12 – Main Distribution Panel 3 (MDP-3) Startup Alignment

Data Sheet 13 – Distribution Panel 2 (DP-2) Startup Alignment

Data Sheet 14 – Distribution Panel 5 (DP-5) Startup Alignment

Data Sheet 15 – Distribution Panel 6 (DP-6) Startup Alignment – Rm. 104

FWS/OE/Shift Manager SEND the completed records to the Central Shift Office for records

retention.

/ /

Signature Print (First & Last) Date

FWS/OE/Shift Manager

The record custodian identified in the Company Level Records Inventory and Disposition

Schedule (RIDS) is responsible for record retention in accordance with

TFC-BSM-IRM_DC-C-02.

Page 12: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

12 of 32

Data Sheet 1 – Distribution Panel 1 (DP-1) Startup Alignment

Sheet 1 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

Elec. 1 Recept Rms 100, 101 ON

Elec. 2 Recept Rms 100, 101, 107 ON

Elec. 3 Recept Rms103, 106 ON

Elec. 4 Recept Rms 114, 123 ON

Elec. 5 Recept Rms 115, 121, 127, 128 ON

Elec. 6 Recept Rms 116, 122, 126 ON

Elec. 7 Recept Rms 125, 129, 130, 131 ON

Elec. 8 Recept Rms 125, 131 ON

Elec. 9 Recept Rms 104, 105, 131 ON

Elec. 10 Recept Rms 201, 204, 206 ON

Elec. 11 Recept Rms 200, 206, 207, 208 ON

Elec. 12 Rectpt Rm 107 ON

Elec. 13 Recept Rms 132, 133, 134 ON

Elec. 14 Recept Rms 102, 111, 117, 118 ON

Elec. 15 Recept Rms 106, 113 ON

Elec. 16 Recept Rm 100 ON

Elec. 17 Recept Rm 100 ON

Elec. 18 Recept Rm 100 ON

Elec. 19 Recept Rm 100 ON

Elec. 20 Recept Rm 100 ON

(Continued on Next Sheet)

Page 13: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

13 of 32

Data Sheet 1 – Distribution Panel 1 (DP-1) Startup Alignment (Cont.)

Sheet 2 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

Elec. 21 Recept Rm 206 ON

Elec. 22/24/26/

28/30/32

25I-UPS-1 ON

Elec. 23/25/27 25I-UPS-1 (BY-PASS) ON

Elec. 29 Recept Rms 113, 114 ON

Elec. 31/33 Spare OFF

Elec. 34/36 Spare OFF

Elec. 35 Recept Rm 100 ON

Elec. 37 Recept Rm 100 ON

Elec. 38 Recept Rm 101 ON

Elec. 39 Recept Rms 203, 206 ON

Elec. 40 Recept Rm 122 ON

Elec. 41 Rectpt Rms 201, 202, 203 ON

Elec. 42 Recept Rms 131, 138 ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

Electrician

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 14: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

14 of 32

Data Sheet 2 – Distribution Panel 3 (DP-3) Startup Alignment

Sheet 1 of 2

Breaker

Number Breaker Name and Location Required Position Initials Date

N/A Main Circuit Breaker ON

1 JB-95C001 ON

2 IDP-1 ON

3 IDP-2 ON

4 IDP-3 ON

5 IDP-4 ON

6 IDP-5 ON

7 LCP-80C001 ON

8 LCU-4 ON

9 LCU-1 ON

10 LCU-5 ON

11 LCU-2A & 2B ON

12 LCU-6 ON

13 LCU-3 ON

14 IDP-6 ON

15 MCS-1 ON

16 Spare OFF

17 MCS-2 ON

18 JB-60D003 (UV Power) ON

19 Spare OFF

20 MCS-3 ON

21 LCU-H ON

22 CREWS ON

23 Spare OFF

(Continued on Next Sheet)

Page 15: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

15 of 32

Data Sheet 2 – Distribution Panel 3 (DP-3) Startup Alignment (Cont.)

Sheet 2 of 2

Breaker

Number Breaker Name and Location Required Position Initials Date

24 Spare OFF

25 Spare OFF

26 Spare OFF

27 Spare OFF

28 Spare OFF

29 Spare OFF

30 Spare OFF

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

Electrician

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 16: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

16 of 32

Data Sheet 3 – Distribution Panel 4 (DP-4) Startup Alignment

Sheet 1 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO N/A Main Circuit Breaker ON

NCO 1 Communication Rm 207 ON

NCO 2 Communication Rm 207 ON

NCO 3 Communication Rm 207 ON

NCO 4 Communication Rm 207 ON

NCO 5 Communication Rm 207 ON

NCO 6 Communication Rm 207 ON

NCO 7 Communication Rm 207 ON

NCO 8 Server Cabinet “A” (RM 207) ON

NCO 9 Server Cabinet “B” (RM 207) ON

NCO 10 WHELEN Paging System ON

NCO 11 Communication Rm 124 ON

NCO 12 Communication Rm 124 ON

NCO 13 Spare OFF

NCO 14 MCS-4 (TEDF OCS) ON

SOE 15 45B-EVU-6 (PIC) ON

NCO 16 MCS-5 (TEDF OCS’s) ON

SOE 17 45B-EVU-8 (PIC) ON

NCO 18 MCS-6 (LERF/Load-In OCS) ON

SOE 19 45B-EVU-7 (PIC) ON

NCO 20 Blank N/A

SOE 21 JB-EVU-4-01 ON

NCO 22 UV Oxidizer #1 Compartment Fans ON

NCO 23 Blank N/A

NCO 24 UV/OX #2 Compartment Fans ON

(Continued on Next Sheet)

Page 17: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

17 of 32

Data Sheet 3 – Distribution Panel 4 (DP-4) Startup Alignment (Cont.)

Sheet 2 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 25 Blank N/A

NCO 26 Blank N/A

NCO 27 Blank N/A

NCO 28 Blank N/A

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 18: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

18 of 32

Data Sheet 4 – Main Switchgear (MSWGR-1) Startup Alignment

Resp. Breaker

Number

Breaker Name and

Location Required Position Initials Date

NCO F8X 628 MSWGR-1 Main CLOSED

NCO N/A MCC-1 CLOSED

NCO N/A 60I-C-1 Vapor Compressor OPEN

NCO N/A MCC-2 CLOSED

NCO N/A MCC-4 CLOSED

SOE N/A 65A-B-1 Dryer Boiler CLOSED

N/A N/A Blank N/A

NCO N/A MCC-3 CLOSED

N/A N/A Blank N/A

N/A N/A Blank N/A

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 19: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

19 of 32

Data Sheet 5 – Main Switchgear 2 (MSWGR-2) Startup Alignment

Resp. Breaker

Number Breaker Name and Location Required Position Initials Date

NCO F8X 627 MSWGR-2 Main CLOSED

NCO N/A Panel MDP-1 CLOSED

NCO N/A Panel MDP-2 CLOSED

NCO N/A Panel MDP-3 CLOSED

SOE N/A Central Station/AHU-No. 1/45B-E-1A CLOSED

SOE N/A Central Station/AHU-No. 1/45B-E-2A CLOSED

N/A N/A Blank N/A

SOE N/A Central Station/AHU-No. 2/45B-E-1B CLOSED

SOE N/A Central Station/AHU-No. 2/45B-E-2B CLOSED

N/A N/A Blank N/A

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 20: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

20 of 32

Data Sheet 6 – Motor Control Center 1 (MCC-1) Startup Alignment

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 1F 60F-P-2A 2nd R.O. Feed Tank Pump “A” ON

NCO 1O 60C-P-2A Effluent PH Adjustment Tank Pump

“A”

ON

NCO 2C 60C-P-2B Effluent PH Adjustment Tank Pump

“B”

ON

NCO 2I 60F-P-1A 1st R.O. Feed Tank Pump “A” ON

NCO 2Q 60H-E-1A Verification Tank “A” Heater ON

NCO 3C 60C-P-1A PH Adjustment Tank Pump “A” ON

NCO 3K 65C-P-3 4% H2SO4 Solution Feed Pump ON

NCO 3Q 60F-P-1B 1st R.O. Feed Tank Pump “B” ON

NCO 4C 65C-P-4 4% NaOH Solution Feed Pump ON

NCO 4I 60C-P-1B PH Adjustment Tank Pump “B” ON

NCO 4Q 60H-P-1 Verification Return Pump ON

NCO 5C 60E-P-1A Degasification Pump “A” ON

NCO 5I 60E-P-1B Degasification Pump “B” ON

NCO 5O 60F-P-2B 2nd R.O. Feed Tank Pump “B” ON

NCO 6C 60E-D-1 Degasification Blower ON

SOE 6I 45B-P-1B Chilled Water Pump “B” ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 21: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

21 of 32

Data Sheet 7 – Motor Control Center 2 (MCC-2) Startup Alignment

Sheet 1 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 1F 60J-M-1 Rotor Drive Motor ON

NCO 1L 60J-BL-1A Concentrate Tank 1A Mixer

Motor

ON

NCO 2C 60A-P-1A Surge Tank Pump “A” ON

NCO 2K 60A-P-1B Surge Tank Pump “B” ON

NCO 2S 60J-BL-1B Concentrate Tank 1B Mixer

Motor

ON

NCO 3G 95C-P-1 Cooling Water Pump ON

NCO 3P 60I-P-2 Evaporater Recirculation Pump ON

NCO 4G 60I-P-3 Distillate Flash Tank Pump ON

NCO 4M 20B-P-1A Sump Pump “1A” ON

NCO 4S 60J-P-1A Concentrate Circulation Pump “A” ON

NCO 5C 20B-P-1B Sump Pump “1B” ON

NCO 5I 60A-P-1C Surge Tank Pump “C” ON

NCO 5Q 60J-P-1B Concentrate Circulation Pump “B” ON

NCO 6C 20B-P-2A Sump Pump “2A” ON

NCO 6I 20B-P-2B Sump Pump “2B” ON

NCO 6O 80E-F-1 Resin Dewatering System ON

(Continued on Next Sheet)

Page 22: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

22 of 32

Data Sheet 7 – Motor Control Center 2 (MCC-2) Startup Alignment (Cont.)

Sheet 2 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 7C 60J-E-4 Thin Film Dryer Heat Trace ON

NCO 7I 60J-P-3 Thin Film Dryer Distillate Pump ON

NCO 7O 60J-F-1 Vent Blower ON

NCO 8C 60J-P-2 Concentrate Feed Pump ON

NCO 8I 60I-P-1A Secondary Waste Feed Pump “A” ON

NCO 8Q 60I-P-1B Secondary Waste Feed Pump “B” ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 23: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

23 of 32

Data Sheet 8 - Motor Control Center 3 (MCC-3) Startup Alignment

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 1F 60H-E-1B Verification Tank “B” Heater ON

NCO 1O 95C-F-1A Cooling Tower Fan “A” ON

SOE 2G 1B-C-1 Air Compressor ON

SOE 3C 45A-F-1A RCA Exhaust Fan “A” ON

NCO 3L 65C-P-1 92% H2SO4 Storage Tank Pump ON

NCO 3R 95C-F-1B Cooling Tower Fan “B” ON

SOE 4C 65A-P-1 Boiler Feed Pump ON

NCO 4I 65C-P-2 50% NaOH Storage Tank Pump ON

NCO 4O 95B-P-1 Seal Water Pump ON

NCO 5C 45D-F-1A VOG Blower “A” ON

NCO 5I 45D-F-1B VOG Blower “B” ON

NCO 5O 95C-P-2 Cooling Water Blowdown Pump ON

NCO 6C 60H-P-2A Verification Transfer Pump “A” ON

NCO 6K 60H-P-2B Verification Transfer Pump “B” ON

NCO 6S 95C-E-2B Cooling Tower Heater “2B” ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 24: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

24 of 32

Data Sheet 9 – Motor Control Center 4 (MCC-4) Startup Alignment

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

SOE 1F 45A-F-1C RCA Exhaust Fan “C” ON

SOE 1O 45B-P-1A Chilled Water Pump “A” ON

SOE 2C 45B-F-1A Air Handling Unit Fan “A” ON

NCO 2K 60H-E-1C Verification Tank “C” Heater ON

NCO 2S Spare OFF

NCO 3C 60I-P-6 Silencer Drain Pump ON

SOE 3M 45B-F-6 AHU Fan Rm 139 (45B-EVU-10) ON

NCO 3S 60F-P-4 R.O. Cleaning Agent Feed System Unit “B” ON

NCO 4G 60I-P-7 Compressor Aux. Oil Pump ON

SOE 4M 45B-F-5 AHU Fan Rm 132 (45B-EVU-9) ON

NCO 4S 60I-P-4 Concentrate Transfer Pump ON

SOE 5C 45B-F-1B Air Handling Unit Fan “B” ON

SOE 5K 45A-F-1B RCA Exhaust Fan “B” ON

NCO 5T 95C-E-2A Cooling Tower Heater “2A” ON

NCO 6C 60A-E-1 Surge Tank Heater ON

NCO 6I 60F-P-3A R.O. Booster Pump “A” ON

NCO 6O 60F-P-3B R.O. Booster Pump “B” ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 25: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

25 of 32

Data Sheet 10 – Main Distribution Panel 1 (MDP-1) Startup Alignment

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 1 LP-1 ON

NCO 2 60D-UV-1 Lamp Drive B ON

NCO 3 25B-WR-1 Welding Recept ON

NCO 4 60D-UV-1 Lamp Drive A ON

NCO 5 Spare OFF

NCO 6 DP-2/DP-5 ON

NCO 7 20A-P-1/20A-P-2 Septic Pumps ON

NCO 8 19A-RD-1 Roll up Door ON

NCO 9 19A-RD-2 Roll up Door ON

NCO 10 Spare OFF

NCO 11 Load-In Station, Main Power ON

SOE 12 Air Compressor Canopy Fan 1B-F-1and JB-

1B001 Control Power

ON

SOE 13 45B-F-3 EVU-7 Fan ON

SOE 14 45B-E-4 EVU-7 Heater ON

N/A 15 Blank N/A

SOE 16 45B-E-3 EVU-6 Heater ON

N/A 17 Blank N/A

N/A 18 Blank N/A

N/A 19 Blank N/A

N/A 20 Blank N/A

N/A 21 Blank N/A

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 26: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

26 of 32

Data Sheet 11 – Main Distribution Panel 2 (MDP-2) Startup Alignment

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 1 25B-WR-2 Welding Recept ON

NCO 2 60D-UV-2 Lamp Drive B ON

SOE 3 Safety Shower/Eyewash Hot Water Htr. 95I-TK-4 ON

NCO 4 60D-UV-2 Lamp Drive A ON

NCO 5 Spare OFF

NCO 6 MO-148 MO-251 MO-269 ON

NCO 7 25E-HT-1 Heat Trace Panel #1 ON

NCO 8 45D-E-1 VOG Heater ON

NCO 9 DP-6 ON

NCO 10 JB-112 Lab Distilling Unit OFF

NCO 11 Spare OFF

NCO 12 25E-HT-2 Heat Trace Panel #2 ON

SOE 13 45B-HU-1 Control Room Humid OFF

SOE 14 45A-F16, 17, 18 Lab Hood Fans ON

NCO 15 65C-E-2 NAOH Tank Heater ON

SOE 16 45B-EVU-3 Support Area Cndsr ON

SOE 17 45B-E-5 EVU-8 Heater ON

NCO 18 Blank N/A

NCO 19 Blank N/A

NCO 20 Blank N/A

NCO 21 Blank N/A

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 27: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

27 of 32

Data Sheet 12 – Main Distribution Panel 3 (MDP-3) Startup Alignment

Resp. Breaker

Number Breaker Name and Location Required Position Initials Date

N/A 1 Blank N/A

NCO 2 XFMR / DP-9 ON

NCO 3 DP-7 and 2025E-25B-DS-001 ON

SOE 4 45B-EVU-2B Chiller ON

N/A 5 Blank N/A

SOE 6 45B-EVU-2A Chiller ON

NCO 7 19A-RD-3 Roll up Door ON

NCO 8 19A-RD-4 Roll up Door ON

NCO 9 60F-E-1A, 1B CIP Tank Heaters ON

NCO 10 PP-80C002 Drum Handling Pnl ON

SOE 11 45B-F-2 EVU-6 Fan ON

SOE 12 60I-B-1 EVAPORATOR Boiler

Unit

ON

SOE 13 45B-EVU-5 Control Room Cndsr ON

N/A 14 Blank N/A

SOE 15 45B-F-4 EVU-8 Fan ON

N/A 16 Blank N/A

N/A 17 Blank N/A

N/A 18 Blank N/A

N/A 19 Blank N/A

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 28: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

28 of 32

Data Sheet 13 – Distribution Panel 2 (DP-2) Startup Alignment

Sheet 1 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

N/A Main Circuit Breaker ON

NCO 1 60I-BL-1 (Mixer MTR) JB-60I007 ON

NCO 2 60I-P-5 (JB-60I006) ON

NCO 3 HEPA “C” Light ON

NCO 4 20B-P-3 Surge Pump ON

SOE 5 45A-F-2 (Fan) ON

NCO 6 20B-P-4 Verification Sump ON

SOE 7 45A-F-6 (Fan) ON

NCO 8 20B-P-5 Chem Sump ON

SOE 9 45A-F-7 (Fan) ON

NCO 10 20B-P-6 Chem Sump ON

SOE 11 45A-F-3 (Fan) ON

NCO 12 65C-P-5 ON

NCO 13 1D-D-1 (Dryer) ON

SOE 14 HEPA A Lights ON

SOE 15 45A-F-4 (Fan) ON

SOE 16 HEPA B Light ON

SOE 17 45A-F-5 (Fan) ON

NCO 18 65C-P-6 ON

NCO 19 60F-P-5 (JB-60F-P5-01) ON

NCO 20 Outside Lighting, Tank Area ON

(Continued on Next Sheet)

Page 29: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

29 of 32

Data Sheet 13 – Distribution Panel 2 (DP-2) Startup Alignment (Cont.)

Sheet 2 of 2

Resp. Breaker

Number Breaker Name and Location Required Position Initials Date

SOE 21 45B-EM-1A (Pump) OFF

SOE 22 Boiler Pre-heater 95D-E-01 ON

SOE 23 45B-EM-1B (Pump) OFF

NCO 24 Outside Receptacles and LTS, Tank Area ON

SOE 25 Hot Wtr Recirc Pump 95I-P-1 ON

NCO 26 65C-P-7 ON

NCO 27 65C-P-9 (Pump) ON

NCO 28 65C-P-8 ON

NCO 29 65C-P-10 (Pump) ON

NCO 30 FACP – Fire Alarm ON

NCO 31 Motor Heaters, Cooling Tower ON

NCO 32 RFAR – Fire Alarm ON

SOE 33/35 45B-EVU-4 (2-pole breaker) ON

NCO 34 Spare OFF

SOE 36/38 45B-EUH-1 Stairwell 130 Heater OFF

NCO 37/39/ 41 Lab Washer Rm 112 (3-pole breaker) ON

N/A 40 Blank N/A

N/A 42 Blank N/A

NCO NA Sub-feed DP-5 ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 30: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

30 of 32

Data Sheet 14 – Distribution Panel 5 (DP-5) Startup Alignment

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO N/A DP-5 Main Circuit Breaker ON

NCO 1 FDAS ON

NCO 2 Receptacles, High Mezzanine OFF

NCO 3 AHU Lights/Receptacles ON

NCO 4 SP95C015 ON

NCO 5 Room 206 Receptacles ON

NCO 6 Recept ON

NCO 7/9 HVAC Stack Sampler (2-pole

breaker)

ON

NCO 8 SP60C228 ON

SOE 10 45B-EVU-2A and 2B, Heat Trace ON

NCO 11 Spare OFF

SOE 12 45B-EVU-1A and 1B, Heat Trace ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review

Page 31: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

31 of 32

Data Sheet 15 – Distribution Panel 6 (DP-6) Startup Alignment – Rm. 104

Sheet 1 of 2

Resp. Breaker

Number Breaker Name and Location Required Position Initials Date

NCO N/A DP-6 Main Circuit Breaker ON

NCO 1 Spare OFF

NCO 2 Spare OFF

NCO 3 Spare OFF

SOE 4 Hot Water Heater, Rm 103 ON

NCO 5 Spare OFF

NCO 6 Recept Rm 112 Refrigerator ON

NCO 7 Recept Rm 112 Power Strip ON

NCO 8 Recept Rm 112 Refrigerator ON

NCO 9 Recept Rm 112 Power Strip ON

NCO 10 Recept Rm 112 Refrigerator ON

SOE 11 Recept Rm 112 Hood Lights ON

NCO 12 Recept Rm 112 ON

NCO 13 RM 104 Shop Retractable Recept ON

SOE 14/16 Rm 112 Hood 208V Recpt (2-pole

breaker)

ON

NCO 15 Recept Rm 112 ON

NCO 17 SP60A008 ON

NCO 18 SP60D006 ON

NCO 19 Recept Rm 100 (Lunch Room) ON

NCO 20 SP60F280 ON

NCO 21 Deluge Air Compressor ON

(Continued on Next Sheet)

Page 32: Tank Farm Plant Operating Procedure Effluent Treatment ... Library/011819... · 5.2.2 CLOSE breaker for Panel MDP-1, at MSWGR-2. 5.2.3 CLOSE CKT-1 breaker for LP-1 at MDP-1. NOTE

Electrical Distribution System Startup and Operation

Type

CONTINUOUS Document No.

ETF-25B-001 Rev/Mod

A-6 Release Date

01/14/2019 Page

32 of 32

Data Sheet 15 – Distribution Panel 6 (DP-6) Startup Alignment – Rm. 104 (Cont.)

Sheet 2 of 2

Resp. Breaker

Number Breaker Name and Location

Required

Position Initials Date

NCO 22/24 Heat Trace (Influent Recept-GFCI) (2-pole

breaker)

ON

NCO 23 SP60H144 ON

NCO 25 Recept Rm 134 ON

SOE 26 Heat Trace, Emergency Eye Wash ON

NCO 27 Recept Rm 101 ON

NCO 28 Grinder ON

NCO 29 Recept Rm 105 ON

NCO 30/32 Recept Rm 104, Pipe Threader, Sand Grinder,

Sand Blaster, Vacuum (2-pole Breaker)

ON

NCO 31 Recept Rm 104 ON

NCO 33/35 Recept Rm 104 Drill Press (2-pole Breaker) ON

NCO 34/36 Panel Board DP-8 Room 112 Lab (2-pole

Breaker

ON

NCO 37 Outdoor Recept and Surge LGT ON

NCO 39 Floodlights (East) ON

NCO 38/40/42 Rm 104 Power Saw (3-pole Breaker) ON

NCO 41 Floodlights (South) ON

COMMENTS:

/ / /

Signature Print (First & Last) Initials Date

NCO

/ / /

Signature Print (First & Last) Initials Date

SOE

/ / /

Signature Print (First & Last) Initials Date

SOM Completion Review